Plan Review Details - Project Z22060006
| Plan Review Stops For Project Z22060006 |
| Review Stop |
AIPP |
ART IN PUBLIC PLACES |
| Rev No |
1 |
Status |
P |
Date |
08-08-2022 |
|
|
Cont ID |
|
| Sent By |
scwelter |
Date |
08-02-2022 |
Time |
11:03 |
Rev Time |
0.00 |
| Received By |
scwelter |
Date |
08-08-2022 |
Time |
14:17 |
Sent To |
|
|
| Notes |
| 2022-08-02 11:13:39 | DEVELOPER SUBMITTED ART ASSESSMENT APPLICATION OPTION 2 | | | - CONTRIBUTION TO THE PUBLIC ART ACCOUNT. SITE PLAN | | | APPROVAL PASSED. 8.8.2022 | | | | | | | | | ON THE SITE PLAN, EVEN THOUGH IT IS A MINOR AMENDMENT | | | AND TO SATISFY THE PUBLIC ART REQUIREMENT, NEEDS TO | | | STATE/SHOW WHERE ART WILL BE INTEGRATED OR THE | | | APPLICANT MUST STATE THAT THEY WILL CONTRIBUTE TO THE | | | PUBLIC ART FUND. EITHER CHOICE MUST BE PROVIDED FOR | | | SITE PLAN APPROVAL. | | | | | | PLEASE EMAIL [email protected] I WILL PROVIDE AN ART | | | ASSESSMENT APPLICATION, AND COPY [email protected] | | | FOR FURTHER QUESTIONS CONTACT SYBILLE WELTER, | | | ADMINISTRATOR OF PUBLIC ART AND CULTURE | | | [email protected] | | | |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
1 |
Status |
P |
Date |
03-10-2023 |
|
|
Cont ID |
|
| Sent By |
rbrown |
Date |
03-10-2023 |
Time |
18:59 |
Rev Time |
0.00 |
| Received By |
rbrown |
Date |
03-10-2023 |
Time |
18:59 |
Sent To |
|
|
| Notes |
| 2023-03-10 18:59:23 | DEVELOPMENT SERVICES DEPARTMENT, BUILDING DIVISION, | | | COMMENTS: | | | | | | 1. THIS REVIEW IS A CURSORY REVIEW AS IT RELATES TO THE | | | SITE. IT IS NOT A REVIEW FOR FULL COMPLIANCE WITH | | | FLORIDA BUILDING CODE. THE FOLLOWING COMMENTS ARE TO BE | | | ADDRESSED FOR THE BUILDING PERMIT APPLICATION. | | | | | | 2. FLOOD ZONE. ACCORDING TO THE ADOPTED FLOOD INSURANCE | | | RATE MAPS (FIRMS), THE PROPOSED BUILDING IS IN FLOOD | | | ZONE AE, WITH A BASE FLOOD ELEVATION OF 12.7 FT NAVD. | | | THE FIRST FLOOR OF THE BUILDING AND ALL ASSOCIATED | | | MECHANICAL EQUIPMENT (CHILLERS, GENERATORS ETC.) SHALL | | | BE 24 INCHES (FREEBOARD) ABOVE THE BASE FLOOD | | | ELEVATION. | | | | | | 3. ELECTRIC VEHICLE CHARGING STATION. IF ELECTRIC | | | VEHICLE (EV) CHARGING STATIONS ARE PROVIDED AT LEAST 1 | | | IN 25 MUST COMPLY WITH ACCESSIBLE PARKING SPACE | | | REQUIREMENTS. | | | | | | 4. BUILDING SIZE. WHEN SUBMITTED FOR BUILDING PERMIT, | | | THE PLANS SHALL SHOW THAT THE TYPE OF CONSTRUCTION FOR | | | THE BUILDINGS WILL BE IN ACCORDANCE WITH THE HEIGHT, | | | AREA AND OCCUPANCY LIMITATIONS IN CHAPTER 5 OF THE | | | FLORIDA BUILDING CODE. | | | | | | 5. ENCLOSED PARKING GARAGES. IF THE PARKING GARAGE DOES | | | NOT HAVE WALL OPENINGS, OR SUFFICIENT WALL OPENINGS TO | | | MEET THE DEFINITION OF AN OPEN PARKING GARAGE, IT WILL | | | BE CONSIDERED AN ENCLOSED PARKING GARAGE AND MUST HAVE | | | EXHAUST SYSTEMS. THE EXHAUST SYSTEMS SHALL BE DESIGNED | | | TO MINIMIZE NOISE LEVELS USING INLINE FAN SILENCERS OR | | | OTHER APPROVED METHODS. | | | | | | 6. SEPARATE PERMITS REQUIRED. ALL APPLICABLE PERMITS | | | AND SUB-PERMITS MUST BE OBTAINED BEFORE COMMENCING THE | | | WORK. SEPARATE PERMITS, PLANS AND FEES, ARE REQUIRED | | | FOR SIGNS, SWIMMING POOLS AND SPAS, GAS SYSTEMS, | | | GENERATORS, FIRE ALARM SYSTEMS, FIRE SPRINKLER AND | | | OTHER FIRE SUPPRESSION SYSTEMS, GREASE INTERCEPTORS, | | | SITE LIGHTING, SITE LANDSCAPE, SITE IRRIGATION, ETC. | | | | | | 7. CONTRACTOR VEHICLE PARKING. PROPERTY OWNER AND | | | CONTRACTOR SHALL MAKE ARRANGEMENTS FOR PARKING OF | | | CONTRACTOR VEHICLES TO MINIMIZE THE IMPACT ON ALL | | | NEIGHBORING PROPERTIES. | | | | | | 8. PROTECTION OF NEIGHBORING PROPERTY. PROPERTY OWNER | | | AND CONTRACTOR SHALL PROTECT ALL NEIGHBORING PROPERTY, | | | INCLUDING VEHICLES, FROM DAMAGE OR DIRT CAUSED BY THE | | | CONSTRUCTION, AND SHALL NOTIFY THE OCCUPANTS OF | | | NEIGHBORING PROPERTIES ABOUT ALL STAGES OF CONSTRUCTION | | | THAT MAY AFFECT THE USE OF THEIR PROPERTY. | | | | | | 9. BUILDING ADDRESS. EACH SEPARATE BUILDING, AND UNIT | | | WITH AN INDEPENDENT ENTRANCE FROM THE STREET, SHALL | | | HAVE A SEPARATE ADDRESS ASSIGNED BASED ON THE LOCATION | | | OF THE BUILDING ENTRANCE. FOR STREET ADDRESSING, | | | CONTACT CAROLINE PUELL, ADDRESSING COORDINATOR, AT | | | (561) 805 6659, OR BY EMAIL: [email protected] | | | | | | 10. ART IN PUBLIC PLACES. THIS PROJECT WILL BE SUBJECT | | | TO ART LIFE ASSESSMENT UNDER THE CITY OF WEST PALM | | | BEACH ART IN PUBLIC PLACES (AIPP) PROGRAM. FOR ADVICE | | | ON THE PROVISION OF PUBLIC ARTWORK IN LIEU OF THE AIPP | | | ASSESSMENT, CONTACT SYBILLE WELTER, ART IN PUBLIC | | | PLACES COORDINATOR, AT (561) 822-1521, OR BY EMAIL: | | | [email protected] | | | | | | ROBERT BROWN | | | BUILDING OFFICIAL | | | TEL: 561 805 6652 | | | EMAIL: [email protected] | | | |
|
|
| Review Stop |
ENG - PPRC |
ENGINEERING - PPRC |
| Rev No |
3 |
Status |
P |
Date |
12-30-2022 |
|
|
Cont ID |
|
| Sent By |
rrossano |
Date |
12-30-2022 |
Time |
|
Rev Time |
0.00 |
| Received By |
rrossano |
Date |
12-30-2022 |
Time |
|
Sent To |
|
|
| Notes |
|
|
| Review Stop |
ENG - PPRC |
ENGINEERING - PPRC |
| Rev No |
2 |
Status |
F |
Date |
10-26-2022 |
|
|
Cont ID |
|
| Sent By |
rrossano |
Date |
10-26-2022 |
Time |
|
Rev Time |
0.00 |
| Received By |
rrossano |
Date |
10-26-2022 |
Time |
|
Sent To |
|
|
| Notes |
| 2022-10-26 08:41:05 | COMMENTS FROM RICK ROSSANO, SENIOR PROJECT COORDINATOR, | | | ENGINEERING SERVICES AT 561-494-1098 [email protected] | | | | | | 1. PREVIOUS COMMENT: INDICATE IMPACT ON EXISTING | | | ENGINEERING PROJECT E21080013. (PROVIDE SUMMARY OF | | | IMPACT. ARE METER LOCATIONS CHANGING, ETC. WHAT IMPACTS | | | WILL AFFECT UTILITIES?) | | | | | | 2. COMMENTS 2-11 UNDER ENGINEERING RESPONSES WERE NOT | | | ISSUED BY ME. NOT SURE WHERE THEY CAME FROM. PLEASE | | | CLARIFY. | | | |
|
|
| Review Stop |
ENG - PPRC |
ENGINEERING - PPRC |
| Rev No |
1 |
Status |
F |
Date |
07-20-2022 |
|
|
Cont ID |
|
| Sent By |
RROSSANO |
Date |
07-20-2022 |
Time |
|
Rev Time |
|
| Received By |
rrossano |
Date |
07-20-2022 |
Time |
|
Sent To |
|
|
| Notes |
| 2022-07-20 12:02:32 | PLEASE PROVIDE SUMMARY OF IMPACT TO EXISTING | | | ENGINEERING PROJECT E21080013. PLANS WILL NEED TO BE | | | UPDATED ACCORDINGLY ONCE SITE PLAN REVISION IS | | | APPROVED. | | | | | | RICK ROSSANO, SR. PROJECT COORDINATOR, ENGINEERING | | | SERVICES AT 561-494-1098 [email protected] |
