Plan Review Notes For Project Z13120009
Project Number Z13120009
Review Stop STORM
Sequence Number 1
Notes
Date Text
2014-01-03 15:41:321. PROVIDE COPY OF SFWMD ERP PERMIT BEFORE START OF
 CONSTRUCTION.
 2. PROVIDE COPY OF LWDD DRAINAGE PERMIT BEFORE START OF
 CONSTRUCTION.
 3. PROVIDE COPY OF NPDES NOI BEFORE START OF
 CONSTRUCTION.
 4. PROVIDE SWPPP AND PGD PLANS WITH ENGINEERING PERMIT
 APPLICATION.
 5. PROVIDE SIGNED AND SEALED DRAINAGE CALCULATIONS WITH
 ENGINEERING PERMIT APPLICATION.
 6. CAR WASH WATERS SHOULD BE PREVENTED FROM ENTERING
 THE DRAINAGE SYSTEM.
 7. AVOID PLANTING OF TREES WITHIN 5 FEET OF UNDERGROUND
 UTILITIES.
 8. WHERE DOES THE EXISTING CATCH BASIN AT THE SOUTHWEST
 CORNER OF THE SITE DRAIN TO.
 9. SITE PLAN SHOWS WHEEL STOPS IN THE 90-DEGREE PARKING
 SPACES NORTH OF DETAIL BAYS. CONCEPTUAL ENGINEERIING
 PLAN DOES NOT.
 10. SHOW CURB AND/OR WHEEL STOP IN PARKING AND STRIPING
 DETAIL ON SHEET SP-2 OF 2.
 11. HOW DOES HANDICAP PARKING PATRON ACCESS THE MAIN
 OFFICE? IS CURB RAMP NEEDED AT EAST END OF PARKING
 STALL?
 12. CORRECT LEADER FOR SIDEWALK RAMP IN ACCORDANCE WITH
 FDOT STND. INDEX#304. IT POINTS TO SIDEWALK AT EAST
 PROPERTY LINE.
 13. DOES INGRESS DRIVE NEED TO BE 24-FEET WIDE.
 14. NO CURBING SHOWN ALONG THE EAST SIDE OF THE COVERED
 LOADING AREA.
 15. SHOW CROSS WALK STRIPING AND SIDEWALK AT NORTH END
 OF SITE ON THE CONCEPTUAL ENGINEERING PLAN AS IT IS
 SHOWN ON THE SITE PLAN. WILL THE SIDEWALK CONNECT TO
 THE SIDEWALK ALONG OKEECHOBEE BLVD.? IS THIS THE ADA
 ACCESSIBLE ROUTE FROM PUBLIC R/W?
  
 TRACY L. WARD, P.E.
 SENIOR STORMWATER ENGINEER
 ENGINEERING AND PUBLIC WORKS DEPARTMENT
 561-494-1120
  