Plan Review Notes
Plan Review Notes For Project Z12020014
Project Number Z12020014
Review Stop STORM
Sequence Number 2
Notes
Date Text
2012-03-28 13:38:481. ON FINAL ENGINEERING PLANS:
 A. SHOW THE PROPOSED CATCH BASINS INSIDE THE CURB LINE.
 B. DETAILS OF HOW WEIR WILL BE AFFIXED TO CONTROL
 STRUCTURE.
 2. VERIFY LAND USE AREAS (PERVIOUS, IMPERVIOUS,
 BUILDING, TOTAL AREA). INSCRIBING A 173' X 160'
 RECTANGLE AROUND THE PARKING LOT CALCULATES TO 0.64 AC.
 THE EXFILTRATION TRENCH CALCULATIONS SHOW TOTAL AREA =
 0.;47 ACRES,
 3. VERIFY WATER QUALITY TREATMENT VOLUME (PER SFWMD,
 MIN. OF: (A) 1" OVER SITE [=0.47 AC-IN] OR (B) 2.5"
 TIMES PERCENT IMPERVIOUS [=2.5 X ((0.4 - 0.1) /(0.47 -
 0.07)) X (0.47-0.0) = 0.88 AC-IN] USING THE LAND USE
 AREAS ON THE PLANS.
 4. ADJUST EXFILTRATION TRENCH LENGTH BASED ON 2 AND 3
 ABOVE.
 5. SINCE DRIVEWAY CONNECTIONS ARE SLOPED TO DRAIN OFF
 OF THE SITE INTO AJACENT PARKING/DRIVE LANE, VERIFY THE
 ADJACENT AREAS DRAIN AWAY FROM THE TIE-IN LINE AND
 WATER WILL NOT BE TRAPPED AT THE NEW INTERFACE LINE.
  
 TRACY L. WARD, P.E.
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120