|
|
| Review Stop |
FIRE |
FIRE DEPARTMENT |
| Rev No |
1 |
Status |
P |
Date |
07-27-2022 |
|
|
Cont ID |
|
| Sent By |
pleduc |
Date |
07-27-2022 |
Time |
|
Rev Time |
0.00 |
| Received By |
pleduc |
Date |
07-27-2022 |
Time |
15:29 |
Sent To |
|
|
| Notes |
| 2022-07-27 15:29:48 | FIRE HAS NO OBJECTIONS TO THE PROPOSED AND APPROVES. | | | | | | FIRE'S APPROVAL OF THIS SUBMITTED PROJECT MAY NOT | | | CONSTITUTE IT'S FINAL REVIEW OR APPROVAL. | | | | | | FIRE SHALL REVIEW ALL SUBMITTED BUILDING PLANS AT THE | | | APPROPRIATE TIME AND IN ACCORDANCE WITH THE | | | REQUIREMENTS OF ALL APPLICABLE FIRE CODES AND | | | STANDARDS. | | | | | | PETER LEDUC | | | FIRE MARSHAL | | | 561-804-4709 | | | [email protected] |
|
|
| Review Stop |
L |
LANDSCAPING |
| Rev No |
3 |
Status |
F |
Date |
03-13-2023 |
|
|
Cont ID |
|
| Sent By |
rcaranci |
Date |
02-07-2023 |
Time |
15:04 |
Rev Time |
0.00 |
| Received By |
rcaranci |
Date |
02-07-2023 |
Time |
15:04 |
Sent To |
|
|
| Notes |
| 2023-03-13 15:05:12 | FROM: RAY CARANCI, SENIOR LANDSCAPE PLANNER | | | 561-822-1462 | | | PROJECT: 1415 (1885) CENTREPARK Z23010013 PB791NN | | | (Z22060006 PB791LL) | | | FEBRUARY 7, 2023 | | | I HAVE REVIEWED THE ABOVE REFERENCED PETITION, AND | | | PROVIDE THE FOLLOWING COMMENTS: | | | | | | | | | 1. CHANGES MUST BE CLOUDED ON THE LANDSCAPE PLANS TO | | | INDICATE WHAT IS PROPOSED WHEN COMPARED TO THE APPROVED | | | PLANS. | | | | | | 2. PROVIDE A LANDSCAPE REQUIREMENTS CHART REFLECTING | | | THE PROPOSED CHANGES AND A FINAL PLANT LIST AS SHOWN ON | | | THE APPROVED PLANS. | | | | | | 3. PARTIALLY SATISFIED. ON THE LANDSCAPE REQUIREMENTS | | | CHART, CORRECT THE SITE LANDSCAPE CALCULATIONS TO SHOW | | | THE SHADE TREE AND FLOWERING TREE CALCULATIONS BASED ON | | | 40 PERCENT REQUIRED OPEN SPACE PER CPD ZONING, AND THEN | | | ADD THE MULTIFAMILY TREES TO ACHIEVE THE TOTAL TREES | | | REQUIRED. THEN SHOW PROVIDED NUMBER OF TREES ON SITE. | | | ONCE ANY TREE PLANTING PLAN FOR THE POA PARCELS HAS | | | BEEN FINALIZED AND SUBMITTED FOR REVIEW, THE FINAL | | | COUNT OF DEFICIENT TREES SHALL BE DETERMINED. THE | | | WAIVER FOR THE OPEN SPACE DOES NOT AFFECT THE | | | CALCULATIONS FOR REQUIRED OPEN SPACE TREES, FLOWERING | | | TREES AND SHRUBS. | | | PROVIDE A FINAL TALLY OF THE TREE COUNTS AS SHOWN IN | | | THE PROJECT TREES CHART ON SHEET LP-7 OF THE APPROVED | | | PLANS. | | | 2/7/23 THE JUSTIFICATION STATEMENT FOR THE ADDITION OF | | | UNITS STATES THE NUMBER OF TREES THAT WILL BE PLANTED | | | OFF SITE, BUT THE PLANS DO NOT SHOW THE BREAKDOWN OF | | | THE NUMBER OF TREES PROVIDED AND THEIR LOCATIONS. THIS | | | MUST BE CLEARLY PROVIDED ON THE PLANS. | | | | | | | | | 4. SATISFIED. TREES PROPOSED ON PARCEL 4 CANNOT BE | | | COUNTED TOWARD THE REQUIREMENTS FOR THIS LOT. SHOW THE | | | OFFSITE TREES RELATED TO THE RECONFIGURATION OF THE | | | EXISTING PARKING AREA AS A SEPARATE PLAN AND PLANT | | | LIST. ADDRESS ALL MISSING PARKING AREA TREES IN | | | TERMINAL ISLANDS. | | | THIS IS A SEPARATE PARCEL, SO WILL REQUIRE AN AMENDMENT | | | TO THAT PARCEL???S APPROVED SITE PLAN AND LANDSCAPE | | | PLAN. PLACEMENT OF UTILITY LINES FOR THE PROPOSED SITE | | | WITHIN THIS PARKING AREA CREATES NONCONFORMING | | | LANDSCAPE AREAS BY DISPLACING REQUIRED TREES. | | | | | | 5. PARTIALLY SATISFIED. THE SEWER LINE SHOWN IN THE | | | PARKING AREA OF PARCEL 4 CUTS THROUGH THE LANDSCAPE | | | ISLAND IN CONFLICT WITH THE REQUIRED TREE. THIS NEEDS | | | TO BE RELOCATED TO AVOID THE LANDSCAPE AREA. | | | | | | 6. NOT SATISFIED. THE WATER AND FIRE LINES HAVE BEEN | | | MOVED BACK ONTO PARCEL 4 IN CONFLICT WITH LANDSCAPING. | | | THIS NEEDS TO BE RESOLVED. | | | 2/7/23 PLACEMENT OF WATER METER ON CIVIL PLAN SHEET IS | | | IN CONFLICT WITH LANDSCAPING ON SHEET LP.5. | | | | | | | | | | | | 7. SATISFIED. THE APPROVED LITTORAL PLANTING PLAN SHOWS | | | AREAS WITH EACH SPECIES AS A GROUP. THE PROPOSED LAYERS | | | OF DIFFERENT SPECIES DOES NOT WORK FOR ESTABLISHING | | | PLANTINGS. | | | THE LITTORAL PLANTINGS ARE REFERENCED TO BE SHOWN ON | | | SHEET LP-6 BUT ARE NOT FULLY SHOWN. | | | | | | RESOLUTION NO. 97-17 | | | | | | 8. PARTIALLY SATISFIED. PER EXHIBIT F, APPROVAL FROM | | | THE ARCHITECTURAL REVIEW BOARD MUST BE PROVIDED FOR THE | | | LANDSCAPE AND IRRIGATION PROPOSED. | | | THIS NEEDS TO BE CLARIFIED WHEN APPROVAL WILL BE | | | PROVIDED FOR THE PROPOSED CHANGES TO THE PLANS. | | | | | | 9. PARTIALLY SATISFIED. SHOW LOCATION OF PUMP EQUIPMENT | | | AND SOURCE FOR THE IRRIGATION SYSTEM TO MEET CONDITION | | | #11 REQUIRING USE OF SURFACE WATER FROM LAKES. | | | A NOTE ON SHEET LP.4 READS: ALL IRRIGATION ON THIS | | | LEVEL SHALL BE PROVIDED USING POTABLE WATER. EXPLAIN | | | HOW THIS IS AN EXCEPTION TO THE REQUIREMENT. | | | | | | ADDITIONAL COMMENTS 2/7/23: | | | | | | 10. SITE PLAN SHEET SP-1 DOES NOT MATCH CIVIL OR | | | LANDSCAPE PLANS WITH THE SAME REVISION DATE. PARKING ON | | | 4N IS DIFFERENT. SIGN IN ENTRANCE MEDIAN IS NOT SHOWN | | | ON LANDSCAPE PLAN. | | | | | | CONDITIONS OF APPROVAL | | | 1. PRIOR TO THE REMOVAL OR RELOCATION OF ANY TREES ON | | | THE PROPERTY, A TREE ALTERATION PERMIT SHALL BE | | | SUBMITTED, REVIEWED AND APPROVED BY THE DEVELOPMENT | | | SERVICES DEPARTMENT, PLANNING DIVISION. | | | |
|
|
| Review Stop |
L |
LANDSCAPING |
| Rev No |
2 |
Status |
F |
Date |
11-17-2022 |
|
|
Cont ID |
|
| Sent By |
rcaranci |
Date |
11-17-2022 |
Time |
11:23 |
Rev Time |
0.00 |
| Received By |
rcaranci |
Date |
11-17-2022 |
Time |
11:23 |
Sent To |
|
|
| Notes |
