Notes
Date Text
2012-12-21 16:16:201. WATER QUALITY CRITERIA PER SFWMD IS THE LARGER OF 1"
 OF RUNOFF FROM THE SITE OR 2.5" OF RUNOFF TIMES PERCENT
 IMPERVIOUS. BOTH CALCULATIONS ARE TO INCLUDE THE
 PERVIOUS AREA IN THE RUNOFF VOLUME CALCULATION.
 DEPENDING ON METHOD OF TREATMENT, REQUIRED TREATMENT
 VOLUME CAN BE REDUCED (25% FOR DRY DETENTION, 50% FOR
 RETENTION). SOIL STORAGE CANNOT BE CONSIDERED BECAUSE
 THE VOLUME CALCULATIONS ASSUME SOIL STORAGE IS ALREADY
 USED UP.
 2. WHERE DO ROOF RAIN LEADERS DRAIN?
 3. SHOW PROPOSED STORM WATER MANAGEMENT SYSTEM ON THE
 LANDSCAPE PLANS.
 4. IS THE PROPOSED PRIVATE OUTDOOR PATIO AREA WITHIN
 THE PROPOSED PARK AREA?
  
 TRACY L. WARD, P.E.
 SENIOR STORMWATER ENGINEER
 ENGINEERING AND PUBLIC WORKS DEPARTMENT
 561-494-1120
  