Plan Review Details - Project Z21020016
Plan Review Stops For Project Z21020016
Review Stop AIPP ART IN PUBLIC PLACES
Rev No 3 Status F Date 04-09-2021 Cont ID  
Sent By scwelter Date 04-09-2021 Time 15:32 Rev Time 0.00
Received By scwelter Date 04-09-2021 Time 15:32 Sent To  
Notes
2021-04-09 15:35:45PUBLIC ART REQUIREMENT:
 IF TOTAL CONSTRUCTION COSTS OF THIS DEVELOPMENT ARE
 OVER $500,000 IT WILL BE SUBJECT TO THE PUBLIC ART
 REQUIREMENT AS PER CITY ORDINANCE.
 SECTION 78-129: ALL PRIVATE DEVELOPMENT PROJECTS,
 INCLUDING NEW CONSTRUCTION, OR THE RENOVATION OR
 IMPROVEMENT OF AN EXISTING BUILDING, WHERE TOTAL
 CONSTRUCTION COSTS ARE EQUAL TO OR GREATER THAN
 $500,000 ARE SUBJECT TO THE PUBLIC ART REQUIREMENT.
 OPTION 1: INSTALL ARTWORK ON THE DEVELOPMENT SITE
 VALUED IN AN AMOUNT NOT LESS THAN ONE PERCENT OF THE
 TOTAL CONSTRUCTION COSTS; OR
 OPTION 2: CONTRIBUTE AN AMOUNT EQUAL TO 75 PERCENT OF
 ONE PERCENT OF THE TOTAL CONSTRUCTION COSTS FOR DEPOSIT
 TO THE PUBLIC ART ACCOUNT.
 A COMPLETED PUBLIC ART ASSESSMENT APPLICATION IS
 REQUIRED AT TIME OF BUILDING PERMIT SUBMITTAL.
  
 NOTE GIANT PINK FLAMINGO MAY NOT BE USED TO SATISFY THE
 PUBLIC ART REQUIREMENT.
  
 PLEASE CONTACT SYBILLE WELTER AT [email protected] OR
 561.822.1521 TO OBTAIN AN APPLICATION AND REVIEW THE
 REQUIREMENTS.
  

Review Stop AIPP ART IN PUBLIC PLACES
Rev No 1 Status F Date 03-11-2021 Cont ID  
Sent By scwelter Date 03-11-2021 Time 10:55 Rev Time 0.00
Received By scwelter Date 03-11-2021 Time 10:53 Sent To  
Notes
2021-03-11 10:55:12PUBLIC ART REQUIREMENT:
 IF TOTAL CONSTRUCTION COSTS OF THIS DEVELOPMENT ARE
 OVER $500,000 IT WILL BE SUBJECT TO THE PUBLIC ART
 REQUIREMENT AS PER CITY ORDINANCE.
 SECTION 78-129: ALL PRIVATE DEVELOPMENT PROJECTS,
 INCLUDING NEW CONSTRUCTION, OR THE RENOVATION OR
 IMPROVEMENT OF AN EXISTING BUILDING, WHERE TOTAL
 CONSTRUCTION COSTS ARE EQUAL TO OR GREATER THAN
 $500,000 ARE SUBJECT TO THE PUBLIC ART REQUIREMENT.
 OPTION 1: INSTALL ARTWORK ON THE DEVELOPMENT SITE
 VALUED IN AN AMOUNT NOT LESS THAN ONE PERCENT OF THE
 TOTAL CONSTRUCTION COSTS; OR
 OPTION 2: CONTRIBUTE AN AMOUNT EQUAL TO 75 PERCENT OF
 ONE PERCENT OF THE TOTAL CONSTRUCTION COSTS FOR DEPOSIT
 TO THE PUBLIC ART ACCOUNT.
 A COMPLETED PUBLIC ART ASSESSMENT APPLICATION IS
 REQUIRED AT TIME OF BUILDING PERMIT SUBMITTAL.
  
 PLEASE CONTACT SYBILLE WELTER AT [email protected] OR
 561.822.1521 TO OBTAIN AN APPLICATION AND REVIEW THE
 REQUIREMENTS.
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 04-16-2021 Cont ID  
Sent By rbrown Date 04-16-2021 Time 18:12 Rev Time 0.00
Received By rbrown Date 04-16-2021 Time 18:12 Sent To  
Notes
2021-04-16 18:13:38DEVELOPMENT SERVICES DEPARTMENT, BUILDING DIVISION,
 COMMENTS:
  
 1. THIS REVIEW IS A CURSORY REVIEW AS IT RELATES TO THE
 SITE. IT IS NOT A REVIEW FOR FULL COMPLIANCE WITH
 FLORIDA BUILDING CODE. THE FOLLOWING COMMENTS ARE TO BE
 ADDRESSED FOR THE BUILDING PERMIT APPLICATION.
  
 2. DEMOLITION OF THE EXISTING BUILDING. AN ASBESTOS
 SURVEY SHALL BE PERFORMED AND AN ASBESTOS ABATEMENT
 REPORT SUBMITTED TO THE HEALTH DEPARTMENT PALM BEACH
 COUNTY OFFICE. CONTACT ALEX ORTEGA AT (561) 837-5963,
 OR BY EMAIL: [email protected]
  
 3. BUILDING SIZE. WHEN SUBMITTED FOR BUILDING PERMIT,
 THE PLANS SHALL SHOW THAT THE TYPE OF CONSTRUCTION FOR
 THE BUILDINGS WILL BE IN ACCORDANCE WITH THE HEIGHT,
 AREA AND OCCUPANCY LIMITATIONS IN CHAPTER 5 OF THE
 FLORIDA BUILDING CODE.
  
 4. GREASE/OIL INTERCEPTOR. A GREASE/OIL INTERCEPTOR
 WILL BE REQUIRED. FOR INFORMATION ON THE REQUIRED TYPE,
 SIZE AND LOCATION, PLEASE CONTACT TIM LARGE, CHIEF
 PLUMBING INSPECTOR, DEVELOPMENT SERVICES DEPARTMENT, AT
 (561) 805-6692, OR BY EMAIL: [email protected]
  
 5. SEPARATE PERMITS REQUIRED. ALL APPLICABLE PERMITS
 AND SUB-PERMITS MUST BE OBTAINED BEFORE COMMENCING THE
 WORK. SEPARATE PERMITS, PLANS AND FEES, ARE REQUIRED
 FOR SIGNS, GAS SYSTEMS, GENERATORS, FIRE ALARM SYSTEMS,
 FIRE SPRINKLER AND OTHER FIRE SUPPRESSION SYSTEMS,
 GREASE INTERCEPTORS, SITE LIGHTING, SITE LANDSCAPE,
 SITE IRRIGATION, ETC.
  
 6. PROTECTION OF NEIGHBORING PROPERTY. PROPERTY OWNER
 AND CONTRACTOR SHALL PROTECT ALL NEIGHBORING PROPERTY,
 INCLUDING VEHICLES, FROM DAMAGE OR DIRT CAUSED BY THE
 CONSTRUCTION, AND SHALL NOTIFY THE OCCUPANTS OF
 NEIGHBORING PROPERTIES ABOUT ALL STAGES OF CONSTRUCTION
 THAT MAY AFFECT THE USE OF THEIR PROPERTY.
  
 7. ART IN PUBLIC PLACES. THIS PROJECT WILL BE SUBJECT
 TO ART IN PUBLIC PLACES (AIPP) ASSESSMENT. FOR ADVICE
 ON THE PROVISION OF PUBLIC ARTWORK IN LIEU OF THE AIPP
 ASSESSMENT, CONTACT SYBILLE WELTER, ART IN PUBLIC
 PLACES COORDINATOR, AT (561) 822-1521, OR BY EMAIL:
 [email protected]
  
  
 ROBERT BROWN
 BUILDING OFFICIAL
 TEL: 561 805 6652
 EMAIL: [email protected]
  
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 03-10-2021 Cont ID  
Sent By rbrown Date 03-10-2021 Time 20:46 Rev Time 0.00
Received By scwelter Date 03-11-2021 Time 10:52 Sent To  
Notes
2021-03-10 20:56:03DEVELOPMENT SERVICES DEPARTMENT, BUILDING DIVISION,
 COMMENTS:
  
 1. THIS REVIEW IS A CURSORY REVIEW AS IT RELATES TO THE
 SITE. IT IS NOT A REVIEW FOR FULL COMPLIANCE WITH
 FLORIDA BUILDING CODE. THE FOLLOWING COMMENTS ARE TO BE
 ADDRESSED FOR THE BUILDING PERMIT APPLICATION.
  
 2. DEMOLITION OF THE EXISTING BUILDING. AN ASBESTOS
 SURVEY SHALL BE PERFORMED AND AN ASBESTOS ABATEMENT
 REPORT SUBMITTED TO THE HEALTH DEPARTMENT PALM BEACH
 COUNTY OFFICE. CONTACT ALEX ORTEGA AT (561) 837-5963,
 OR BY EMAIL: [email protected]
  
 3. LOCATION OF ACCESSIBLE PARKING SPACES. SITE PLAN,
 SHEET SP-1, SHOWS THAT THE ACCESSIBLE PARKING SPACES
 ARE NOT THE CLOSEST PARKING SPACES TO THE OFFICE. PER
 SECTION 208.3 OF FLORIDA ACCESSIBILITY CODE, ACCESSIBLE
 PARKING SPACES ARE TO BE LOCATED ON THE SHORTEST
 POSSIBLE ROUTE OF TRAVEL FROM ADJACENT PARKING TO AN
 ACCESSIBLE ENTRANCE. THE DESIGN OF ACCESSIBLE PARKING
 SPACES SHALL COMPLY WITH SECTION 502 OF FLORIDA
 ACCESSIBILITY CODE
  
 4. BUILDING SIZE. WHEN SUBMITTED FOR BUILDING PERMIT,
 THE PLANS SHALL SHOW THAT THE TYPE OF CONSTRUCTION FOR
 THE BUILDINGS WILL BE IN ACCORDANCE WITH THE HEIGHT,
 AREA AND OCCUPANCY LIMITATIONS IN CHAPTER 5 OF THE
 FLORIDA BUILDING CODE.
  
 5. GREASE/OIL INTERCEPTOR. A GREASE/OIL INTERCEPTOR
 WILL BE REQUIRED. FOR INFORMATION ON THE REQUIRED TYPE,
 SIZE AND LOCATION, PLEASE CONTACT TIM LARGE, CHIEF
 PLUMBING INSPECTOR, DEVELOPMENT SERVICES DEPARTMENT, AT
 (561) 805-6692, OR BY EMAIL: [email protected]
  
 6. SEPARATE PERMITS REQUIRED. ALL APPLICABLE PERMITS
 AND SUB-PERMITS MUST BE OBTAINED BEFORE COMMENCING THE
 WORK. SEPARATE PERMITS, PLANS AND FEES, ARE REQUIRED
 FOR SIGNS, GAS SYSTEMS, GENERATORS, FIRE ALARM SYSTEMS,
 FIRE SPRINKLER AND OTHER FIRE SUPPRESSION SYSTEMS,
 GREASE INTERCEPTORS, SITE LIGHTING, SITE LANDSCAPE,
 SITE IRRIGATION, ETC.
  
 7. PROTECTION OF NEIGHBORING PROPERTY. PROPERTY OWNER
 AND CONTRACTOR SHALL PROTECT ALL NEIGHBORING PROPERTY,
 INCLUDING VEHICLES, FROM DAMAGE OR DIRT CAUSED BY THE
 CONSTRUCTION, AND SHALL NOTIFY THE OCCUPANTS OF
 NEIGHBORING PROPERTIES ABOUT ALL STAGES OF CONSTRUCTION
 THAT MAY AFFECT THE USE OF THEIR PROPERTY.
  
 8. ART IN PUBLIC PLACES. THIS PROJECT WILL BE SUBJECT
 TO ART IN PUBLIC PLACES (AIPP) ASSESSMENT. FOR ADVICE
 ON THE PROVISION OF PUBLIC ARTWORK IN LIEU OF THE AIPP
 ASSESSMENT, CONTACT SYBILLE WELTER, ART IN PUBLIC
 PLACES COORDINATOR, AT (561) 822-1521, OR BY EMAIL:
 [email protected]
  
  
 ROBERT BROWN
 BUILDING OFFICIAL
 TEL: 561 805 6652
 EMAIL: [email protected]
  

Review Stop ENG - PPRC ENGINEERING - PPRC
Rev No 4 Status P Date 07-09-2021 Cont ID  
Sent By rrossano Date 07-09-2021 Time   Rev Time 0.00
Received By rrossano Date 07-09-2021 Time   Sent To  
Notes
***NONE***

Review Stop ENG - PPRC ENGINEERING - PPRC
Rev No 3 Status F Date 06-16-2021 Cont ID  
Sent By rrossano Date 06-16-2021 Time   Rev Time 0.00
Received By rrossano Date 06-16-2021 Time   Sent To  
Notes
2021-06-16 09:41:05THE FOLLOWING COMMENTS ARE FROM MARK HURLEY, FIELD
 CUSTOMER SERVICE SUPERVISOR
 CITY OF WEST PALM BEACH PUBLIC UTILITIES, 561-822-2262
 [email protected]
  
 -IF DOMESTIC WATER SERVICE AND METER BOX ON PRIVATE
 PROPERTY AND NOT IN UTILITY EASEMENT, THEN NEEDS
 UTILITY EASEMENT AROUND IT. UE SHOULD NOT INCLUDE
 BACKFLOW ASSEMBLIES.
  
 -PLEASE UPDATE LIGHT POLE POSITIONS ON CIVIL PLANS TO
 MATCH ADJUSTED SITE PLANS. ALSO ADD THE SAME CALLOUT
 NOTES ABOUT FIELD ADJUSTMENTS.
  
 -VERIFY WATER METER BOX WILL BE IN SOD.
  
 -HISTORIC PICTURES SHOW CROSSWALK AT NORTH DRIVEWAY.
 PLEASE VERIFY IF THE PROJECT CHANGING THAT TO CURBING
 OR IF REMAINING THE SAME.
  
 -FOR THE DIRECTIONAL SEPARATOR AT NORTH DRIVEWAY PLEASE
 VERIFY: 1) IF IT WILL BE SOD. 2) IF WILL HAVE RAISED
 CURBING. 3) WILL NOT CONFLICT WITH ADJACENT DRAINAGE
 STRUCTURE MAINTENANCE ? MAY NEED SOME SEPARATION
 DISTANCE.
  