| 2022-11-17 11:23:22 | FROM: RAY CARANCI, SENIOR LANDSCAPE PLANNER | | | 561-822-1462 | | | PROJECT: 1415 (1885) CENTREPARK Z22060006 | | | NOVEMBER 16, 2022 | | | I HAVE REVIEWED THE ABOVE REFERENCED PETITION, AND | | | PROVIDE THE FOLLOWING COMMENTS: | | | | | | | | | 1. SATISFIED. CHANGES MUST BE CLOUDED ON THE LANDSCAPE | | | PLANS TO INDICATE WHAT IS PROPOSED WHEN COMPARED TO THE | | | APPROVED PLANS. | | | | | | 2. SATISFIED. PROVIDE A LANDSCAPE REQUIREMENTS CHART | | | REFLECTING THE PROPOSED CHANGES AND A FINAL PLANT LIST | | | AS SHOWN ON THE APPROVED PLANS. | | | | | | 3. PARTIALLY SATISFIED. ON THE LANDSCAPE REQUIREMENTS | | | CHART, CORRECT THE SITE LANDSCAPE CALCULATIONS TO SHOW | | | THE SHADE TREE AND FLOWERING TREE CALCULATIONS BASED ON | | | 40 PERCENT REQUIRED OPEN SPACE PER CPD ZONING, AND THEN | | | ADD THE MULTIFAMILY TREES TO ACHIEVE THE TOTAL TREES | | | REQUIRED. THEN SHOW PROVIDED NUMBER OF TREES ON SITE. | | | ONCE ANY TREE PLANTING PLAN FOR THE POA PARCELS HAS | | | BEEN FINALIZED AND SUBMITTED FOR REVIEW, THE FINAL | | | COUNT OF DEFICIENT TREES SHALL BE DETERMINED. THE | | | WAIVER FOR THE OPEN SPACE DOES NOT AFFECT THE | | | CALCULATIONS FOR REQUIRED OPEN SPACE TREES, FLOWERING | | | TREES AND SHRUBS. | | | PROVIDE A FINAL TALLY OF THE TREE COUNTS AS SHOWN IN | | | THE PROJECT TREES CHART ON SHEET LP-7 OF THE APPROVED | | | PLANS. | | | | | | | | | 4. SATISFIED. TREES PROPOSED ON PARCEL 4 CANNOT BE | | | COUNTED TOWARD THE REQUIREMENTS FOR THIS LOT. SHOW THE | | | OFFSITE TREES RELATED TO THE RECONFIGURATION OF THE | | | EXISTING PARKING AREA AS A SEPARATE PLAN AND PLANT | | | LIST. ADDRESS ALL MISSING PARKING AREA TREES IN | | | TERMINAL ISLANDS. | | | THIS IS A SEPARATE PARCEL, SO WILL REQUIRE AN AMENDMENT | | | TO THAT PARCEL???S APPROVED SITE PLAN AND LANDSCAPE | | | PLAN. PLACEMENT OF UTILITY LINES FOR THE PROPOSED SITE | | | WITHIN THIS PARKING AREA CREATES NONCONFORMING | | | LANDSCAPE AREAS BY DISPLACING REQUIRED TREES. | | | | | | 5. SATISFIED. THE SEWER LINE SHOWN IN THE PARKING AREA | | | OF PARCEL 4 CUTS THROUGH THE LANDSCAPE ISLAND IN | | | CONFLICT WITH THE REQUIRED TREE. THIS NEEDS TO BE | | | RELOCATED TO AVOID THE LANDSCAPE AREA. | | | | | | 6. SATISFIED. THE WATER AND FIRE LINES HAVE BEEN MOVED | | | BACK ONTO PARCEL 4 IN CONFLICT WITH LANDSCAPING. THIS | | | NEEDS TO BE RESOLVED. | | | | | | 7. PARTIALLY SATISFIED. THE APPROVED LITTORAL PLANTING | | | PLAN SHOWS AREAS WITH EACH SPECIES AS A GROUP. THE | | | PROPOSED LAYERS OF DIFFERENT SPECIES DOES NOT WORK FOR | | | ESTABLISHING PLANTINGS. | | | THE LITTORAL PLANTINGS ARE REFERENCED TO BE SHOWN ON | | | SHEET LP-6 BUT ARE NOT FULLY SHOWN. | | | | | | RESOLUTION NO. 97-17 | | | | | | 8. PARTIALLY SATISFIED. PER EXHIBIT F, APPROVAL FROM | | | THE ARCHITECTURAL REVIEW BOARD MUST BE PROVIDED FOR THE | | | LANDSCAPE AND IRRIGATION PROPOSED. | | | THIS NEEDS TO BE CLARIFIED WHEN APPROVAL WILL BE | | | PROVIDED FOR THE PROPOSED CHANGES TO THE PLANS. | | | | | | 9. SATISFIED. SHOW LOCATION OF PUMP EQUIPMENT AND | | | SOURCE FOR THE IRRIGATION SYSTEM TO MEET CONDITION #11 | | | REQUIRING USE OF SURFACE WATER FROM LAKES. | | | | | | CONDITIONS OF APPROVAL | | | 1. PRIOR TO THE REMOVAL OR RELOCATION OF ANY TREES ON | | | THE PROPERTY, A TREE ALTERATION PERMIT SHALL BE | | | SUBMITTED, REVIEWED AND APPROVED BY THE DEVELOPMENT | | | SERVICES DEPARTMENT, PLANNING DIVISION. | | | |
|
|
| Review Stop |
L |
LANDSCAPING |
| Rev No |
1 |
Status |
F |
Date |
08-01-2022 |
|
|
Cont ID |
|
| Sent By |
rcaranci |
Date |
08-01-2022 |
Time |
17:30 |
Rev Time |
0.00 |
| Received By |
rcaranci |
Date |
08-01-2022 |
Time |
17:30 |
Sent To |
|
|
| Notes |
| 2022-08-01 17:30:41 | FROM: RAY CARANCI, SENIOR LANDSCAPE PLANNER | | | 561-822-1462 | | | PROJECT: 1885 CENTREPARK Z22060006 | | | AUGUST 1, 2022 | | | I HAVE REVIEWED THE ABOVE REFERENCED PETITION, AND | | | PROVIDE THE FOLLOWING COMMENTS: | | | | | | | | | 1. CHANGES MUST BE CLOUDED ON THE LANDSCAPE PLANS TO | | | INDICATE WHAT IS PROPOSED WHEN COMPARED TO THE APPROVED | | | PLANS. | | | | | | 2. PROVIDE A LANDSCAPE REQUIREMENTS CHART REFLECTING | | | THE PROPOSED CHANGES AND A FINAL PLANT LIST AS SHOWN ON | | | THE APPROVED PLANS. | | | | | | 3. ON THE LANDSCAPE REQUIREMENTS CHART, CORRECT THE | | | SITE LANDSCAPE CALCULATIONS TO SHOW THE SHADE TREE AND | | | FLOWERING TREE CALCULATIONS BASED ON 40 PERCENT | | | REQUIRED OPEN SPACE PER CPD ZONING, AND THEN ADD THE | | | MULTIFAMILY TREES TO ACHIEVE THE TOTAL TREES REQUIRED. | | | THEN SHOW PROVIDED NUMBER OF TREES ON SITE. ONCE ANY | | | TREE PLANTING PLAN FOR THE POA PARCELS HAS BEEN | | | FINALIZED AND SUBMITTED FOR REVIEW, THE FINAL COUNT OF | | | DEFICIENT TREES SHALL BE DETERMINED. THE WAIVER FOR THE | | | OPEN SPACE DOES NOT AFFECT THE CALCULATIONS FOR | | | REQUIRED OPEN SPACE TREES, FLOWERING TREES AND SHRUBS. | | | | | | 4. TREES PROPOSED ON PARCEL 4 CANNOT BE COUNTED TOWARD | | | THE REQUIREMENTS FOR THIS LOT. SHOW THE OFFSITE TREES | | | RELATED TO THE RECONFIGURATION OF THE EXISTING PARKING | | | AREA AS A SEPARATE PLAN AND PLANT LIST. ADDRESS ALL | | | MISSING PARKING AREA TREES IN TERMINAL ISLANDS. | | | THIS IS A SEPARATE PARCEL, SO WILL REQUIRE AN AMENDMENT | | | TO THAT PARCEL?S APPROVED SITE PLAN AND LANDSCAPE PLAN. | | | PLACEMENT OF UTILITY LINES FOR THE PROPOSED SITE WITHIN | | | THIS PARKING AREA CREATES NONCONFORMING LANDSCAPE AREAS | | | BY DISPLACING REQUIRED TREES. | | | | | | 5. THE SEWER LINE SHOWN IN THE PARKING AREA OF PARCEL 4 | | | CUTS THROUGH THE LANDSCAPE ISLAND IN CONFLICT WITH THE | | | REQUIRED TREE. THIS NEEDS TO BE RELOCATED TO AVOID THE | | | LANDSCAPE AREA. | | | | | | 6. THE WATER AND FIRE LINES HAVE BEEN MOVED BACK ONTO | | | PARCEL 4 IN CONFLICT WITH LANDSCAPING. THIS NEEDS TO BE | | | RESOLVED. | | | | | | 7. THE APPROVED LITTORAL PLANTING PLAN SHOWS AREAS WITH | | | EACH SPECIES AS A GROUP. THE PROPOSED LAYERS OF | | | DIFFERENT SPECIES DOES NOT WORK FOR ESTABLISHING | | | PLANTINGS. | | | | | | | | | | | | | | | RESOLUTION NO. 97-17 | | | | | | 8. PER EXHIBIT F, APPROVAL FROM THE ARCHITECTURAL | | | REVIEW BOARD MUST BE PROVIDED FOR THE LANDSCAPE AND | | | IRRIGATION PROPOSED. | | | | | | 9. SHOW LOCATION OF PUMP EQUIPMENT AND SOURCE FOR THE | | | IRRIGATION SYSTEM TO MEET CONDITION #11 REQUIRING USE | | | OF SURFACE WATER FROM LAKES. | | | | | | CONDITIONS OF APPROVAL | | | 1. PRIOR TO THE REMOVAL OR RELOCATION OF ANY TREES ON | | | THE PROPERTY, A TREE ALTERATION PERMIT SHALL BE | | | SUBMITTED, REVIEWED AND APPROVED BY THE DEVELOPMENT | | | SERVICES DEPARTMENT, PLANNING DIVISION. | | | |
|
|
| Review Stop |
PU |
PUBLIC UTILITIES |
| Rev No |
1 |
Status |
P |
Date |
08-16-2022 |
|
|
Cont ID |
|
| Sent By |
jroach |
Date |
08-16-2022 |
Time |
13:33 |
Rev Time |
0.00 |
| Received By |
jroach |
Date |
08-16-2022 |
Time |
13:33 |
Sent To |
|
|
| Notes |
