Plan Review Details - Project Z23020025
Plan Review Stops For Project Z23020025
Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 04-12-2023 Cont ID  
Sent By rbrown Date 04-12-2023 Time 17:59 Rev Time 0.00
Received By rbrown Date 04-12-2023 Time 17:59 Sent To  
Notes
2023-04-12 18:00:16NO COMMENTS ON THE PROPSED REPLAT.

Review Stop ENG - PPRC ENGINEERING - PPRC
Rev No 1 Status P Date 03-31-2023 Cont ID  
Sent By rrossano Date 03-31-2023 Time   Rev Time 0.00
Received By   Date 04-13-2023 Time 12:00 Sent To  
Notes
2023-04-06 09:27:27 
  

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status P Date 04-06-2023 Cont ID  
Sent By pleduc Date 04-06-2023 Time   Rev Time 0.00
Received By pleduc Date 04-06-2023 Time 09:26 Sent To  
Notes
2023-04-06 09:28:31FIRE HAS NO OBJECTIONS TO THE PROPOSED AND APPROVES.
  
 FIRE'S APPROVAL OF THIS SUBMITTED PROJECT MAY NOT
 CONSTITUTE IT'S FINAL REVIEW OR APPROVAL.
  
 IF APPLICABLE, FIRE SHALL REVIEW ALL SUBMITTED PROJECT
 PLANS AT THE APPLICABLE TIME AND IN ACCORDANCE WITH THE
 REQUIREMENTS OF ALL APPLICABLE FIRE CODES AND
 STANDARDS.
  
 PETER LEDUC
 FIRE MARSHAL
 561-804-4709
 [email protected]

Review Stop PU PUBLIC UTILITIES
Rev No 1 Status P Date 04-13-2023 Cont ID  
Sent By relizond Date 04-13-2023 Time 11:40 Rev Time 0.00
Received By relizond Date 04-13-2023 Time 11:40 Sent To  
Notes
***NONE***

Review Stop PU-CS PUBLIC UTILITIES CUSTOMER SRVC
Rev No 1 Status P Date 04-06-2023 Cont ID  
Sent By mhurley Date 04-06-2023 Time 16:39 Rev Time 0.00
Received By mhurley Date   Time   Sent To  
Notes
***NONE***

Review Stop PW PUBLIC WORKS
Rev No 1 Status P Date 04-13-2023 Cont ID  
Sent By   Date 04-13-2023 Time   Rev Time 0.00
Received By jbjoseph Date 04-13-2023 Time 12:01 Sent To  
Notes
2023-04-13 11:57:01PW DOES NOT HAVE ANY COMMENTS AT THIS TIME. NO
 OBJECTIONS TO THE PROPOSED RE-PLAT.
  
 BRUCELY A. JOSEPH
 PW PROGRAM MANAGER
 [email protected]
 561-494-1141

Review Stop STORM STORMWATER
Rev No 1 Status P Date 04-12-2023 Cont ID  
Sent By tward Date 04-12-2023 Time 09:43 Rev Time 0.00
Received By tward Date   Time   Sent To  
Notes
***NONE***

Review Stop SURVEY SURVEYING
Rev No 1 Status F Date 04-10-2023 Cont ID  
Sent By vnoel Date 04-10-2023 Time 11:08 Rev Time 0.00
Received By vnoel Date   Time   Sent To  
Notes
2023-04-10 11:08:35A SEPARATE PLAT COMMENTS LETTER WILL BE ISSUED.
 NOTE: THERE IS AN OVERLAP BETWEEN THIS PROPERTY AND
 BANYAN BLVD. RIGHT-OF-WAY BASED ON PLATTED AND FOUND
 MONUMENTATION. STRONGLY SUGGEST LIDBERG LAND SURVEYING
 MEET WITH BROWN & PHILLIPS/CAULFIELD & WHEELER TO
 DISCUSS.

Review Stop TRAFFIC TRAFFIC ENGINEERING
Rev No 1 Status P Date 04-13-2023 Cont ID  
Sent By   Date 04-13-2023 Time   Rev Time 0.00
Received By   Date 04-13-2023 Time   Sent To  
Notes
2023-04-13 12:27:03NO COMMENTS.
  
 VALERIO ORICCHIO
 CITY TRANSPORTATION ENGINEER
 561-494-1092
 [email protected]
  

Review Stop Z ZONING
Rev No 1 Status F Date 04-11-2023 Cont ID  
Sent By ckimmerl Date 04-11-2023 Time 15:51 Rev Time 0.00
Received By ckimmerl Date 04-11-2023 Time 15:50 Sent To  
Notes
2023-04-11 15:51:071. DURING THE SITE PLAN APPROVAL PROCESS FOR TRANSIT
 VILLAGE, IT WAS DISCUSSED AND REPRESENTED ON SEVERAL
 PLANS THAT THE FPL EASEMENTS WOULD BE VACATED OR
 ABANDONED, THE PLANS WITHIN THIS SUBJECT REPLAT
 SUBMITTAL INDICATE THAT THESE FPL EASEMENTS REMAIN;
 PLEASE CLARIFY WHAT IS HAPPENING WITH THE FPL EASEMENTS
 AND POLE LOCATIONS.
  
  
  
 CHRIS KIMMERLY, AICP
 URBAN DESIGN PLANNER
 561-822-1426 [email protected]

  Print


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved