Plan Review Notes
Plan Review Notes For Project Z15040039
Project Number Z15040039
Review Stop ENG - PPRC
Sequence Number 1
Notes
Date Text
2015-05-08 13:46:31CITY OF WEST PALM BEACH
 PUBLIC WORKS DEPARTMENT
  
 THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL
 DETAILS, DESIGN CALCULATIONS AND THE POLLUTION
 PREVENTION PLAN WILL BE REVIEWED AS PART OF THE
 ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT
 APPLICATION PROCESSES. THE ENGINEERING DEVELOPMENT
 APPROVAL APPLICATION FORMS CAN BE DOWNLOADED AT
 HTTP://WPB.ORG/ENGINEERING/FORMS-AND-PUBLICATIONS/
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE
 PLAN APPROVAL.
  
 1. PLEASE SUBMIT ESTIMATES FOR THE PEAK POTABLE WATER
 DEMAND, SANITARY SEWER FLOW, AND SOLID WASTE COLLECTION
 YARDAGE.
  
 2. PLEASE SHOW THE SIGHT TRIANGLES ON THE LANDSCAPING
 PLAN FOR THE VEHICULAR EXITS. (SECTION 94-305E, CODE OF
 ORDINANCES)
  
 3. PAVEMENT RESTORATION WILL NEED TO BE IN ACCORDANCE
 WITH CITY STANDARD DETAIL GC-9. THE ROAD SHALL BE
 MILLED/RESURFACED FOR FULL LANE WIDTH OF THE TRAVEL
 LANE(S) ENCROACHED BY THE TRENCH AREA, INCLUDING A
 TRANSITION AREA OF 50 FEET ON EACH SIDE OF THE TRENCH.
 PLEASE REVISE THE PLANS TO REFLECT THE CORRECT EXTENT
 OF THE MILLING AND RESURFACING.
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED IN THE PRIOR
 TO ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING
 BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL.
  
 1. AS SEPARATE SUBMITTAL WILL BE REQUIRED TO THE
 ENGINEERING DIVISION OF THE PUBLIC WORKS DEPARTMENT FOR
 ENGINEERING DEVELOPMENT APPROVAL. THE ENGINEERING
 DEVELOPMENT APPROVAL APPLICATION FORMS CAN BE
 DOWNLOADED AT
 HTTP://WPB.ORG/ENGINEERING/FORMS-AND-PUBLICATIONS/
  
 2. AS SEPARATE SUBMITTAL WILL BE REQUIRED TO THE
 ENGINEERING DIVISION OF THE PUBLIC WORKS DEPARTMENT FOR
 PLAT APPROVAL. PLEASE CONTACT VINCE NOEL AT
 [email protected] TO GET A COPY OF THE PLAT APPLICATION.
  
 3. SOLID WASTE YARDAGE WILL NEED TO BE ESTIMATED AS
 PART OF THE FINAL DESIGN TO VERIFY THAT THE DESIGN
 INCLUDES APPROPRIATE NUMBER AND SIZE OF TRASH BINS.
  
 4. PLEASE IDENTIFY THE SOURCE OF THE AS-BUILT
 INFORMATION UTILIZED FOR THE POTABLE WATER, SANITARY
 SEWER, AND STORM SEWER DESIGN.
  
 5. INDICATE ON THE PLANS WHICH PORTIONS OF THE POTABLE
 WATER, SANITARY SEWER, AND STORMWATER SYSTEM WILL
 REMAIN PUBLICALLY OWNED AND WHICH SECTIONS WILL BE
 MAINTAINED BY THE APPLICANT. TYPICALLY, THE CITY'S
 OWNERSHIP STOPS AT THE RIGHT-OF-WAY LINE UNLESS
 EXTENUATING CIRCUMSTANCES REQUIRED THE OWNERSHIP
 DIVISION TO TAKE PLACE AT ANOTHER LOCATION.
  
 6. A PROPERTY OWNERS ASSOCIATION MUST BE FORMED TO BE
 RESPONSIBLE FOR THE OPERATION AND MAINTENANCE OF THE
 COMMONLY OWNED UTILITIES.
  
 7. THE CITY WILL CONSIDER A REQUEST TO MAKE N STREET A
 NO PARKING ZONE.
  
 KELLY CRANFORD, P.E.
 LAND DEVELOPMENT ENGINEER
 [email protected]
 561-494-1098 (OFFICE)
  
 VINCE NOEL, PSM
 CITY SURVEYOR / REAL ESTATE SUPERVISOR
 [email protected]
 561-494-1096
  
 BRIAN COLLINS, PE
 CITY TRAFFIC ENGINEER
 [email protected]
 561-494-1040
  
 FERDINAND RIVERA
 PUBLIC WORKS OPERATIONS MANAGER
 [email protected]
 561-822-2076
  
 TRACY WARD, PE
 CITY STORMWATER ENGINEER
 561-494-1120
 [email protected]
  