Plan Review Notes
Plan Review Notes For Project Z12110027
Project Number Z12110027
Review Stop STORM
Sequence Number 1
Notes
Date Text
2012-12-07 14:14:381. ENGINEERING PLANS NOT PROVIDED OTHER THAN PRELMINARY
 ENGINEERING SITE PLAN.
 2. SFWMD ENVIRONMENTAL RESOURCES PERMIT WILL BE NEEDED
 BEFORE START OF CONSTRUCTION.
 3, EROSION CONTROL PLAN AND STORM WATER POLLUTION
 PREVENTION PLAN WILL BE REQUIRED WITH FINAL ENGINEERING
 PLANS.
 4. STORMWATER WATER QUALITY TREATMENT VOLUME TO BE
 PROVIDED ON SITE (MINIMUM OF 1" OF RUNOFF FROM SITE OR
 2.5" RUNOFF TIMES PERCENT IMPERVIOUS).
 5. DRAINAGE CALCULATIONS WILL BE REQUIRED FOR
 ENGINEERING PERMITS.
 6. ARCHITECTURAL SITE LAYOUT PLAN LACKING DIMENSIONS
 FOR SIDEWALKS, OFFSETS BETWEEN PROPERTY LINE AND
 PARKING.
 7. CHEVRON STRIPING ON PBL BLVD. SHOULD BE ROTATED 90
 DEGREES.
  
 TRACY L. WARD, P.E.
 SENIOR STORM WATER ENGINEER
 ENGINEERING AND PUBLIC WORKS DEPARTMENT
 (561) 494-1120
  
  Print