| Plan Review Notes For Project Z15020013 |
| Project Number |
Z15020013 |
|
| Review Stop |
L |
| Sequence Number |
3 |
|
| Notes |
| Date |
Text |
| 2015-10-09 10:54:59 | ALL PREVIOUS COMMENTS SATISFIED, | | | CONDITIONS OF APPROVAL: | | | CONDITIONS OF APPROVAL | | | 1. PRIOR TO THE REMOVAL OR RELOCATION OF ANY TREES ON | | | THE PROPERTY, A TREE ALTERATION PERMIT SHALL BE | | | SUBMITTED, REVIEWED AND APPROVED BY THE DEVELOPMENT | | | SERVICES DEPARTMENT, PLANNING DIVISION. | | | 2. PRIOR TO THE ISSUANCE OF THE CERTIFICATE OF | | | OCCUPANCY FOR THE BUILDING, ALL INVASIVE EXOTIC PLANTS | | | SHALL BE REMOVED FROM THE ENTIRE SITE AND VERIFIED BY | | | THE LANDSCAPE ARCHITECT. | | | 3. THE LANDSCAPE PLANS SHALL BE REVISED AT PERMITTING | | | TO REFLECT THE NEW LOCATION OF THE FPL TRANSFORMER AS | | | SHOWN ON THE SITE LAYOUT PLAN, SHEET 4, DATED 10/6/15, | | | AND SHOW A HEDGE ADDED ON THE NORTH SIDE OF THE | | | TRANSFORMER. | | | RAY CARANCI, LANDSCAPE PLANNER | | | |
| |
Print |
|