| Plan Review Notes For Project Z14070022 |
| Project Number |
Z14070022 |
|
| Review Stop |
STORM |
| Sequence Number |
1 |
|
| Notes |
| Date |
Text |
| 2014-08-12 15:53:13 | 1. SUGGEST RELOOCATING SANITARY SEWER LATERAL FROM | | | WITHIN THE LANDSCAPE AREA. | | | 2. THE FOLLOWING WILL NEED TO BE SUBMITTED WITH THE | | | ENGINEERING PERMIT APPLICATION: | | | A. STORMWATER QUALITY TREATMENT CALCULATIONS | | | B. LAND USE (PERVIOUS/IMPERVIOUS) AREAS | | | C. SWPPP (EROSION CONTROL) PLAN | | | D. FINAL ENGINEERING PLANS | | | 3. THE FOLLOWING WILL NEED TO BE SUBMITTED BEFORE START | | | OF CONSTRUCTION | | | A. MODIFICATION OF SFWMD ERP PERMIT. | | | B. FDEP NPDES NOI. | | | | | | TRACY L. WARD, P.E. | | | SENIOR STORMWATER ENGINEER | | | ENGINEERING AND PUBLIC WORKS DEPARTMENT | | | (561) 494-1120 |
| |