| Project Number |
Z13040029 |
|
| Review Stop |
STORM |
| Sequence Number |
1 |
|
| Notes |
| Date |
Text |
| 2013-05-08 11:44:30 | 1. PROVIDE COPY OF SFWMD ERP OR NO-NOTICE PERMIT PRIOR | | | TO START OF CONSTRUCTION. | | | 2. PROVIDE COPY OF NPDES NOI PERMIT PRIOR TO START OF | | | CONSTRUCTION. | | | 3. PROVIDE DRAINAGE CALCULATIONS, INCLUDING LAND USE | | | BREAKDOWN (PERVIOUS, IMPERVIOUS, BUILDING, ETC), WATER | | | QUALITY TREATMENT, ETC., WITH THE CITY'S ENGINEERING | | | PERMIT APPLICATION. | | | 4. PROVIDE SWPPP PLAN WITH THE CITY'S ENGINEERING | | | PERMIT APPLICATION. | | | 5. INDICATE VERTICAL DATUM ON THE PLANS (SHOULD BE NGVD | | | 1929). | | | 6. RE-ROUTING OF OUTFALL PIPING OF FLAGLER DRIVE | | | DRAINAGE TO BE DESIGNED TO HAVE NO ADVERSE IMPACT TO | | | THE HYDRAULIC GRADE LINE OF THE FLAGLER DRIVE DRAINAGE | | | SYSTEM. | | | 7. PROVIDE AN EASEMENT IN FAVOR OF THE CITY OVER THE | | | RE-DIRECTED DRAINAGE SYSTEM CONVEYING RUNOFF FROM | | | FLAGLER DRIVE TO THE OUTFALL. | | | 8. SUGGEST PLUG AND GROUT FILL THE OUTFALL PIPE | | | PROPOSED TO BE ABANDONED AT SEAWALL. | | | | | | TRACY L. WARD, P.E. | | | SENIOR STORMWATER ENGINEER | | | ENGINEERING AND PUBLIC WORKS DEPARTMENT | | | (561) 494-1120 |
| |
Print |
|