Plan Review Notes
Plan Review Notes For Project Z11120014
Project Number Z11120014
Review Stop TRAFFIC
Sequence Number 3
Notes
Date Text
2012-06-13 10:38:51ACCESS CAN BE ACHIEVED DIRECTLY FROM DIXIE HIGHWAY, IN
 THE DIRECTION OF TRAFFIC FLOW ON DIXIE HIGHWAY, BY
 ANGLING THE DRIVEWAY SO AS NOT TO ENTER FROM THE ALLEY.
 ENTERING FROM THE PROPOSED SOUTHERN HOTEL DRIVEWAY
 WOULD REQUIRE A 180 DEGREE TURN WHICH COULD PRESENT
 OPERATIONAL AND SAFETY ISSUES. ALL VALET EGRESS FROM
 THE CITY CENTER GARAGE SHOULD BE FROM BANYAN BOULEVARD.
 THIS WILL MINIMIZE CONFLICTS WITH THE ENTRANCE/EXIT OF
 THE CITY CENTER GARAGE ON DIXIE HIGHWAY.