 -VERIFY WHAT THE 2 FOOT UTILITY EASEMENT RUNNING ALONG
 EASTERN PROPERTY LINE IS BEING USED FOR. MAY BE A
 FRANCHISE UTILITY. IF SO, CHECK TO MAKE SURE THERE WILL
 BE NO MAINTENANCE CONFLICTS SUCH AS TREE ROOTS DAMAGING
 UTILITIES. MAY NEED ADDITIONAL ROOT BARRIERS OR
 CLEARANCE DISTANCE FOR PROPOSED TREES.
  
 -PROPOSED TREE LOOKS CLOSE TO PRIVATE FIRELINE BACKFLOW
 ASSEMBLY. ADD ROOT BARRIERS AS NEEDED.
  
 -IS THE WATER METER BOX REMAINING IN EXISTING LOCATION
 OR BEING RELOCATED?
  
  

Review Stop ENG - PPRC ENGINEERING - PPRC
Rev No 2 Status F Date 04-06-2021 Cont ID  
Sent By rrossano Date 04-06-2021 Time   Rev Time 0.00
Received By rrossano Date 04-06-2021 Time   Sent To  
Notes
2021-04-15 14:06:55THE FOLLOWING COMMENTS ARE FROM MARK HURLEY, FIELD
 CUSTOMER SERVICE SUPERVISOR
 CITY OF WEST PALM BEACH PUBLIC UTILITIES, 561-822-2262
 [email protected]
  
 PLEASE RESPOND IN WRITING TO COMMENTS AS FOLLOW:
  
 -LANDSCAPE PLAN SHOWS A 6 FOOT MONUMENT SIGN NEAR
 BACKFLOW ASSEMBLIES AND WATER SERVICES. PLEASE VERIFY
 MONUMENT SIGN IS AT LEAST THREE FEET AWAY FROM WATER
 UTILITIES.
  
 -LANDSCAPE PLAN SHOWS TREES NEAR WATER UTILITIES
 (BACKFLOW ASSEMBLIES, WATER SERVICES, METER BOXES, AND
 FIRE HYDRANTS). PLEASE ENSURE THERE ARE NO CONFLICTS
 AND ADD ROOT BARRIERS WHERE TREE ROOTS CAN ENCROACH ON
 WATER UTILITIES.
  
 -PROPERTY WILL HAVE TO PAY ASSOCIATED UTILITY BILLING
 FEES/CHARGES FOR FIRELINES ON SITE.
  
 -PLEASE ENSURE THAT LIGHTING POLES HAVE SUFFICIENT
 CLEARANCE DISTANCE FROM WATER UTILITIES.
  
 -EASTERN FIRE HYDRANT APPEARS TO BE SLIGHTLY
 ENCROACHING ON SIDEWALK. AT FORMAL ENGINEERING
 SUBMITTAL, PLEASE RELOCATE SLIGHTLY SO THAT PEDESTRIANS
 DO NOT WALK INTO THE FIRE HYDRANT.
  
 -AT FORMAL ENGINEERING SUBMITTAL, SUBMIT
 ENLARGED/ZOOMED PLAN OF THE AREA AROUND THE METERED
 WATER SERVICES AND BACKFLOW ASSEMBLIES. CANNOT SEE
 CLEARLY IF THE PROPOSED LAYOUT MEETS STANDARDS.
  

Review Stop ENG - PPRC ENGINEERING - PPRC
Rev No 1 Status F Date 03-04-2021 Cont ID  
Sent By rrossano Date 03-04-2021 Time   Rev Time  
Received By rrossano Date 03-04-2021 Time   Sent To  
Notes
2021-03-11 08:02:251. PLEASE SUBMIT A FORMAL AS-BUILT REQUEST FOR ALL CITY
 OF WEST PALM BEACH-OWNED UTILITIES WITHIN THE PUBLIC
 RIGHT OF WAY FOR THE ENTIRE EXTENT OF THE LIMITS OF
 YOUR PROJECT. IDENTIFY TYPE OF UTILITY, LOCATION, PIPE
 MATERIAL, AGE AND SIZE. PLEASE CONTACT JANICE TARBILL
 IN THE WPB ENGINEERING SERVICES DEPARTMENT AT
 [email protected] OR 561-494-1079 FOR FURTHER
 ASSISTANCE. NOTE THAT FIELD RECORDS ARE FOR INFORMATION
 ONLY. FIELD VERIFY UTILITY LOCATIONS USING FIELD
 SURVEY, POT-HOLING, SOFT DIGS ETC.
 2. AS OF DECEMBER 20, 2015, THE CITY OF WEST PALM BEACH
 CROSS-CONNECTION CONTROL MANUAL HAS BEEN REVISED,
 STATING "ALL BACKFLOW DEVICES MUST BE LEAD-FREE". FOR
 MORE INFORMATION, REFER TO THE LINK BELOW:
 HTTP://WPB.ORG/DEPARTMENTS/PUBLIC-UTILITIES/FORMS-PUBLI
 CATIONS/BACKFLOW-CROSS-CONNECTION-CONTROL-MANUAL
 3. PLEASE SUBMIT PRELIMINARY UTILITY ENGINEERING PLANS.
 PLANS SHALL SHOW PROPOSED LOCATIONS AND DIMENSIONS OF
 ALL WATER, STORM WATER, AND SANITARY AND SEWER LINES,
 INCLUDING STUBS TO EACH PROPERTY LINE FOR WATER AND
 SANITARY SEWERS, THE MAKE AND MODEL OF ALL VALVES,
 METERS, AND OTHERS DEVICES TO BE INSTALLED ON THE
 SYSTEM, CATCH BASINS, CULVERTS, DITCHES INCLUDING
 GRADES, PIPES SIZES, MATERIALS, ELEVATIONS,
 ASSUMPTIONS, CALCULATIONS, INVERT ELEVATIONS FOR ALL
 INLETS AND MANHOLES AND PROFILES OF SANITARY SEWER
 LINES. ALL AVAILABLE ELEVATION SHALL BE SHOWN ON THE
 PROFILE VIEW. DIRECTION OF FLOW SHALL BE SHOWN ON PLAN
 VIEW ON PLAN VIEW FOR ALL SANITARY AND STORM SEWERS.
 ADDITIONALLY, PLAN VIEW SHALL SHOW ALL EXISTING AND
 PROPOSED UNDERGROUND UTILITY LAYOUT, INCLUDING FIBER
 OPTIC, ELECTRIC, GAS, AND CABLEVISION &
 TELECOMMUNICATION FACILITIES LOCATED ON THE
 RIGHT-OF-WAY. PROVIDE PROFILE AND CLEARANCES AT ALL
 UTILITY CROSSINGS. CUT AND CAP UTILITIES NOT IN USE,
 AND REMOVE ANY ABANDONED UTILITY LINES LARGER THAN 2
 INCHES FROM CITY RIGHT OF WAY.
 4. PLEASE SUBMIT COMPLETED LOS ANALYSIS SUMMARY TABLE
 DIRECTLY TO ENGINEERING (SHEET 33 OF CITY OF WPB
 DEVELOPMENT APPLICATION).
 5. SHOW PROPOSED DUMPSTER ENCLOSURE PER CURRENT CITY OF
 WPB STANDARD DETAIL GC-7.
 6. CHECK TO SEE IF FDEP FORMS FOR PROPOSED SANITARY
 SEWER ARE REQUIRED.
 7. PLEASE CALLOUT DOMESTIC BACKFLOW PREVENTER AS RPPA
 AND FIRE BACKFLOW PREVENTER AS DCDA.
 8. PROVIDE VERTICAL DATUM AND DATUM CONVERSION
 INFORMATION (NAVD 1988 AND NGVD 1929).
 9. PROVIDE CALCULATIONS ON PLANS OF EXISTING AND
 PROPOSED DEMANDS FOR WATER & SEWER (AVERAGE, MAXIMUM
 AND PEAK) AND FIRE FLOW DEMANDS. CALCULATIONS SHALL BE
 PER FAC 64E-6 FOR SEWER AND PER FAC 64-E.008 FOR WATER.
 10. IS THERE A PROPOSED SANITARY CONNECTION? IF SO
 PROVIDE CCTV VIDEO OF EXISTING SANITARY AND STORM SEWER
 ALONG ENTIRE PROJECT FRONTAGE.
 11. FOR FORMAL ENGINEERING SUBMITTAL, PLEASE PROVIDE
 EASEMENT FOR PLACEMENT OF PROPOSED WATER METERS.
 12. FOR FORMAL ENGINEERING SUBMITTAL, PLEASE PROVIDE
 ENLARGED VIEW ON PLANS OF PROPOSED LOCATION OF WATER
 METER AND BACKFLOW PREVENTION.
 13. FOR FORMAL ENGINEERING SUBMITTAL, PROVIDE PROFILES
 OF WATER AND SEWER AND SHOW ANY CROSSINGS/CONFLICTS.
 14. FOR FORMAL ENGINEERING SUBMITTAL, WHEN SUBMITTING
 APPROVED MATERIALS LIST, PLEASE PROVIDE MATERIAL/CUT
 SHEETS FOR ALL PROPOSED BACKFLOW DEVICES SHOWING
 SPECIFIC MODEL NUMBER AND SPECIFYING USC APPROVED
 LEAD-FREE DESIGN.
 15. FOR FORMAL ENGINEERING SUBMITTAL CLEARLY SHOW ROAD
 RIGHT OF WAY.
 16. FOR FORMAL ENGINEERING SUBMITTAL, IF SANITARY MAINS
 ARE PROPOSED IN ROW PLEASE SHOW ADJACENT SANITARY
 LATERAL LOCATIONS AND SHOW ADDRESSES OF ADJACENT
 PARCELS.
 18. FOR FORMAL ENGINEERING SUBMITTAL, IF WATER MAINS
 ARE BEING REPLACED IN ROW, SHOW ADJACENT PARCEL
 ADDRESSES.
 19. FOR FORMAL ENGINEERING SUBMITTAL, ADD NOTE TO
 PROVIDE 50 FT. PAVEMENT RESTORATION TRANSITION ON EACH
 SIDE OF PROPOSED TRENCH IN CITY MAINTAINED ROADWAY
 AREAS PER CITY OF WPB STANDARD DETAIL GC-9.
 20. PLEASE NOTE THAT A PRE-PPRC-SUBMITTAL MEETING WITH
 ENGINEERING SERVICES IS HIGHLY SUGGESTED.
 21. PLEASE RESPOND TO ALL COMMENTS IN WRITING.
  
 RICK ROSSANO, PROJECT COORDINATOR, CITY OF WPB ENG.
 SERVICES
 DIRECT: (561) 494-1098 MOBILE: (561) 246-9525 FAX:
 (561) 494-1116 EMAIL: [email protected]
  
  
 THE FOLLOWING COMMENTS ARE FROM MARK HURLEY, FIELD
 CUSTOMER SERVICE SUPERVISOR
 CITY OF WEST PALM BEACH PUBLIC UTILITIES, 561-822-2262
 [email protected]
  
 PLEASE RESPOND IN WRITING TO COMMENTS AS FOLLOW:
  
 -PLEASE ADD SYMBOL LEGEND TO CIVIL ENGINEERING PLAN.
 INCLUDE THE SYMBOL THAT LOOKS LIKE A BULLSEYE.
  
 -ADD WATER DEMAND CALCULATIONS TO CIVIL PLAN.
  
 -DUMPSTER ENCLOSURE IS BUILT IN DRAINAGE EASEMENT. IS
 SPECIAL APPROVAL NEEDED TO DO THAT?
  
 -IF EXISTING DOMESTIC BACKFLOW ASSEMBLY IS NOT
 LEAD-FREE COMPLIANT, IT WILL NEED TO BE REPLACED WHEN
 RELOCATED.
  
 -IS A DRAINAGE EASEMENT NEEDED AT THE NORTH CORNER OF
 PROPERTY SIMILAR TO THE EAST CORNER?
  
 -FOR FORMAL ENGINEERING SUBMITTAL: VERIFY IF THERE IS A
 SHUT OFF VALVE FOR THE EASTERN FIRE HYDRANT AND SHOW ON
 PLAN, ADD WATER MAIN MATERIAL TYPE TO LABELS, AND ADD
 WATER SERVICE STANDARD DETAILS PAGE.
  
 -ADD PROPERTY ADDRESS TO CIVIL PLAN
  
 -THE EASTERN FIRE HYDRANT AND ENTRANCE SIDEWALK APPEAR
 TOO CLOSE TOGETHER. NEED MORE CLEARANCE FOR
 MAINTENANCE.
  
 -VERIFY LOCATION OF EASTERN HYDRANT. IF OUTSIDE OF
 UTILITY EASEMENT, MAY NEED ADDITIONAL EASEMENT.
  
 -STORMWATER UTILITY APPEARS TO BE CROSSING INTO
 ADJACENT PROPERTY. IS SPECIAL APPROVAL NEEDED TO DO
 THAT?
  
 -APPEARS TO BE SOME TREES CONFLICTS WITH UNDERGROUND
 UTILITIES. PLEASE VERIFY NO CONFLICT WITH ROOTS AND
 TREES NEAR THE DCDA FIRELINE SERVICE AND NEAR THE
 EASTERN CORNER OF PROPERTY NEAR PROPOSED CONTROL
 STRUCTURE AND OUTFALL PIPE.
  
 -IS THE MANHOLE NEAR EASTERN CORNER OF PROPERTY FOR
 STORMWATER DRAINAGE OR SANITARY SEWER?
  
 -ARE THERE PROPOSED FIRE SPRINKLERS IN BUILDING, AND IS
 THE BUSINESS INTENDING TO USE THE PRIVATELY-OWNED
 FIRELINE BACKFLOW ASSEMBLY.
  
  
  

Review Stop FIRE FIRE DEPARTMENT
Rev No 2 Status P Date 06-22-2021 Cont ID  
Sent By pleduc Date 06-22-2021 Time   Rev Time 0.00
Received By pleduc Date 06-22-2021 Time 11:52 Sent To  
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status P Date 03-05-2021 Cont ID  
Sent By pleduc Date 03-05-2021 Time 12:59 Rev Time 0.00
Received By pleduc Date 03-05-2021 Time 12:54 Sent To  
Notes
2021-03-05 12:59:05THE FOLLOWING COMMENTS WERE SUBMITTED BY PETER LEDUC,
 FIRE MARSHAL, BUREAU OF FIRE PREVENTION, WEST PALM
 BEACH FIRE RESCUE.
  
 THIS REVIEW CAN ONLY BE CONSIDERED PRELIMINARY AS THE
 DRAWINGS THAT WERE REVIEWED WERE NOT COMPLETE.
 ADDITIONAL COMMENTS CAN BE EXPECTED WHEN FULL DRAWINGS
 ARE SUBMITTED FOR PERMIT.
  
