| Plan Review Stops For Project Z22020030 |
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
1 |
Status |
|
Date |
02-25-2022 |
|
|
Cont ID |
|
| Sent By |
ldeloren |
Date |
02-25-2022 |
Time |
08:57 |
Rev Time |
|
| Received By |
ldeloren |
Date |
|
Time |
|
Sent To |
|
|
| Notes |
| 2022-02-16 14:14:46 | MET WITH STEPHEN BUTLER, MICHAEL PERRY AND LANDSCAPE | | | ARCHITECT ON 2/16/2022 TO GO OVER IMPROVEMENTS AND | | | INCONSISTENCIES WITH THE ZLDRS TO THE SITE AND | | | LANDSCAPE PLANS. RESUBMITTAL EXPECTED SHORTLY. |
|
|
| Review Stop |
ENG - PPRC |
ENGINEERING - PPRC |
| Rev No |
4 |
Status |
P |
Date |
03-31-2022 |
|
|
Cont ID |
|
| Sent By |
rrossano |
Date |
03-31-2022 |
Time |
|
Rev Time |
0.00 |
| Received By |
rrossano |
Date |
03-31-2022 |
Time |
|
Sent To |
|
|
| Notes |
|
|
| Review Stop |
ENG - PPRC |
ENGINEERING - PPRC |
| Rev No |
3 |
Status |
F |
Date |
03-14-2022 |
|
|
Cont ID |
|
| Sent By |
RROSSANO |
Date |
03-14-2022 |
Time |
|
Rev Time |
0.00 |
| Received By |
rrossano |
Date |
03-14-2022 |
Time |
|
Sent To |
|
|
| Notes |
| 2022-03-14 07:22:14 | -PLANTING PLAN SHOWS SABAL PALM IN SOUTHEAST CORNER OF | | | PROPERTY IN UTILITY EASEMENT, BUT PROVIDED THE | | | FOLLOWING REVIEW COMMENT ON 15FEB2022: ENSURE TREE | | | TRUNK OF RELOCATED SABAL PALM NEAR SOUTHEAST CORNER OF | | | PROPERTY IS OUTSIDE OF PROPOSED 5 FOOT UTILITY | | | EASEMENT. RELOCATE SLIGHTLY NORTHWEST AND ADD CALLOUTS | | | TO LANDSCAPING PLAN AS NEEDED. | | | | | | -PLANTING PLAN CONFLICTS WITH A001 PLAN. PLANTING PLAN | | | PROPOSES TREE WHERE A001 SHOWS SIGN NEAR NORTHWEST AREA | | | OF PROPERTY. NORTH OF SIGN, PLANTING PLAN SHOWS 5 | | | PARKING SPACES WHERE A001 SHOWS 4. PLEASE MAKE SURE | | | PLANS MATCH BASIC LAYOUT AND HAVE NO CONFLICTS. | | | | | | RESPECTFULLY, | | | | | | MARK HURLEY | | | FIELD CUSTOMER SERVICE SUPERVISOR | | | CITY OF WEST PALM BEACH PUBLIC UTILITIES | | | 561-822-2262 | | | |
|
|
| Review Stop |
ENG - PPRC |
ENGINEERING - PPRC |
| Rev No |
2 |
Status |
|
Date |
|
|
|
Cont ID |
|
| Sent By |
|
Date |
|
Time |
|
Rev Time |
0.00 |
| Received By |
|
Date |
|
Time |
|
Sent To |
|
|
| Notes |
|
|
| Review Stop |
ENG - PPRC |
ENGINEERING - PPRC |
| Rev No |
1 |
Status |
F |
Date |
02-25-2022 |
|
|
Cont ID |
|
| Sent By |
ldeloren |
Date |
02-25-2022 |
Time |
|
Rev Time |
|
| Received By |
ldeloren |
Date |
02-25-2022 |
Time |
|
Sent To |
|
|
| Notes |
| 2022-02-25 08:57:06 | COMMENTS FROM RICK ROSSANO,SENIOR PROJECT COORDINATOR, | | | ENGINEERING SERVICES DEPT., 561-494-1098 | | | [email protected] : | | | | | | PLEASE ADVISE IF ANY OF THE PROPOSED UTILITY | | | IMPROVEMENTS FROM THE APPROVED ENGINEERING SUBMITTAL | | | (E21080015 ? PIG BEACH BBQ) WILL BE AFFECTED BY THIS | | | PROPOSED SITE PLAN CHANGE. | | | | | | COMMENTS FROM MARK HURLEY, FIELD CUSTOMER SERVICE | | | SUPER., WPB PUBLIC UTILITIES, 561-822-2262 OR | | | [email protected]: | | | | | | PROPOSED GUMBO LIMBO TREE NEAR SOUTH PROPERTY LINE AND | | | SOUTH SIDE OF BUILDING SHOULD NOT BE LOCATED ON TOP OF | | | WATER MAIN WHERE IT WOULD IMPEDE UTILITY MAINTENANCE. | | | THAT LOCATION ALSO LOOKS TO CONFLICT WITH POWER POLE | | | GUY WIRE AND ANCHOR. | | | | | | LYNN DELELORENZO | | | PROJECT COORDINATOR |
|
|
| Review Stop |
FIRE |
FIRE DEPARTMENT |
| Rev No |
1 |
Status |
|
Date |
|
|
|
Cont ID |
|
| Sent By |
|
Date |
|
Time |
|
Rev Time |
|
| Received By |
|
Date |
|
Time |
|
Sent To |
|
|
| Notes |
|
|
| Review Stop |
L |
LANDSCAPING |
| Rev No |
4 |
Status |
P |
Date |
03-29-2022 |
|
|
Cont ID |
|
| Sent By |
rcaranci |
Date |
03-29-2022 |
Time |
13:07 |
Rev Time |
0.00 |
