| 2015-04-15 12:12:50 | PUBLIC WORKS DEPT. 2ND REVIEW |
| | |
| | THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL |
| | DETAILS, DESIGN CALCULATIONS AND THE POLLUTION |
| | PREVENTION PLAN WILL BE REVIEWED AS PART OF THE |
| | ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT |
| | APPLICATION PROCESSES. THE ENGINEERING DEVELOPMENT |
| | APPROVAL APPLICATION FORMS CAN BE DOWNLOADED AT |
| | HTTP://WPB.ORG/ENGINEERING/FORMS-AND-PUBLICATIONS/ |
| | |
| | 1) AS DISCUSSED WITH STAFF DURING OUR MEETING ON MARCH |
| | 18, THE SUBMITTED TRAFFIC STUDIES DO NOT SUFFICIENTLY |
| | EVALUATE THE PROJECT'S IMPACT ON THE SURROUNDING LOCAL |
| | ROADWAYS. AS MENTIONED IN OUR ORIGINAL COMMENTS, PLEASE |
| | PROVIDE VEHICULAR AND PEDESTRIAN TRAFFIC STUDIES |
| | SHOWING HOW THE NEW SITE CONFIGURATION AND USE WILL |
| | EFFECT THE TRAFFIC VOLUME AND SURROUNDING LOCAL |
| | ROADWAYS AND WELL AS AN EVALUATION OF THE MINIMUM |
| | REQUIRED THROAT DEPTH (MRTD) NEEDED FOR EACH ON-SITE |
| | ACCESS POINT. THE RESULTS OF THE STUDY SHOULD SUPPORT |
| | TO PROPOSED MID-BLOCK PEDESTRIAN CROSSINGS AND MULTIPLE |
| | MID-BLOCK VEHICULAR STOPS. |
| | |
| | 2) AS DISCUSSED WITH STAFF DURING OUR MEETING ON MARCH |
| | 18, THE UNSIGNALIZED DOUBLE RIGHT TURN PROPOSED AT THE |
| | SOUTHERN EXIT IS AN UNSAFE CONDITION. PLEASE REMOVE |
| | UNSIGNALIZED DOUBLE RIGHT TURN. |
| | |
| | 3) AS MENTIONED DURING OUR ORIGINAL REVIEW, THE |
| | PROPOSED POWER LINES ALONG TAMARIND MUST BE |
| | UNDERGROUND. THE SUBMITTED EMAIL FROM FPL INDICATES AN |
| | ESTIMATED COST FOR MOVING THE LINES UNDERGROUND RATHER |
| | THAN INDICATING THAT MOVING THE LINES IS NOT FEASIBLE. |
| | |
| | |
| | KELLY CRANFORD, PE |
| | CITY LAND DEVELOPMENT ENGINEER |
| | [email protected] |
| | 561-494-1098 (OFFICE) |
| | |
| | VINCE NOEL, PSM |
| | CITY SURVEYOR / REAL ESTATE SUPERVISOR |
| | [email protected] |
| | 561-494-1096 |
| | |
| | BRIAN COLLINS, PE |
| | CITY TRAFFIC ENGINEER |
| | [email protected] |
| | 561-494-1040 |
| | |
| | TRACY WARD, PE |
| | CITY STORMWATER ENGINEER |
| | 561-494-1120 |
| | [email protected] |
| | |
| | |
| |