 THE FIRE PREVENTION BUREAU HAS NO OBJECTIONS TO THE
 PROPOSED PROJECT. THE FOLLOWING COMMENTS ARE INTENDED
 TO PROVIDE GUIDANCE FOR BUILDING PLAN SUBMITTAL.
  
 1. CONSTRUCTION, DEMOLITION, AND RENOVATION TO COMPLY
 WITH NFPA 241. EXTRA ATTENTION SHALL BE GIVEN TO THE
 PERMITTING AND LOCATION OF CONSTRUCTION TRAILERS. A
 PERMIT IS REQUIRED FOR ANY CONSTRUCTION TRAILER RELATED
 TO THIS PROJECT. SEPARATION DISTANCES FROM MAIN
 STRUCTURES AS WELL AS OTHER TRAILERS SHALL BE CLOSELY
 MONITORED FOR THE REQUIREMENTS OF FIRE SPRINKLER
 PROTECTION.
  
 2. SITE ACCESS AND EXIT POINTS ARE TO BE CLEARLY
 IDENTIFIED AND MAINTAINED FOR EMERGENCY VEHICLES DURING
 ALL CONSTRUCTION ACTIVITIES.
  
 3. THE BUILDING ADDRESS SHALL BE CLEARLY VISIBLE FROM
 ALL ACCESS ROADWAYS, INCLUDING DURING CONSTRUCTION.
 ADDRESS NUMBERS SHALL CONTRAST WITH THEIR BACKGROUND
 AND SHALL NOT BE LESS THAN SIX (6) INCHES IN HEIGHT
 WITH A ONE (1) INCH STROKE FOR ALL BUILDINGS.
  
 4. DURING CONSTRUCTION, TRASH AND DEBRIS IS TO BE
 REMOVED FROM THE SITE DAILY OR MORE OFTEN TO REDUCE THE
 ACCUMULATION OF POTENTIAL LIFE AND FIRE SAFETY HAZARDS.
  
 5. THE CONSTRUCTION OF THE BUILDING SHALL COMPLY WITH
 THE 7TH EDITION OF THE FLORIDA FIRE PREVENTION CODE,
 INCLUDING NFPA 1 & 101, AND ALL ASSOCIATED FIRE CODES.
  
 6. FOR PLAN REVIEW SUBMITTAL, PLEASE INCLUDE THE
 OCCUPANCY TYPE, PER THE FLORIDA FIRE PREVENTION CODE.
  
 7. FOR PLAN REVIEW SUBMITTAL, PLEASE ENSURE THAT AN
 THAT WATER SUPPLY IS EXISTING OR WILL BE PROVIDED.
  
 8. ALL EXISTING AND NEW FIRE HYDRANTS PLANNED FOR THIS
 DEVELOPMENT SHALL BE CLEARLY INDICATED AND IDENTIFIED
 ON THE PLAN AND CLOSELY COORDINATED WITH THE BUREAU OF
 FIRE PREVENTION.
  
 9. A COMPLETE LIFE SAFETY PLAN SHALL BE PROVIDED THAT
 ILLUSTRATE OCCUPANT LOADS, TRAVEL DISTANCES, COMMON
 PATHS OF TRAVEL, DEAD-END CORRIDORS, EXIT SIGNS,
 EMERGENCY LIGHTING, EXITS LEADING TO A PUBLIC WAY, FIRE
 EXTINGUISHER LOCATIONS, AND ALL FIRE SAFETY FEATURES
 AND EQUIPMENT.
  
 11. IT IS HIGHLY RECOMMENDED (REQUIRED WITH FIRE
 SPRINKLER SYSTEM) THAT A KNOX BOX WITH KEYS FOR ENTRY
 DOOR LOCKS BE PROVIDED FOR 24 HOUR EMERGENCY ACCESS.
  
 12. THE BUREAU'S APPROVAL OF THIS SUBMITTED PROJECT
 DOES NOT CONSTITUTE ITS FINAL REVIEW OR APPROVAL.
  
 13. THE BUREAU SHALL REVIEW ALL SUBMITTED BUILDING
 PLANS AT THE APPROPRIATE TIME AND IN ACCORDANCE WITH
 THE REQUIREMENTS OF ALL APPLICABLE CODES AND STANDARDS.
  
 PETER LEDUC
 FIRE MARSHAL
 561-804-4709
 [email protected]
  

Review Stop L LANDSCAPING
Rev No 4 Status P Date 07-12-2021 Cont ID  
Sent By aburnett Date 07-12-2021 Time 15:21 Rev Time 0.00
Received By aburnett Date 07-12-2021 Time 15:20 Sent To  
Notes
2021-07-12 15:23:47FROM: ANDREW BURNETT, LANDSCAPE PLANNER 561-822-1562
 PROJECT: FLAMINGO CAR WASH CPD Z21020016
 JULY 12,2021
 I HAVE REVIEWED THE ABOVE REFERENCED PETITION, AND
 PROVIDE THE FOLLOWING COMMENTS:
  
 1. MAKE THE FOLLOWING CORRECTIONS TO THE TREE
 DISPOSITION PLAN:
 ? SATISFIED. ADD BRAZILIAN PEPPER TO LIST AND SHOW AS
 REMOVE WITH NO MITIGATION REQUIRED.
 ? SATISFIED. SHOW SQUARE FOOTAGE OF MITIGATION DUE FOR
 EACH TREE TO BE REMOVED ON THE CHART.
 ? SATISFIED. CHART SHOWS 2 RELOCATED LIVE OAKS, BUT 3
 ARE SHOWN ON THE PLANT LIST.
  
 2. SATISFIED. REQUIRED OPEN SPACE FOR CALCULATING
 REQUIRED SHADE TREES AND FLOWERING TREES IS 40%. SHOW
 THE CORRECT SQUARE FOOTAGE ON THE REQUIREMENTS CHART
 AND RECALCULATE.
  
 52925.4 SQ FT LOT, 40% IS 21170 SQ FT. 15 TREES
 REQUIRED, 6 FLOWERING TREES AND 43 SHRUBS. CORRECT ON
 CHART. BUFFER TREES AND PARKING LOT TREES CAN BE
 COUNTED. SHORT ON FLOWERING TREES.
  
 3. SATISFIED. SHOW THE PERCENTAGE AND NUMBER OF PALM
 SUBSTITUTIONS FOR REQUIRED TREES NOT EXCEEDING 35
 PERCENT PER SECTION 94-442 (D).
 COULD NOT LOCATE ON PLAN, ADD TO TREE REQUIREMENT CHART
 SO INFORMATION IS CONSOLIDATED.
  
 4. SATISFIED. PROVIDE A PLAN SHOWING THE PARKING
 LANDSCAPE AREAS COUNTED TOWARD COMPLIANCE WITH SECTION
 94-443(C)(3) AND (4) AND PROVIDE CALCULATIONS.
 COULD NOT LOCATE PLAN IN THE SUBMITTAL.
  
 5. SATISFIED. BUFFER LENGTHS SHOWN ON CHART ON LP-2 DO
 NOT MATCH SURVEY LENGTHS. REVISE AND SHOW NEW
 CALCULATIONS. (6/21/21 SEE NOTE :#17)
  
 6. SATISFIED. PROVIDE REQUIRED BUFFER TREES AT ONE FOR
 EVERY 30 FEET OR PORTION THEREOF FOR EASTERN BUFFER OR
 REQUEST A WAIVER. THE DRAINAGE EASEMENT NEEDS TO BE
 CLARIFIED IF IT WILL BE USED OR NOT IN COORDINATION
 WITH THE ADJACENT PROJECT. PERMISSION MAY BE SOUGHT FOR
 INSTALLING THE REQUIRED LANDSCAPE AS AN ALTERNATIVE.
 EXTRA TREES IN PARKING AREA WOULD HAVE TO BE PART OF
 ANY WAIVER JUSTIFICATION.
  
 7. SATISFIED. WESTERN BUFFER WILL NEED TO BE MODIFIED
 TO INCORPORATE THE SIDEWALK CONNECTION AS DESCRIBED IN
 THE ZONING COMMENTS.
  
 8. SATISFIED. NORTHERN 5 FOOT BUFFER SHOULD BE CONSTANT
 ACROSS THE ENTIRE LENGTH WITH ACCESS OPENINGS FOR
 SIDEWALK ACCESS ONLY. SHADE TREES SHOULD BE CONSISTENT
 WITH THE THEME FOR ALL PROPERTIES, THE ROYAL PALMS DO
 NOT PROVIDE THE REQUIRED TREE CANOPY.
  
 9. SATISFIED. SHOW LINEAR FOOTAGE OF LANDSCAPED AREA
 ADJACENT TO THE BUILDING MEETS THE REQUIREMENT OF 30
 PERCENT PER SECTION 94-443(E)(1) FOR THE BUILDING.
  
 COULD NOT LOCATE ON PLAN. CONSOLIDATE ALL LANDSCAPE
 REQUIREMENTS IN ONE CHART.
  
 10. SATISFIED. TAGS ARE NOT SHOWN ON LP-1, MAKE SURE
 THEY ARE ADDED.
  
 11. MAKE THE FOLLOWING CORRECTIONS TO THE PLANT LIST:
 ? SATISFIED. QUANTITY FOR SILVER BUTTONWOOD TREES IS
 NOT INDICATED, AND SIZE MUST BE 12 FEET.
 ? SATISFIED. CRAPE MYRTLE MUST BE 12 FEET.
 ? ALL SPECIES LISTED UNDER TREES MUST MEET THE 12 FOOT
 HEIGHT REQUIREMENT TO QUALIFY AS TREES, OTHERWISE MOVE
 TO SHRUB CATEGORY.
  
 12. SATISFIED. SHOW THE LOCATIONS OF DRAINAGE LINES ON
 THE LANDSCAPE PLAN AND RESOLVE ANY CONFLICTS WITH TREES
 AND LANDSCAPING. RELOCATE UTILITY LOCATIONS OR EXPAND
 LANDSCAPE AREAS TO ACCOMMODATE REQUIRED LANDSCAPING.
  
 13. SATISFIED. SHOW LOCATIONS OF FPL TRANSFORMERS ON
 THE LANDSCAPE PLAN AND RESOLVE CONFLICTS WITH
 LANDSCAPING. PROVIDE SCREENING FOR ALL GROUND MOUNTED
 VALVES AND EQUIPMENT.
  
 14. SATISFIED. ROW OF PARKING SOUTH OF BUILDING SHOULD
 BE MODIFIED TO BE 18 FEET LENGTH INCLUDING CURB AND
 OVERHANG.
  
 ADDITIONAL COMMENT 4/16/21:
  
 15. SATISFIED REMOVE TREE MITIGATION CREDITS FOR THE
 RELOCATED PIGEON PLUM, LIVE OAKS AND SABAL PALMS AND
 RECALCULATE TOTAL. MITIGATION CAN ONLY BE PROVIDED WITH
 NEWLY ADDED MATERIAL.
  
 ADDITIONAL COMMENT 6/21/2021
  
 16. SATISFIED THE TREES AND PALMS THAT ARE LISTED AS
 TO BE RELOCATED AND REMOVED MUST NO LONGER BE SHOWN ON
 THE LANDSCAPE PLAN. THIS INCLUDES USING A LIGHTER LINE
 WEIGHT. THE LANDSCAPE PLAN IS TO SHOW THE FINAL
 LANDSCAPE LAYOUT, SO THE TREES WOULD BE SHOWN WHERE
 THEY WILL BE RELOCATED TO, NOT WHERE THEY CAME FROM.
  
 17. SATISFIED THE PROPERTY LINE DIMENSIONS LISTED ON
 THE TREE REQUIREMENTS CHART DO NOT MATCH THE DIMENSIONS
 SHOWN ON THE SITE PLAN OR SURVEY. WHILE THEY ARE CLOSE,
 THE WEST PROPERTY LINE WILL GO TO 215 FEET AND THUS
 REQUIRES AN ADDITIONAL TREE. UPDATE THE CHART
 ACCORDINGLY. NOTE: IT APPEARS THAT THE BUFFERS HAVE
 ENOUGH BUFFER TREES, EVEN WITH THE ONE ADDITIONAL THAT
 IS REQUIRED.
  
 18. SATISFIED LEAVING THE AREA WITH THE OLD DRIVEWAY
 CUT VIOLATES THE 1 TREE EVERY 30 FEET AND THE HEDGE
 REQUIRED WITHIN BUFFERS ADJACENT TO VEHICULAR USE
 AREAS. THE LANDSCAPE PLANS MUST SHOW FULL COMPLIANCE
 WITH THE LANDSCAPE CODE. NOTE: THE LANDSCAPE TABLES
 NEED TO BE UPDATED TO REFLECT MATERIAL THAT IS SHOW IN
 THIS LOCATION. 9 BUTTON SIGNS CAN BE INCORPORATED INTO
 THE LANDSCAPE BUFFER.
  
 19. SATISFIED A SABAL PALM IS SHOWN LOCATED WITHIN THE
 REVISED DRAINAGE EASEMENT ALONG THE BRANDSMART
 PROPERTY. THE CITY DOES NOT PERMIT TREES TO BE PLANTED
 WITHIN CITY DRAINAGE EASEMENTS. THE SABAL PALM WILL
 NEED TO BE RELOCATED OUT OF THE EASEMENT.
  
 20. SATISFIED THE LIVE OAKS ARE IN CLOSE PROXIMITY OF
 THE REVISED DRAINAGE EASEMENT BY BRANDSMART PROPERTY
 ROOT BARRIER. PLANTING LOCATION OF OAK SHOULD BE
 SHIFTED AWAY FROM THE BARRIER IF POSSIBLE OR SELECT A
 SMALLER TREE VARIETY FOR THE LOCATION.
  
 CONDITIONS OF APPROVAL
 1. PRIOR TO THE REMOVAL OR RELOCATION OF ANY TREES ON
 THE PROPERTY, A TREE ALTERATION PERMIT SHALL BE
 SUBMITTED, REVIEWED AND APPROVED BY THE DEVELOPMENT
 SERVICES DEPARTMENT, PLANNING DIVISION.