| 2022-08-16 13:35:10 | NO COMMENT, PER EMAIL FROM MICHAEL TECHNOW, PROJECT | | | ENGINEER - PUBLIC UTILITIES DEPARTMENT, DATED AUGUST | | | 16, 2022. | | | ________________________________________ | | | | | | QUESTIONS/COMMENTS, PLEASE CONTACT THE FOLLOWING: | | | | | | JOHN P. ROACH, AICP, PRINCIPAL PLANNER | | | CITY OF WEST PALM BEACH | | | DEVELOPMENT SERVICES DEPARTMENT ? PLANNING DIVISION | | | 401 CLEMATIS STREET - P.O. BOX 3147 | | | WEST PALM BEACH, FLORIDA 33402 | | | | | | P: 561.822.1448 | | | TTY: 800.955.8771 | | | E: [email protected] | | | | | | W: WPB.ORG |
|
|
| Review Stop |
PU-CS |
PUBLIC UTILITIES CUSTOMER SRVC |
| Rev No |
2 |
Status |
P |
Date |
11-18-2022 |
|
|
Cont ID |
|
| Sent By |
mhurley |
Date |
11-18-2022 |
Time |
14:22 |
Rev Time |
0.00 |
| Received By |
mhurley |
Date |
|
Time |
|
Sent To |
|
|
| Notes |
| 2022-11-18 14:22:00 | -CIVIL PLANS AND LANDSCAPING PLANS SEEM TO SHOW | | | ABOVE-GROUND WATER METER BLOCKING A SIDEWALK. CORRECT | | | IN REVISED ENGINEERING SUBMITTAL. | | | -RESPONSE LETTER SAID SURVEY WAS UPDATED BUT IT WAS NOT | | | IN SUBMITTAL PACKAGE. INCLUDE COPY IN NEXT ENGINEERING | | | PROJECT RESUBMITTAL. | | | -MAY NEED ADDITIONAL UTILITY EASEMENTS. | | | -REMINDER TO REVISE ENGINEERING SUBMITTAL AS INDICATED | | | IN RESPONSE LETTER. | | | RESPECTFULLY, | | | MARK HURLEY [email protected] |
|
|
| Review Stop |
PU-CS |
PUBLIC UTILITIES CUSTOMER SRVC |
| Rev No |
1 |
Status |
F |
Date |
07-15-2022 |
|
|
Cont ID |
|
| Sent By |
mhurley |
Date |
07-15-2022 |
Time |
16:54 |
Rev Time |
0.00 |
| Received By |
mhurley |
Date |
07-15-2022 |
Time |
|
Sent To |
|
|
| Notes |
| 2022-07-15 16:54:19 | PLEASE PROVIDE WRITTEN RESPONSES TO THE FOLLOWING: | | | | | | -PRIOR REVIEW COMMENT FOR THE PROJECT: THE FORCE MAIN | | | EASEMENT IS NOT SHOWN ON THE PLAN SHEETS. PLEASE SHOW | | | AND LABEL. MAR2022 RESPONSE: IT HAS BEEN REQUESTED FOR | | | THE SURVEYOR TO PICK UP THE EXISTING FORCE MAIN | | | EASEMENT. WE HAVE NOT RECEIVED UPDATED SURVEY BACK YET | | | AND WILL UPDATE OUR PLANS ONCE AVAILABLE. | | | PLEASE UPDATE CIVIL PLANS TO SHOW FORCE MAIN EASEMENT. | | | | | | -PAGE 4 OF MINOR AMENDMENT JUSTIFICATION LETTER | | | MENTIONED PARKING EASEMENTS EXHIBT A PGS 10-12. COULD | | | NOT LOCATE IT IN SUBMITTAL PACKAGE. PLEASE ADD WITH | | | RESUBMITTAL. | | | | | | -PG 6 OF MINOR AMENDMENT JUSTIFICATION LETTER SHOWS | | | PROPOSED GARAGE ENTRANCE FURTHER NORTH, BUT I COULD NOT | | | LOCATE PLANS THAT LOOKED SIMILAR. PLEASE INDICATE IF | | | GARAGE ENTRANCE LOCATION IS CHANGING AND UPDATE EITHER | | | JUSTIFICATION LETTER PICTURE OR PLANS. | | | | | | -WOULD NEED TO UPDATE THE OPEN ENGINEERING DEVELOPMENT | | | PROJECT WITH ANY CHANGES THAT ARE APPROVED. | | | | | | -PRIOR REVIEW COMMENT FOR THE PROJECT: PLAN SAYS THERE | | | IS A CAFE, BUT CANNOT FIND GREASE TRAP. WHERE IS IT | | | INSTALLED AT? MEP. FEB2022 RESPONSE: GREASE TRAP DESIGN | | | IS BEING HANDLED BY THE GREASE TRAP TO BE LOCATED ON | | | SOUTH SIDE OF BUILDING AND LINE IS TO ROUTE BACK | | | THROUGH THE BUILDING TO THE TIE-IN POINT FOR THE | | | SANITARY SERVICE LOCATED AT THE NORTH SIDE OF THE | | | BUILDING NEAR GARAGE. | | | PLEASE VERIFY GREASE TRAP IS STILL GOING TO BE | | | INSTALLED AND INDICATE IF IT WILL BE INSIDE BUILDING OR | | | ON THE OUTSIDE. IF OUTSIDE, PLEASE SHOW AND LABEL ON | | | PLANS. | | | | | | -LP.3 DOES NOT ACCURATELY SHOW UTILITIES. PLEASE UPDATE | | | LP.3 AND VERIFY NO CONFLICTS BETWEEN TREES AND | | | UTILITIES. | | | | | | -THERE WERE TWO PRIOR ACTION ITEMS FOR THE PROJECT AS | | | DESCRIBED IN BELOW COMMENTS AND RESPONSES. HAVE THEY | | | BEEN COMPLETED? ALSO INDICATE IF ANY OF THE PROPOSED | | | BUILDING CHANGES WOUDL CAUSE NEW ENCROACHMENTS. | | | | | | 3. IS IT ALRIGHT FOR RETAINING WALL, SOUTHWEST CORNERS | | | OF BUILDING, AND SIDEWALK TO | | | BE IN 20 FOOT CANAL BUFFER AS SHOWN ON SHEET 4 AND | | | SHEET 5? | | | ATTACHED IS THE CANAL BUFFER SURVEY SHOWING THE | | | ENCROACHMENTS AND THE LETTER | | | SIGNED BY THE DECLARANT ACCEPTING THESE ENCROACHMENTS. | | | DOCUMENTS ARE IN THE | | | PROCESS OF BEING RECORDED. | | | 4. CIVIL PLANS DO NOT SHOW 20 FOOT LAKE EASEMENT THAT | | | IS SHOWN ON SURVEY. PLEASE | | | SHOW AND LABEL IT ON CIVIL PLANS IF STILL THERE. IS IT | | | ALRIGHT FOR RETAINING WALL | | | AND NORTH CORNER OF BUILDING TO BE IN THAT EASEMENT? | | | THE LAKE EASEMENT AND WATER MANAGEMENT TRACT WILL BE | | | REPLATTED TO SO THAT THE WALL | | | AND BUILDING DO NOT ENCROACH INTO THEM. |
|
|
| Review Stop |
PW |
PUBLIC WORKS |
| Rev No |
1 |
Status |
P |
Date |
07-19-2022 |
|
|
Cont ID |
|
| Sent By |
|
Date |
07-19-2022 |
Time |
|
Rev Time |
|
| Received By |
|
Date |
07-19-2022 |
Time |
|
Sent To |
|
|
| Notes |
| 2022-07-19 14:23:32 | NO OBJECTIONS TO THE PROPOSED MINOR AMENDMENT. | | | | | | MATT HEJAZI | | | DEPT OF PUBLIC WORKS | | | [email protected] | | | |
|
|
| Review Stop |
STORM |
STORMWATER |
| Rev No |
1 |
Status |
P |
Date |
08-16-2022 |
|
|
Cont ID |
|
| Sent By |
tward |
Date |
08-16-2022 |
Time |
08:28 |
Rev Time |
0.00 |
| Received By |
tward |
Date |
08-16-2022 |
Time |
08:28 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
SURVEY |
SURVEYING |
| Rev No |
2 |
Status |
F |
Date |
11-21-2022 |
|
|
Cont ID |
|
| Sent By |
vnoel |
Date |
11-21-2022 |
Time |
07:10 |
Rev Time |
0.00 |
| Received By |
vnoel |
Date |
|
Time |
|
Sent To |
|
|
| Notes |
| 2022-11-21 07:11:22 | NO RESPONSE TO PREVIOUS COMMENTS. |
|
|
| Review Stop |
SURVEY |
SURVEYING |
| Rev No |
1 |
Status |
F |
Date |
08-10-2022 |
|
|
Cont ID |
|
| Sent By |
vnoel |
Date |
08-10-2022 |
Time |
10:10 |
Rev Time |
|
| Received By |
vnoel |
Date |
|
Time |
|
Sent To |
|
|
| Notes |
| 2022-08-10 10:20:48 | 1. NEED GRANT OF EASEMENT TO CITY FOR THE EXISTING 12" | | | FORCE MAIN CROSSING PARCELS P AND L. | | | 2, WHAT IS CONTINGENCY PLAN IF CONFLICT EXISTS? | | | RECOMMEND POT HOLING NOW TO DETERMINE DEPTH. |
|
|
| Review Stop |
TRAFFIC |
TRAFFIC ENGINEERING |
| Rev No |
3 |
Status |
P |
Date |
03-15-2023 |
|
|
Cont ID |
|
| Sent By |
|
Date |
03-15-2023 |
Time |
|
Rev Time |
0.00 |
| Received By |
|
Date |
03-15-2023 |
Time |
|
Sent To |
|
|
| Notes |
|
|
| Review Stop |
TRAFFIC |
TRAFFIC ENGINEERING |
| Rev No |
2 |
Status |
F |
Date |
11-08-2022 |
|
|
Cont ID |
|
| Sent By |
|
Date |
11-08-2022 |
Time |
|
Rev Time |
0.00 |
| Received By |
|
Date |
11-08-2022 |
Time |
|
Sent To |
|
|
| Notes |
