| Plan Review Notes For Project Z10050014 |
| Project Number |
Z10050014 |
|
| Review Stop |
SURVEY |
| Sequence Number |
2 |
|
| Notes |
| Date |
Text |
| 2010-07-14 09:31:47 | THE RESUBMITTAL IS ACCEPTABLE AND THE UNITY OF TITLE | | | HAS BEEN COMPLETED. AS WE DISCUSSED, PRIOR TO THE | | | ISSUANCE OF THE C.O. THE UTILITY EASEMENT WILL NEED TO | | | BE RECORDED. THE REVIEW FEE THROUGH ENGINEERING | | | SERVICES IS $257.50. I HAVE ATTACHED OUR FORM OF | | | UTILITY EASEMENT TO BE USED. THE EXHIBIT A NEEDS TO BE | | | PREPARED BY THE APPLICANT AND SUBMITTED FOR REVIEW. |
| |
Print |
|