Review Stop L LANDSCAPING
Rev No 3 Status F Date 06-21-2021 Cont ID  
Sent By aburnett Date 06-21-2021 Time 15:32 Rev Time 0.00
Received By aburnett Date 06-21-2021 Time 15:31 Sent To  
Notes
2021-06-21 15:33:55FROM: ANDREW BURNETT, LANDSCAPE PLANNER 561-822-1562
 PROJECT: FLAMINGO CAR WASH CPD Z21020016
 JUNE 21,2021
 I HAVE REVIEWED THE ABOVE REFERENCED PETITION, AND
 PROVIDE THE FOLLOWING COMMENTS:
  
 1. MAKE THE FOLLOWING CORRECTIONS TO THE TREE
 DISPOSITION PLAN:
 ? SATISFIED. ADD BRAZILIAN PEPPER TO LIST AND SHOW AS
 REMOVE WITH NO MITIGATION REQUIRED.
 ? SATISFIED. SHOW SQUARE FOOTAGE OF MITIGATION DUE FOR
 EACH TREE TO BE REMOVED ON THE CHART.
 ? SATISFIED. CHART SHOWS 2 RELOCATED LIVE OAKS, BUT 3
 ARE SHOWN ON THE PLANT LIST.
  
 2. SATISFIED. REQUIRED OPEN SPACE FOR CALCULATING
 REQUIRED SHADE TREES AND FLOWERING TREES IS 40%. SHOW
 THE CORRECT SQUARE FOOTAGE ON THE REQUIREMENTS CHART
 AND RECALCULATE.
  
 52925.4 SQ FT LOT, 40% IS 21170 SQ FT. 15 TREES
 REQUIRED, 6 FLOWERING TREES AND 43 SHRUBS. CORRECT ON
 CHART. BUFFER TREES AND PARKING LOT TREES CAN BE
 COUNTED. SHORT ON FLOWERING TREES.
  
 3. SATISFIED. SHOW THE PERCENTAGE AND NUMBER OF PALM
 SUBSTITUTIONS FOR REQUIRED TREES NOT EXCEEDING 35
 PERCENT PER SECTION 94-442 (D).
 COULD NOT LOCATE ON PLAN, ADD TO TREE REQUIREMENT CHART
 SO INFORMATION IS CONSOLIDATED.
  
 4. SATISFIED. PROVIDE A PLAN SHOWING THE PARKING
 LANDSCAPE AREAS COUNTED TOWARD COMPLIANCE WITH SECTION
 94-443(C)(3) AND (4) AND PROVIDE CALCULATIONS.
 COULD NOT LOCATE PLAN IN THE SUBMITTAL.
  
 5. NOT SATISFIED. BUFFER LENGTHS SHOWN ON CHART ON LP-2
 DO NOT MATCH SURVEY LENGTHS. REVISE AND SHOW NEW
 CALCULATIONS. (6/21/21 SEE NOTE :#17)
  
 6. SATISFIED. PROVIDE REQUIRED BUFFER TREES AT ONE FOR
 EVERY 30 FEET OR PORTION THEREOF FOR EASTERN BUFFER OR
 REQUEST A WAIVER. THE DRAINAGE EASEMENT NEEDS TO BE
 CLARIFIED IF IT WILL BE USED OR NOT IN COORDINATION
 WITH THE ADJACENT PROJECT. PERMISSION MAY BE SOUGHT FOR
 INSTALLING THE REQUIRED LANDSCAPE AS AN ALTERNATIVE.
 EXTRA TREES IN PARKING AREA WOULD HAVE TO BE PART OF
 ANY WAIVER JUSTIFICATION.
  
 7. SATISFIED. WESTERN BUFFER WILL NEED TO BE MODIFIED
 TO INCORPORATE THE SIDEWALK CONNECTION AS DESCRIBED IN
 THE ZONING COMMENTS.
  
 8. SATISFIED. NORTHERN 5 FOOT BUFFER SHOULD BE CONSTANT
 ACROSS THE ENTIRE LENGTH WITH ACCESS OPENINGS FOR
 SIDEWALK ACCESS ONLY. SHADE TREES SHOULD BE CONSISTENT
 WITH THE THEME FOR ALL PROPERTIES, THE ROYAL PALMS DO
 NOT PROVIDE THE REQUIRED TREE CANOPY.
  
 9. SATISFIED. SHOW LINEAR FOOTAGE OF LANDSCAPED AREA
 ADJACENT TO THE BUILDING MEETS THE REQUIREMENT OF 30
 PERCENT PER SECTION 94-443(E)(1) FOR THE BUILDING.
  
 COULD NOT LOCATE ON PLAN. CONSOLIDATE ALL LANDSCAPE
 REQUIREMENTS IN ONE CHART.
  
 10. SATISFIED. TAGS ARE NOT SHOWN ON LP-1, MAKE SURE
 THEY ARE ADDED.
  
 11. MAKE THE FOLLOWING CORRECTIONS TO THE PLANT LIST:
 ? SATISFIED. QUANTITY FOR SILVER BUTTONWOOD TREES IS
 NOT INDICATED, AND SIZE MUST BE 12 FEET.
 ? SATISFIED. CRAPE MYRTLE MUST BE 12 FEET.
 ? ALL SPECIES LISTED UNDER TREES MUST MEET THE 12 FOOT
 HEIGHT REQUIREMENT TO QUALIFY AS TREES, OTHERWISE MOVE
 TO SHRUB CATEGORY.
  
 12. SATISFIED. SHOW THE LOCATIONS OF DRAINAGE LINES ON
 THE LANDSCAPE PLAN AND RESOLVE ANY CONFLICTS WITH TREES
 AND LANDSCAPING. RELOCATE UTILITY LOCATIONS OR EXPAND
 LANDSCAPE AREAS TO ACCOMMODATE REQUIRED LANDSCAPING.
  
 13. SATISFIED. SHOW LOCATIONS OF FPL TRANSFORMERS ON
 THE LANDSCAPE PLAN AND RESOLVE CONFLICTS WITH
 LANDSCAPING. PROVIDE SCREENING FOR ALL GROUND MOUNTED
 VALVES AND EQUIPMENT.
  
 14. SATISFIED. ROW OF PARKING SOUTH OF BUILDING SHOULD
 BE MODIFIED TO BE 18 FEET LENGTH INCLUDING CURB AND
 OVERHANG.
  
 ADDITIONAL COMMENT 4/16/21:
  
 15. REMOVE TREE MITIGATION CREDITS FOR THE RELOCATED
 PIGEON PLUM, LIVE OAKS AND SABAL PALMS AND RECALCULATE
 TOTAL. MITIGATION CAN ONLY BE PROVIDED WITH NEWLY ADDED
 MATERIAL.
  
 ADDITIONAL COMMENT 6/21/2021
  
 16. THE TREES AND PALMS THAT ARE LISTED AS TO BE
 RELOCATED AND REMOVED MUST NO LONGER BE SHOWN ON THE
 LANDSCAPE PLAN. THIS INCLUDES USING A LIGHTER LINE
 WEIGHT. THE LANDSCAPE PLAN IS TO SHOW THE FINAL
 LANDSCAPE LAYOUT, SO THE TREES WOULD BE SHOWN WHERE
 THEY WILL BE RELOCATED TO, NOT WHERE THEY CAME FROM.
  
 17. THE PROPERTY LINE DIMENSIONS LISTED ON THE TREE
 REQUIREMENTS CHART DO NOT MATCH THE DIMENSIONS SHOWN ON
 THE SITE PLAN OR SURVEY. WHILE THEY ARE CLOSE, THE WEST
 PROPERTY LINE WILL GO TO 215 FEET AND THUS REQUIRES AN
 ADDITIONAL TREE. UPDATE THE CHART ACCORDINGLY. NOTE: IT
 APPEARS THAT THE BUFFERS HAVE ENOUGH BUFFER TREES, EVEN
 WITH THE ONE ADDITIONAL THAT IS REQUIRED.
  
 18. LEAVING THE AREA WITH THE OLD DRIVEWAY CUT
 VIOLATES THE 1 TREE EVERY 30 FEET AND THE HEDGE
 REQUIRED WITHIN BUFFERS ADJACENT TO VEHICULAR USE
 AREAS. THE LANDSCAPE PLANS MUST SHOW FULL COMPLIANCE
 WITH THE LANDSCAPE CODE. NOTE: THE LANDSCAPE TABLES
 NEED TO BE UPDATED TO REFLECT MATERIAL THAT IS SHOW IN
 THIS LOCATION. 9 BUTTON SIGNS CAN BE INCORPORATED INTO
 THE LANDSCAPE BUFFER.
  
 19. A SABAL PALM IS SHOWN LOCATED WITHIN THE REVISED
 DRAINAGE EASEMENT ALONG THE BRANDSMART PROPERTY. THE
 CITY DOES NOT PERMIT TREES TO BE PLANTED WITHIN CITY
 DRAINAGE EASEMENTS. THE SABAL PALM WILL NEED TO BE
 RELOCATED OUT OF THE EASEMENT.
  
 20. THE LIVE OAKS ARE IN CLOSE PROXIMITY OF THE REVISED
 DRAINAGE EASEMENT BY BRANDSMART PROPERTY ROOT BARRIER.
 PLANTING LOCATION OF OAK SHOULD BE SHIFTED AWAY FROM
 THE BARRIER IF POSSIBLE OR SELECT A SMALLER TREE
 VARIETY FOR THE LOCATION.
  
 CONDITIONS OF APPROVAL
 1. PRIOR TO THE REMOVAL OR RELOCATION OF ANY TREES ON
 THE PROPERTY, A TREE ALTERATION PERMIT SHALL BE
 SUBMITTED, REVIEWED AND APPROVED BY THE DEVELOPMENT
 SERVICES DEPARTMENT, PLANNING DIVISION.
  

Review Stop L LANDSCAPING
Rev No 2 Status F Date 04-16-2021 Cont ID  
Sent By rcaranci Date 04-16-2021 Time 17:02 Rev Time 0.00
Received By rcaranci Date 04-16-2021 Time 17:02 Sent To  
Notes
2021-04-16 17:03:14FROM: RAY CARANCI, SENIOR LANDSCAPE PLANNER
 561-822-1462
 PROJECT: FLAMINGO CAR WASH CPD Z21020016
 APRIL 16, 2021
 I HAVE REVIEWED THE ABOVE REFERENCED PETITION, AND
 PROVIDE THE FOLLOWING COMMENTS:
  
 1. MAKE THE FOLLOWING CORRECTIONS TO THE TREE
 DISPOSITION PLAN:
 ? SATISFIED. ADD BRAZILIAN PEPPER TO LIST AND SHOW AS
 REMOVE WITH NO MITIGATION REQUIRED.
 ? SATISFIED. SHOW SQUARE FOOTAGE OF MITIGATION DUE FOR
 EACH TREE TO BE REMOVED ON THE CHART.
 ? SATISFIED. CHART SHOWS 2 RELOCATED LIVE OAKS, BUT 3
 ARE SHOWN ON THE PLANT LIST.
  
 2. NOT SATISFIED. REQUIRED OPEN SPACE FOR CALCULATING
 REQUIRED SHADE TREES AND FLOWERING TREES IS 40%. SHOW
 THE CORRECT SQUARE FOOTAGE ON THE REQUIREMENTS CHART
 AND RECALCULATE.
  
 52925.4 SQ FT LOT, 40% IS 21170 SQ FT. 15 TREES
 REQUIRED, 6 FLOWERING TREES AND 43 SHRUBS. CORRECT ON
 CHART. BUFFER TREES AND PARKING LOT TREES CAN BE
 COUNTED. SHORT ON FLOWERING TREES.
  
 3. NOT SATISFIED. SHOW THE PERCENTAGE AND NUMBER OF
 PALM SUBSTITUTIONS FOR REQUIRED TREES NOT EXCEEDING 35
 PERCENT PER SECTION 94-442 (D).
 COULD NOT LOCATE ON PLAN, ADD TO TREE REQUIREMENT CHART
 SO INFORMATION IS CONSOLIDATED.
  
 4. NOT SATISFIED. PROVIDE A PLAN SHOWING THE PARKING
 LANDSCAPE AREAS COUNTED TOWARD COMPLIANCE WITH SECTION
 94-443(C)(3) AND (4) AND PROVIDE CALCULATIONS.
 COULD NOT LOCATE PLAN IN THE SUBMITTAL.
  
 5. SATISFIED. BUFFER LENGTHS SHOWN ON CHART ON LP-2 DO
 NOT MATCH SURVEY LENGTHS. REVISE AND SHOW NEW
 CALCULATIONS.
  
 6. SATISFIED. PROVIDE REQUIRED BUFFER TREES AT ONE FOR
 EVERY 30 FEET OR PORTION THEREOF FOR EASTERN BUFFER OR
 REQUEST A WAIVER. THE DRAINAGE EASEMENT NEEDS TO BE
 CLARIFIED IF IT WILL BE USED OR NOT IN COORDINATION
 WITH THE ADJACENT PROJECT. PERMISSION MAY BE SOUGHT FOR
 INSTALLING THE REQUIRED LANDSCAPE AS AN ALTERNATIVE.
 EXTRA TREES IN PARKING AREA WOULD HAVE TO BE PART OF
 ANY WAIVER JUSTIFICATION.
  
 7. SATISFIED. WESTERN BUFFER WILL NEED TO BE MODIFIED
 TO INCORPORATE THE SIDEWALK CONNECTION AS DESCRIBED IN
 THE ZONING COMMENTS.
  
 8. SATISFIED. NORTHERN 5 FOOT BUFFER SHOULD BE CONSTANT
 ACROSS THE ENTIRE LENGTH WITH ACCESS OPENINGS FOR
 SIDEWALK ACCESS ONLY. SHADE TREES SHOULD BE CONSISTENT
 WITH THE THEME FOR ALL PROPERTIES, THE ROYAL PALMS DO
 NOT PROVIDE THE REQUIRED TREE CANOPY.
  
 9. NOT SATISFIED. SHOW LINEAR FOOTAGE OF LANDSCAPED
 AREA ADJACENT TO THE BUILDING MEETS THE REQUIREMENT OF
 30 PERCENT PER SECTION 94-443(E)(1) FOR THE BUILDING.
  
 COULD NOT LOCATE ON PLAN. CONSOLIDATE ALL LANDSCAPE
 REQUIREMENTS IN ONE CHART.
  
 10. SATISFIED. TAGS ARE NOT SHOWN ON LP-1, MAKE SURE
 THEY ARE ADDED.
  
 11. MAKE THE FOLLOWING CORRECTIONS TO THE PLANT LIST:
 ? NOT SATISFIED. QUANTITY FOR SILVER BUTTONWOOD TREES
 IS NOT INDICATED, AND SIZE MUST BE 12 FEET.
 ? NOT SATISFIED. CRAPE MYRTLE MUST BE 12 FEET.
 ? ALL SPECIES LISTED UNDER TREES MUST MEET THE 12 FOOT
 HEIGHT REQUIREMENT TO QUALIFY AS TREES, OTHERWISE MOVE
 TO SHRUB CATEGORY.
  
