| Plan Review Notes For Project Z13040037 |
| Project Number |
Z13040037 |
|
| Review Stop |
STORM |
| Sequence Number |
1 |
|
| Notes |
| Date |
Text |
| 2013-06-06 19:05:18 | 1. CIVIL PLAN IS A COPY OF A SIGNED AND SEALED PLAN. | | | 2. CIVIL PLAN DOES NOT MATCH SITE PLAN. SITE PLAN SHOWS | | | A SIDEWALK CONNECTION TO NORTH DIXIE HIGHWAY SIDEWALK. | | | THIS SIDEWALK WILL AFFECT THE PROPOSED DRAINAGE SWALE. | | | 3. INDICATE VERTICAL DATUM ON CIVIL PLAN AND SITE | | | PLAN.SURVEY INDICATES NGVD 1929. | | | 4. SIGNED AND SEALED DRAINAGE CALCULATIONS TO BE | | | PROVIDED SHOWING WATER QUALITY TREATMENT IS BEING | | | PROVIDED (PER SFWMD CRITERIA). | | | 5. ENTRANCE GATE WILL BLOCK THE FIRST REGULAR AND | | | HANDICAP PARKING SPACES. | | | 6. CHECK PAVEMENT SLOPE OF EXISTING PARKING SO THAT NEW | | | CURBING OF LANDSCAPE ISLANDS DOESN'T TRAP RUNOFF. | | | 7. SUGGEST THE 10' WIDE SIDEWALK BETWEEN HANDICAP | | | PARKING SPACES BE 6" THICK IN CASE IT IS INADVERTENTLY | | | USED FOR PARKING. | | | 8. SWPPP NEEDED WITH ENGINEERING PERMIT APPLICATION. | | | | | | TRACY L. WARD, P.E. | | | ENGINEERING AND PUBLIC WORKS DEPARTMENT | | | 561-494-1120 | | | |
| |
Print |
|