| Received By |
rcaranci |
Date |
03-29-2022 |
Time |
13:07 |
Sent To |
|
|
| Notes |
| 2022-03-29 13:08:22 | PLAN FROM 3/17 PASSED |
|
|
| Review Stop |
L |
LANDSCAPING |
| Rev No |
3 |
Status |
P |
Date |
03-17-2022 |
|
|
Cont ID |
|
| Sent By |
rcaranci |
Date |
03-17-2022 |
Time |
16:33 |
Rev Time |
0.00 |
| Received By |
rcaranci |
Date |
03-17-2022 |
Time |
16:32 |
Sent To |
|
|
| Notes |
| 2022-03-17 16:35:29 | FROM: RAY CARANCI, LANDSCAPE PLANNER 561-822-1462 | | | PROJECT: 2400 S DIXIE Z22020030 | | | MARCH 17, 2022 | | | RESUBMITTED VERSION OF LANDSCAPE PLAN ON 3/17/22 | | | I HAVE REVIEWED THE ABOVE REFERENCED PETITION, AND | | | PROVIDE THE FOLLOWING COMMENTS: | | | | | | 1. SATISFIED. PROVIDE THE REQUIRED TREE IN THE | | | NORTHWEST TERMINAL LANDSCAPE ISLAND. | | | | | | 2. SATISFIED. SECTION 94-443(C)(3) REQUIRES THAT A | | | MINIMUM OF 75 PERCENT OF ALL TREES THAT ARE REQUIRED TO | | | BE PLANTED WITHIN THE INTERIOR OF AN OFF STREET PARKING | | | AREA SHALL BE CATEGORY 1 SHADE TREES. SHOW THE | | | PERCENTAGE OF CATEGORY 1 TREES PROVIDED FOR THE | | | REQUIRED LANDSCAPE AREAS. | | | THERE ARE 6 TERMINAL ISLANDS, REQUIRING 5 BE CATEGORY 1 | | | TREES. | | | | | | 3. SATISFIED. THE PROPOSED ROYAL POINCIANA TREES WILL | | | CONFLICT WITH THE SEWER LINE AND GREASE TRAPS AND | | | OBSCURE THE PROPOSED SIGNAGE ON THE FRONT OF THE | | | BUILDING. CHOOSE A SMALLER TREE OR PALMS THAT WILL NOT | | | CONFLICT AND PLACE SO THEY ARE NOT IN CONFLICT WITH | | | SEWER LINES. | | | | | | 4. SATISFIED. LABEL ALL EXISTING TREES TO REMAIN ON THE | | | LANDSCAPE PLAN WITH SPECIES AND NUMBER FROM THE TREE | | | DISPOSITION PLAN. | | | | | | 5. SATISFIED. THE FICUS TREES MAY NOT BE ABLE TO REMAIN | | | ALONG THE EAST PROPERTY LINE WITH THE REQUIRED FENCE TO | | | BE INSTALLED, AND THEY ARE IN POOR CONDITION. BUFFER | | | TREES MAY BE PLACED OUTSIDE THE 5 FOOT LANDSCAPE BUFFER | | | IN ADDITIONAL GREEN SPACE. | | | | | | 6. SATISFIED. THE GUMBO LIMBO TREE IS NOT APPROPRIATE | | | FOR THE SOUTH PROPERTY LINE AS IT CONFLICTS WITH | | | UTILITIES. REPLACE WITH AN APPROPRIATE SPECIES. | | | CONDITIONS OF APPROVAL | | | 1. PRIOR TO THE REMOVAL OR RELOCATION OF ANY TREES ON | | | THE PROPERTY, A TREE ALTERATION PERMIT SHALL BE | | | SUBMITTED, REVIEWED AND APPROVED BY THE DEVELOPMENT | | | SERVICES DEPARTMENT, PLANNING DIVISION. | | | |
|
|
| Review Stop |
L |
LANDSCAPING |
| Rev No |
2 |
Status |
F |
Date |
02-25-2022 |
|
|
Cont ID |
|
| Sent By |
rcaranci |
Date |
02-25-2022 |
Time |
16:11 |
Rev Time |
0.00 |
| Received By |
rcaranci |
Date |
02-25-2022 |
Time |
16:11 |
Sent To |
|
|
| Notes |
| 2022-02-25 16:11:46 | FROM: RAY CARANCI, LANDSCAPE PLANNER 561-822-1462 | | | PROJECT: 2400 S DIXIE Z22020030 | | | FEBRUARY 25, 2022 | | | I HAVE REVIEWED THE ABOVE REFERENCED PETITION, AND | | | PROVIDE THE FOLLOWING COMMENTS: | | | | | | 1. PROVIDE THE REQUIRED TREE IN THE NORTHWEST TERMINAL | | | LANDSCAPE ISLAND. | | | | | | 2. SECTION 94-443(C)(3) REQUIRES THAT A MINIMUM OF 75 | | | PERCENT OF ALL TREES THAT ARE REQUIRED TO BE PLANTED | | | WITHIN THE INTERIOR OF AN OFF STREET PARKING AREA SHALL | | | BE CATEGORY 1 SHADE TREES. SHOW THE PERCENTAGE OF | | | CATEGORY 1 TREES PROVIDED FOR THE REQUIRED LANDSCAPE | | | AREAS. | | | THERE ARE 6 TERMINAL ISLANDS, REQUIRING 5 BE CATEGORY 1 | | | TREES. | | | | | | 3. THE PROPOSED ROYAL POINCIANA TREES WILL CONFLICT | | | WITH THE SEWER LINE AND GREASE TRAPS AND OBSCURE THE | | | PROPOSED SIGNAGE ON THE FRONT OF THE BUILDING. CHOOSE A | | | SMALLER TREE OR PALMS THAT WILL NOT CONFLICT AND PLACE | | | SO THEY ARE NOT IN CONFLICT WITH SEWER LINES. | | | | | | 4. LABEL ALL EXISTING TREES TO REMAIN ON THE LANDSCAPE | | | PLAN WITH SPECIES AND NUMBER FROM THE TREE DISPOSITION | | | PLAN. | | | | | | 5. THE FICUS TREES MAY NOT BE ABLE TO REMAIN ALONG THE | | | EAST PROPERTY LINE WITH THE REQUIRED FENCE TO BE | | | INSTALLED, AND THEY ARE IN POOR CONDITION. BUFFER TREES | | | MAY BE PLACED OUTSIDE THE 5 FOOT LANDSCAPE BUFFER IN | | | ADDITIONAL GREEN SPACE. | | | | | | 6. THE GUMBO LIMBO TREE IS NOT APPROPRIATE FOR THE | | | SOUTH PROPERTY LINE AS IT CONFLICTS WITH UTILITIES. | | | REPLACE WITH AN APPROPRIATE SPECIES. | | | CONDITIONS OF APPROVAL | | | 1. PRIOR TO THE REMOVAL OR RELOCATION OF ANY TREES ON | | | THE PROPERTY, A TREE ALTERATION PERMIT SHALL BE | | | SUBMITTED, REVIEWED AND APPROVED BY THE DEVELOPMENT | | | SERVICES DEPARTMENT, PLANNING DIVISION. | | | |
|
|
| Review Stop |
L |
LANDSCAPING |
| Rev No |
1 |
Status |
F |
Date |
02-23-2022 |
|
|
Cont ID |
|
| Sent By |
rcaranci |
Date |
02-23-2022 |
Time |
17:02 |
Rev Time |
0.00 |
| Received By |
rcaranci |
Date |
02-23-2022 |
Time |
17:02 |
Sent To |
|
|
| Notes |
| 2022-02-23 17:03:02 | MET WITH STEPHEN BUTLER, MICHAEL PERRY AND LANDSCAPE | | | ARCHITECT ON 2/16/2022 TO GO OVER IMPROVEMENTS AND | | | INCONSISTENCIES WITH THE ZLDRS TO THE SITE AND | | | LANDSCAPE PLANS. RESUBMITTAL EXPECTED SHORTLY. |
|
|
| Review Stop |
PARK |
PARKING |
| Rev No |
1 |
Status |
|
Date |
|
|
|
Cont ID |
|
| Sent By |
|
Date |
|
Time |
|
Rev Time |
|
| Received By |
|
Date |
|
Time |
|
Sent To |
|
|
| Notes |
|
|
| Review Stop |
POLICE |
POLICE |
| Rev No |
1 |
Status |
|
Date |
|
|
|
Cont ID |
|
| Sent By |
|
Date |
|
Time |
|
Rev Time |
|
| Received By |
|
Date |
|
Time |
|
Sent To |
|
|
| Notes |
|
|
| Review Stop |
PW |
PUBLIC WORKS |
| Rev No |
4 |
Status |
P |
Date |
03-29-2022 |
|
|
Cont ID |
|
| Sent By |
|
Date |
03-29-2022 |
Time |
|
Rev Time |
0.00 |
| Received By |
|
Date |
03-29-2022 |
Time |
|
Sent To |
|
|
| Notes |
| 2022-03-29 13:59:03 | PASSED WITH A PROVISO. FOR A FREESTANDING SITE DUMPSTER | | | ENCLOSURE, THE ENCLOSURE SHALL COMPLY WITH THE LATEST | | | REVISION OF CITY OF WEST PALM BEACH GENERAL | | | CONSTRUCTION-GARBAGE ENCLOSURE STANDARD, GC-7. (LINK TO | | | THE LATEST REVISION OF THE GC-7 DOCUMENT: HTTPS://WWW.W | | | PB.ORG/HOME/SHOWPUBLISHEDDOCUMENT/3690/6376290604221000 | | | 00). | | | | | | MATT HEJAZI | | | DEPT. OF PUBLIC WORKS | | | [email protected] | | | 561-822-2045 |
|
|
| Review Stop |
PW |
PUBLIC WORKS |
| Rev No |
3 |
Status |
P |
Date |
03-14-2022 |
|
|
Cont ID |
|
| Sent By |
|
Date |
03-14-2022 |
Time |
|
Rev Time |
0.00 |
| Received By |
|
Date |
03-14-2022 |
Time |
|
Sent To |
|
|
| Notes |
| 2022-03-11 15:41:43 | NO COMMENTS FROM DEPARTMENT OF PUBLIC WORKS. | | | | | | MATT HEJAZI | | | DEPT. OF PUBLIC WORKS | | | [email protected] | | | 561-822-2045 |
|
|
| Review Stop |
PW |
PUBLIC WORKS |
| Rev No |
2 |
Status |
P |
Date |
02-15-2022 |
|
|
Cont ID |
|
| Sent By |
|
Date |
02-15-2022 |
Time |
|
Rev Time |
0.00 |
| Received By |
|
Date |
02-15-2022 |
Time |
|
Sent To |
|
|
| Notes |
| 2022-03-11 15:41:53 | PASSED WITH A PROVISO. FOR A FREESTANDING SITE DUMPSTER | | | ENCLOSURE, THE ENCLOSURE SHALL COMPLY WITH THE LATEST | | | REVISION (OCTOBER 2020) OF CITY OF WEST PALM BEACH | | | GENERAL CONSTRUCTION-GARBAGE ENCLOSURE STANDARD, CG-7 | | | | | | MATT HEJAZI | | | DEPT. OF PUBLIC WORKS | | | [email protected] | | | 561-822-2045V |
|
|
| Review Stop |
PW |
PUBLIC WORKS |
| Rev No |
1 |
Status |
P |
Date |
02-28-2022 |
|
|
Cont ID |
|
| Sent By |
|
Date |
02-28-2022 |
Time |
|
Rev Time |
|
| Received By |
|
Date |
02-28-2022 |
Time |
|
Sent To |
|
|
| Notes |
| 2022-02-28 15:10:07 | PASSED WITH A PROVISO. FOR A FREESTANDING SITE DUMPSTER | | | ENCLOSURE, THE ENCLOSURE SHALL COMPLY WITH THE LATEST | | | REVISION (OCTOBER 2020) OF CITY OF WEST PALM BEACH | | | GENERAL CONSTRUCTION-GARBAGE ENCLOSURE STANDARD, CG-7 | | | | | | MATT HEJAZI | | | DEPT. OF PUBLIC WORKS | | | [email protected] | | | 561-822-2045 |
|
|
| Review Stop |
STORM |
STORMWATER |
| Rev No |
4 |
Status |
P |
Date |
04-05-2022 |
|
|
Cont ID |
|
| Sent By |
tward |
Date |
04-05-2022 |
Time |
17:26 |
Rev Time |
0.00 |
| Received By |
tward |
Date |
04-05-2022 |
Time |
17:26 |
Sent To |
|
|
| Notes |
|
|
| Review Stop |
STORM |
STORMWATER |
| Rev No |
3 |
Status |
|
Date |
|
|
|
Cont ID |
|
| Sent By |
|
Date |
|
Time |
|
Rev Time |
0.00 |
| Received By |
|
Date |
|
Time |
|
Sent To |
|
|
| Notes |
|
|
| Review Stop |
STORM |
STORMWATER |
| Rev No |
2 |
Status |
|
Date |
|
|
|
Cont ID |
|
| Sent By |
|
Date |
|
Time |
|
Rev Time |
0.00 |
| Received By |
|
Date |
|
Time |
|
Sent To |
|
|
| Notes |
|
|
| Review Stop |
STORM |
STORMWATER |
| Rev No |
1 |
Status |
P |
Date |
02-16-2022 |
|
|
Cont ID |
|
| Sent By |
tward |
Date |
02-16-2022 |
Time |
15:12 |
Rev Time |
0.00 |
| Received By |
tward |
Date |
02-16-2022 |
Time |
15:13 |
Sent To |
|
|
| Notes |
| 2022-02-16 15:13:38 | THE FOLLOWING COMMENTS ARE ON THE PROPOSED DRAWINGS FOR | | | THE MINOR AMENDMENT TO THE SITE PLAN SUBMITTED | | | 2/15/2022. | | | | | | 1. REVIEW PROPOSED GRADE OF 13.00 FT NAVD ADJACENT TO | | | THE LANDSCAPE ISLAND IN THE MIDDLE OF THE EAST PARKING | | | SPACES. THERE IS A PROPOSED GRADE OF 13.50 FT NAVD AT | | | THE NOSE OF THE LANDSCAPE ISLAND. | | | | | | 2. SUGGEST GRADING HANDICAP ACCESS ISLAND BEHIND THE | | | DUMPSTER TO NOT DRAIN TO THE DUMSPSTER PAD. | | | | | | 3. PEDESTRIAN CROSSING FOR EAST HANDICAP PARKING SPACE | | | MAY NOT BE PERMISSABLE BECAUSE IT IS LOCATED BEHIND A | | | PARKING SPACE. CHECK WITH THE BUILDING DEPARTMENT. | | | | | | 4. WHY THE CURVY CURBING BETWEEN THE DUMPSTER AND | | | PARKING BEHIND THE BUILDING. | | | | | | 5. LIGHT POLES SHOULD NOT BE PLACED WITHIN THE 2-FOOT | | | LANDSCAPE OVERHANG OF PARKING SPACES. | | | | | | TRACY WARD, PE | | | SENIOR STORMWATER ENGINEER | | | ENGINEERING SERVICES DEPARTMENT | | | 561-494-1120 (O) | | | [email protected] | | | |
|
|
| Review Stop |
SURVEY |
SURVEYING |
| Rev No |
1 |
Status |
|
Date |
|
|
|
Cont ID |
|
| Sent By |
|
Date |
|
Time |
|
Rev Time |
|
| Received By |
|
Date |
|
Time |
|
Sent To |
|
|
| Notes |
|
|
| Review Stop |
TRAFFIC |
TRAFFIC ENGINEERING |
| Rev No |
4 |
Status |
P |
Date |
03-29-2022 |
|
|
Cont ID |
|
| Sent By |
|
Date |
03-29-2022 |
Time |
|
Rev Time |
0.00 |
| Received By |
|
Date |
|
Time |
|
Sent To |
|
|
| Notes |
| 2022-03-29 15:09:49 | 1) SATISFIED. TO VERIFY THE PROPOSED NEW LOADING ZONE | | | OPERATIONAL FEASIBILITY, PLEASE PROVIDE AUTOTURN | | | ANALYSIS FOR GARBAGE TRUCK AND DELIVERY/SERVICE | | | VEHICLES DRIVING IN AND OUT OF THE PROPOSED DEVELOPMENT | | | WITH VEHICLE DYNAMIC ENVELOPES CLEARLY DEFINED. | | | ANALYSIS SHOULD BE PROVIDED IN A SEPARATE SITE PLAN | | | DRAWING FOR CLARITY PURPOSES | | | 2) SATISFIED. CONTACT PALM TRAN PERTAINING THE BUS STOP | | | RELOCATION. IF FEASIBLE, PLEASE INSTALL A BUS SHELTER. | | | PLEASE CC ENGINEERING SERVICES FOR EMAIL CORRESPONDENCE | | | IN THIS MATTER. | | | 3) SATISFIED. PLEASE ADDRESS THE CONDITIONS IMPOSED | | | DURING THE PREVIOUS APPLICATION: | | | A. UPDATE THE TRAFFIC STUDY BY SHOWCASING EXPECTED | | | TURNING VOLUMES OF THE DRIVEWAY ON DIXIE HIGHWAY | | | B. PROVIDE SYNCHRO ANALYSIS FOR THE FOLLOWING TWO | | | INTERSECTIONS: S DIXIE/BELVEDERE AND S DIXIE/VALENCIA | | | | | | VALERIO ORICCHIO | | | CITY TRANSPORTATION ENGINEER | | | 561-494-1092 | | | [email protected] | | | |
|
|
| Review Stop |
TRAFFIC |
TRAFFIC ENGINEERING |
| Rev No |
3 |
Status |
P |
Date |
03-25-2022 |
|
|
Cont ID |
|
| Sent By |
|
Date |
03-25-2022 |
Time |
|
Rev Time |
0.00 |
| Received By |
|
Date |
|
Time |
|
Sent To |
|
|
| Notes |
| 2022-03-11 15:13:04 | 1) SATISFIED. TO VERIFY THE PROPOSED NEW LOADING ZONE | | | OPERATIONAL FEASIBILITY, PLEASE PROVIDE AUTOTURN | | | ANALYSIS FOR GARBAGE TRUCK AND DELIVERY/SERVICE | | | VEHICLES DRIVING IN AND OUT OF THE PROPOSED DEVELOPMENT | | | WITH VEHICLE DYNAMIC ENVELOPES CLEARLY DEFINED. | | | ANALYSIS SHOULD BE PROVIDED IN A SEPARATE SITE PLAN | | | DRAWING FOR CLARITY PURPOSES | | | 2) SATISFIED. CONTACT PALM TRAN PERTAINING THE BUS STOP | | | RELOCATION. IF FEASIBLE, PLEASE INSTALL A BUS SHELTER. | | | PLEASE CC [email protected] FOR EMAIL CORRESPONDENCE IN | | | THIS MATTER. | | | 3) SATISFIED. PLEASE ADDRESS THE CONDITIONS IMPOSED | | | DURING THE PREVIOUS APPLICATION: | | | A. UPDATE THE TRAFFIC STUDY BY SHOWCASING EXPECTED | | | TURNING VOLUMES OF THE DRIVEWAY ON DIXIE HIGHWAY | | | B. PROVIDE SYNCHRO ANALYSIS FOR THE FOLLOWING TWO | | | INTERSECTIONS: S DIXIE/BELVEDERE AND S DIXIE/VALENCIA | | | | | | VALERIO ORICCHIO | | | CITY TRANSPORTATION ENGINEER | | | 561-494-1092 | | | [email protected] | | | |
|
|
| Review Stop |
TRAFFIC |
TRAFFIC ENGINEERING |
| Rev No |
2 |
Status |
F |
Date |
03-04-2022 |
|
|
Cont ID |
|
| Sent By |
|
Date |
03-04-2022 |
Time |
|
Rev Time |
0.00 |
| Received By |
|
Date |
|
Time |
|
Sent To |
|
|
| Notes |
| 2022-03-04 13:01:30 | 1) VERIFY THE PROPOSED NEW LOADING ZONE OPERATIONAL | | | FEASIBILITY, PLEASE PROVIDE AUTOTURN ANALYSIS FOR | | | GARBAGE TRUCK AND DELIVERY/SERVICE VEHICLES DRIVING IN | | | AND OUT OF THE PROPOSED DEVELOPMENT WITH VEHICLE | | | DYNAMIC ENVELOPES CLEARLY DEFINED. ANALYSIS SHOULD BE | | | PROVIDED IN A SEPARATE SITE PLAN DRAWING FOR CLARITY | | | PURPOSES | | | 2) CONTACT PALM TRAN PERTAINING THE BUS STOP | | | RELOCATION. IF FEASIBLE, PLEASE INSTALL A BUS SHELTER | | | 3) PLEASE ADDRESS THE CONDITIONS IMPOSED DURING THE | | | PREVIOUS APPLICATION, SPECIFICALLY: | | | A. UPDATE THE TRAFFIC STUDY BY SHOWCASING EXPECTED | | | TURNING VOLUMES OF THE DRIVEWAY ON DIXIE HIGHWAY | | | B. PROVIDE SYNCHRO ANALYSIS FOR THE FOLLOWING TWO | | | INTERSECTIONS: S DIXIE/BELVEDERE AND S DIXIE/VALENCIA | | | | | | VALERIO ORICCHIO | | | CITY TRANSPORTATION ENGINEER | | | 561-494-1092 | | | [email protected] | | | |
|
|
| Review Stop |
TRAFFIC |
TRAFFIC ENGINEERING |
| Rev No |
1 |
Status |
F |
Date |
02-16-2022 |
|
|
Cont ID |
|
| Sent By |
|
Date |
02-16-2022 |
Time |
|
Rev Time |
|
| Received By |
|
Date |
|
Time |
|
Sent To |
|
|
| Notes |
| 2022-02-16 21:47:13 | SITE AND TRAFFIC COMMENTS | | | 1) TO VERIFY PROPOSED LOADING ZONE OPERATIONAL | | | FEASIBILITY, PLEASE PROVIDE AUTOTURN ANALYSIS FOR | | | GARBAGE TRUCK AND DELIVERY/SERVICE VEHICLES DRIVING IN | | | AND OUT OF THE PROPOSED DEVELOPMENT WITH VEHICLE | | | DYNAMIC ENVELOPES CLEARLY DEFINED. ANALYSIS SHOULD BE | | | PROVIDED IN A SEPARATE FILE/DRAWING. PLEASE PROVIDE | | | DOCUMENT NAME AND SHEET NUMBER SHOWCASING THE ANALYSIS | | | 2) CONTACT PALM TRAN PERTAINING THE BUS STOP | | | RELOCATION. IF FEASIBLE, PROVIDE A BUS SHELTER. | | | 3) PLEASE ADDRESS THE CONDITIONS IMPOSED DURING THE | | | PREVIOUS APPLICATION: | | | A. UPDATE THE TRAFFIC STUDY BY SHOWCASING EXPECTED | | | TURNING VOLUMES OF THE DRIVEWAY ON DIXIE HIGHWAY | | | B. PROVIDE SYNCHRO ANALYSIS FOR THE FOLLOWING TWO | | | INTERSECTIONS: S DIXIE/BELVEDERE AND S DIXIE/VALENCIA | | | | | | VALERIO ORICCHIO | | | CITY TRANSPORTATION ENGINEER | | | 561-494-1092 | | | [email protected] | | | |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
