Plan Review Notes For Project Z13040019
Project Number Z13040019
Review Stop Z
Sequence Number 1
Notes
Date Text
2013-05-08 12:50:171. TOP FLOOR OF THE PARKING GARAGE CANNOT BE EXPOSED.
 2. SETBACK ALONG 8YH STREET IS 17' MEASURED FROM THE
 BACK OF CURB CLOSER TO THE PROPERTY LINE.
 3.PUBLIC OPEN SPACE FOR PARCEL A DOES NOT COMPLY WITH
 THE MINIMUM SIZE (NO ONE SIDE > 5 TIMES ANY OTHER SIDE)
 4.SETABACK AREAS CANNOT BE COUNTED AS PART OF THE
 PRIVATE OPEN SPACE CALCULATION, OR PUBLIC OPEN SPACE
 CALCULATIONS.
 5. SETBACK AREA ALONG A STREET MAY INCLUDE SEMI-PUBLIC
 OPEN SPACE, BUT ENOUGH SPACE SHALL BE PROVIDED FOR A
 SIDEWLAK AND STREET TREES.
 6.PARKING SPACES ADJACENT TO COLUMNS OR OTHER
 OBSTRUCTIONS SHALL BE WIDENED ACCORDING TO SECTON
 94-111(C)
 7. PLEASE PROVIDE INFORMATION REGADING THE TOTAL WIDTH
 OF THE ROW AND THE EXISTING TRAVEL LANES TO DETERMINE
 THE FEASIBILITY OF THE PROPOSED ON-STREET PARKING.
 8. PLEASE CONFIRM COMPLIANCE WITH THE MINIMUM 20'
 SETBACK FOR SIDE INTERIOR ON THE NEW PROPERTY LINES
 BETWEEN PHASE I AND II IF CREATED.
 9. BRIDGE WILL REQUIRE CITY COMMISSION APPROVAL OF AN
 AIR RIGHTS EASEMENT.
 10. STREET TREES SHALL BE PLANTED ALONG ROW FRONTAGE ON
 TREE GRATES NEXT TO THE CURB.
 11. PLEASE PROVIDE INFORMATION TO CONFIRM COMPLIANCE
 WITH TABLE IV-4- FACADE ARTICULATION REQUIREMENTS.
 12. HOW IS THE PARKIGN FOR RETAIL USES GOING TO WORK?
 STAFF SUGGEST PROVIDING ON-STREET PARKING ALONG DIXIE
 HWAY.
 13. LOADING AREA FOR NORTH PHASE IS ENCROACHING INTO
 THE PROPERTY LINE. HOW DO TRUCKS TURN AROUND?
 14. PROJECT WILL BE SUBJECT OF DAC SPECIAL REVIEW. 3D
 RENDERS WILL BE REQUIRED.
 15. PLEASE PROVIDE A 3 DIMENSIONAL VIEW OF THE PROJECT
 INSERTED INTO THE CONTEXT. VERY IMPORTANT FOR THE NORTH
 BLCOK.
 16. PLEASE PROVIDE A BUIDLING TABLE INCLUDING THE AREA
 OF EACH PARCEL OR PHASE, THE FAR PROVIDED BASED ON THE
 GROSS BUIDLING AREA DEFINITION AND THE MECHANICAL
 EQUIPEMENT AREA ( SKETCHES SHALL BE PROVIDED INDICATING
 THE AREAS WHICH ARE CALCULATED AS PART OF THE FAR OR
 NOT).
 17. ARE PHASE I AND II SEPARATED WITH PROPERTY LINES?
  
 FOR ADDITIONAL INFORMATION PLEASE CONTACT ANA MARIA