 12. SATISFIED. SHOW THE LOCATIONS OF DRAINAGE LINES ON
 THE LANDSCAPE PLAN AND RESOLVE ANY CONFLICTS WITH TREES
 AND LANDSCAPING. RELOCATE UTILITY LOCATIONS OR EXPAND
 LANDSCAPE AREAS TO ACCOMMODATE REQUIRED LANDSCAPING.
  
 13. SATISFIED. SHOW LOCATIONS OF FPL TRANSFORMERS ON
 THE LANDSCAPE PLAN AND RESOLVE CONFLICTS WITH
 LANDSCAPING. PROVIDE SCREENING FOR ALL GROUND MOUNTED
 VALVES AND EQUIPMENT.
  
 14. SATISFIED. ROW OF PARKING SOUTH OF BUILDING SHOULD
 BE MODIFIED TO BE 18 FEET LENGTH INCLUDING CURB AND
 OVERHANG.
  
 ADDITIONAL COMMENT 4/16/21:
  
 15. REMOVE TREE MITIGATION CREDITS FOR THE RELOCATED
 PIGEON PLUM, LIVE OAKS AND SABAL PALMS AND RECALCULATE
 TOTAL. MITIGATION CAN ONLY BE PROVIDED WITH NEWLY ADDED
 MATERIAL.
 CONDITIONS OF APPROVAL
 1. PRIOR TO THE REMOVAL OR RELOCATION OF ANY TREES ON
 THE PROPERTY, A TREE ALTERATION PERMIT SHALL BE
 SUBMITTED, REVIEWED AND APPROVED BY THE DEVELOPMENT
 SERVICES DEPARTMENT, PLANNING DIVISION.
  

Review Stop L LANDSCAPING
Rev No 1 Status F Date 03-10-2021 Cont ID  
Sent By rcaranci Date 03-10-2021 Time 18:02 Rev Time 0.00
Received By rcaranci Date 03-10-2021 Time 18:02 Sent To  
Notes
2021-03-10 18:03:18FROM: RAY CARANCI, SENIOR LANDSCAPE PLANNER
 561-822-1462
 PROJECT: FLAMINGO CAR WASH CPD Z21020016
 MARCH 10, 2021
 I HAVE REVIEWED THE ABOVE REFERENCED PETITION, AND
 PROVIDE THE FOLLOWING COMMENTS:
  
 1. MAKE THE FOLLOWING CORRECTIONS TO THE TREE
 DISPOSITION PLAN:
 ? ADD BRAZILIAN PEPPER TO LIST AND SHOW AS REMOVE WITH
 NO MITIGATION REQUIRED.
 ? SHOW SQUARE FOOTAGE OF MITIGATION DUE FOR EACH TREE
 TO BE REMOVED ON THE CHART.
 ? CHART SHOWS 2 RELOCATED LIVE OAKS, BUT 3 ARE SHOWN ON
 THE PLANT LIST.
  
 2. REQUIRED OPEN SPACE FOR CALCULATING REQUIRED SHADE
 TREES AND FLOWERING TREES IS 40%. SHOW THE CORRECT
 SQUARE FOOTAGE ON THE REQUIREMENTS CHART AND
 RECALCULATE.
  
 3. SHOW THE PERCENTAGE AND NUMBER OF PALM SUBSTITUTIONS
 FOR REQUIRED TREES NOT EXCEEDING 35 PERCENT PER SECTION
 94-442 (D).
  
 4. PROVIDE A PLAN SHOWING THE PARKING LANDSCAPE AREAS
 COUNTED TOWARD COMPLIANCE WITH SECTION 94-443(C)(3) AND
 (4) AND PROVIDE CALCULATIONS.
  
 5. BUFFER LENGTHS SHOWN ON CHART ON LP-2 DO NOT MATCH
 SURVEY LENGTHS. REVISE AND SHOW NEW CALCULATIONS.
  
 6. PROVIDE REQUIRED BUFFER TREES AT ONE FOR EVERY 30
 FEET OR PORTION THEREOF FOR EASTERN BUFFER OR REQUEST A
 WAIVER. THE DRAINAGE EASEMENT NEEDS TO BE CLARIFIED IF
 IT WILL BE USED OR NOT IN COORDINATION WITH THE
 ADJACENT PROJECT. PERMISSION MAY BE SOUGHT FOR
 INSTALLING THE REQUIRED LANDSCAPE AS AN ALTERNATIVE.
 EXTRA TREES IN PARKING AREA WOULD HAVE TO BE PART OF
 ANY WAIVER JUSTIFICATION.
  
 7. WESTERN BUFFER WILL NEED TO BE MODIFIED TO
 INCORPORATE THE SIDEWALK CONNECTION AS DESCRIBED IN THE
 ZONING COMMENTS.
  
 8. NORTHERN 5 FOOT BUFFER SHOULD BE CONSTANT ACROSS THE
 ENTIRE LENGTH WITH ACCESS OPENINGS FOR SIDEWALK ACCESS
 ONLY. SHADE TREES SHOULD BE CONSISTENT WITH THE THEME
 FOR ALL PROPERTIES, THE ROYAL PALMS DO NOT PROVIDE THE
 REQUIRED TREE CANOPY.
  
 9. SHOW LINEAR FOOTAGE OF LANDSCAPED AREA ADJACENT TO
 THE BUILDING MEETS THE REQUIREMENT OF 30 PERCENT PER
 SECTION 94-443(E)(1) FOR THE BUILDING.
  
 10. TAGS ARE NOT SHOWN ON LP-1, MAKE SURE THEY ARE
 ADDED.
  
 11. MAKE THE FOLLOWING CORRECTIONS TO THE PLANT LIST:
 ? QUANTITY FOR SILVER BUTTONWOOD TREES IS NOT
 INDICATED, AND SIZE MUST BE 12 FEET.
 ? CRAPE MYRTLE MUST BE 12 FEET.
  
 12. SHOW THE LOCATIONS OF DRAINAGE LINES ON THE
 LANDSCAPE PLAN AND RESOLVE ANY CONFLICTS WITH TREES AND
 LANDSCAPING. RELOCATE UTILITY LOCATIONS OR EXPAND
 LANDSCAPE AREAS TO ACCOMMODATE REQUIRED LANDSCAPING.
  
 13. SHOW LOCATIONS OF FPL TRANSFORMERS ON THE LANDSCAPE
 PLAN AND RESOLVE CONFLICTS WITH LANDSCAPING. PROVIDE
 SCREENING FOR ALL GROUND MOUNTED VALVES AND EQUIPMENT.
  
 14. ROW OF PARKING SOUTH OF BUILDING SHOULD BE MODIFIED
 TO BE 18 FEET LENGTH INCLUDING CURB AND OVERHANG.
 CONDITIONS OF APPROVAL
 1. PRIOR TO THE REMOVAL OR RELOCATION OF ANY TREES ON
 THE PROPERTY, A TREE ALTERATION PERMIT SHALL BE
 SUBMITTED, REVIEWED AND APPROVED BY THE DEVELOPMENT
 SERVICES DEPARTMENT, PLANNING DIVISION.
  

Review Stop PW PUBLIC WORKS
Rev No 4 Status P Date 07-16-2021 Cont ID  
Sent By   Date 07-16-2021 Time   Rev Time 0.00
Received By   Date 07-16-2021 Time   Sent To  
Notes
2021-07-16 10:35:52NO FURTHER COMMENTS FROM DEPT OF PUBLIC WORKS.
  
 MATT HEJAZI
 DEPT. OF PUBLIC WORKS
 [email protected]
 561-822-2045

Review Stop PW PUBLIC WORKS
Rev No 3 Status F Date 06-16-2023 Cont ID  
Sent By   Date 06-16-2021 Time   Rev Time 0.00
Received By   Date 06-16-2021 Time   Sent To  
Notes
2021-06-16 10:41:32PLEASE RELOCATE THE DUMPSTER ENCLOSURE TO THE ORIGINAL
 LOCATION AND ORIENTATION SUBMITTED ON THE SITE PLAN,
 SHEET SP-1, DATED 1/28/2028. THE PROPOSED DUMPSTER
 ENLOSURE IS NOT FEASIBLE TO SAFELY ACCESS AND SERVICE
 THE DUMPSTER WITH A FRONT LOADER VEHICLE.
  
 MATT HEJAZI
 DEPT. OF PUBLIC WORKS
 [email protected]
 561-822-2045

Review Stop PW PUBLIC WORKS
Rev No 2 Status F Date 04-01-2021 Cont ID  
Sent By   Date 04-01-2021 Time   Rev Time 0.00
Received By   Date 04-01-2021 Time   Sent To  
Notes
2021-04-01 11:25:09PLEASE PROVIDE THE REVISED DUMPSTER ENCLOSURE DETAIL,
 SHEET SP-3 AND CIVIL ENG. PLAN SHEET 1, TO REFELCT THE
 LATEST REVISION OF THE LATEST REVISION OF CITY OF WEST
 PALM BEACH GENERAL CONSTRUCTION-GARBAGE ENCLOSURE
 STANDARD, GC-7
  
 MATT HEJAZI
 DEPT. OF PUBLIC WORKS
 [email protected]
 561-822-2045

Review Stop PW PUBLIC WORKS
Rev No 1 Status F Date 03-08-2021 Cont ID  
Sent By   Date 03-08-2021 Time   Rev Time  
Received By   Date 03-08-2021 Time   Sent To  
Notes
2021-03-08 09:16:27PLEASE PROVIDE THE FOLLOWINGS:
 1- LOS (LEVEL OF SERVICE ANALYSIS) TO REFLECT THE SOLID
 WASTE VOLUME PRODUCED ALONG WITH THE SIZE AND TYPE OF
 THE CONTAINER THAT WILL BE UTILIZED THAT WILL BE
 UTILIZED FOR THE SANITATION SERVICE.
 2- DUMPSTER ENCLOSURE DETAIL. FOR A FREESTANDING SITE
 DUMPSTER ENCLOSURE, THE ENCLOSURE SHALL COMPLY WITH THE
 LATEST REVISION OF CITY OF WEST PALM BEACH GENERAL
 CONSTRUCTION-GARBAGE ENCLOSURE STANDARD, GC-7.
 3- AUTOTURN (DYNAMIC ENVELOPE AND THE TIRES PATH) FOR
 THE SANITATION SERVICE, FRONT LOADER TRUCK WITH THE
 FOLLOWING SPECS:
 - DUAL AXLES
 - TRUCK LENGTH: 35 FT
 - TRUCK WIDTH: 11 FT
 - TURNING RADIUS:
 - SAE TURNING RADIUS: 32.5 FT
 - CURB-TO-CURB DIAMETER: 74 FT
 - WALL-TO-WALL DIAMETER: 86.3 FT
  
 MATT HEJAZI
 DEPT. OF PUBLIC WORKS
 [email protected]
 561-822-2045
  

Review Stop STORM STORMWATER
Rev No 2 Status P Date 05-03-2021 Cont ID  
Sent By tward Date 05-03-2021 Time 16:10 Rev Time 0.00
Received By tward Date 05-03-2021 Time 16:10 Sent To  
Notes
***NONE***

Review Stop STORM STORMWATER
Rev No 1 Status F Date 03-10-2021 Cont ID  
Sent By tward Date 03-10-2021 Time 22:37 Rev Time 0.00
Received By tward Date 03-10-2021 Time 22:39 Sent To  
Notes
2021-03-10 22:39:43THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL
 DETAILS, DESIGN CALCULATIONS AND THE POLLUTION
 PREVENTION PLAN WILL BE REVIEWED AS PART OF THE
 ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT
 APPLICATION PROCESSES.
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE
 PLAN APPROVAL:
  
 1. RELOCATE THE PROPOSED CONTROL STRUCTURE TO WITHIN
 THE PROPERTY.
  
 2. NO PROPOSED GRADES ARE PROVIDED ON THE CONCEPTUAL
 ENGINEERING PLAN. MINIMIZE THE AMOUNT OF PAVED AREAS
 FLOWING ONTO ADJACENT PROPERTY.
  
 3. THE 12' DRAINAGE EASEMENT ALONG THE SOUTHEAST
 PROPERTY LINE MAY BE IN USE BY THE BEST BUY PARCEL TO
 CONVEY EXCESS STORMWATER RUNOFF TO THE DITCH ON THE
 EAST SIDE OF EXECUTIVE CENTER DRIVE. REVIEW RECORDED
 EASEMENT DOCUMENT TO DETERMINE IF THERE ARE
 RESTRICTIONS OF CONSTRUCTING STRUCTURES WITHIN THE
 DRAINAGE EASEMENT SUCH AS THE PROPOSED DUMPSTER
 ENCLOSURE.
  
 4. DETERMINE IF THE STORM PIPE FROM THE SOUTHEAST
 CORNER OF THE BEST BUY LOT CONNECTS TO THE CATCH BASIN
 INLET IN THE SOUTHEAST CORNER OF THE CHINESE RESTAURANT
 (CARWASH) SITE OR TO THE EXISTING MANHOLE IN THE
 BRANDSMART DRIVEWAY OR GOES ALL THE WAY TO THE DITCH ON
 THE EAST SIDE OF EXCUTIVE CENTER DRIVE AND SHOW THIS
 PIPE ON THE CONCEPTUAL ENGINEERING PLAN.
  
 5. THE DRAINAGE SYSTEM IS TO BE DESIGNED TO BE SFWMD
 ERP CRITERIA WATER QUALITY AND PEAK FLOW LIMITATIONS.
 IF A PERIMETER BERM IS NEEDED TO CONTROL DISCHARGE UP
 TO THE 25-YEAR 3-DAY DESIGN STORM, HOW WILL THIS
 PERIMETER ELEVATION BE ACHIEVED AT THE DRIVEWAYS TO
 OFFSITE PARCELS? HOW DOES THE PEAK 25-YEAR 3-DAY STAGE
 COMPARE TO THE 25-YEAR 3-DAY PEAK STAGE OF ADJACENT
 SITES?
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO
 ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING
 BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL.
  
 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION MAY
 BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT.
  