4 |
Status |
P |
Date |
04-06-2022 |
|
|
Cont ID |
|
| Sent By |
llouie |
Date |
04-06-2022 |
Time |
|
Rev Time |
0.00 |
| Received By |
llouie |
Date |
04-06-2022 |
Time |
|
Sent To |
|
|
| Notes |
| 2022-04-06 09:05:27 | SUBJECT TO THE FOLLOWING CONDITIONS: | | | | | | 1.) A 6-FOOT TALL PROTECTIVE OPAQUE SCREEN FENCE/WALL | | | SHALL BE PROVIDED ALONG THE EAST PROPERTY LINE ABUTTING | | | THE PROPERTY AT 320 VALENCIA ROAD. IT IS RECOMMENDED | | | THAT THE REQUIRED 6-FOOT TALL FENCE/WALL IS PLACED AT | | | LEAST 1-FOOT FROM THE EAST PROPERTY LINE WITHIN THE | | | 5-FOOT WIDE UTILITY EASEMENT. | | | | | | 2.) SIGNED EASEMENT CONSENT FROM ALL UTILITY PROVIDERS | | | (AT&T, COMCAST, FPL, FPU AND THE CITY OF WEST PALM | | | BEACH) SHALL BE REQUIRED FOR THE 6-FOOT TALL PROTECTIVE | | | OPAQUE SCREEN FENCE/WALL LOCATED ALONG THE EAST | | | PROPERTY LINE WITHIN THE 5-FOOT WIDE UTILITY EASEMENT | | | PRIOR TO THE ISSUANCE OF THE BUILDING PERMIT FOR THE | | | REQUIRED FENCE/WALL. | | | | | | 3.) THE APPLICANT SHALL MAINTAIN THE EAST LANDSCAPE | | | BUFFER AND REQUIRED 6-FOOT TALL PROTECTIVE OPAQUE | | | FENCE/WALL ALONG THE EAST PROPERTY LINE AT ALL TIMES. | | | | | | 4.) SIGNAGE IS NOT A PART OF THIS APPROVAL. ALL SIGNAGE | | | FOR THE PROJECT SHALL BE REVIEWED AT TIME OF BUILDING | | | PERMIT FOR CONSISTENCY WITH ARTICLE XIII (SIGN | | | REGULATIONS) OF THE ZONING AND LAND DEVELOPMENT | | | REGULATIONS (ZLDRS). | | | | | | 5.) THE DUMPSTER ENCLOSURE SHALL COMPLY WITH THE LATEST | | | REVISION OF THE CITY OF WEST PALM BEACH GENERAL | | | CONSTRUCTION-GARBAGE ENCLOSURE STANDARDS , GC-7. | | | | | | 6.) PRIOR TO THE REMOVAL OR RELOCATION OF ANY TREES ON | | | THE PROPERTY, A TREE ALTERATION PERMIT SHALL BE | | | SUBMITTED, REVIEWED AND APPROVED BY THE DEVELOPMENT | | | SERVICES DEPARTMENT - PLANNING DIVISION. | | | | | | 7.) THE CONDITIONS PROVIDED IN THE CONDITIONAL APPROVAL | | | LETTER FOR ISPR CASE NO. 20-09, ISSUED BY THE | | | DEVELOPMENT SERVICES DEPARTMENT - PLANNING DIVISION ON | | | MAY 19, 2021, ARE STILL VALID AND SHALL ALSO APPLY TO | | | THE APPROVAL OF THIS AMENDMENT (IN ADDITION TO THE | | | CONDITIONS LISTED ABOVE). | | | | | | | | | |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
3 |
Status |
P |
Date |
03-18-2022 |
|
|
Cont ID |
|
| Sent By |
llouie |
Date |
03-18-2022 |
Time |
|
Rev Time |
0.00 |
| Received By |
llouie |
Date |
03-18-2022 |
Time |
|
Sent To |
|
|
| Notes |
| 2022-03-18 14:10:07 | GENERAL COMMENTS: | | | | | | 1.) CAN THE RECENTLY-INSTALLED (AND UNATTRACTIVE) | | | ROOFTOP MECHANICAL EQUIPMENT BE SCREENED FROM VIEW? THE | | | ADDITIONAL SCREENING WOULD MAKE THE BUILDING LOOK MORE | | | ATTRACTIVE FROM THE STREET LEVEL. | | | | | | 2.) ALL FINAL PLANS (I.E. ARCHITECTURAL, CIVIL AND | | | LANDSCAPE PLANS) SHALL BE SIGNED, DATED AND SEALED BY | | | THE ENGINEER, ARCHITECT AND LANDSCAPE ARCHITECT. | | | . ANY CHANGES TO THE PLAN SHEETS WILL REQUIRE | | | CONSISTENCY WITH ALL OTHER PLAN SHEETS FOR THE PROJECT. | | | 3.) ANY CHANGES TO THE PLAN SHEETS WILL REQUIRE | | | CONSISTENCY WITH ALL OTHER PLAN SHEETS FOR THE PROJECT. | | | | | | | | | CONDITIONS OF APPROVAL: | | | | | | * SIGNAGE IS NOT A PART OF THIS APPROVAL. ALL SIGNAGE | | | FOR THE PROJECT SHALL BE REVIEWED AT THE TIME OF | | | BUILDING PERMIT FOR CONSISTENCY WITH THE ZONING AND | | | LAND DEVELOPMENT REGULATIONS (ZLDRS). | | | | | | * SIGNED EASEMENT CONSENT FROM ALL UTILITY PROVIDERS | | | (AT&T, COMCAST, FPL, FPU AND THE CITY OF WEST PALM | | | BEACH) FOR THE REQUIRED 6-FOOT TALL PROTECTIVE OPAQUE | | | SCREEN WALL LOCATED WITHIN THE 5 FT. WIDE UTILITY | | | EASEMENT ALONG THE EAST PROPERTY LINE SHALL BE PROVIDED | | | TO STAFF PRIOR TO THE ISSUANCE OF A BUILDING PERMIT FOR | | | THE FENCE. | | | | | | * THE APPLICANT WILL BE REQUIRED TO MAINTAIN THE EAST | | | LANDSCAPE BUFFER AND REQUIRED 6 FT. HIGH PROTECTIVE | | | OPAQUE SCREEN WALL ALONG THE ENTIRE EAST PROPERTY LINE | | | AT ALL TIMES. | | | | | | | | | INSTRUCTIONS FOR RESUBMITTAL: | | | | | | * PLEASE PROVIDE RESPONSES TO REVIEW COMMENTS IN | | | WRITTEN FORMAT. | | | | | | * WHEN RESUBMITTING, PLEASE PROVIDE A MINIMUM OF 4 | | | PAPER COPIES, ONE REDUCED COPY IN 11 INCHES X 17 | | | INCHES, AND AN ELECTRONIC COPY OF ALL DOCUMENTS AND | | | PLANS. | | | | | | * PLEASE NOTE THAT CHANGES ON THE RESUBMITTED PLANS MAY | | | RESULT IN ADDITIONAL COMMENTS. | | | | | | * PLEASE NOTE THAT YOU WILL BE PERMITTED ONE (1) | | | RESUBMITTAL AT NO ADDITIONAL COST. IF PREVIOUSLY-ISSUED | | | COMMENTS CONTINUE TO NOT BE SUFFICIENTLY ADDRESSED, THE | | | APPLICANT WILL BE ASSESSED A RESUBMITTAL FEE. SUCH FEE | | | WILL BE 20% OF THE ORIGINAL APPLICATION FEE ($60). | | | | | | * CONTACT LINDA LOUIE @ (561) 822-1458 IF THERE ARE ANY | | | QUESTIONS. | | | |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
2 |
Status |
F |
Date |
02-25-2022 |
|
|
Cont ID |
|
| Sent By |
llouie |
Date |
02-25-2022 |
Time |
|
Rev Time |
0.00 |
| Received By |
llouie |
Date |
02-25-2022 |
Time |
|
Sent To |
|
|
| Notes |
| 2022-02-25 15:04:51 | GENERAL COMMENTS: | | | | | | 1.) THE SIGNED LETTER FROM THE PROPERTY OWNER AT 326 | | | VALENCIA ROAD, EXEMPTING THE PROJECT FROM PROVIDING THE | | | REQUIRED OPAQUE FENCE/WALL BETWEEN PROPERTIES, MUST BE | | | NOTARIZED PER SEC. 94-443(A) OF THE ZONING AND LAND | | | DEVELOPMENT REGULATIONS (ZLDRS). | | | | | | 2.) A SIGNED AND NOTARIZED LETTER FROM THE PROPERTY | | | OWNER AT 320 VALENCIA ROAD SHALL BE PROVIDED TO EXEMPT | | | THE PROJECT FROM PROVIDING THE REQUIRED OPAQUE | | | FENCE/WALL BETWEEN PROPERTIES. IF THIS CANNOT BE | | | ACHIEVED, THE APPLICANT WILL BE REQUIRED TO PROVIDE THE | | | OPAQUE FENCE/WALL PER SEC. 94-443(A) OF THE ZLDRS. IT | | | WAS RECOMMENDED BY STAFF THAT THE FENCE/WALL BE PLACE 1 | | | FT. OFF THE PROPERTY LINE, WITHIN THE 5 FT. WIDE | | | LANDSCAPE BUFFER/UTILITY EASEMENT. | | | | | | 3.) IN ADDITION TO A NOTATION IN THE SITE PLAN (SEE | | | SITE PLAN COMMENT), IT MUST BE CLEAR IN THE | | | JUSTIFICATION STATEMENT THAT THE 12 FT. WIDE CONCRETE | | | SLAB "TO SEAT SMALL GROUPS," IS NOT MEANT FOR | | | ADDITIONAL PATRON SEATING BEYOND THE 166 SEATS APPROVED | | | FOR THE PROJECT. ANY ADDITIONAL SEATING BEYOND THE | | | APPROVED 166 SEATS WILL IMPACT THE PARKING REQUIREMENT | | | AND ADDITIONAL PARKING SPACES WILL NEED TO BE PROVIDED | | | FOR THE PROJECT. | | | | | | 4.) ALL FINAL PLANS (I.E. ARCHITECTURAL, CIVIL AND | | | LANDSCAPE PLANS) SHALL BE SIGNED, DATED AND SEALED BY | | | THE ENGINEERING, ARCHITECT AND LANDSCAPE ARCHITECT. | | | | | | | | | SITE PLAN COMMENTS: | | | | | | 1.) PLEASE PROVIDE THE FOLLOWING NOTE ALONG THE EAST | | | PROPERTY LINE (ALONG THE ADJACENT LOT LINE FOR 326 | | | VALENCIA ROAD): "EXISTING CHAIN LINK FENCE AND HEDGE ON | | | THE PROPERTY AT 326 VALENCIA ROAD TO REMAIN PER SIGNED | | | AND NOTARIZED LETTER FROM THE PROPERTY OWNER AT 326 | | | VALENCIA ROAD (LETTER ON FILE WITH THE DEVELOPMENT | | | SERVICES DEPARTMENT ? PLANNING DIVISION)." | | | | | | 2.) PLEASE ADDRESS THE FOLLOWING IN THE ZONING AND SITE | | | DATA CALCULATIONS: A) PER THE DEFINITION FOR "BUILDING" | | | IN THE ZLDRS, THE SMOKER AREA MUST BE INCLUDED IN THE | | | BUILDING AREA CALCULATIONS. THE BUILDING CALCULATIONS | | | ONLY REFLECT THE EXISTING BUILDING AND THE NEW WALK- IN | | | COOLER. REVISE CALCULATIONS WHERE NECESSARY. B) THE | | | DATA INDICATES THAT THERE ARE 26 PARKING SPACES | | | PROVIDED; HOWEVER, ONLY 25 PARKING SPACES HAVE BEEN | | | COUNTED IN THE SITE PLAN. PLEASE ADDRESS FOR | | | CONSISTENCY. | | | | | | 3.) ALTHOUGH PROVIDED IN THE ARCHITECTURAL ELEVATIONS, | | | PLEASE NOTE THE HEIGHT OF THE WALL FOR THE ELECTRICAL | | | EQUIPMENT ON THE SOUTH SIDE OF THE BUILDING IN THE SITE | | | PLAN FOR REFERENCE. | | | | | | 4.) A ROW OF 5 PARKING SPACES HAVE BEEN COUNTED ALONG | | | THE WEST SIDE OF THE PROPERTY (NOT 4 SPACES). PLEASE | | | CORRECT FOR CONSISTENCY. | | | | | | 5.) PLEASE UPDATE SHEET A002 IN THE PREVIOUS APPROVED | | | SITE PLAN AND INCLUDE THE UPDATED SHEET AS PART OF THE | | | MINOR SITE PLAN AMENDMENT PLAN SET. PARKING STALL | | | STRIPING/BIKE PARKING DETAIL MUST BE INCLUDED AS PART | | | OF THE REVISION AND THE "EXISTING SIGN DETAIL" MUST BE | | | ELIMINATED FROM SHEET A002, AS THE EXISTING SIGN WILL | | | BE REMOVED FROM THE SITE AND A NEW FREESTANDING SIGN | | | WILL BE PROVIDED IN ITS PLACE. | | | | | | | | | INSTRUCTIONS FOR RESUBMITTAL: | | | | | | * PLEASE PROVIDE RESPONSES TO REVIEW COMMENTS IN | | | WRITTEN FORMAT. | | | | | | * WHEN RESUBMITTING, PLEASE PROVIDE A MINIMUM OF 4 | | | PAPER COPIES, ONE REDUCED COPY IN 11 INCHES X 17 | | | INCHES, AND AN ELECTRONIC COPY OF ALL DOCUMENTS AND | | | PLANS. | | | | | | * PLEASE NOTE THAT CHANGES ON THE RESUBMITTED PLANS MAY | | | RESULT IN ADDITIONAL COMMENTS. | | | | | | * PLEASE NOTE THAT YOU WILL BE PERMITTED ONE (1) | | | RESUBMITTAL AT NO ADDITIONAL COST. IF PREVIOUSLY-ISSUED | | | COMMENTS CONTINUE TO NOT BE SUFFICIENTLY ADDRESSED, THE | | | APPLICANT WILL BE ASSESSED A RESUBMITTAL FEE. SUCH FEE | | | WILL BE 20% OF THE ORIGINAL APPLICATION FEE ($60). | | | | | | * CONTACT LINDA LOUIE @ (561) 822-1458 IF THERE ARE ANY | | | QUESTIONS. | | | | | | | | | | | | CONDITIONS OF APPROVAL: | | | | | | * SIGNAGE IS NOT A PART OF THIS APPROVAL. ALL SIGNAGE | | | FOR THE PROJECT SHALL BE REVIEWED AT THE TIME OF | | | BUILDING PERMIT FOR CONSISTENCY WITH THE ZONING AND | | | LAND DEVELOPMENT REGULATIONS (ZLDRS). | | | | | | * SIGNED EASEMENT CONSENT FROM ALL UTILITY PROVIDERS | | | (AT&T, COMCAST, FPL, FPU AND THE CITY OF WEST PALM | | | BEACH) FOR THE 8-FOOT TALL OPAQUE FENCE LOCATED WITHIN | | | THE 5 FT. UTILITY EASEMENT ALONG THE EAST PROPERTY LINE | | | SHALL BE PROVIDED TO STAFF PRIOR TO THE ISSUANCE OF THE | | | BUILDING PERMIT FOR THE FENCE. | | | | | | * THE APPLICANT WILL BE REQUIRED TO MAINTAIN THE EAST | | | LANDSCAPE BUFFER AND 8 FT. HIGH FENCE WITHIN THE 5 FT. | | | WIDE UTILITY EASEMENT AS PROVIDED IN THE APPROVED SITE | | | AND LANDSCAPE PLANS AT ALL TIMES. | | | |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
1 |
Status |
F |
Date |
02-16-2022 |
|
|
Cont ID |
|
| Sent By |
llouie |
Date |
02-16-2022 |
Time |
|
Rev Time |
|
| Received By |
llouie |
Date |
02-16-2022 |
Time |
|
Sent To |
|
|
| Notes |
| 2022-02-16 14:15:22 | MET WITH STEPHEN BUTLER, MICHAEL PERRY AND LANDSCAPE | | | ARCHITECT ON 2/16/2022 TO GO OVER IMPROVEMENTS AND | | | INCONSISTENCIES WITH THE ZLDRS TO THE SITE AND | | | LANDSCAPE PLANS. RESUBMITTAL EXPECTED SHORTLY. |
|
|
| |
Print |