| 2014-08-15 15:53:37 | ZONING COMMENTS |
| | |
| | * PLEASE PROVIDE RESPONSES TO REVIEW COMMENTS IN |
| | WRITTEN FORMAT. |
| | |
| | * WHEN RESUBMITTING, PLEASE PROVIDE A MINIMUM OF TEN |
| | (10) COPIES, ONE (1) REDUCED COPY (8 1/2 BY 11), AND AN |
| | ELECTRONIC COPY IN .PNG FORMAT OF ALL PLANS. PLEASE |
| | NOTE THAT RE-SUBMITTALS MAY BE SUBJECT TO ADDITIONAL |
| | COMMENTS. |
| | |
| | * PLEASE NOTE THAT YOU WILL BE PERMITTED ONE (1) |
| | RESUBMITTAL AT NO ADDITIONAL COST. IF PREVIOUSLY-ISSUED |
| | COMMENTS CONTINUE TO NOT BE SUFFICIENTLY ADDRESSED, THE |
| | APPLICANT WILL BE ACCESSED A RESUBMITTAL FEE. SUCH FEE |
| | WILL BE 20% ($200) OF THE ORIGINAL APPLICATION FEE. |
| | |
| | * NOTE: ANY CHANGES ON THE RESUBMITTED PLANS MAY RESULT |
| | IN ADDITIONAL COMMENTS. |
| | |
| | |
| | GENERAL COMMENTS: |
| | |
| | 1.) ON-STREET PARKING SHALL BE REVIEWED BY THE |
| | ENGINEERING SERVICES DEPARTMENT. (REPEAT COMMENT) |
| | |
| | 2.) PLEASE REVIEW SITE DATA CALCULATIONS IN THE SITE |
| | PLAN (SHEET SP-1) AND LANDSCAPE PLAN (SHEET LP-1). |
| | THERE SEEMS TO BE DISCREPANCIES WITH THE CALCULATIONS |
| | PROVIDED. CORRECT WHERE NECESSARY. (REPEAT COMMENT: |
| | INCONSISTENCIES INCLUDE THE FOLLOWING: SITE AREA = |
| | 11,500 SQ. FT.; CALCULATIONS WITH THE EXISTING AND |
| | PROPOSED SQUARE FOOTAGE DOES NOT ADD-UP; OFFICE PARKING |
| | REQUIREMENT IS 1/350 SQ. FT. NOT 1/250 SQ. FT., ETC.) |
| | |
| | 3.) DUMPSTER ENCLOSURE AND LOCATION MUST BE APPROVED BY |
| | FERDINAND RIVERA, SANITATION SUPERVISOR (561) 822-2076. |
| | |
| | 4.) HAS THE WOOD DECKING AND FENCE BEEN PERMITTED BY |
| | FEC? |
| | |
| | |
| | SITE PLAN: |
| | |
| | 1.) ON-STREET PARKING USED FOR REQUIRED PARKING MAY NOT |
| | BE PROVIDED WHERE THERE IS A "NO PARKING SIGN." THERE |
| | MAY BE A "NO PARKING" SIGN LOCATED ADJACENT TO THE |
| | PROPERTY WHERE THERE ARE TWO (2) ON-STREET PARKING |
| | SPACES AT THE NORTHWEST CORNER. |
| | |
| | |
| | LANDSCAPE PLAN: |
| | |
| | 1.) PROVIDE A CERTIFIED COST ESTIMATE OF THE PROPOSED |
| | CONSTRUCTION. IF THE COST ESTIMATE EXCEEDS 50 PERCENT |
| | OF THE STRUCTURE'S VALUE ACCORDING TO THE PBC PROPERTY |
| | APPRAISER'S OFFICE ($106,815), THEN THE SITE SHALL COME |
| | INTO FULL COMPLIANCE WITH THE ARTICLE XIV OF THE ZLDR. |
| | (ZLDR S.94-441(C)(2)) |
| | |
| | 2.) PALM TREES MAY NOT BE SUBSTITUTED FOR MORE THAN 35 |
| | PERCENT OF REQUIRED SHADE OR FLOWERING TREES. (ZLDR |
| | S.94-442(C)) |
| | |
| | 3.) LANDSCAPE AREAS AND PLANT MATERIALS MUST BE |
| | PROTECTED FROM VEHICULAR ENCROACHMENT. PARKED VEHICLES |
| | SHALL NOT EXTEND INTO A LANDSCAPE AREA THAT IS 5 FT. |
| | WIDE UNLESS TWO ADDITIONAL FEET ARE ADDED TO THE |
| | BUFFER. THE TWO ADDITIONAL FEET OF LANDSCAPING SHALL |
| | CONTAIN NO PLANT, IRRIGATION DEVICES OR OTHER OBJECT |
| | HIGHER THAN 6-INCHES ABOVE THE TOP OF THE CURB. PLEASE |
| | ILLUSTRATE THAT THIS REQUIREMENT WILL BE MET. (ZLDR |
| | S.94-443(C)(5)) |
| | |
| | 4.) THE LANDSCAPE PLAN INDICATES THAT A SCHEFFLERA TREE |
| | WILL BE REMOVED AND REPLACED WITH A GREEN BUTTONWOOD |
| | TREE AT THE SOUTHWEST CORNER OF THE PROPERTY. NO TREE |
| | SHALL BE REMOVED UNLESS A TREE ALTERATION PERMIT IS |
| | GRANTED. PLEASE SUBMIT AN APPLICATION FOR A TREE |
| | ALTERATION PERMIT. (ZLDR S.94-448(D)) |
| | |
| | 5.) ALL NEWLY INSTALLED TREES SHALL BE A MINIMUM OF 8 |
| | FT. IN HEIGHT AND POSSESS A MINIMUM OF 5 FT. OF CLEAR |
| | TRUNK. (ZLDR S.94-445(4)A.) |
| | |
| | 6.) PROVIDE LANDSCAPE DETAILS (INCLUDING LANDSCAPE |
| | INSTALLATION, STAKING, AND TREE PROTECTIVE BARRIERS) |
| | SUFFICIENT TO COMPLY WITH ARTICLE XIV OF THE ZLDR. |
| | |
| | 7.) THERE IS CONFLICTING INFORMATION IN THE PLANT LIST |
| | AND WHAT IS PROVIDED IN THE PLAN. PLEASE ADDRESS. |
| | |
| | 8.) NOT ALL LANDSCAPE PLAN REQUIREMENTS HAVE BEEN |
| | PROVIDED IN THE LANDSCAPE PLAN. PLEASE REFER TO P.18 OF |
| | THE DEVELOPMENT APPLICATION FOR SPECIFICATIONS. |
| | |
| |