| 2013-10-07 14:47:33 | 1. SITE/CIVIL PLANS WILL NEED TO BE SUBMITTED TO | | | ENGINEERING SERVICES. | | | 2. ADD RIGHT-OF-WAY LINES TO ELEVATION PLANS. | | | 3. DEVELOPERS AGREEMENT WILL BE REQUIRED FOR | | | IMPROVEMENTS WITHIN RIGHT-OF-WAY. | | | 4. METERS AND BACKFLOW ASSEMBLY WILL NEED TO BE | | | RELOCATED OUT OF RIGHT-OF-WAY. | | | 5. IS ALLEY TO BE DESIGNATED ONE-WAY WEST? | | | 6. SANITATION COLLECTION WILL NEED TO BE APPROVED BY | | | FERDINAND RIVERA, SANITATION SUPERINTENDENT. | | | 7. AMENITY AND MECHANICAL ROOM DOORS CANNOT OPEN INTO | | | RIGHT-OF-WAY. | | | |
| |