| 2022-11-08 02:07:00 | 1. NOT SATISFIED. SHOWCASE IN THE SITE PLANS THE BIKE | | | LANE TRANSITION PRIOR TO THE WESTBOUND RIGHT-TURN LANE | | | ON CENTREPARK BLVD. THIS COMMENT WILL BE A CONDITIONAL | | | APPROVAL IF NOT SATISFIED. | | | 2. NOT SATISFIED. SHOWCASE PAVEMENT MARKINGS THAT WOULD | | | SEPARATE BIKE AND TRAVEL LANES ALONG THE WESTBOUND | | | RIGHT-TURN LANE. THIS COMMENT WILL BE A CONDITIONAL | | | APPROVAL IF NOT SATISFIED. | | | 3. SATISFIED. GARAGE ENTRANCE IN THE REVISED SITE PLAN | | | DOES NOT MATCH LATEST ARCHITECTURAL IMAGES | | | 4. SATISFIED. HOW COME THE SIZE OF THE MINIMUM PUBLIC | | | OPEN SPACE, AND THE VARIANCE REQUEST, INCREASES EVEN | | | THOUGH THERE IS A REDUCTION IN NUMBER OF RESIDENTIAL | | | UNITS AND COMMERCIAL SPACE? | | | 5. DUE TO THE CHANGE OF THE GARAGE ENTRY AND LOADING | | | ZONES LOCATION/CONFIGURATION, PROVIDE UPDATED GARAGE | | | FLOOR PLANS. PLEASE PROVIDE DOCUMENT NAME/SHEET NUMBER | | | 6. DUE TO THE CHANGE OF THE GARAGE ENTRY AND LOADING | | | ZONES LOCATION/CONFIGURATION, PROVIDE AN UPDATED | | | AUTOTURN ANALYSIS. PLEASE PROVIDE DOCUMENT NAME/SHEET | | | NUMBER | | | 7. CLEARLY MARK AND DIMENSION EACH OF THE PROPOSED | | | LOADING ZONES | | | 8. FOR EACH GARAGE FLOOR, CLEARLY MARK AND DIMENSION | | | RAMP SLOPES, DRIVE AISLES, PARKING STALLS AND | | | TURN-AROUND SPACES | | | 9. PROVIDE AN UPDATED PARKING TABLE. IF ALREADY | | | SUBMITTED, PLEASE PROVIDE DOCUMENT NAME/SHEET NUMBER | | | 10. PROVIDE A PAVEMENT MARKING AND SIGNAGE PLAN. IF | | | ALREADY SUBMITTED, PLEASE PROVIDE DOCUMENT NAME/SHEET | | | NUMBER | | | 11. PROVIDE A HORIZONTAL CONTROL SITE PLAN. IF ALREADY | | | SUBMITTED, PLEASE PROVIDE DOCUMENT NAME/SHEET NUMBER | | | 12. CLEARLY MARK AND DIMENSION THE TURN-AROUND SPACE(S) | | | AT EACH DEAD-END AISLE OF THE SURFACE PARKING LOT(S) | | | | | | VALERIO ORICCHIO | | | CITY TRANSPORTATION ENGINEER | | | 561-494-1092 | | | [email protected] | | | | | | |
|
|
| Review Stop |
TRAFFIC |
TRAFFIC ENGINEERING |
| Rev No |
1 |
Status |
F |
Date |
07-25-2022 |
|
|
Cont ID |
|
| Sent By |
|
Date |
07-25-2022 |
Time |
|
Rev Time |
|
| Received By |
|
Date |
07-25-2022 |
Time |
|
Sent To |
|
|
| Notes |
| 2022-07-25 12:10:44 | 1. SHOWCASE IN THE SITE PLANS THE BIKE LANE TRANSITION | | | PRIOR TO THE WESTBOUND RIGHT-TURN LANE ON CENTREPARK | | | BLVD | | | 2. SHOWCASE PAVEMENT MARKINGS THAT WOULD SEPARATE BIKE | | | AND TRAVEL LANES ALONG THE WESTBOUND RIGHT-TURN LANE | | | 3. GARAGE ENTRANCE IN THE REVISED SITE PLAN DOES NOT | | | MATCH LATEST ARCHITECTURAL IMAGES | | | 4. HOW COME THE SIZE OF THE MINIMUM PUBLIC OPEN SPACE, | | | AND THE VARIANCE REQUEST, INCREASES EVEN THOUGH THERE | | | IS A REDUCTION IN NUMBER OF RESIDENTIAL UNITS AND | | | COMMERCIAL SPACE? | | | | | | VALERIO ORICCHIO | | | CITY TRANSPORTATION ENGINEER | | | 561-494-1092 | | | [email protected] | | | |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
3 |
Status |
F |
Date |
01-20-2023 |
|
|
Cont ID |
|
| Sent By |
|
Date |
01-20-2023 |
Time |
|
Rev Time |
0.00 |
| Received By |
jroach |
Date |
01-20-2023 |
Time |
15:31 |
Sent To |
|
|
| Notes |
| 2023-01-20 15:56:11 | PLANS AND PLATS REVIEW COMMITTEE (PPRC) ZONING REVIEW | | | ________________________________________ | | | | | | DATE OF REVIEW: 01.20.2023 | | | PROJECT NO.: Z22060006 | | | CASE NO.: PB 791LL | | | ________________________________________ | | | | | | PLEASE PROVIDE A WRITTEN RESPONSE TO THE FOLLOWING | | | REVIEW COMMENTS: | | | | | | 1. NOT SATISFIED - THE SITE DATA TABLE INDICATES THAT | | | FIVE (5) BIKE RACKS ARE BEING PROPOSED ON THE EXTERIOR | | | OF THE BUILDING; PLEASE IDENTIFY THEIR LOCATION AND | | | ENSURE THAT PROPER CLEARANCE IS PROVIDED (AS SHOWN IN | | | THE DETAIL) TO AVOID BLOCKING OF THE SIDEWALK, ETC. | | | | | | 1.1. NOT SATISFIED - THE BIKE RACKS SHOWN ALONG | | | CENTREPARK BOULEVARD DO NOT APPEAR TO PROVIDE THE | | | PROPER CLEARANCE (AS INDICATED IN THE DETAIL) AND WOULD | | | OBSTRUCT CIRCULATION ON THE SIDEWALK. PLEASE ENSURE | | | THAT ALL BIKE RACK LOCATIONS PROVIDE THE PROPER | | | CLEARANCE. | | | | | | 2. SATISFIED - THE WAIVER TABLE SHOULD BE REVISED TO | | | INDICATE: | | | 2.1. SATISFIED - REQUIRED | | | 2.2. SATISFIED - ORIGINALLY PROVIDED | | | 2.3. SATISFIED - APPROVED WAIVER | | | 2.4. SATISFIED - CURRENT PROPOSAL | | | | | | 3. SATISFIED - WHY IS LOT 4N NOT SHOWING ANY PARKING | | | REQUIRED IN THE ?REQUIRED (NON-SHARED) PARKING? TABLE? | | | | | | 4. SATISFIED - REVISED TPS LETTER SHALL BE PROVIDED. | | | | | | 5. SATISFIED - REVISED SCAD APPROVAL REQUIRED. | | | | | | 6. SATISFIED - WHY ARE THERE TWO (2) SITE PLANS LABELED | | | SP1? ONE IS PREPARED BY SCHMIDT NICHOLS, THE OTHER IS | | | PREPARED BY MSA. | | | | | | 6.1. SATISFIED - THERE ARE STILL TWO (2) SITE PLANS, | | | BOTH ARE LABELED SP1. IT IS STRONGLY ENCOURAGED THAT | | | ONLY ONE SITE PLAN BE PROVIDED TO AVOID CONFLICTS, | | | INCONSISTENCIES, ETC. | | | | | | 7. SATISFIED - FLOOR PLANS SHALL BE PROVIDED FOR ALL | | | LEVELS TO CONFIRM UNIT COUNTS, NUMBER OF PARKING | | | SPACES, ETC. | | | | | | 7.1.. SATISFIED - NUMEROUS ARCHITECTURAL SHEETS THAT | | | WERE PROVIDED ARE NOT ASSOCIATED WITH THE SUBJECT | | | PROJECT - THE SHEETS ARE IDENTIFIED AS "THE TROPIC", A | | | PROJECT ON S. FEDERAL HIGHWAY IN HOLLYWOOD. | | | | | | 8. NOT SATISFIED - PLEASE CONFIRM THAT THE SYNTHETIC | | | TURF IS BEING CONSIDERED IMPERVIOUS SURFACE AS REQUIRED | | | BY SECTION 94-451 OF THE CITY?S ZLDRS. | | | | | | 8.1. SATISFIED - IS SYNTHETIC TURF NO LONGER PROPOSED? | | | IT DOES NOT APPEAR TO BE LABELED ON ANY OF THE PLANS | | | OTHER THAN THE SITE PLAN PREPARED BY MSA. PLEASE | | | CONFIRM. | | | | | | 9. SATISFIED - MULTIPLE PORTIONS OF THE BUILDING ARE | | | EXTENDING INTO THE 20 FOOT CANAL BUFFER REQUIRED BY THE | | | DECLARATION OF COVENANTS. PER RESOLUTION NO. 16-21, | | | ?ANY AND ALL MODIFICATIONS TO THE CENTREPARK | | | DECLARATION OF COVENANTS, CONDITIONS AND RESTRICTIONS | | | (ORB 5430 | PG 1548) SHALL BE COMPLETED AND RECORDED IN | | | THE PUBLIC RECORDS OF PALM BEACH COUNTY? PRIOR TO THE | | | ISSUANCE OF A BUILDING PERMIT. PLEASE PROVIDE A STATUS | | | ON SUCH REVISIONS. | | | | | | 9.1. SATISFIED - THERE WAS NO CLEAR RESPONSE PROVIDED | | | TO THIS COMMENT. YOU INDICATED "WE ALLOW PLANTING | | | WITHIN THE CANAL BUFFER" HOWEVER THERE ARE PORTIONS OF | | | THE BUILDING ENCROACHING INTO THE CANAL BUFFER, ETC. | | | | | | 10. SATISFIED - THE AMOUNT OF OPEN SPACE PROVIDED IS | | | INCORRECT IN THE SITE DATA TABLE?IT APPEARS NOT TO HAVE | | | BEEN UPDATED. | | | | | | 11. SATISFIED - THE MONUMENT SIGN CANNOT EXCEED 4 FEET | | | IN HEIGHT BUT SHALL OTHERWISE MEET THE PROVISIONS OF | | | ARTICLE XIII OF THE CITY?S ZLDRS. | | | | | | 11.1. SATISFIED - THE SIGN DETAIL INDICATES 200 SF PER | | | SIGN FACE, BUT THEN ALSO HAS A NOT ABOUT NOT EXCEEDING | | | 16 SF PER SIGN FACE. PER THE ZLDRS, PERMANENT | | | IDENTIFICATION SIGNS FOR RESIDENTIAL DEVELOPMENTS ARE | | | ALLOWED 48 SF PER SIGN FACE IF OVER 50 RESIDENTIAL | | | UNITS. PLEASE CORRECT AND ENSURE CONSISTENCY. | | | | | | 12. SATISFIED - IT APPEARS THAT A NUMBER OF NOTES THAT | | | WERE ON THE PREVIOUSLY-APPROVED SITE PLAN RELATING TO | | | IRRIGATION, PLUMBING FIXTURES, ETC. HAS BEEN REMOVED; | | | PLEASE CLARIFY WHY. | | | | | | 13. NOT SATISFIED - THE PREVIOUSLY-APPROVED SP-3 NEEDS | | | TO BE REVISED. | | | | | | 13.1. NOT SATISFIED - THE RESPONSE TO COMMENTS STATES | | | THAT WITHOUT THE ALTERNATIVES, THIS SHEET IS NO LONGER | | | NEEDED. PLEASE NOTE THAT SP-3 WAS AN OVERALL SITE PLAN | | | SHOWING PARKING COMPLIANCE, ETC. FOR LOT 4 NORTH AND | | | LOT 4 SOUTH AS A COLLECTIVE PARCEL. | | | | | | 14. SATISFIED - IS ALL OF THE INFORMATION ON THE | | | PREVIOUSLY-APPROVED SP-2 NOW LOCATED ON SP-1? | | | | | | 15. SATISFIED - A LABEL FOR THE ?5? LANDSCAPE BUFFER? | | | IS POINTING TO A STAIRWELL IN THE NORTHEAST CORNER OF | | | THE GARAGE. | | | | | | 16. SATISFIED - ADA STRIPING IS BEING SHOWN IN THE | | | LOADING DOCK, GARAGE ENTRY, AND TWO (2) PARKING SPACES | | | NORTH OF THE VAN-ACCESSIBLE PARKING. | | | | | | 16.1. SATISFIED - STRIPING IS STILL SHOWN CONFLICTING | | | WITH THE TWO (2) PARKING SPACES NORTH OF THE | | | VAN-ACCESSIBLE PARKING. | | | | | | 17. NOT SATISFIED - THE BUILDING OUTLINE DOES NOT MATCH | | | THAT SHOWN ON THE FLOOR PLAN, SPECIFICALLY THE | | | SOUTHEAST CORNER OF THE BUILDING. | | | | | | 17.1. NOT SATISFIED - ARE THESE ROOF PROJECTIONS THAT | | | ARE BEING SHOWN? THEY ARE NOT LABELED, DIMENSIONED, | | | ETC. SEE COMMENT #20 BELOW. | | | | | | 18. SATISFIED - IMPROVEMENTS SHOWN ON LOT 2 NORTH | | | (LANDSCAPING, PARKING MODIFICATIONS, ETC.) ? PLEASE | | | PROVIDE AN APPROVAL BY THE PROPERTY OWNER? THE | | | LANDSCAPING SHOWN ON THIS PARCEL SHOULD NOT BE COUNTED | | | TOWARD THE REQUIRED LANDSCAPING OF THE PROPOSED | | | DEVELOPMENT. | | | | | | 19. SATISFIED - THE COLOR ELEVATIONS PROVIDED DO NOT | | | MATCH THE PROPOSED BUILDING. | | | | | | 19.1. SATISFIED - THE COLOR ELEVATIONS PROVIDED WERE | | | INDICATED AS EXHIBIT D WITHIN THE REPSONSE TO COMMENTS; | | | THESE ARE TOO SMALL TO BE REVIEWED. PLEASE PROVIDE | | | FULL-SIZE PDFS, AS DONE PREVIOUSLY. | | | | | | 20. NOT SATISFIED - THERE APPEAR TO BE NUMEROUS | | | ENCROACHMENTS INTO THE SOUTH (CORNER SIDE) SETBACK. | | | STRUCTURAL OVERHANGS, BALCONIES, ETC. ARE ALLOWED TO | | | ENCROACH INTO THE SETBACK, BUT NOT BY MORE THAN THREE | | | (3) FEET. PLEASE DIMENSION ALL ENCROACHMENTS AND ENSURE | | | THEY DO NOT EXCEED THREE (3) FEET. | | | | | | 21. SATISFIED - SHEET LP.2 OF THE LANDSCAPE PLANS | | | STATES THAT SHEET LP.4 SHOULD BE REFERRED TO FOR THE | | | COURTYARD PLANTINGS, HOWEVER IT APPERS THAT THE | | | COURTYARD IS BEING SHOWN ON SHEET LP.3. PLEASE ENSURE | | | THAT ALL REFERENCES ARE CORRECT. | | | | | | ________________________________________ | | | | | | PLEASE NOTE THE FOLLOWING WHEN RESUBMITTING: | | | | | | A) WRITTEN RESPONSES TO COMMENTS MADE BY ALL | | | DEPARTMENTS SHALL BE PROVIDED UPON RESUBMISSION. | | | | | | B) ELECTRONIC COPIES OF REVISED PLANS AND/OR DOCUMENTS | | | SHALL BE PROVIDED. | | | | | | C) PLEASE NOTE THAT RE-SUBMITTALS MAY BE SUBJECT TO | | | ADDITIONAL COMMENTS. | | | | | | D) IF NO RESPONSE IS RECEIVED WITHIN 60 DAYS OF THE | | | ISSUANCE OF THESE COMMENTS, THE APPLICATION WILL BE | | | CONSIDERED WITHDRAWN AND ANY FURTHER ACTION WILL | | | REQUIRE SUBMISSION OF A NEW DEVELOPMENT APPLICATION. | | | | | | E) PLEASE NOTE THAT YOU WILL BE PERMITTED ONE (1) | | | RESUBMITTAL AT NO ADDITIONAL COST. IF PREVIOUSLY-ISSUED | | | COMMENTS CONTINUE TO NOT BE SUFFICIENTLY ADDRESSED, THE | | | APPLICANT WILL BE ACCESSED A RESUBMITTAL FEE. SUCH FEE | | | WILL BE 20% OF THE ORIGINAL APPLICATION FEE. | | | ________________________________________ | | | | | | QUESTIONS/COMMENTS, PLEASE CONTACT THE FOLLOWING: | | | | | | JOHN P. ROACH, AICP, PRINCIPAL PLANNER | | | CITY OF WEST PALM BEACH | | | DEVELOPMENT SERVICES DEPARTMENT ? PLANNING DIVISION | | | 401 CLEMATIS STREET - P.O. BOX 3147 | | | WEST PALM BEACH, FLORIDA 33402 | | | | | | P: 561.822.1448 | | | TTY: 800.955.8771 | | | E: [email protected] | | | | | | W: WPB.ORG |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
2 |
Status |
F |
Date |
11-18-2022 |
|
|
Cont ID |
|
| Sent By |
jroach |
Date |
11-18-2022 |
Time |
12:27 |
Rev Time |
0.00 |
| Received By |
jroach |
Date |
11-18-2022 |
Time |
12:27 |
Sent To |
|
|
| Notes |
| 2022-11-18 12:26:50 | PLANS AND PLATS REVIEW COMMITTEE (PPRC) ZONING REVIEW | | | ________________________________________ | | | | | | DATE OF REVIEW: 11.18.2022 | | | PROJECT NO.: Z22060006 | | | CASE NO.: PB 791LL | | | ________________________________________ | | | | | | PLEASE PROVIDE A WRITTEN RESPONSE TO THE FOLLOWING | | | REVIEW COMMENTS: | | | | | | IMPORTANT: THE RESPONSE TO COMMENTS PROVIDED DOES NOT | | | APPEAR TO CORRESPOND EXACTLY WITH THE COMMENTS ISSUED. | | | THE COMMENT NUMBERS DIFFER, THERE ARE RESPONSES TO | | | COMMENTS THAT AREN'T EVEN INCLUDED IN MY 8/1/22 PLAN | | | REVIEW, ETC. PLEASE CLARIFY. THE RESPONSES SHOULD | | | CLEARLY MATCH THE COMMENTS ISSUED INCLUDING COMMENT | | | NUMBERS. | | | | | | 1. NOT SATISFIED - THE SITE DATA TABLE INDICATES THAT | | | FIVE (5) BIKE RACKS ARE BEING PROPOSED ON THE EXTERIOR | | | OF THE BUILDING; PLEASE IDENTIFY THEIR LOCATION AND | | | ENSURE THAT PROPER CLEARANCE IS PROVIDED (AS SHOWN IN | | | THE DETAIL) TO AVOID BLOCKING OF THE SIDEWALK, ETC. | | | | | | 1.1. NEW COMMENT - THE BIKE RACKS SHOWN ALONG | | | CENTREPARK BOULEVARD DO NOT APPEAR TO PROVIDE THE | | | PROPER CLEARANCE (AS INDICATED IN THE DETAIL) AND WOULD | | | OBSTRUCT CIRCULATION ON THE SIDEWALK. PLEASE ENSURE | | | THAT ALL BIKE RACK LOCATIONS PROVIDE THE PROPER | | | CLEARANCE. | | | | | | 2. SATISFIED - THE WAIVER TABLE SHOULD BE REVISED TO | | | INDICATE: | | | 2.1. SATISFIED - REQUIRED | | | 2.2. SATISFIED - ORIGINALLY PROVIDED | | | 2.3. SATISFIED - APPROVED WAIVER | | | 2.4. SATISFIED - CURRENT PROPOSAL | | | | | | 3. SATISFIED - WHY IS LOT 4N NOT SHOWING ANY PARKING | | | REQUIRED IN THE ?REQUIRED (NON-SHARED) PARKING? TABLE? | | | | | | 4. SATISFIED - REVISED TPS LETTER SHALL BE PROVIDED. | | | | | | 5. SATISFIED - REVISED SCAD APPROVAL REQUIRED. | | | | | | 6. NOT SATISFIED - WHY ARE THERE TWO (2) SITE PLANS | | | LABELED SP1? ONE IS PREPARED BY SCHMIDT NICHOLS, THE | | | OTHER IS PREPARED BY MSA. | | | | | | 6.1. NEW COMMENT - THERE ARE STILL TWO (2) SITE PLANS, | | | BOTH ARE LABELED SP1. IT IS STRONGLY ENCOURAGED THAT | | | ONLY ONE SITE PLAN BE PROVIDED TO AVOID CONFLICTS, | | | INCONSISTENCIES, ETC. | | | | | | 7. NOT SATISFIED - FLOOR PLANS SHALL BE PROVIDED FOR | | | ALL LEVELS TO CONFIRM UNIT COUNTS, NUMBER OF PARKING | | | SPACES, ETC. | | | | | | 7.1.. NEW COMMENT - NUMEROUS ARCHITECTURAL SHEETS THAT | | | WERE PROVIDED ARE NOT ASSOCIATED WITH THE SUBJECT | | | PROJECT - THE SHEETS ARE IDENTIFIED AS "THE TROPIC", A | | | PROJECT ON S. FEDERAL HIGHWAY IN HOLLYWOOD. | | | | | | 8. NOT SATISFIED - PLEASE CONFIRM THAT THE SYNTHETIC | | | TURF IS BEING CONSIDERED IMPERVIOUS SURFACE AS REQUIRED | | | BY SECTION 94-451 OF THE CITY?S ZLDRS. | | | | | | 8.1. NEW COMMENT - IS SYNTHETIC TURF NO LONGER | | | PROPOSED? IT DOES NOT APPEAR TO BE LABELED ON ANY OF | | | THE PLANS OTHER THAN THE SITE PLAN PREPARED BY MSA. | | | PLEASE CONFIRM. | | | | | | 9. NOT SATISFIED - MULTIPLE PORTIONS OF THE BUILDING | | | ARE EXTENDING INTO THE 20 FOOT CANAL BUFFER REQUIRED BY | | | THE DECLARATION OF COVENANTS. PER RESOLUTION NO. 16-21, | | | ?ANY AND ALL MODIFICATIONS TO THE CENTREPARK | | | DECLARATION OF COVENANTS, CONDITIONS AND RESTRICTIONS | | | (ORB 5430 | PG 1548) SHALL BE COMPLETED AND RECORDED IN | | | THE PUBLIC RECORDS OF PALM BEACH COUNTY? PRIOR TO THE | | | ISSUANCE OF A BUILDING PERMIT. PLEASE PROVIDE A STATUS | | | ON SUCH REVISIONS. | | | | | | 9.1. NEW COMMENT - THERE WAS NO CLEAR RESPONSE PROVIDED | | | TO THIS COMMENT. YOU INDICATED "WE ALLOW PLANTING | | | WITHIN THE CANAL BUFFER" HOWEVER THERE ARE PORTIONS OF | | | THE BUILDING ENCROACHING INTO THE CANAL BUFFER, ETC. | | | | | | 10. SATISFIED - THE AMOUNT OF OPEN SPACE PROVIDED IS | | | INCORRECT IN THE SITE DATA TABLE?IT APPEARS NOT TO HAVE | | | BEEN UPDATED. | | | | | | 11. PARTIALLY SATISFIED - THE MONUMENT SIGN CANNOT | | | EXCEED 4 FEET IN HEIGHT BUT SHALL OTHERWISE MEET THE | | | PROVISIONS OF ARTICLE XIII OF THE CITY?S ZLDRS. | | | | | | 11.1. NEW COMMENT - THE SIGN DETAIL INDICATES 200 SF | | | PER SIGN FACE, BUT THEN ALSO HAS A NOT ABOUT NOT | | | EXCEEDING 16 SF PER SIGN FACE. PER THE ZLDRS, PERMANENT | | | IDENTIFICATION SIGNS FOR RESIDENTIAL DEVELOPMENTS ARE | | | ALLOWED 48 SF PER SIGN FACE IF OVER 50 RESIDENTIAL | | | UNITS. PLEASE CORRECT AND ENSURE CONSISTENCY. | | | | | | 12. SATISFIED - IT APPEARS THAT A NUMBER OF NOTES THAT | | | WERE ON THE PREVIOUSLY-APPROVED SITE PLAN RELATING TO | | | IRRIGATION, PLUMBING FIXTURES, ETC. HAS BEEN REMOVED; | | | PLEASE CLARIFY WHY. | | | | | | 13. NOT SATISFIED - THE PREVIOUSLY-APPROVED SP-3 NEEDS | | | TO BE REVISED. | | | | | | 13.1. NEW COMMENT - THE RESPONSE TO COMMENTS STATES | | | THAT WITHOUT THE ALTERNATIVES, THIS SHEET IS NO LONGER | | | NEEDED. PLEASE NOTE THAT SP-3 WAS AN OVERALL SITE PLAN | | | SHOWING PARKING COMPLIANCE, ETC. FOR LOT 4 NORTH AND | | | LOT 4 SOUTH AS A COLLECTIVE PARCEL. | | | | | | 14. SATISFIED - IS ALL OF THE INFORMATION ON THE | | | PREVIOUSLY-APPROVED SP-2 NOW LOCATED ON SP-1? | | | | | | 15. SATISFIED - A LABEL FOR THE ?5? LANDSCAPE BUFFER? | | | IS POINTING TO A STAIRWELL IN THE NORTHEAST CORNER OF | | | THE GARAGE. | | | | | | 16. NOT SATISFIED - ADA STRIPING IS BEING SHOWN IN THE | | | LOADING DOCK, GARAGE ENTRY, AND TWO (2) PARKING SPACES | | | NORTH OF THE VAN-ACCESSIBLE PARKING. | | | | | | 16.1. NEW COMMENT - STRIPING IS STILL SHOWN CONFLICTING | | | WITH THE TWO (2) PARKING SPACES NORTH OF THE | | | VAN-ACCESSIBLE PARKING. | | | | | | 17. NOT SATISFIED - THE BUILDING OUTLINE DOES NOT MATCH | | | THAT SHOWN ON THE FLOOR PLAN, SPECIFICALLY THE | | | SOUTHEAST CORNER OF THE BUILDING. | | | | | | 17.1. NEW COMMENT - ARE THESE ROOF PROJECTIONS THAT ARE | | | BEING SHOWN? THEY ARE NOT LABELED, DIMENSIONED, ETC. | | | SEE COMMENT #20 BELOW. | | | | | | 18. SATISFIED - IMPROVEMENTS SHOWN ON LOT 2 NORTH | | | (LANDSCAPING, PARKING MODIFICATIONS, ETC.) ? PLEASE | | | PROVIDE AN APPROVAL BY THE PROPERTY OWNER? THE | | | LANDSCAPING SHOWN ON THIS PARCEL SHOULD NOT BE COUNTED | | | TOWARD THE REQUIRED LANDSCAPING OF THE PROPOSED | | | DEVELOPMENT. | | | | | | 19. NOT SATISFIED - THE COLOR ELEVATIONS PROVIDED DO | | | NOT MATCH THE PROPOSED BUILDING. | | | | | | 19.1. NEW COMMENT - THE COLOR ELEVATIONS PROVIDED WERE | | | INDICATED AS EXHIBIT D WITHIN THE REPSONSE TO COMMENTS; | | | THESE ARE TOO SMALL TO BE REVIEWED. PLEASE PROVIDE | | | FULL-SIZE PDFS, AS DONE PREVIOUSLY. | | | | | | 20. NOT SATISFIED - THERE APPEAR TO BE NUMEROUS | | | ENCROACHMENTS INTO THE SOUTH (CORNER SIDE) SETBACK. | | | STRUCTURAL OVERHANGS, BALCONIES, ETC. ARE ALLOWED TO | | | ENCROACH INTO THE SETBACK, BUT NOT BY MORE THAN THREE | | | (3) FEET. PLEASE DIMENSION ALL ENCROACHMENTS AND ENSURE | | | THEY DO NOT EXCEED THREE (3) FEET. | | | | | | 21. NEW COMMENT - SHEET LP.2 OF THE LANDSCAPE PLANS | | | STATES THAT SHEET LP.4 SHOULD BE REFERRED TO FOR THE | | | COURTYARD PLANTINGS, HOWEVER IT APPERS THAT THE | | | COURTYARD IS BEING SHOWN ON SHEET LP.3. PLEASE ENSURE | | | THAT ALL REFERENCES ARE CORRECT. | | | | | | ________________________________________ | | | | | | PLEASE NOTE THE FOLLOWING WHEN RESUBMITTING: | | | | | | A) WRITTEN RESPONSES TO COMMENTS MADE BY ALL | | | DEPARTMENTS SHALL BE PROVIDED UPON RESUBMISSION. | | | | | | B) ELECTRONIC COPIES OF REVISED PLANS AND/OR DOCUMENTS | | | SHALL BE PROVIDED. | | | | | | C) PLEASE NOTE THAT RE-SUBMITTALS MAY BE SUBJECT TO | | | ADDITIONAL COMMENTS. | | | | | | D) IF NO RESPONSE IS RECEIVED WITHIN 60 DAYS OF THE | | | ISSUANCE OF THESE COMMENTS, THE APPLICATION WILL BE | | | CONSIDERED WITHDRAWN AND ANY FURTHER ACTION WILL | | | REQUIRE SUBMISSION OF A NEW DEVELOPMENT APPLICATION. | | | | | | E) PLEASE NOTE THAT YOU WILL BE PERMITTED ONE (1) | | | RESUBMITTAL AT NO ADDITIONAL COST. IF PREVIOUSLY-ISSUED | | | COMMENTS CONTINUE TO NOT BE SUFFICIENTLY ADDRESSED, THE | | | APPLICANT WILL BE ACCESSED A RESUBMITTAL FEE. SUCH FEE | | | WILL BE 20% OF THE ORIGINAL APPLICATION FEE. | | | ________________________________________ | | | | | | QUESTIONS/COMMENTS, PLEASE CONTACT THE FOLLOWING: | | | | | | JOHN P. ROACH, AICP, PRINCIPAL PLANNER | | | CITY OF WEST PALM BEACH | | | DEVELOPMENT SERVICES DEPARTMENT ? PLANNING DIVISION | | | 401 CLEMATIS STREET - P.O. BOX 3147 | | | WEST PALM BEACH, FLORIDA 33402 | | | | | | P: 561.822.1448 | | | TTY: 800.955.8771 | | | E: [email protected] | | | | | | W: WPB.ORG |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
1 |
Status |
F |
Date |
08-01-2022 |
|
|
Cont ID |
|
| Sent By |
jroach |
Date |
08-01-2022 |
Time |
13:58 |
Rev Time |
0.00 |
| Received By |
jroach |
Date |
08-01-2022 |
Time |
13:58 |
Sent To |
|
|
| Notes |
| 2022-08-01 13:59:04 | PLANS AND PLATS REVIEW COMMITTEE (PPRC) ZONING REVIEW | | | ________________________________________ | | | | | | DATE OF REVIEW: 08.01.2022 | | | PROJECT NO.: Z22060006 | | | CASE NO.: PB 791LL | | | ________________________________________ | | | | | | PLEASE PROVIDE A WRITTEN RESPONSE TO THE FOLLOWING | | | REVIEW COMMENTS: | | | | | | 1. THE SITE DATA TABLE INDICATES THAT FIVE (5) BIKE | | | RACKS ARE BEING PROPOSED ON THE EXTERIOR OF THE | | | BUILDING; PLEASE IDENTIFY THEIR LOCATION AND ENSURE | | | THAT PROPER CLEARANCE IS PROVIDED (AS SHOWN IN THE | | | DETAIL) TO AVOID BLOCKING OF THE SIDEWALK, ETC. | | | | | | 2. THE WAIVER TABLE SHOULD BE REVISED TO INDICATE: | | | 2.1. REQUIRED | | | 2.2. ORIGINALLY PROVIDED | | | 2.3. APPROVED WAIVER | | | 2.4. CURRENT PROPOSAL | | | | | | 3. WHY IS LOT 4N NOT SHOWING ANY PARKING REQUIRED IN | | | THE ?REQUIRED (NON-SHARED) PARKING? TABLE? | | | | | | 4. REVISED TPS LETTER SHALL BE PROVIDED. | | | | | | 5. REVISED SCAD APPROVAL REQUIRED. | | | | | | 6. WHY ARE THERE TWO (2) SITE PLANS LABELED SP1? ONE IS | | | PREPARED BY SCHMIDT NICHOLS, THE OTHER IS PREPARED BY | | | MSA. | | | | | | 7. FLOOR PLANS SHALL BE PROVIDED FOR ALL LEVELS TO | | | CONFIRM UNIT COUNTS, NUMBER OF PARKING SPACES, ETC. | | | | | | 8. PLEASE CONFIRM THAT THE SYNTHETIC TURF IS BEING | | | CONSIDERED IMPERVIOUS SURFACE AS REQUIRED BY SECTION | | | 94-451 OF THE CITY?S ZLDRS. | | | | | | 9. MULTIPLE PORTIONS OF THE BUILDING ARE EXTENDING INTO | | | THE 20 FOOT CANAL BUFFER REQUIRED BY THE DECLARATION OF | | | COVENANTS. PER RESOLUTION NO. 16-21, ?ANY AND ALL | | | MODIFICATIONS TO THE CENTREPARK DECLARATION OF | | | COVENANTS, CONDITIONS AND RESTRICTIONS (ORB 5430 | PG | | | 1548) SHALL BE COMPLETED AND RECORDED IN THE PUBLIC | | | RECORDS OF PALM BEACH COUNTY? PRIOR TO THE ISSUANCE OF | | | A BUILDING PERMIT. PLEASE PROVIDE A STATUS ON SUCH | | | REVISIONS. | | | | | | 10. THE AMOUNT OF OPEN SPACE PROVIDED IS INCORRECT IN | | | THE SITE DATA TABLE?IT APPEARS NOT TO HAVE BEEN | | | UPDATED. | | | | | | 11. THE MONUMENT SIGN CANNOT EXCEED 4 FEET IN HEIGHT | | | BUT SHALL OTHERWISE MEET THE PROVISIONS OF ARTICLE XIII | | | OF THE CITY?S ZLDRS. | | | | | | 12. IT APPEARS THAT A NUMBER OF NOTES THAT WERE ON THE | | | PREVIOUSLY-APPROVED SITE PLAN RELATING TO IRRIGATION, | | | PLUMBING FIXTURES, ETC. HAS BEEN REMOVED; PLEASE | | | CLARIFY WHY. | | | | | | 13. THE PREVIOUSLY-APPROVED SP-3 NEEDS TO BE REVISED. | | | | | | 14. IS ALL OF THE INFORMATION ON THE | | | PREVIOUSLY-APPROVED SP-2 NOW LOCATED ON SP-1? | | | | | | 15. A LABEL FOR THE ?5? LANDSCAPE BUFFER? IS POINTING | | | TO A STAIRWELL IN THE NORTHEAST CORNER OF THE GARAGE. | | | | | | 16. ADA STRIPING IS BEING SHOWN IN THE LOADING DOCK, | | | GARAGE ENTRY, AND TWO (2) PARKING SPACES NORTH OF THE | | | VAN-ACCESSIBLE PARKING. | | | | | | 17. THE BUILDING OUTLINE DOES NOT MATCH THAT SHOWN ON | | | THE FLOOR PLAN, SPECIFICALLY THE SOUTHEAST CORNER OF | | | THE BUILDING. | | | | | | 18. IMPROVEMENTS SHOWN ON LOT 2 NORTH (LANDSCAPING, | | | PARKING MODIFICATIONS, ETC.) ? PLEASE PROVIDE AN | | | APPROVAL BY THE PROPERTY OWNER? THE LANDSCAPING SHOWN | | | ON THIS PARCEL SHOULD NOT BE COUNTED TOWARD THE | | | REQUIRED LANDSCAPING OF THE PROPOSED DEVELOPMENT. | | | | | | 19. THE COLOR ELEVATIONS PROVIDED DO NOT MATCH THE | | | PROPOSED BUILDING. | | | | | | 20. THERE APPEAR TO BE NUMEROUS ENCROACHMENTS INTO THE | | | SOUTH (CORNER SIDE) SETBACK. STRUCTURAL OVERHANGS, | | | BALCONIES, ETC. ARE ALLOWED TO ENCROACH INTO THE | | | SETBACK, BUT NOT BY MORE THAN THREE (3) FEET. PLEASE | | | DIMENSION ALL ENCROACHMENTS AND ENSURE THEY DO NOT | | | EXCEED THREE (3) FEET. | | | ________________________________________ | | | | | | PLEASE NOTE THE FOLLOWING WHEN RESUBMITTING: | | | | | | A) WRITTEN RESPONSES TO COMMENTS MADE BY ALL | | | DEPARTMENTS SHALL BE PROVIDED UPON RESUBMISSION. | | | | | | B) ELECTRONIC COPIES OF REVISED PLANS AND/OR DOCUMENTS | | | SHALL BE PROVIDED. | | | | | | C) PLEASE NOTE THAT RE-SUBMITTALS MAY BE SUBJECT TO | | | ADDITIONAL COMMENTS. | | | | | | D) IF NO RESPONSE IS RECEIVED WITHIN 60 DAYS OF THE | | | ISSUANCE OF THESE COMMENTS, THE APPLICATION WILL BE | | | CONSIDERED WITHDRAWN AND ANY FURTHER ACTION WILL | | | REQUIRE SUBMISSION OF A NEW DEVELOPMENT APPLICATION. | | | | | | E) PLEASE NOTE THAT YOU WILL BE PERMITTED ONE (1) | | | RESUBMITTAL AT NO ADDITIONAL COST. IF PREVIOUSLY-ISSUED | | | COMMENTS CONTINUE TO NOT BE SUFFICIENTLY ADDRESSED, THE | | | APPLICANT WILL BE ACCESSED A RESUBMITTAL FEE. SUCH FEE | | | WILL BE 20% OF THE ORIGINAL APPLICATION FEE. | | | ________________________________________ | | | | | | QUESTIONS/COMMENTS, PLEASE CONTACT THE FOLLOWING: | | | | | | JOHN P. ROACH, AICP, PRINCIPAL PLANNER | | | CITY OF WEST PALM BEACH | | | DEVELOPMENT SERVICES DEPARTMENT ? PLANNING DIVISION | | | 401 CLEMATIS STREET - P.O. BOX 3147 | | | WEST PALM BEACH, FLORIDA 33402 | | | | | | P: 561.822.1448 | | | TTY: 800.955.8771 | | | E: [email protected] | | | | | | W: WPB.ORG |
|
|
| |
Print |
|
Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved |
 |