| Plan Review Notes For Project Z12040011 |
| Project Number |
Z12040011 |
|
| Review Stop |
STORM |
| Sequence Number |
1 |
|
| Notes |
| Date |
Text |
| 2012-05-09 07:26:43 | 1. WHY 15' EXFILTRATION TRENCH DEPTH? | | | 2. STORMWATER RUNOFF FROM WESTERN 1/3 OF PARKING LOT | | | NOT GETTING WATER QUALITY TREATMENT. | | | 3. PROVIDE COPY OF SFWMD ERP PERMIT FOR PROPOSED WORK. | | | 4. PROVIDE DRAINAGE CALCULATIONS SIGNED AND SEALED BY A | | | FLORIDA P.E. SHOWING LAND USE BREAKDOWN (PERVIOUS, | | | IMPERVIOUS, BUILDING, ETC.), WATER QUALITY TREATMENT | | | VOLUMES (REQUIRED, PROVIDED) AND DESIGN STORM FLOOD | | | STAGES (5-YEAR 24-HOUR, 25-YEAR 72-HOUR AND 100-YEAR | | | 72-HOUR ZERO DISCHARGE). | | | 5. FINAL PLANS TO INCLUDE STORM WATER POLLUTION | | | PREVENTION PLAN. | | | | | | TRACY L. WARD, P.E. | | | SENIOR STORMWATER ENGINEER | | | ENGINEERING SERVICES DEPARTMENT | | | OFFICE 561-494-1120 |
| |