 2. EROSION CONTROL PLAN AND DETAILS TO BE SUBMITTED
 WITH THE ENGINEERING PERMIT APPLICATION.
  
 3. PROVIDE A COPY OF THE SFWMD ERP MODIFICATION BEFORE
 THE START OF CONSTRUCTION.
  
 4. DRAINAGE CALCULATIONS WILL BE REVIEWED WITH THE
 ENGINEERING PERMIT APPLICATION.
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120 (O)
 561-351-0510 (M)
 [email protected]
  

Review Stop SURVEY SURVEYING
Rev No 4 Status P Date 07-16-2021 Cont ID  
Sent By vnoel Date 07-16-2021 Time 09:05 Rev Time 0.00
Received By vnoel Date   Time   Sent To  
Notes
2021-07-16 09:09:57SEE PROPOSED CONDITIONS OF APPROVAL IN DEVELOPER'S
 APPROVAL LETTER:
  
 2) CONDITION: PRIOR TO SCHEDULING THE HEARING BEFORE
 THE CITY COMMISSION, PROVIDE A SKETCH AND LEGAL
 DESCRIPTION FOR THAT PORTION OF THE NEW DRAINAGE
 EASEMENT WITHIN THE CAR WASH PROPERTY SO THAT THE CITY
 CAN PREPARE THE AGREEMENT TO TERMINATE AND REDEDICATE
 THE DRAINAGE EASEMENT TO REFLECT THE ACTUAL PIPE
 LOCATION.
  
 3) DEVELOPMENT REGULATION (DRAFT): PRIOR TO ZONING
 APPROVAL OF ANY BUILDING PERMITS FOR DEVELOPMENT OF THE
 SITE BASED ON THE CURRENTLY SUBMITTED PLANS, YOU WILL
 NEED TO PROVIDE VERIFICATION THAT BEST BUY HAS RELEASED
 THEIR INTEREST IN THEIR CROSS-ACCESS EASEMENT. THE SITE
 AND LANDSCAPE PLANS SHOW REQUIRED LANDSCAPE WITHIN THE
 EASEMENT WHICH WOULD PREVENT ITS USE FOR CROSS-ACCESS
 PURPOSES. IF BEST BUY DOES NOT RELEASE THEIR INTEREST
 IN THE EASEMENT, THEN THE SITE WILL NEED TO BE
 RECONFIGURED VIA A PLANNED DEVELOPMENT AMENDMENT PRIOR
 TO THE ISSUANCE OF PERMITS.
  
 4) DEVELOPMENT REGULATION (DRAFT): PRIOR TO CO OF THE
 BUILDING, A PLAT FOR THE SITE MUST BE APPROVED BY THE
 CITY AND RECORDED BY THE APPLICANT.
  
  
  

Review Stop SURVEY SURVEYING
Rev No 3 Status F Date 06-23-2021 Cont ID  
Sent By vnoel Date 06-23-2021 Time 08:20 Rev Time 0.00
Received By vnoel Date   Time   Sent To  
Notes
2021-06-23 08:27:201. AFTER DISCUSSIONS WITH OUR LAW DEPT. AND PLANNING,
 BEST BUY WILL NEED TO SIGN OFF ON THE PROPOSED
 IMPROVEMENTS WITHIN THEIR ACCESS EASEMENT.
 2. INSTEAD OF DEDICATION BY PLAT, THE NEW DRAINAGE
 EASEMENT WILL BE BY SEPARATE INSTRUMENT. PLEASE PROVIDE
 A SKETCH AND LEGAL DESCRIPTION FOR THAT PORTION WITHIN
 THE CAR WASH PROPERTY.
 3. CONDITIONS OF APPROVAL WILL BE THE REQUIREMENT TO
 PLAT AND SIGN-OFF BY BEST BUY.

Review Stop SURVEY SURVEYING
Rev No 2 Status F Date 04-26-2021 Cont ID  
Sent By vnoel Date 04-26-2021 Time 07:43 Rev Time 0.00
Received By vnoel Date   Time   Sent To  
Notes
2021-04-26 07:54:361. REPLAT WILL NEED TO INCLUDE DEDICATION OF PORTION OF
 NEW DRAINAGE EASEMENT.
 2. THE ACCESS EASEMENT DOES NOT EXTEND WESTERLY TO
 COVER THE NEW ENTRANCE. REVISED AGREEMENT WILL BE
 REQUIRED.
 3. DATUM CONVERSION NEEDS TO BE SHOWN ON SURVEY AS
 WELL.
 4. EASEMENT AGREEMENT PROVIDED IS NOT A RECORDED COPY.

Review Stop SURVEY SURVEYING
Rev No 1 Status F Date 03-08-2021 Cont ID  
Sent By vnoel Date 03-08-2021 Time 07:54 Rev Time  
Received By vnoel Date   Time   Sent To  
Notes
2021-03-08 07:57:551. PROPERTY WILL NEED TO BE PLATTED. APPLICATION FOR
 MINOR SUBDIVISION IS MADE THROUGH PLANNING.
 2. ADD CONVERSION TO NGVD ON ALL PLANS.
 3. PROVIDE COPIES OF DRAINAGE AND INGRESS/EGRESS
 EASEMENTS.

Review Stop TRAFFIC TRAFFIC ENGINEERING
Rev No 4 Status P Date 06-29-2021 Cont ID  
Sent By   Date 06-29-2021 Time   Rev Time 0.00
Received By   Date   Time   Sent To  
Notes
2021-06-29 11:38:12ALL COMMENTS SATISFIED.
  
  
 TRAFFIC COMMENTS
 1) SATISFIED. PROVIDE COUNTY TPS LETTER
 2) SATISFIED. UPDATE FIGURE 2 IN THE TRAFFIC STUDY SO
 TO PROPERLY DEPICT THE DEVELOPER PROPOSED AND COUNTY
 APPROVED RIGHT-IN/RIGHT OUT TURNING MOVEMENT
 OPERATIONS. LATEST TRAFFIC STATEMENT SHOWS
 NON-ALLOWABLE LEFT-TURN VEHICULAR VOLUMES FROM THE
 DRIVEWAY TO EXECUTIVE CENTER DR
 SITE COMMENTS
 3) SATISFIED. ESTIMATE VACUUM STALLS OCCUPANCY RATE
 4) SATISFIED. WHAT PRECLUDES VEHICLES NOT COMING FROM
 THE CARWASH TO USE THE VACUUM STATIONS?
 5) SATISFIED. CONSIDER CHARGING FOR VACUUM STALLS OR
 MONITOR USAGE AND OCCUPANCY
 6) SATISFIED. PROVIDE A 5 FEET SIDEWALK ON THE WEST
 SIDE OF THE PROPERTY
 7) SATISFIED. MAKE SURE NORTH SIDE SIDEWALK IS AT THE
 MINIMUM 5 FEET
 8) SATISFIED. TPS LETTER APPROVES ONE RIGHT-IN/RIGHT
 OUT ACCESS DRIVEWAY ONTO EXECUTIVE CENTER DRIVE.
 INSTALL A PORK-CHOP ISLAND AND CORRESPONDING SIGNAGE AT
 SUCH LOCATION SO TO ENFORCE THE COUNTY APPROVED
 RIGHT-IN/RIGHT OUT VEHICULAR MOVEMENTS RESTRICTION.
 9) SATISFIED. PROVIDE DESIGN DETAIL OF THE PORK-CHOP
 ISLAND. SPECIFICALLY: IT MUST ALSO FUNCTION AS A
 PEDESTRIAN REFUGE ISLAND. THUS, A SECTION OF THE MIDDLE
 PORTION MUST BE AT LEVEL WITH THE DRIVEWAY APRON
  
 VALERIO ORICCHIO
 CITY TRANSPORTATION ENGINEER
 561-494-1092
 [email protected]
  

Review Stop TRAFFIC TRAFFIC ENGINEERING
Rev No 3 Status F Date 06-23-2021 Cont ID  
Sent By   Date 06-23-2021 Time   Rev Time 0.00
Received By   Date   Time   Sent To  
Notes
2021-06-23 20:57:08TRAFFIC COMMENTS
 1) SATISFIED. PROVIDE COUNTY TPS LETTER
 2) SATISFIED. UPDATE FIGURE 2 IN THE TRAFFIC STUDY SO
 TO PROPERLY DEPICT THE DEVELOPER PROPOSED AND COUNTY
 APPROVED RIGHT-IN/RIGHT OUT TURNING MOVEMENT
 OPERATIONS. LATEST TRAFFIC STATEMENT SHOWS
 NON-ALLOWABLE LEFT-TURN VEHICULAR VOLUMES FROM THE
 DRIVEWAY TO EXECUTIVE CENTER DR
  
 SITE COMMENTS
 3) SATISFIED. ESTIMATE VACUUM STALLS OCCUPANCY RATE
 4) SATISFIED. WHAT PRECLUDES VEHICLES NOT COMING FROM
 THE CARWASH TO USE THE VACUUM STATIONS?
 5) SATISFIED. CONSIDER CHARGING FOR VACUUM STALLS OR
 MONITOR USAGE AND OCCUPANCY
 6) SATISFIED. PROVIDE A 5 FEET SIDEWALK ON THE WEST
 SIDE OF THE PROPERTY
 7) SATISFIED. MAKE SURE NORTH SIDE SIDEWALK IS AT THE
 MINIMUM 5 FEET
 8) SATISFIED. TPS LETTER APPROVES ONE RIGHT-IN/RIGHT
 OUT ACCESS DRIVEWAY ONTO EXECUTIVE CENTER DRIVE.
 INSTALL A PORK-CHOP ISLAND AND CORRESPONDING SIGNAGE AT
 SUCH LOCATION SO TO ENFORCE THE COUNTY APPROVED
 RIGHT-IN/RIGHT OUT VEHICULAR MOVEMENTS RESTRICTION.
 9) NEW COMMENT: PROVIDE DESIGN DETAIL OF THE PORK-CHOP
 ISLAND. SPECIFICALLY: IT MUST ALSO FUNCTION AS A
 PEDESTRIAN REFUGE ISLAND. THUS, A SECTION OF ITS MIDDLE
 PORTION MUST BE AT LEVEL WITH THE DRIVEWAY APRON
  
 VALERIO ORICCHIO
 CITY TRANSPORTATION ENGINEER
 561-494-1092
 [email protected]
  

Review Stop TRAFFIC TRAFFIC ENGINEERING
Rev No 2 Status F Date 04-30-2021 Cont ID  
Sent By   Date 04-30-2021 Time   Rev Time 0.00
Received By   Date   Time   Sent To  
Notes
2021-04-30 15:08:36TRAFFIC COMMENTS
 1) SATISFIED. PROVIDE COUNTY TPS LETTER
 2) NOT SATISFIED. UPDATE FIGURE 2 IN THE TRAFFIC STUDY
 SO TO PROPERLY DEPICT THE DEVELOPER PROPOSED AND COUNTY
 APPROVED RIGHT-IN/RIGHT OUT TURNING MOVEMENT
 OPERATIONS. LATEST TRAFFIC STATEMENT SHOWS
 NON-ALLOWABLE LEFT-TURN VEHICULAR VOLUMES FROM THE
 DRIVEWAY TO EXECUTIVE CENTER DR
  
 SITE COMMENTS
 3) SATISFIED. ESTIMATE VACUUM STALLS OCCUPANCY RATE
 4) SATISFIED. WHAT PRECLUDES VEHICLES NOT COMING FROM
 THE CARWASH TO USE THE VACUUM STATIONS?
 5) SATISFIED. CONSIDER CHARGING FOR VACUUM STALLS OR
 MONITOR USAGE AND OCCUPANCY
 6) SATISFIED. PROVIDE A 5 FEET SIDEWALK ON THE WEST
 SIDE OF THE PROPERTY
 7) SATISFIED. MAKE SURE NORTH SIDE SIDEWALK IS AT THE
 MINIMUM 5 FEET
 8) NOT SATISFIED. TPS LETTER APPROVES ONE
 RIGHT-IN/RIGHT OUT ACCESS DRIVEWAY ONTO EXECUTIVE
 CENTER DRIVE. INSTALL A PORK-CHOP ISLAND AND
 CORRESPONDING SIGNAGE AT SUCH LOCATION SO TO ENFORCE
 THE COUNTY APPROVED RIGHT-IN/RIGHT OUT VEHICULAR
 MOVEMENTS RESTRICTION.
  
 VALERIO ORICCHIO
 CITY TRANSPORTATION ENGINEER
 561-494-1092
 [email protected]
  
  

Review Stop TRAFFIC TRAFFIC ENGINEERING
Rev No 1 Status F Date 03-10-2021 Cont ID  
Sent By   Date 03-10-2021 Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
2021-03-10 18:07:53TRAFFIC COMMENTS
 1) PROVIDE COUNTY TPS LETTER
  
 SITE COMMENTS
 2) ESTIMATE VACUUM STALLS OCCUPANCY RATE
 3) WHAT PRECLUDES VEHICLES NOT COMING FROM THE CARWASH
 TO USE THE VACUUM STATIONS?
 4) CONSIDER CHARGING FOR VACUUM STALLS OR MONITOR USAGE
 AND OCCUPANCY
 5) PROVIDE A 5 FEET SIDEWALK ON THE WEST SIDE OF THE
 PROPERTY
  
 VALERIO ORICCHIO
 CITY TRANSPORTATION ENGINEER
 561-494-1092
 [email protected]
  

Review Stop Z ZONING
Rev No 4 Status P Date 07-16-2021 Cont ID  
Sent By eschneid Date 07-15-2021 Time 11:46 Rev Time 1.00
Received By eschneid Date 07-14-2021 Time 15:27 Sent To  
Notes
2021-07-16 09:15:021) CONDITION: PRIOR TO SCHEDULING THE HEARING BEFORE
 THE CITY COMMISSION, PROVIDE THE COPY OF THE COMCAST
 LETTER OF NO OBJECTION.
  
 2) CONDITION: PRIOR TO SCHEDULING THE HEARING BEFORE
 THE CITY COMMISSION, PROVIDE A SKETCH AND LEGAL
 DESCRIPTION FOR THAT PORTION OF THE NEW DRAINAGE
 EASEMENT WITHIN THE CAR WASH PROPERTY SO THAT THE CITY
 CAN PREPARE THE AGREEMENT TO TERMINATE AND REDEDICATE
 THE DRAINAGE EASEMENT TO REFLECT THE ACTUAL PIPE
 LOCATION.
  
 3) DEVELOPMENT REGULATION (DRAFT): PRIOR TO ZONING
 APPROVAL OF ANY BUILDING PERMITS FOR DEVELOPMENT OF THE
 SITE BASED ON THE CURRENTLY SUBMITTED PLANS, YOU WILL
 NEED TO PROVIDE VERIFICATION THAT BEST BUY HAS RELEASED
 THEIR INTEREST IN THEIR CROSS-ACCESS EASEMENT. THE SITE
 AND LANDSCAPE PLANS SHOW REQUIRED LANDSCAPE WITHIN THE
 EASEMENT WHICH WOULD PREVENT ITS USE FOR CROSS-ACCESS
 PURPOSES. IF BEST BUY DOES NOT RELEASE THEIR INTEREST
 IN THE EASEMENT, THEN THE SITE WILL NEED TO BE
 RECONFIGURED VIA A PLANNED DEVELOPMENT AMENDMENT PRIOR
 TO THE ISSUANCE OF PERMITS.
  
