| 2014-09-03 08:45:43 | ENGINEERING/PUBLIC WORKS DEPT. |
| | LAND DEVELOPMENT / STORMWATER |
| | |
| | THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION |
| | DETAILLS WILL BE REVIEWED AS PART OF THE ENGINEERING |
| | DEVELOPMENT APPROVAL AND BUILDING PERMIT APPLICATION |
| | PROCESSES.A RIGHT-OF-WAY PERMIT FROM THE ENGINEERING |
| | DEPARTMENT WILL BE REQUIRED FOR ALL WORK WITHIN THE |
| | CITY OF WEST PALM BEACH RIGHT-OF-WAY. THE APPLICATION |
| | FORMS AND CONSTRUCTION STANDARDS CAN BE FOUND AT |
| | HTTP://WPB.ORG/ENGINEERING/FORMS-AND-PUBLICATIONS/ |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE |
| | PLAN APPROVAL. |
| | |
| | 1. SHOW THE DUMPSTER ENCLOSURE AREAS ON THE PLANS. THE |
| | PROPOSED LOCATIONS MUST BE EASILY ACCESSIBLE TO THE |
| | SOLID WASTE TRUCKS (35 FT LONG, 15 FT HIGH). THE DESIGN |
| | MUST COMPLY WITH SECTION 74-35(A)(9) OF THE CODE OF |
| | ORDINANCES. INCLUDE THE CITY OF WEST PALM BEACH GARBAGE |
| | RECEPTACLE DETAI ON THE PLANS. [CODE OF ORDINANCES, |
| | SECTION 94-444(B), FIGURE XIV-3] |
| | |
| | 2. PROVIDE CALCULATIONS DEMONSTRATING THE PROPOSED SIZE |
| | AND QUANTITY OF TRASH BINS IS APPROPRIATE FOR THE WASTE |
| | YARDAGE ANTICIPATED TO BE GENERATED BY THE COMPLEX |
| | |
| | 3. PROVIDE STORMWATER CALCULATIONS AND CONSTRUCTION |
| | PLANS. THE PROJECT MUST PROVIDE ADEQUATE STORMWATER |
| | MANAGEMENT, INCLUDING NOT MODIFYING THE VELOCITY OR |
| | VOLUME OF OFF-SITE STORMWATER DISCHARGE. COMPLIANCE |
| | WITH CHAPTER 40E-4 FAC WILL DEMONSTRATE COMPLIANCE WITH |
| | THIS PROVISION. [CODE OF ORDINANCES SECTIONS 90-201, |
| | 94-35(C )(11), 94-307, AND 94-580] |
| | |
| | 4. THE SUBMITTED SURVEY AND PLANS REFERENCE VERTICAL |
| | DATUM NAVD 1988. THE SECTION 78-9 OF THE CITY?S CODE OF |
| | ORDINANCES SPECIFIES NGVD 1929 AS THE OFFICIAL CITY |
| | VERTICAL DATUM. REVISE THE PLANS TO REFERENCE NGVD |
| | 1929. |
| | |
| | 5. STRIPING TO COMPLY WITH CITY OF WEST PALM BEACH CODE |
| | OF ORDINANCES, ARTICLE XV, SECTION 94-485. ADD A |
| | TYPICAL PARKING SPOT STRIPING DETAIL TO THE PLANS. |
| | |
| | 6. REVISE THE PLANS TO SHOW THE EXISTING EASEMENTS OVER |
| | THE 48-INCH STORMWATER SYSTEM. |
| | |
| | 7. SHOW THE EXTENT OF FLOOD ZONE AE ON THE SITE PLAN. |
| | |
| | 8. THE PROPOSED BUILDING IS NOT WITHIN THE CITY OF WEST |
| | PALM BEACH POTABLE WATER SERVICE AREA. IF THE BUILDING |
| | IS NOT PROPOSED TO BE SERVED BY RIVIERA BEACH |
| | UTILITIES, PROVIDE A WRITTEN REQUEST FROM RIVIERA BEACH |
| | REQUESTING THAT SERVICE BE PROVIDED BY THE CITY OF WEST |
| | PALM BEACH. |
| | |
| | KELLY CRANFORD, P.E. |
| | LAND DEVELOPMENT ENGINEER |
| | ENGINEERING & PUBLIC WORKS DEPARTMENT |
| | CITY OF WEST PALM BEACH |
| | [email protected] |
| | 561-494-1098 (OFFICE) |
| | |
| | |
| |