Plan Review Notes
Plan Review Notes For Project Z14030060
Project Number Z14030060
Review Stop STORM
Sequence Number 1
Notes
Date Text
2014-04-04 13:57:141. INCLUDE WITH THE ENGINEERING PERMIT APPLICATION THE
 FOLLOWING:
 - SIGNED AND SEALED DRAINAGE CALCULATIONS AND LAND USE
 BREAKDOWN (PERVIOUS/IMPERVIOUS/BUILDING/ETC.)
 - SIGNED AND SEALED ENGINEERING PLANS INCLUDING PAVING,
 GRADING AND DRAINAGE PLAN AND AN EROSION CONTROL PLAN
 2. BEFORE START OF CONSTRUCTION, PROVIDE FDEP NPDES
 PERMIT
 3. WEIR BOX DETAIL SHOWS HEIGHT TO BE PIPE DIAMETER +
 6". BASED ON EXFILTRATION TRENCH DESIGN, THE HEIGHT
 SHOULD BE PIPE DIAMETER + 18" (6" BELOW AND 12" ABOVE
 THE PIPE).
 4. INCLUDE BAFFLES IN INLETS CONNECTED TO EXFILTRATION
 TRENCHES.
 5. WILL THE OVERHEAD ELECTRIC LINES IN THE ALLEY BE
 AFFECTED?
 6. SHOW PROPERTY LINES ON THE BUILDING SECTION SHEET
 A-6.
 7. WHERE IS THE ALLEY EXFILTRATION TRENCH IN RELATION
 TO THE SUBTERRANEAN PARKING AREAS?
  
 TRACY L. WARD, P.E.
 SENIOR STORMWATER ENGINEER
 ENGINEERING AND PUBLIC WORKS DEPARTMENT
 561-494-1120