2009-08-28 16:31:11NO FLOOR DRAIN TO THE SANITARY SEWER CAN BE INSTALLED
 IN THE DUMPSTER ENCLOSURE, UNLESS IT IS ROOFED SO NO
 RAIN WATER WILL GET INTO THE DRAIN.
  
 ARTICLE II. SOLID WASTE COLLECTION AND DISPOSAL
 SEC. 74-34. PREPARATION AND STORAGE OF SOLID WASTE FOR
 COLLECTION.
 (2) COMMERCIAL.
 C. COMMERCIAL GARBAGE AND REFUSE SHALL BE DRAINED OF
 ALL LIQUID BEFORE BEING PLACED FOR COLLECTION.
  
 IF A ROOF IS TO BE ADDED TO THE DUMPSTER ENCLOSURE, IT
 WILL ALTER THE SERVICE AREA LOCATION, SINCE 26 FEET OF
 UNOBSTRUCTED VERTICAL CLEARANCE IS REQUIRED FOR
 SANITATION TRUCK'S FRONT/TOP LOADING OPERATION.