2015-05-12 10:34:001. VERIFY THE 18" PIPE CONNECTING THE TWO WET RETENTION
 AREAS ON THE WEST SIDE OF THE SITE IS OF SUFFICIENT
 SIZE TO PROVIDE STAGE EQUALIZATION BETWEEN THE WET
 DETENTION AREAS DURING LARGE STORM EVENTS.
  
 2. THE WET DETENTION AREAS TO MEET SFWMD DIMENSIONAL
 CRITERIA.
  
 3. WHERE IS EXFILTRATION PROPOSED? IT COULD NOT BE
 LOCATED ON THE DRAINAGE PLANS.
  
 4. VERIFY THE DESIGN OF THE STORMWATER MANAGEMENT
 SYSTEM INCLUDES RUNOFF FROM THE CITY'S PARK PARCEL.
  
 5. DELETE THE HINGED MANHOLE COVER DETAILS FOR BOTH
 STORM AND SANITARY SEWER.
  
 6. PROVIDE A CROSS SECTION OF THE BERM PROPOSED IN THE
 50' M-CANAL EASEMENT AND SHOW THE LIMITS OF THE BERM ON
 THE PLANS. WHO WILL BE RESPONSIBLE TO CONSTRUCT THE
 BERM?
  
 7. THE POINT OF INTERSECTION NEAR SHILOH DRIVE IS NOT
 SHOWN FOR THE EAST BOUNDARY LINE ON THE SITE PLAN.
  
 TRACY L. WARD, P.E.
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DIVISION
 561-494-1120
  
2015-05-08 13:43:51SEE COMMENTS UNDER PPRC ENGINEERING.