 4) DEVELOPMENT REGULATION (DRAFT): PRIOR TO CO OF THE
 BUILDING, A PLAT FOR THE SITE MUST BE APPROVED BY THE
 CITY AND RECORDED BY THE APPLICANT.
  
 5) DEVELOPMENT REGULATION: THE MENU SIGNS MAY INCLUDE
 THE BUSINESS NAME AND/OR LOGO; HOWEVER, THE NAME/LOGO
 MUST BE POSITIONED SO AS NOT TO FACE OR BE VISIBLE FROM
 EXECUTIVE CENTER DRIVE.
  
 6) DEVELOPMENT REGULATION: SEATING ALONG EXECUTIVE
 CENTER DRIVE MUST MEET CRIME PREVENTION THROUGH
 ENVIRONMENTAL DESIGN (CPTED) STANDARDS.
  

Review Stop Z ZONING
Rev No 3 Status F Date 06-21-2021 Cont ID  
Sent By eschneid Date 06-21-2021 Time 16:58 Rev Time 3.00
Received By eschneid Date 06-21-2021 Time 16:58 Sent To  
Notes
2021-06-21 16:59:13CASE NO. PB 1060NN JUNE 21, 2021 REVIEW
 FLAMINGO CAR WASH II
 879 WEST EXECUTIVE CENTER DRIVE
  
 - CONTACT ERIC SCHNEIDER @ (561) 822-1446
  
 - PLEASE PROVIDE RESPONSES TO REVIEW COMMENTS IN
 WRITTEN FORMAT.
  
 - WHEN RESUBMITTING, PLEASE PROVIDE A MINIMUM OF THREE
 (3) PAPER COPIES AND AN ELECTRONIC COPY IN .PNG FORMAT
 OF ALL PLANS. PLEASE NOTE THAT CHANGES ON THE
 RESUBMITTED PLANS OR THE SUBMITTAL OF INFORMATION/PLANS
 TO ADDRESS THE COMMENTS MAY RESULT IN ADDITIONAL
 COMMENTS.
  
 - UPON STAFF REVIEW OF THE RESUBMITTED PLANS AND
 DETERMINATION THAT THE NEW PLANS HAVE MET THE COMMENTS,
 YOU WILL BE SCHEDULED FOR THE NEXT AVAILABLE PLANNING
 BOARD MEETING.
  
 - PLEASE NOTE THAT YOU WILL BE PERMITTED ONE ADDITIONAL
 RESUBMITTAL AT NO ADDITIONAL COST. IF PREVIOUSLY-ISSUED
 COMMENTS CONTINUE TO NOT BE SUFFICIENTLY ADDRESSED, THE
 APPLICANT WILL BE ASSESSED A RESUBMITTAL FEE. SUCH FEE
 WILL BE 20% OF THE ORIGINAL APPLICATION FEE ($600).
  
 - PUBLIC HEARING NOTIFICATION SIGNAGE SHALL BE POSTED
 IN ACCORDANCE WITH THE REQUIREMENTS OF SECTION
 94-39(I)(5) OF THE ZONING AND LAND DEVELOPMENT
 REGULATIONS.
  
 1) THE TREES AND PALMS THAT ARE LISTED AS TO BE
 RELOCATED AND REMOVED MUST NO LONGER BE SHOWN ON THE
 LANDSCAPE PLAN. SHOWING THEM WITH A LOWER LINE WEIGHT
 IS NOT PERMITTED. THE LANDSCAPE PLAN IS TO SHOW THE
 FINAL LANDSCAPE LAYOUT, SO THE TREES WOULD BE SHOWN
 WHERE THEY WILL BE RELOCATED TO, NOT WHERE THEY CAME
 FROM.
  
 2) THE PROPERTY LINE DIMENSIONS LISTED ON THE TREE
 REQUIREMENTS CHART DO NOT MATCH THE DIMENSIONS SHOWN ON
 THE SITE PLAN OR SURVEY. WHILE THEY ARE CLOSE, THE WEST
 PROPERTY LINE WILL GO TO 215 FEET AND THUS REQUIRES AN
 ADDITIONAL TREE. UPDATE THE CHART ACCORDINGLY. NOTE: IT
 APPEARS THAT THE BUFFERS HAVE ENOUGH BUFFER TREES, EVEN
 WITH THE ONE ADDITIONAL THAT IS REQUIRED.
  
 3) LEAVING THE AREA WITH THE OLD DRIVEWAY CUT VIOLATES
 THE 1 TREE EVERY 30 FEET AND THE HEDGE REQUIRED WITHIN
 BUFFERS ADJACENT TO VEHICULAR USE AREAS. THE LANDSCAPE
 PLANS MUST SHOW FULL COMPLIANCE WITH THE LANDSCAPE
 CODE. NOTE: THE LANDSCAPE TABLES NEED TO BE UPDATED TO
 REFLECT MATERIAL THAT IS SHOW IN THIS LOCATION.
  
 4) A SABAL PALM IS SHOWN LOCATED WITHIN THE REVISED
 DRAINAGE EASEMENT ALONG THE BRANDSMART PROPERTY. THE
 CITY DOES NOT PERMIT TREES TO BE PLANTED WITHIN CITY
 DRAINAGE EASEMENTS. THE SABAL PALM WILL NEED TO BE
 RELOCATED OUT OF THE EASEMENT.
  
 5) PROVIDE A COPY OF THE COMCAST LETTER OF NO
 OBJECTION.
  
 6) WILL THE MENU SIGNS INCLUDE THE BUSINESS NAME OR
 LOGO ON THEM? IF SO, THEN THIS WILL NEED TO BE
 SPECIFICALLY PERMITTED BY THE DEVELOPMENT ORDER.
  
 7) CONDITION (DRAFT): PRIOR TO CO OF THE CAR WASH
 BUILDING, THE APPLICANT WILL WORK WITH THE CITY TO
 TERMINATE AND REDEDICATE THE DRAINAGE EASEMENT IN THE
 SOUTHWEST PORTION OF THE SITE TO REFLECT THE ACTUAL
 PIPE LOCATION.
  
 8) CONDITION (DRAFT): THE BENCHES PROPOSED ALONG
 EXECUTIVE CENTER DRIVE MUST MET CRIME PREVENTION
 THROUGH ENVIRONMENTAL DESIGN (CPTED) STANDARDS.
  
 9) CONDITION (DRAFT): THE CITY HAS PLOTTED, AND YOUR
 SURVEYOR HAS VERIFIED, THAT THE CROSS ACCESS EASEMENT
 THAT BEST BUY HAS AN INTEREST IN AS LAID OUT IN THE
 EASEMENT WITH COVENANTS AND RESTRICTIONS CROSSES THE
 CAR WASH SITE. BASED ON THE LATEST PROPOSAL, THE
 DUMPSTER ENCLOSURE AND REQUIRED BUFFER LANDSCAPE WOULD
 BLOCK BEST BUY'S ABILITY TO UTILIZE THE EASEMENT TO
 CONSTRUCT ACCESS TO EXECUTIVE CENTER DRIVE. PRIOR TO
 ZONING APPROVAL OF ANY BUILDING PERMITS FOR DEVELOPMENT
 OF THE SITE BASED ON THE CURRENTLY SUBMITTED PLANS, YOU
 WILL NEED TO PROVIDE VERIFICATION THAT BEST BUY HAS
 RELEASED THEIR INTEREST IN THE EASEMENT. IF BEST BUY
 DOES NOT RELEASE THEIR INTEREST IN THE EASEMENT, THEN
 THE SITE WILL NEED TO BE RECONFIGURED VIA A PLANNED
 DEVELOPMENT AMENDMENT PRIOR TO THE ISSUANCE OF PERMITS.
  
  
  

Review Stop Z ZONING
Rev No 2 Status F Date 04-26-2021 Cont ID  
Sent By eschneid Date 04-26-2021 Time 10:22 Rev Time 6.00
Received By eschneid Date 04-23-2021 Time 09:38 Sent To  
Notes
2021-04-26 10:23:11CASE NO. PB 1060NN
 FLAMINGO CAR WASH II
 879 WEST EXECUTIVE CENTER DRIVE
  
 - CONTACT ERIC SCHNEIDER @ (561) 822-1446
  
 - PLEASE PROVIDE RESPONSES TO REVIEW COMMENTS IN
 WRITTEN FORMAT.
  
 - WHEN RESUBMITTING, PLEASE PROVIDE A MINIMUM OF FOUR
 (4) PAPER COPIES AND AN ELECTRONIC COPY IN .PNG FORMAT
 OF ALL PLANS. PLEASE NOTE THAT CHANGES ON THE
 RESUBMITTED PLANS OR THE SUBMITTAL OF INFORMATION/PLANS
 TO ADDRESS THE COMMENTS MAY RESULT IN ADDITIONAL
 COMMENTS.
  
 - UPON STAFF REVIEW OF THE RESUBMITTED PLANS AND
 DETERMINATION THAT THE NEW PLANS HAVE MET THE COMMENTS,
 YOU WILL BE SCHEDULED FOR THE NEXT AVAILABLE PLANNING
 BOARD MEETING.
  
 - PLEASE NOTE THAT IF THE PLANNING DIVISION HAS NOT
 RECEIVED A RESPONSE TO THE PPRC COMMENTS WITHIN 60 DAYS
 FROM THE DATE OF THE PPRC MEETING (BY MAY 11, 2021),
 THE CASE SHALL BE CONSIDERED WITHDRAWN. ANY FURTHER
 ACTION SHALL REQUIRE A NEW DEVELOPMENT APPLICATION.
  
 - PLEASE NOTE THAT YOU WILL BE PERMITTED ONE ADDITIONAL
 RESUBMITTAL AT NO ADDITIONAL COST. IF PREVIOUSLY-ISSUED
 COMMENTS CONTINUE TO NOT BE SUFFICIENTLY ADDRESSED, THE
 APPLICANT WILL BE ASSESSED A RESUBMITTAL FEE. SUCH FEE
 WILL BE 20% OF THE ORIGINAL APPLICATION FEE ($600).
  
 - PUBLIC HEARING NOTIFICATION SIGNAGE SHALL BE POSTED
 IN ACCORDANCE WITH THE REQUIREMENTS OF SECTION
 94-39(I)(5) OF THE ZONING AND LAND DEVELOPMENT
 REGULATIONS.
  
 1) REPEAT COMMENT: YOU NEED TO SHOW THE CORRECT TRAFFIC
 MARKINGS ON THE SITE PLAN (EXAMPLE STOP BAR AND SIGN
 FOR VEHICLES EXITING THE BRANDSMART/BJS SITE), EVEN
 THOUGH THEY WILL NOT NEED TO BE INSTALLED UNTIL THE
 CONNECTION IS COMPLETED.
  
 2) REPEAT COMMENT: PROVIDE A COPY OF THE FPU, FPL AND
 COMCAST LETTERS OF NO OBJECTION.
  
 3) THANK YOU FOR PROVIDING THE PAY STRUCTURE
 ELEVATIONS. THE SOUTHERN WALL CONTINUES TO BE SHOWN
 ENCROACHING INTO THE REQUIRED FIVE (5) FOOT SIDE
 SETBACK, WHICH IS NOT PERMITTED. PROVIDE THE DIMENSION
 OF THE ARCHITECTURAL OVERHANG FROM THE BUILDING WALL.
 THE OVERHANG MAY NOT ENCROACH MORE THEN THREE (3) FEET
 INTO THE REQUIRED SETBACK.
  
 4) THE LANDSCAPE AND SITE PLANS NEED TO SHOW THE
 REVISED LOCATION OF THE CONTROL STRUCTURE AND OUTFALL
 PIPE AND THE CONNECTION TO THE STORM MANHOLE ON THE
 BRANDSMART PROPERTY. NOTE: THE LANDSCAPE PLAN NEEDS TO
 SHOW ALL THE UNDERGROUND UTILITY AND DRAINAGE LOCATIONS
 (TO INCLUDE THE EXTENT OF THE EASEMENT) SO THAT STAFF
 CAN VERIFY THAT THERE ARE NOT CONFLICTS AND THE
 PROPOSED ROOT BARRIERS WILL BE EFFECTIVE. IF POSSIBLE,
 THE CONTROL STRUCTURE AND OUTFALL PIPES SHOULD BE
 LOCATED OUTSIDE OF LANDSCAPE AREAS TO PERMIT TREE ROOT
 GROWTH.
  
 5) THE CIVIL PLAN CONTINUES TO SHOW THE CITY'S OLD, TOO
 SMALL OPENING, DUMPSTER ENCLOSURE. PLEASE REMOVE OR
 REPLACE.
  
 6) CURRENTLY THE SITE IS ONLY PERMITTED TO HAVE A
 RESTAURANT, WHICH IS THE REASON THAT YOU NEED TO AMEND
 THE PLANNED DEVELOPMENT TO PERMIT THE CAR WASH USE
 (FALLS UNDER THE MOTOR VEHICLE FUEL SALES AND SERVICE
 CATEGORY. STAFF IS WONDERING WHY YOU HAVE INCLUDED
 MOTOR VEHICLE REPAIR, LIGHT, AS A PERMITTED USE. THIS
 ITEM NEEDS FURTHER DISCUSSION.
  
 7) PROVIDE THE DIMENSION OF THE ARCHITECTURAL OVERHANG
 FROM THE BUILDING WALL OF THE CAR WASH BUILDING. IT
 SCALES AT TWO (2) FEET, WHICH WOULD STILL MEET CODE
 SINCE THE BUILDING WALL IS SHOWN AT SEVEN (7) AT ITS
 CLOSEST POINT TO THE PROPERTY LINE. REMEMBER, THE
 OVERHANG MAY NOT ENCROACH MORE THAN THREE (3) FEET INTO
 THE REQUIRED SETBACK.
  
 8) PROVIDE NOTARIZED VERIFICATION FROM THE NEIGHBORING
 PROPERTY OWNER AT 1840 PALM BEACH LAKES BOULEVARD THAT
 HE WILL EXTEND THE ACCESS EASEMENT TO THE NEW DRIVEWAY
 LOCATION.
  
