Plan Review Notes
Plan Review Notes For Project Z13120017
Project Number Z13120017
Review Stop STORM
Sequence Number 1
Notes
Date Text
2014-01-08 12:37:021. PROVIDE COPY OF SFWMD ERP PERMIT MODIFCATIONBEFORE
 START OF CONSTRUCTION.
 2. PROVIDE COPY OF NPDES NOI BEFORE START OF
 CONSTRUCTION.
 3. PROVIDE SIGNED AND SEALED SWPPP AND PGD PLANS WITH
 ENGINEERING PERMIT APPLICATION.
 4. PROVIDE SIGNED AND SEALED DRAINAGE CALCULATIONS WITH
 ENGINEERING PERMIT APPLICATION.
 5. ONLY CONCEPTUAL ENGINEERING PLAN SUBMITTED.
 6. WHAT PART OF STORMWATER MANAGEMENT SYSTEM CURRENTLY
 EXISTS? WILL ANY OF THE EXISTING DRAINAGE SYSTEM BE
 REMOVED/ABANDONED?
 7. AVOID PLANTING OF TREES WITHIN 5 FEET OF UNDERGROUND
 UTILITIES.
 8. MINIMIZE THE NUMBER OF OUTFALLS INTO THE PRESERVE.
 9. INCORPORATE BAFFLES AND SEDIMENT SUMPS IN THE
 DRAINAGE STRUCTURES TO PREVENT OFFISITE DISCHARGE OF
 POLLUTANTS, SEDIMENTS AND FLOATABLES.
 10. DETAILS FOR CONTROL STRUCTURES AND EXFILTRATION
 TRENCHES WILL BE REQUIRED WITH THE ENGINEERING PERMIT
 APPLICATION.
  
 TRACY L. WARD, P.E.
 SENIOR STORMWATER ENGINEER
 ENGINEERING AND PUBLIC WORKS DEPARTMENT
 561-494-1120
  