Plan Review Details - Project Z22030014
Plan Review Stops For Project Z22030014
Review Stop AIPP ART IN PUBLIC PLACES
Rev No 1 Status N Date 04-12-2022 Cont ID  
Sent By scwelter Date 04-12-2022 Time 12:45 Rev Time 0.00
Received By scwelter Date   Time   Sent To  
Notes
2022-04-12 12:46:58THE REQUEST IS FOR REZONING -

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 04-13-2022 Cont ID  
Sent By rbrown Date 04-13-2022 Time 19:00 Rev Time 0.00
Received By rbrown Date 04-13-2022 Time 19:00 Sent To  
Notes
2022-04-13 19:00:40NO COMMENTS ON PROPOSED REZONING.

Review Stop ENG - PPRC ENGINEERING - PPRC
Rev No 2 Status P Date 04-28-2022 Cont ID  
Sent By rrossano Date 04-28-2022 Time   Rev Time 0.00
Received By rrossano Date 04-28-2022 Time   Sent To  
Notes
***NONE***

Review Stop ENG - PPRC ENGINEERING - PPRC
Rev No 1 Status F Date 04-09-2022 Cont ID  
Sent By rrossano Date 04-09-2022 Time   Rev Time 0.00
Received By rrossano Date 04-09-2022 Time   Sent To  
Notes
2022-04-09 13:58:04COMMENTS FROM MARK HURLEY, FIELD CUSTOMER SERVICE
 SUPERVISOR WITH CITY OF WPB PUBLIC UTILITIES
 561-822-2262 OR [email protected]
  
 -SURVEYOR NOTE 1 SAYS LANDS WERE NOT ABSTRACTED FOR
 RIGHT OF WAYS AND EASEMENTS. WHEN WILL THEY BE
 ABSTRACTED?
  
 -IN 1010 CLEARWATER PL UTILITY EASEMENT, THERE IS
 LIKELY A LARGE DIAMETER WATER MAIN THAT STRUCTURES
 COULD NOT BE BUILT OVER OR NEAR.
  

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status P Date 04-07-2022 Cont ID  
Sent By pleduc Date 04-07-2022 Time   Rev Time 0.00
Received By pleduc Date 04-07-2022 Time 13:18 Sent To  
Notes
2022-04-07 13:19:25FIRE HAS NO OBJECTIONS TO THE PROPOSED AND APPROVES.
  
 PETER LEDUC
 FIRE MARSHAL
 561-804-4709
 [email protected]
  

Review Stop L LANDSCAPING
Rev No 1 Status P Date 04-13-2022 Cont ID  
Sent By rcaranci Date 04-13-2022 Time 18:38 Rev Time 0.00
Received By rcaranci Date 04-13-2022 Time 18:38 Sent To  
Notes
2022-04-13 18:39:05NO COMMENTS AT THIS TIME, BUT WILL REVIEW AT TIME OF
 SITE PLAN SUBMITTAL.

Review Stop PW PUBLIC WORKS
Rev No 1 Status P Date 04-13-2022 Cont ID  
Sent By   Date 04-13-2022 Time   Rev Time 0.00
Received By   Date 04-13-2022 Time   Sent To  
Notes
2022-04-13 09:10:38PUBLIC WORKS HAS NO OBJECTIONS TO THE PROPOSED
 REZONING.
  
 MATT HEJAZI
 DEPT. OF PUBLIC WORKS
 [email protected]
 561-822-2045

Review Stop STORM STORMWATER
Rev No 1 Status P Date 04-14-2022 Cont ID  
Sent By tward Date 04-14-2022 Time 10:20 Rev Time 0.00
Received By tward Date 04-14-2022 Time 10:20 Sent To  
Notes
***NONE***

Review Stop SURVEY SURVEYING
Rev No 1 Status P Date 04-11-2022 Cont ID  
Sent By vnoel Date 04-11-2022 Time 10:08 Rev Time 0.00
Received By vnoel Date   Time   Sent To  
Notes
2022-04-11 10:12:47PASSED WITH ITEMS TO CONSIDER:
  
 1. PROPOSED FERN STREET EXTENSION WITH POSSIBLE LIFT
 STATION RELOCATION.
 2. REVISE SURVEY WHEN TITLE COMMITMENT IS FINALIZED.

Review Stop TRAFFIC TRAFFIC ENGINEERING
Rev No 2 Status F Date 05-19-2022 Cont ID  
Sent By   Date 05-19-2022 Time   Rev Time 0.00
Received By   Date   Time   Sent To  
Notes
2022-05-19 16:09:351) PROVIDE PROVISION FOR EASEMENT AND/OR ROW DEDICATION
 IN ORDER TO ACCOMMODATE THE FUTURE FERN ST EXTENSION. A
 MEETING OR DISCUSSION WITH ENGINEERING SERVICES IS
 RECOMMENDED. NO DEVELOPER'S REPRESENTATIVE HAS MADE
 CONTACT AS OF MAY 19, 2022
  
 2) PROVIDE THEORETICAL MAXIMUM TRIP GENERATION AND
 POTENTIAL ACCESS DRIVEWAY LOCATIONS FOR EXISTING AND
 FUTURE DEVELOPMENTS. AS DISCUSSED, AND INFORMALLY
 AGREED, A CAP ON THE MAXIMUM NUMBER OF TRIPS GENERATED
 SHALL BE DEFINED, PRIOR TO APPROVAL FROM TRAFFIC
 ENGINEERING PERTAINING THE REZONING. THE DRIVEWAY
 LOCATION REQUEST CAN BE DISMISSED. NOTE: THIS IS NOT A
 FULL TRAFFIC STUDY REQUEST.
  
 VALERIO ORICCHIO
 CITY TRANSPORTATION ENGINEER
 561-494-1092
 [email protected]
  

Review Stop TRAFFIC TRAFFIC ENGINEERING
Rev No 1 Status F Date 04-14-2022 Cont ID  
Sent By   Date 04-14-2022 Time   Rev Time 0.00
Received By   Date   Time   Sent To  
Notes
2022-04-14 20:51:161) PROVIDE PROVISION FOR EASEMENT AND/OR ROW DEDICATION
 IN ORDER TO ACCOMMODATE THE FUTURE FERN ST EXTENSION. A
 MEETING OR DISCUSSION WITH ENGINEERING SERVICES IS
 RECOMMENDED
 2) PROVIDE THEORETICAL MAXIMUM TRIP GENERATION AND
 POTENTIAL ACCESS DRIVEWAY LOCATIONS FOR FUTURE
 DEVELOPMENTS
  
 VALERIO ORICCHIO
 CITY TRANSPORTATION ENGINEER
 561-494-1092
 [email protected]
  
  

Review Stop Z ZONING
Rev No 1 Status F Date 04-13-2022 Cont ID  
Sent By ckimmerl Date 04-13-2022 Time 17:03 Rev Time 0.00
Received By ckimmerl Date 04-13-2022 Time 17:02 Sent To  
Notes
2022-04-13 17:02:391. PLEASE PROVIDE A MASSING STUDY OF POTENTIAL SITE
 BUILD-OUT OR FUTURE PLANS FOR CC.
 2. FURTHER DISCUSSION WILL BE NECESSARY REGARDING THE
 POTENTIAL DEDICATION OF A PORTION OF LAND FOR THE FERN
 ST. CROSSING.
 3. PLEASE NOTE THAT PROPERTY INCLUDES FOUR SEPARATE
 EASEMENTS, SHOULD THE PROPERTY UNDERGO REDEVELOPMENT:
 FPL EASEMENT; LIFT STATION EASEMENT; 5? UTILITY ANCHOR
 EASEMENT; AND A RIGHT OF ENTRY/USE AGREEMENT ON 400
 AUSTRALIAN ALONG CLEARWATER PL.
  