 9) CONDITION (DRAFT): PRIOR TO THE ISSUANCE FOR THE
 PERMIT TO CONSTRUCT THE DRIVEWAY CONNECTION TO THE
 INTERNAL DRIVE ON THE GAS STATION PARCEL, PROVIDE
 VERIFICATION THAT THE ACCESS EASEMENT HAS BEEN MODIFIED
 TO REACH YOUR PROPOSED DRIVEWAY.
  
 10) CONDITION (DRAFT): PRIOR TO CO OF THE CAR WASH
 BUILDING, THE APPLICANT WILL WORK WITH THE CITY TO
 TERMINATE AND REDEDICATE THE DRAINAGE EASEMENT IN THE
 SOUTHWEST PORTION OF THE SITE TO REFLECT THE ACTUAL
 PIPE LOCATION.
  

Review Stop Z ZONING
Rev No 1 Status F Date 03-10-2021 Cont ID  
Sent By eschneid Date 03-10-2021 Time 10:45 Rev Time 8.00
Received By eschneid Date 03-08-2021 Time 15:25 Sent To  
Notes
2021-03-10 10:45:47CASE NO. PB 1060NN
 FLAMINGO CAR WASH II
 879 WEST EXECUTIVE CENTER DRIVE
  
 - CONTACT ERIC SCHNEIDER @ (561) 822-1446
  
 - PLEASE PROVIDE RESPONSES TO REVIEW COMMENTS IN
 WRITTEN FORMAT.
  
 - WHEN RESUBMITTING, PLEASE PROVIDE A MINIMUM OF FOUR
 (4) PAPER COPIES AND AN ELECTRONIC COPY IN .PNG FORMAT
 OF ALL PLANS. PLEASE NOTE THAT CHANGES ON THE
 RESUBMITTED PLANS OR THE SUBMITTAL OF INFORMATION/PLANS
 TO ADDRESS THE COMMENTS MAY RESULT IN ADDITIONAL
 COMMENTS.
  
 - THE PPRC COMMENTS SHALL BE SUFFICIENTLY ADDRESSED AND
 SUBMITTED TO THE PLANNING DIVISION BY 5 PM ON FRIDAY,
 MARCH 26, 2021, TO BE ELIGIBLE TO BE SCHEDULED FOR THE
 MAY 18, 2021 PLANNING BOARD MEETING.
  
 - PLEASE NOTE THAT IF THE PLANNING DIVISION HAS NOT
 RECEIVED A RESPONSE TO THE PPRC COMMENTS WITHIN 60 DAYS
 FROM THE DATE OF THE PPRC MEETING (BY MAY 11, 2021),
 THE CASE SHALL BE CONSIDERED WITHDRAWN. ANY FURTHER
 ACTION SHALL REQUIRE A NEW DEVELOPMENT APPLICATION.
  
 - PLEASE NOTE THAT YOU WILL BE PERMITTED ONE (1)
 RESUBMITTAL AT NO ADDITIONAL COST. IF PREVIOUSLY-ISSUED
 COMMENTS CONTINUE TO NOT BE SUFFICIENTLY ADDRESSED, THE
 APPLICANT WILL BE ASSESSED A RESUBMITTAL FEE. SUCH FEE
 WILL BE 20% OF THE ORIGINAL APPLICATION FEE ($600).
  
 - PUBLIC HEARING NOTIFICATION SIGNAGE SHALL BE POSTED
 IN ACCORDANCE WITH THE REQUIREMENTS OF SECTION
 94-39(I)(5) OF THE ZONING AND LAND DEVELOPMENT
 REGULATIONS.
  
 1) THE CHINESE RESTAURANT SITE IS PART OF WHAT WAS
 PARCEL 3 OF THE PALM BEACH LAKES INN AND GOLF COURSE
 CPD AND COVERED BY ORDINANCE NO. 2622-93. PLEASE
 PROVIDE A RESPONSE/STATUS UPDATE TO THE CONDITIONS
 LISTED IN SECTION 5, SUBSECTIONS 3, 7, 8 AND 9 OF
 ORDINANCE NO. 2622-93.
  
 2) EVEN THOUGH THE TRAFFIC STATEMENT FOR THE
 REDEVELOPMENT SHOWS A REDUCTION IN TRIPS FOR THE
 MAJORITY OF THE TESTED TIME FRAMES, YOU ARE STILL
 REQUIRED TO SUBMIT AN APPROVED TRAFFIC PERFORMANCE
 STANDARDS LETTER FROM PALM BEACH COUNTY ENGINEERING. AN
 APPROVAL LETTER IS REQUIRED PRIOR TO SCHEDULING FOR
 PLANNING BOARD.
  
 3) THANK YOU FOR PROVIDING A COPY OF THE EASEMENT WITH
 COVENANTS AND RESTRICTIONS. IT INDICATES THAT BEST BUY
 HAS AN INTEREST IN THE CROSS ACCESS, SPECIFICALLY A
 DRIVE TO EXECUTIVE CENTER DRIVE. PLEASE PROVIDE
 VERIFICATION THAT BEST BUY HAS RELEASED THEIR INTEREST
 IN THE EASEMENT. THE SITE PLAN SHOWS THE DUMPSTER AND
 LANDSCAPING OBSTRUCTING BEST BUY FROM UTILIZING THE
 EASEMENT. PLEASE NOTE THAT REGARDLESS OF WHAT IS STATED
 IN THE EASEMENT, BEST BUY HAS NO RIGHTS TO THE
 INSTALLATION OF AN OFF PREMISE SIGN, WHICH WOULD BE IN
 VIOLATION OF THE ZONING AND LAND DEVELOPMENT
 REGULATIONS.
  
 4) THANK YOU FOR SHOWING THE CROSS ACCESS DRIVEWAY WITH
 THE BRANDSMART/BJS SITE CONSTRUCTED TO THE PROPERTY
 LINE. NOTE: THE RECENT BRANDSMART/BJS RESUBMITTAL DID
 NOT SHOW THEIR SIDE OF THE DRIVEWAY LINED UP WITH THE
 FLAMINGO PROPOSED LOCATION. STAFF WILL BE MAKING THAT
 COMMENT ON THEIR REVIEW; HOWEVER, YOU WILL NEED TO SHOW
 THE CORRECT TRAFFIC MARKINGS ON THE SITE PLAN (EXAMPLE
 STOP BAR AND SIGN FOR VEHICLES EXITING THE
 BRANDSMART/BJS SITE), EVEN THOUGH THEY WILL NOT NEED TO
 BE INSTALLED UNTIL THE CONNECTION IS COMPLETED.
  
 5) PROVIDE A COPY OF THE WARRANTY DEED AND THE FPU, FPL
 AND COMCAST LETTERS OF NO OBJECTION.
  
 6) PROVIDE COPIES OF ALL THE EASEMENTS/RESTRICTIONS
 AFFECTING THE SITE. A QUICK REVIEW OF THE TWO 30 FOOT
 I.E.E. LISTED ON THE SURVEY DO NOT SHOW THE EASEMENT
 EXTENDING TO THE PROPOSED NEW ACCESS CONNECTION TO THE
 DRIVEWAY BETWEEN THE GAS STATION AND THE RESTAURANT
 PARCEL. PLEASE PROVIDE VERIFICATION THAT YOU HAVE
 ACCESS RIGHTS TO THE PARCEL AS SHOWN.
  
 7) PLEASE CONSIDER MAKING THE EMPLOYEE/ADA PARKING
 SPACES ONLY NINE (9) FEET WIDE AND 18 FEET DEEP
 INCLUDING THE TWO (2) FOOT OVERHANG TO REDUCE THE
 AMOUNT OF PAVEMENT WITHIN THE PARKING AREA. THESE
 SPACES DO NOT NEED THE EXTRA SIZE THAT THE VACUUM
 SPACES REQUIRE.
  
 8) THE JUSTIFICATION STATEMENT STATES THAT THE SIDEWALK
 ALONG EXECUTIVE CENTER DRIVE WILL BE WIDENED TO AN 8-10
 FOOT MULTIPURPOSE PATH; HOWEVER, THE SITE PLAN CALLS
 OUT A 7-9 FOOT WIDTH THAT MATCHES THE EXISTING
 CONDITION SHOWN ON THE SURVEY. PLEASE EXPLAIN OR AMEND
 THE JUSTIFICATION STATEMENT.
  
 9) THE ZONING AND LAND DEVELOPMENT REGULATIONS REQUIRE
 THAT ANY SOURCE OF ILLUMINATION LOCATED WITHIN A
 COMMERCIAL PLANNED DEVELOPMENT DISTRICT SHALL NOT
 EXCEED ONE FOOTCANDLE AT OR BEYOND THE BOUNDARIES OF
 SUCH DEVELOPMENT. THE PHOTOMETRIC PLAN SHOWS THIS
 MAXIMUM BEING EXCEEDED ALONG EXECUTIVE CENTER DRIVE.
 THE BOUNDARY WITH BEST BUY DOES NOT MATCH THE SITE
 PLAN, BUT STILL APPEARS TO EXCEED THE PERMITTED LIGHT
 LEVELS.
  
 10) PROVIDE THE DETAILS OF THE PAY LANE STRUCTURE. THE
 POSTS ON THE EAST SIDE OF THE STRUCTURE ARE LOCATED
 WITHIN THE REQUIRED FIVE (5) FOOT SIDE SETBACK, WHICH
 IS NOT PERMITTED.
  
 11) THE PROPOSED BICYCLE RACK NEEDS TO HAVE A SUPPORT
 POST DIMENSION BETWEEN 22 AND 24 INCHES AS OPPOSED TO
 THE 14.375 INCHES SPECIFIED ON THE BICYCLE RACK DETAIL.
 THE NARROW DIMENSION IS NOT ADEQUATE TO APPROPRIATELY
 SECURE A BICYCLE.
  
 12) PROVIDE THE BICYCLE PAD DIMENSIONS ON THE OVERALL
 SITE OR CIVIL PLAN AS WELL AS THE ARCHITECTURAL SITE
 PLAN.
  
 13) THE FLAG POLE MAY NOT EXCEED 50 FEET IN HEIGHT AND
 MAY NOT FLY A FLAG WITH THE NAME OR LOGO OF THE
 BUSINESS.
  
 14) NONE OF THE PLANT MATERIALS ARE LABELED ON THE
 LANDSCAPE PLAN. STAFF CANNOT VERIFY COMPLIANCE WITH THE
 LANDSCAPE CODE REQUIREMENTS.
  
 15) THE EAST AND SOUTH BUFFERS DO NOT APPEAR TO MEET
 THE MINIMUM NUMBER OF REQUIRED TREES NOR DO THEY MEET
 THE REQUIRED SPACING OF THE TREES DUE TO THE DRAINAGE
 EASEMENTS. YOU HAVE NOT DEMONSTRATED COMPLIANCE WITH
 THE LANDSCAPE REQUIREMENTS.
  
 16) FREESTANDING SIGNS ARE REQUIRED TO BE A MINIMUM OF
 24 FEET FROM ADJOINING LOT LINES. THE MONUMENT SIGN
 LOCATION DOES NOT COMPLY WITH THIS SETBACK REQUIREMENT.
 WHAT IS THE PROPOSED HEIGHT OF THE SIGN?
  
 17) DIRECTIONAL SIGNS ARE REQUIRED TO BE A MINIMUM OF
 20 FEET FROM ANOTHER LOT LINE. THE PROPOSED DIRECTIONAL
 SIGNS DO NOT MEET THIS REQUIREMENT. NO DETAILS ON THE
 DIRECTIONAL SIGNS WERE PROVIDED TO VERIFY CODE
 COMPLIANCE. NOTE: DEPENDING ON WHAT THE SIGNS ARE FOR,
 THEY MAY ACTUALLY BE PARKING AREA INSTRUCTIONAL SIGNS,
 WHICH HAVE DIFFERENT SETBACK PROVISIONS.
  
 18) THE DUMPSTER ENCLOSURES DO NOT MEET THE MINIMUM
 CITY STANDARDS.
  
 19) THE CONCEPTUAL ENGINEERING PLAN SHOWS THE PROPOSED
 CONTROL STRUCTURE AND OUTFALL PIPE WITHIN THE LANDSCAPE
 BUFFER ON THE BRANDSMART/BJS SITE. THIS NEEDS TO BE
 RELOCATED TO UNDERNEATH A PAVED AREA SO AS NOT TO
 IMPACT REQUIRED LANDSCAPE BUFFERS.
  
 20) WHAT IS LOCATED WITHIN THE DRAINAGE EASEMENTS? WHAT
 IS THE OPPORTUNITY TO ABANDON, REVISE OR RELOCATE THEM?
 THE NON-EXCLUSIVE OUTFALL DRAINAGE EASEMENT RECORDED IN
 ORB 11870 PG 300 INCLUDES PROVISIONS FOR TERMINATION OF
 THE EASEMENTS OF PORTIONS OF EASEMENTS THAT ARE NO
 LONGER NEEDED.
  
 21) TURN OFF THE TREE DISPOSITION LAYER ON THE SITE
 PLAN. THIS NEEDS TO BE SHOWN ON A SEPARATE PLAN AS IT
 IMPEDES THE READABILITY OF THE SITE PLAN.
  
 22) PLEASE CONSIDER USING A PERVIOUS PAVEMENT
 UNDERNEATH THE VACUUM AREA PARKING SPOTS.
  
 23) STAFF HAS NOTED THAT THERE IS NO INTERNAL
 PEDESTRIAN CIRCULATION BETWEEN THE MARATHON GAS
 STATION, THE PROPOSED FLAMINGO CAR WASH SITE AND THE
 BEST BUY. IN ORDER TO COMPLY WITH THE PEDESTRIAN
 CIRCULATION SITE DESIGN QUALITATIVE DEVELOPMENT
 STANDARDS, YOU WILL NEED TO PROVIDE A FIVE (5) FOOT
 WIDE SIDEWALK ALONG THE WEST PROPERTY LINE OF THE SITE
 FROM EXECUTIVE CENTER DRIVE TO THE BEST BUY PROPERTY
 LINE. THE LANDSCAPE BUFFER WOULD BE SHIFTED TO THE
 SIDEWALK AND YOUR EXISTING CURB LINE.
  
 24) THE BENCHES ALONG EXECUTIVE CENTER DRIVE NEED TO
 MEET CPTED STANDARDS.
  
 25) PLEASE CLARIFY THE INTENT OF THE USE CHART THAT IS
 INCLUDED WITH THE SITE PLAN.
  
 26) IN ORDER TO PROVIDE FOR A UNIFORM STREETSCAPE ON
 THIS SIDE OF EXECUTIVE CENTER DRIVE AND PROVIDE SHADE,
 THE NORTHERN BUFFER TREES NEED TO BE GUMBO LIMBO TREES.
  

  Print


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved