| Plan Review Notes For Project Z12090008 |
| Project Number |
Z12090008 |
|
| Review Stop |
STORM |
| Sequence Number |
2 |
|
| Notes |
| Date |
Text |
| 2012-12-21 16:16:20 | 1. WATER QUALITY CRITERIA PER SFWMD IS THE LARGER OF 1" | | | OF RUNOFF FROM THE SITE OR 2.5" OF RUNOFF TIMES PERCENT | | | IMPERVIOUS. BOTH CALCULATIONS ARE TO INCLUDE THE | | | PERVIOUS AREA IN THE RUNOFF VOLUME CALCULATION. | | | DEPENDING ON METHOD OF TREATMENT, REQUIRED TREATMENT | | | VOLUME CAN BE REDUCED (25% FOR DRY DETENTION, 50% FOR | | | RETENTION). SOIL STORAGE CANNOT BE CONSIDERED BECAUSE | | | THE VOLUME CALCULATIONS ASSUME SOIL STORAGE IS ALREADY | | | USED UP. | | | 2. WHERE DO ROOF RAIN LEADERS DRAIN? | | | 3. SHOW PROPOSED STORM WATER MANAGEMENT SYSTEM ON THE | | | LANDSCAPE PLANS. | | | 4. IS THE PROPOSED PRIVATE OUTDOOR PATIO AREA WITHIN | | | THE PROPOSED PARK AREA? | | | | | | TRACY L. WARD, P.E. | | | SENIOR STORMWATER ENGINEER | | | ENGINEERING AND PUBLIC WORKS DEPARTMENT | | | 561-494-1120 | | | |
| |