Plan Review Details - Project Z21010025
| Plan Review Stops For Project Z21010025 |
| Review Stop |
AIPP |
ART IN PUBLIC PLACES |
| Rev No |
2 |
Status |
F |
Date |
02-05-2021 |
|
|
Cont ID |
|
| Sent By |
scwelter |
Date |
02-05-2021 |
Time |
15:51 |
Rev Time |
0.00 |
| Received By |
rthermid |
Date |
02-05-2021 |
Time |
15:50 |
Sent To |
|
|
| Notes |
| 2021-02-05 15:58:10 | 1% IN PRIVATE DEVELOPMENT. ALL PRIVATE DEVELOPMENT | | | PROJECTS, INCLUDING NEW CONSTRUCTION, OR THE RENOVATION | | | OR IMPROVEMENT OF AN EXISTING BUILDING, WHERE TOTAL | | | CONSTRUCTION COSTS ARE EQUAL TO OR GREATER THAN | | | $500,000 ARE SUBJECT TO THE PUBLIC ART REQUIREMENT. | | | ALL BUILDINGS WITHIN NEW PLANNED DEVELOPMENTS SHALL BE | | | ASSESSED CUMULATIVELY TOWARDS THIS PUBLIC ART | | | REQUIREMENT, EVEN IF THE BUILDINGS ARE PERMITTED | | | SEPARATELY OR DEVELOPED IN PHASES. THE PROVISIONS OF | | | THIS SECTION APPLY TO NEW DEVELOPMENT OR NEW | | | CONSTRUCTION WITHIN EXISTING PLANNED DEVELOPMENTS. | | | DEVELOPER MUST SELECT ONE OF THE FOLLOWING OPTIONS: | | | (1) OPTION 1: INSTALL AND ARTWORK ON THE DEVELOPMENT | | | SITE VALUED IN AN AMOUNT NOT LESS THAN ONE PERCENT OF | | | THE TOTAL CONSTRUCTION COSTS; OR | | | (2) OPTION 2: CONTRIBUTE AN AMOUNT EQUAL TO 75 PERCENT | | | OF ONE PERCENT OF THE TOTAL CONSTRUCTION COSTS FOR | | | DEPOSIT TO THE PUBLIC ART ACCOUNT. | | | PLEASE CONTACT SYBILLE WELTER, ADMINISTRATOR OF PUBLIC | | | ART AND CULTURE AT [email protected] | | | |
|
|
| Review Stop |
AIPP |
ART IN PUBLIC PLACES |
| Rev No |
1 |
Status |
|
Date |
|
|
|
Cont ID |
|
| Sent By |
|
Date |
|
Time |
|
Rev Time |
0.00 |
| Received By |
|
Date |
|
Time |
|
Sent To |
|
|
| Notes |
|
|
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
1 |
Status |
F |
Date |
02-11-2021 |
|
|
Cont ID |
|
| Sent By |
rbrown |
Date |
02-10-2021 |
Time |
20:42 |
Rev Time |
0.00 |
| Received By |
rbrown |
Date |
02-10-2021 |
Time |
20:42 |
Sent To |
|
|
| Notes |
| 2021-02-10 20:44:57 | DEVELOPMENT SERVICES DEPARTMENT, BUILDING DIVISION, | | | COMMENTS: | | | | | | 1. THIS REVIEW IS A CURSORY REVIEW AS IT RELATES TO THE | | | SITE. IT IS NOT A REVIEW FOR FULL COMPLIANCE WITH | | | FLORIDA BUILDING CODE. THE FOLLOWING COMMENTS ARE TO BE | | | ADDRESSED FOR THE BUILDING PERMIT APPLICATION. | | | | | | 2. BUILDING SIZE. WHEN SUBMITTED FOR BUILDING PERMIT, | | | THE PLANS SHALL SHOW THAT THE TYPE OF CONSTRUCTION FOR | | | THE BUILDINGS WILL BE IN ACCORDANCE WITH THE HEIGHT, | | | AREA AND OCCUPANCY LIMITATIONS IN CHAPTER 5 OF THE | | | FLORIDA BUILDING CODE. | | | | | | 3. BUILDING LOCATION RELATIVE TO THE PROPERTY LINE AND | | | OTHER STRUCTURES. WHEN SUBMITTED FOR BUILDING PERMIT, | | | COMPLIANCE WITH ALL BUILDING SEPARATION, PERCENTAGE OF | | | OPENINGS AND OPENING PROTECTIVE REQUIREMENTS OF | | | CHAPTERS 6 AND 7 OF THE FLORIDA BUILDING CODE SHALL BE | | | VERIFIED. | | | | | | 4. SEPARATE PERMITS REQUIRED. ALL APPLICABLE PERMITS | | | AND SUB-PERMITS MUST BE OBTAINED BEFORE COMMENCING THE | | | WORK. SEPARATE PERMITS, PLANS AND FEES, ARE REQUIRED | | | FOR SIGNS, GAS SYSTEMS, GENERATORS, FIRE ALARM SYSTEMS, | | | FIRE SPRINKLER AND OTHER FIRE SUPPRESSION SYSTEMS, | | | GREASE INTERCEPTORS, SITE LIGHTING, SITE LANDSCAPE, | | | SITE IRRIGATION, ETC. | | | | | | 5. CONTRACTOR VEHICLE PARKING. PROPERTY OWNER AND | | | CONTRACTOR SHALL MAKE ARRANGEMENTS FOR PARKING OF | | | CONTRACTOR VEHICLES TO MINIMIZE THE IMPACT ON ALL | | | NEIGHBORING PROPERTIES. | | | | | | 6. PROTECTION OF NEIGHBORING PROPERTY. PROPERTY OWNER | | | AND CONTRACTOR SHALL PROTECT ALL NEIGHBORING PROPERTY, | | | INCLUDING VEHICLES, FROM DAMAGE OR DIRT CAUSED BY THE | | | CONSTRUCTION, AND SHALL NOTIFY THE OCCUPANTS OF | | | NEIGHBORING PROPERTIES ABOUT ALL STAGES OF CONSTRUCTION | | | THAT MAY AFFECT THE USE OF THEIR PROPERTY. | | | | | | 7. BUILDING ADDRESS. EACH SEPARATE BUILDING, AND UNIT | | | WITH AN INDEPENDENT ENTRANCE FROM THE STREET, SHALL | | | HAVE A SEPARATE ADDRESS ASSIGNED BASED ON THE LOCATION | | | OF THE BUILDING ENTRANCE. FOR STREET ADDRESSING, | | | CONTACT CAROLINE PUELL, ADDRESSING COORDINATOR, AT | | | (561) 805 6659, OR BY EMAIL: [email protected] | | | | | | 8. ART IN PUBLIC PLACES. THIS PROJECT WILL BE SUBJECT | | | TO ART IN PUBLIC PLACES (AIPP) ASSESSMENT. FOR ADVICE | | | ON THE PROVISION OF PUBLIC ARTWORK IN LIEU OF THE AIPP | | | ASSESSMENT, CONTACT SYBILLE WELTER, ART IN PUBLIC | | | PLACES COORDINATOR, AT (561) 822-1521, OR BY EMAIL: | | | [email protected] | | | | | | 9. ACCESSIBLE ROUTE FROM SIDEWALK TO BUILDING ENTRANCE. | | | THE ACCISSIBLE ROUTE AND PARKING SPACES SHALL BE | | | LOCATED/CONFIGURED SO THAT THE USER IS NOT COMPELLED TO | | | WALK OR WHEEL BEHIND PARKED VEHICLES OR IN THE TRAVEL | | | LANE. SECTIONS 206.2, 402.2 AND 502.3 OF FLORIDA | | | ACCESSIBILITY CODE | | | | | | ROBERT BROWN | | | BUILDING OFFICIAL | | | TEL: 561 805 6652 | | | EMAIL: [email protected] | | | |
|
|
| Review Stop |
ENG - PPRC |
ENGINEERING - PPRC |
| Rev No |
2 |
Status |
F |
Date |
04-27-2021 |
|
|
Cont ID |
|
| Sent By |
rrossano |
Date |
04-27-2021 |
Time |
|
Rev Time |
0.00 |
| Received By |
rrossano |
Date |
04-27-2021 |
Time |
|
Sent To |
|
|
| Notes |
| 2021-04-27 10:55:49 | COMMENTS PER RICK ROSSANO, PROJ. COORD. WPB ENG. | | | SERVICES, [email protected], 561-494-1098: | | | 1. PROVIDE CCTV VIDEO OF EXISTING SANITARY SEWER | | | (CONDITION OF SITE PLAN APPROVAL). STORMWATER APPEARS | | | TO BE ONSITE ONLY; IF SO, NO CCTV OF CITY STORMWATER | | | INFRASTRUCTURE ALONG PROJECT FRONTAGE IS NEEDED.) | | | | | | COMMENTS FROM MARK HURLEY, FIELD CUSTOMER SERVICE SPV., | | | CITY OF WPB PUB. UTILITIES, 561-822-2262, | | | [email protected] | | | -BACKFLOW ASSEMBLY MAY NOT BE LOCATED IN A UTILITY | | | EASEMENT. ONE WAY TO RESOLVE WOULD BE ADJUSTING | | | BOUNDARIES/DIMENSIONS OF PROPOSED UTILITY EASEMENT. | | | |
|
|
| Review Stop |
ENG - PPRC |
ENGINEERING - PPRC |
| Rev No |
1 |
Status |
F |
Date |
02-04-2021 |
|
|
Cont ID |
|
| Sent By |
RROSSANO |
Date |
02-04-2021 |
Time |
|
Rev Time |
|
| Received By |
rrossano |
Date |
02-04-2021 |
Time |
|
Sent To |
|
|
| Notes |
| 2021-02-04 11:43:23 | COMMENTS PER RICK ROSSANO, PROJ. COORD. WPB ENG. | | | SERVICES, [email protected], 561-494-1098: | | | 1. CONFIRM THAT A COMPLETED LOS ANALYSIS SUMMARY TABLE | | | HAS BEEN SUBMITTED DIRECTLY TO ENGINEERING (SHEET 33 OF | | | CITY OF WPB DEVELOPMENT APPLICATION). | | | 2. CHECK TO SEE IF FDEP FORMS FOR PROPOSED SANITARY | | | SEWER ARE REQUIRED. | | | 3. PROVIDE CALCULATIONS ON PLANS OF EXISTING AND | | | PROPOSED DEMANDS FOR WATER & SEWER (AVERAGE, MAXIMUM | | | AND PEAK) AND FIRE FLOW DEMANDS. CALCULATIONS SHALL BE | | | PER FAC 64E-6 FOR SEWER AND PER FAC 64-E.008 FOR WATER. | | | 4. PROVIDE CCTV VIDEO OF EXISTING SANITARY SEWER AND | | | STORMWATER PIPES ALONG ENTIRE PROJECT FRONTAGE. | | | 5. PLEASE PROVIDE CALCULATIONS OF REVISED PERVIOUS AND | | | IMPERVIOUS CALCULATIONS FOR THE PROPOSED IMPACTED | | | AREAS. | | | 6. COORDINATE WITH MARK HURLEY, FIELD CUSTOMER SERVICE | | | SUPERVISOR WITH CITY OF WPB PUBLIC UTILITIES, REGARDING | | | PLACEMENT OF BACKFLOW DEVICES AND WATER METERS. CONTACT | | | HIM AT 561-494-2262 OR [email protected] | | | 7. FOR FORMAL ENGINEERING SUBMITTAL , PLANS SHALL SHOW | | | PROPOSED LOCATIONS AND DIMENSIONS OF ALL WATER, | | | STORMWATER, AND SANITARY AND SEWER LINES, INCLUDING | | | STUBS TO EACH PROPERTY LINE FOR WATER AND SANITARY | | | SEWERS, THE MAKE AND MODEL OF ALL VALVES, METERS, AND | | | OTHERS DEVICES TO BE INSTALLED ON THE SYSTEM, CATCH | | | BASINS, CULVERTS, DITCHES INCLUDING GRADES, PIPES | | | SIZES, MATERIALS, ELEVATIONS, ASSUMPTIONS, | | | CALCULATIONS, INVERT ELEVATIONS FOR ALL INLETS AND | | | MANHOLES AND PROFILES OF SANITARY SEWER LINES. ALL | | | AVAILABLE ELEVATION SHALL BE SHOWN ON THE PROFILE VIEW. | | | DIRECTION OF FLOW SHALL BE SHOWN ON PLAN VIEW ON PLAN | | | VIEW FOR ALL SANITARY AND STORM SEWERS. ADDITIONALLY, | | | PLAN VIEW SHALL SHOW ALL EXISTING AND PROPOSED | | | UNDERGROUND UTILITY LAYOUT, INCLUDING FIBER OPTIC, | | | ELECTRIC, GAS, AND CABLEVISION & TELECOMMUNICATION | | | FACILITIES LOCATED ON THE RIGHT-OF-WAY. | | | 8. FOR FORMAL ENGINEERING SUBMITTAL , CUT AND CAP | | | UTILITIES NOT IN USE, AND REMOVE ANY ABANDONED UTILITY | | | LINES LARGER THAN 2 INCHES FROM CITY RIGHT OF WAY. | | | 9. FOR FORMAL ENGINEERING SUBMITTAL , PROVIDE DEDICATED | | | UTILITY EASEMENTS TO ALLOW ACCESS FOR CITY PERSONNEL TO | | | PROPOSED UTILITY WATER METERS. | | | 10. FOR FORMAL ENGINEERING SUBMITTAL, PLEASE PROVIDE | | | ENLARGED VIEW ON PLANS OF PROPOSED LOCATION OF WATER | | | METER AND BACKFLOW PREVENTION. | | | 11. FOR FORMAL ENGINEERING SUBMITTAL, PLEASE CALLOUT | | | DOMESTIC BACKFLOW PREVENTER AS RPPA AND FIRE BACKFLOW | | | PREVENTER AS DCDA. SPECIFY LEAD FREE DESIGN ON ALL | | | BACKFLOWS. | | | 12. FOR FORMAL ENGINEERING SUBMITTAL, SFWMD ERP AND | | | NPDES NOI REQUIREMENTS WILL BE ENFORCED. | | | - AN NOI IS REQUIRED FOR PROJECTS THAT: | | | - 1) DISTURB ONE OF MORE ACRES OF LAND OR DISTURB LESS | | | THAN ON ACRE OF LAND BUT ARE PART OF A COMMON PLAN OF | | | DEVELOPMENT OR SALE; | | | - 2) DISCHARGE STORMWATER TO SURFACE WATERS OF THE | | | STATE OR TO SURFACE WATERS OF THE STATE THROUGH A | | | MUNICIPAL SEPARATE STORM SEWER SYSTEM (MS4). | | | - THE SFWMD ERP CAN BE OBTAINED THROUGH A 10-2 SELF | | | CERTIFICATION THROUGH FDEP OR AN ERP APPLICATION | | | THROUGH SFWMD. EITHER WAY, THE DEVELOPER/ENGINEER SHALL | | | SUBMIT A COPY OF THE ERP PERMIT OR FDEP ACKNOWLEDGEMENT | | | OF THE 10-2 CERTIFICATION. | | | 13. FOR FORMAL ENGINEERING SUBMITTAL, PROVIDE PROFILES | | | OF WATER AND SEWER AND SHOW ANY CROSSINGS/CONFLICTS. | | | 14. FOR FORMAL ENGINEERING SUBMITTAL, WHEN SUBMITTING | | | APPROVED MATERIALS LIST, PLEASE PROVIDE MATERIAL/CUT | | | SHEETS FOR ALL PROPOSED BACKFLOW DEVICES SHOWING | | | SPECIFIC MODEL NUMBER AND SPECIFYING USC APPROVED | | | LEAD-FREE DESIGN. | | | 15. FOR FORMAL ENGINEERING SUBMITTAL CLEARLY SHOW ROAD | | | RIGHT OF WAY. | | | 16. FOR FORMAL ENGINEERING SUBMITTAL PROVIDE SANITARY | | | ELEVATIONS AT MANHOLE TIE-IN. | | | 17. FOR FORMAL ENGINEERING SUBMITTAL, IF SANITARY LINES | | | ARE PROPOSED IN ROW PLEASE SHOW ADJACENT SANITARY | | | LATERAL LOCATIONS AND SHOW ADDRESSES OF ADJACENT | | | PARCELS. | | | 18. FOR FORMAL ENGINEERING SUBMITTAL, IF WATER LINES | | | ARE BEING REPLACED IN ROW, SHOW ADJACENT PARCEL | | | ADDRESSES. | | | 19. FOR FORMAL ENGINEERING SUBMITTAL, WHEN TRENCHING IN | | | IN CITY MAINTAINED ROADWAY AREAS ADD NOTE TO PROVIDE 50 | | | FT. PAVEMENT RESTORATION TRANSITION ON EACH SIDE OF | | | PROPOSED TRENCH PER CITY OF WPB STANDARD DETAIL GC-4. | | | 20. PLEASE RESPOND TO ALL COMMENTS IN WRITING AND | | | INCLUDE PROJECT NAME, ADDRESS AND PERMIT NUMBER | | | (Z-XXXXXXXX). | | | | | | COMMENTS FROM MARK HURLEY, FIELD CUSTOMER SERVICE SPV., | | | CITY OF WPB PUB. UTILITIES, 561-822-2262, | | | [email protected] | | | | | | -SITE PLAN SAYS SOUTHERN WALL IS 2INCHES OFF PROPERTY | | | LINE. IS THAT CORRECT, AND WOULD BUILDING FOOTER BE | | | SAME DISTANCE FROM PROPERTY LINE? | | | | | | -PLEASE VERIFY BUILDING WILL NOT HAVE FIRE SPRINKLERS. | | | | | | -WILL A SEPARATE METERED IRRIGATION WATER SERVICE BE | | | NEEDED? | | | | | | -PLANS SAID THERE MAY BE A TENANT, BUT ONLY SHOWING ONE | | | WATER METER ON WATER PLANS. WILL THE WATER ACCOUNT | | | HOLDER LET THE TENANT USE THEIR WATER? | | | | | | -WATER DEMAND CALCULATIONS ARE MISSING FROM WATER PLAN. | | | PLEASE ADD. | | | | | | -PLEASE VERIFY PAVEMENT RESTORATION AREA BOUNDARIES | | | FROM UTILITY WORK ARE CORRECT DIMENSIONS. | | | | | | -UTILITY EASEMENT NEEDED FOR WATER METER BOX ON PRIVATE | | | PROPERTY. | | | | | | -WATER SERVICE STANDARD DETAILS ARE OLD REVISION. | | | PLEASE REPLACE WITH NEWEST REVISION. | | | | | | -USUALLY 5/8? METER HAS 1? TAP. PLEASE UPDATE OR | | | INDICATE WHY 2? TAP IS NEEDED. | | | | | | -FOR FORMAL ENGINEERING SUBMITTAL, PLEASE ADD WATER | | | SERVICE PIPE SIZE AND MATERIAL TYPE. | | | | | | -WPB GIS IS SHOWING A 4INCH WATER MAIN BRANCH IN CLOSE | | | PROXIMITY TO THE WATER SERVICE TAP. PLEASE SHOW THAT ON | | | WATER PLAN FOR FORMAL ENGINEERING SUBMITTAL. | | | | | | -THERE SHOULD BE A FIRE HYDRANT ACROSS FROM THE | | | NORTHEAST CORNER OF THE PROPERTY. PLEASE SHOW ON THE | | | WATER PLAN. | | | | | | |
|
|
| Review Stop |
FIRE |
FIRE DEPARTMENT |
| Rev No |
1 |
Status |
P |
Date |
02-05-2021 |
|
|
Cont ID |
|
| Sent By |
pleduc |
Date |
02-05-2021 |
Time |
12:41 |
Rev Time |
0.00 |
| Received By |
pleduc |
Date |
02-05-2021 |
Time |
12:36 |
Sent To |
|
|
| Notes |
| 2021-02-05 12:36:39 | THE FOLLOWING COMMENTS WERE SUBMITTED BY PETER LEDUC, | | | FIRE MARSHAL, BUREAU OF FIRE PREVENTION, WEST PALM | | | BEACH FIRE RESCUE. | | | | | | THIS REVIEW CAN ONLY BE CONSIDERED PRELIMINARY AS THE | | | DRAWINGS THAT WERE REVIEWED WERE NOT COMPLETE. | | | ADDITIONAL COMMENTS CAN BE EXPECTED WHEN FULL DRAWINGS | | | ARE SUBMITTED FOR PERMIT. | | | | | | THE FIRE PREVENTION BUREAU HAS NO OBJECTIONS TO THE | | | PROPOSED PROJECT. THE FOLLOWING COMMENTS ARE INTENDED | | | TO PROVIDE GUIDANCE FOR BUILDING PLAN SUBMITTAL. | | | | | | 1. CONSTRUCTION, DEMOLITION, AND RENOVATION TO COMPLY | | | WITH NFPA 241. EXTRA ATTENTION SHALL BE GIVEN TO THE | | | PERMITTING AND LOCATION OF CONSTRUCTION TRAILERS. A | | | PERMIT IS REQUIRED FOR ANY CONSTRUCTION TRAILER RELATED | | | TO THIS PROJECT. SEPARATION DISTANCES FROM MAIN | | | STRUCTURES AS WELL AS OTHER TRAILERS SHALL BE CLOSELY | | | MONITORED FOR THE REQUIREMENTS OF FIRE SPRINKLER | | | PROTECTION. | | | | | | 2. SITE ACCESS AND EXIT POINTS ARE TO BE CLEARLY | | | IDENTIFIED AND MAINTAINED FOR EMERGENCY VEHICLES DURING | | | ALL CONSTRUCTION ACTIVITIES. | | | | | | 3. THE BUILDING ADDRESS SHALL BE CLEARLY VISIBLE FROM | | | ALL ACCESS ROADWAYS, INCLUDING DURING CONSTRUCTION. | | | ADDRESS NUMBERS SHALL CONTRAST WITH THEIR BACKGROUND | | | AND SHALL NOT BE LESS THAN SIX (6) INCHES IN HEIGHT | | | WITH A ONE (1) INCH STROKE FOR ALL BUILDINGS. | | | | | | 4. DURING CONSTRUCTION, TRASH AND DEBRIS IS TO BE | | | REMOVED FROM THE SITE DAILY OR MORE OFTEN TO REDUCE THE | | | ACCUMULATION OF POTENTIAL LIFE AND FIRE SAFETY HAZARDS. | | | | | | 5. THE CONSTRUCTION OF THE BUILDING SHALL COMPLY WITH | | | THE 7TH EDITION OF THE FLORIDA FIRE PREVENTION CODE, | | | INCLUDING NFPA 1 & 101, AND ALL ASSOCIATED FIRE CODES. | | | | | | 6. FOR PLAN REVIEW SUBMITTAL, PLEASE INCLUDE THE | | | OCCUPANCY TYPE, PER THE FLORIDA FIRE PREVENTION CODE, | | | AND WHETHER IT IS MIXED OR SEPARATED OCCUPANCY. | | | | | | 7. FOR PLAN REVIEW SUBMITTAL, PLEASE ENSURE THAT A FIRE | | | LOAD CALCULATION IS INCLUDED AND THAT ADEQUATE WATER | | | SUPPLY IS EXISTING OR WILL BE PROVIDED. | | | | | | 8. ALL EXISTING AND NEW FIRE HYDRANTS PLANNED FOR THIS | | | DEVELOPMENT SHALL BE CLEARLY INDICATED AND IDENTIFIED | | | ON THE PLAN AND IF APPLICABLE CLOSELY COORDINATED WITH | | | THE BUREAU OF FIRE PREVENTION. | | | | | | 9. PROVIDE FOR A FIRE SPRINKLER AND/OR FIRE ALARM PER | | | THE APPLICABLE OCCUPANCY CODE. FOR ANY LIFE SAFETY | | | ENGINEERED SYSTEM, I.E FIRE SPRINKLER AND FIRE ALARM, | | | ENSURE THEY COMPLY WITH THE REQUIREMENTS OF FS 61G AND | | | SUBMITTED WITH THE MASTER PERMIT. | | | | | | 9A) THE LOCATION OF ANY APPLICABLE DDCV AND FIRE LINE | | | LOCATIONS SHALL MEET THE REQUIREMENTS OF NFPA 24 AND | | | SHALL BE COORDINATED WITH THE OFFICE OF FIRE MARSHAL, | | | THE CITY'S ENGINEERS OFFICE, THE LANDSCAPE PLANNER, AND | | | THE CITY'S PLANNING AND ZONING OFFICE. | | | | | | 10. COMPLETE LIFE SAFETY PLANS FOR EACH OCCUPANCY SHALL | | | BE PROVIDED THAT ILLUSTRATE OCCUPANT LOADS, TRAVEL | | | DISTANCES, COMMON PATHS OF TRAVEL, DEAD-END CORRIDORS, | | | EXIT SIGNS, EMERGENCY LIGHTING, EXITS LEADING TO A | | | PUBLIC WAY, FIRE EXTINGUISHER LOCATIONS, AND ALL FIRE | | | SAFETY FEATURES AND EQUIPMENT. | | | | | | 11. IT IS HIGHLY RECOMMENDED (REQUIRED WITH FIRE | | | SPRINKLER SYSTEM) THAT A KNOX BOX WITH KEYS FOR ENTRY | | | DOOR LOCKS BE PROVIDED FOR 24 HOUR EMERGENCY ACCESS. | | | | | | 12. THE BUREAU'S APPROVAL OF THIS SUBMITTED PROJECT | | | DOES NOT CONSTITUTE ITS FINAL REVIEW OR APPROVAL. | | | | | | 13. THE BUREAU SHALL REVIEW ALL SUBMITTED BUILDING | | | PLANS AT THE APPROPRIATE TIME AND IN ACCORDANCE WITH | | | THE REQUIREMENTS OF ALL APPLICABLE CODES AND STANDARDS. | | | | | | PETER LEDUC | | | FIRE MARSHAL | | | 561-804-4709 | | | [email protected] | | | |
|
|
| Review Stop |
L |
LANDSCAPING |
| Rev No |
2 |
Status |
P |
Date |
05-03-2021 |
|
|
Cont ID |
|
| Sent By |
rcaranci |
Date |
05-03-2021 |
Time |
16:39 |
Rev Time |
0.00 |
| Received By |
rcaranci |
Date |
05-03-2021 |
Time |
16:39 |
Sent To |
|
|
| Notes |
| 2021-05-03 16:40:25 | FROM: RAY CARANCI, SENIOR LANDSCAPE PLANNER | | | 561-822-1462 | | | PROJECT: 6907 NORTON AVE Z21010025 | | | MAY 3, 2021 | | | I HAVE REVIEWED THE ABOVE REFERENCED PETITION, AND | | | PROVIDE THE FOLLOWING COMMENTS: | | | | | | 1. SATISFIED. PROVIDE THE REQUIRED TERMINAL LANDSCAPE | | | ISLAND WITH 8 FEET LANDSCAPE WIDTH AT THE WEST END OF | | | THE NORTH ROW OF PARKING. | | | ALLOWED PER 94-443(C)(3) FOR LESS THAN 12 SPACES. | | | | | | 2. SATISFIED. PROVIDE THE REQUIRED 5 FOOT LANDSCAPE | | | BUFFER FOR THE NORTH, WEST AND PORTIONS OF THE SOUTH | | | BUFFER THAT ARE NOT COVERED BY THE PROPOSED BUILDING AT | | | ZERO SETBACK. THE ZERO SETBACK IS ONLY POSSIBLE WHERE | | | THE ADJACENT BUILDING TO THE SOUTH IS AT ZERO SETBACK. | | | SHOW THE LENGTH OF ALL FOUR BUFFER SECTIONS AND SHOW | | | THE REQUIRED AND PROVIDED TREES FOR EACH 30 FEET OR | | | PORTION THEREOF. | | | | | | 3. SATISFIED. SECTION 94-443(C)(3) REQUIRES THAT A | | | MINIMUM OF 75 PERCENT OF ALL TREES THAT ARE REQUIRED TO | | | BE PLANTED WITHIN THE INTERIOR OF AN OFF STREET PARKING | | | AREA SHALL BE CATEGORY 1 SHADE TREES. SHOW THE | | | PERCENTAGE OF CATEGORY 1 TREES PROVIDED FOR THE | | | REQUIRED LANDSCAPE AREAS AS REQUIRED BY SECTION | | | 94-443(C)(3) FOR TERMINAL AND INTERIOR ISLANDS. | | | SHADE TREES ARE PROVIDED IN THE BUFFER. | | | | | | 4. SATISFIED. THE PARKING SPACES APPEAR TO BE 18 FEET | | | IN LENGTH WITH A WHEEL STOP AT 16 FEET. STAFF SUGGESTS | | | REDUCING THE PAVED AREAS FOR PARKING SPACES AND PLACING | | | THE CURBS AT 16 FEET TO ALLOW FOR ADDITIONAL PERVIOUS | | | LANDSCAPE AREA AT THE OVERHANG. | | | | | | 5. SATISFIED. PROVIDE THE REQUIRED 50 POINTS FORM THE | | | FLORIDA FRIENDLY DESIGN OPTIONS LIST. | | | | | | 6. SATISFIED. PROVIDE A DETAIL AND LOCATIONS OF ROOT | | | BARRIERS TO SEPARATE LANDSCAPING FROM UTILITY LINES. | | | |
|
|
| Review Stop |
L |
LANDSCAPING |
| Rev No |
1 |
Status |
F |
Date |
02-10-2021 |
|
|
Cont ID |
|
| Sent By |
rcaranci |
Date |
02-10-2021 |
Time |
17:14 |
Rev Time |
0.00 |
| Received By |
rcaranci |
Date |
02-10-2021 |
Time |
17:14 |
Sent To |
|
|
| Notes |
| 2021-02-10 17:14:34 | FROM: RAY CARANCI, SENIOR LANDSCAPE PLANNER | | | 561-822-1462 | | | PROJECT: 6907 NORTON AVE Z21010025 | | | FEBRUARY 10, 2021 | | | I HAVE REVIEWED THE ABOVE REFERENCED PETITION, AND | | | PROVIDE THE FOLLOWING COMMENTS: | | | | | | 1. PROVIDE THE REQUIRED TERMINAL LANDSCAPE ISLAND WITH | | | 8 FEET LANDSCAPE WIDTH AT THE WEST END OF THE NORTH ROW | | | OF PARKING. | | | | | | 2. PROVIDE THE REQUIRED 5 FOOT LANDSCAPE BUFFER FOR THE | | | NORTH, WEST AND PORTIONS OF THE SOUTH BUFFER THAT ARE | | | NOT COVERED BY THE PROPOSED BUILDING AT ZERO SETBACK. | | | THE ZERO SETBACK IS ONLY POSSIBLE WHERE THE ADJACENT | | | BUILDING TO THE SOUTH IS AT ZERO SETBACK. SHOW THE | | | LENGTH OF ALL FOUR BUFFER SECTIONS AND SHOW THE | | | REQUIRED AND PROVIDED TREES FOR EACH 30 FEET OR PORTION | | | THEREOF. | | | | | | 3. SECTION 94-443(C)(3) REQUIRES THAT A MINIMUM OF 75 | | | PERCENT OF ALL TREES THAT ARE REQUIRED TO BE PLANTED | | | WITHIN THE INTERIOR OF AN OFF STREET PARKING AREA SHALL | | | BE CATEGORY 1 SHADE TREES. SHOW THE PERCENTAGE OF | | | CATEGORY 1 TREES PROVIDED FOR THE REQUIRED LANDSCAPE | | | AREAS AS REQUIRED BY SECTION 94-443(C)(3) FOR TERMINAL | | | AND INTERIOR ISLANDS. | | | 4. THE PARKING SPACES APPEAR TO BE 18 FEET IN LENGTH | | | WITH A WHEEL STOP AT 16 FEET. STAFF SUGGESTS REDUCING | | | THE PAVED AREAS FOR PARKING SPACES AND PLACING THE | | | CURBS AT 16 FEET TO ALLOW FOR ADDITIONAL PERVIOUS | | | LANDSCAPE AREA AT THE OVERHANG. | | | | | | 5. PROVIDE THE REQUIRED 50 POINTS FORM THE FLORIDA | | | FRIENDLY DESIGN OPTIONS LIST. | | | | | | 6. PROVIDE A DETAIL AND LOCATIONS OF ROOT BARRIERS TO | | | SEPARATE LANDSCAPING FROM UTILITY LINES. | | | |
|
|
| Review Stop |
PARK |
PARKING |
| Rev No |
1 |
Status |
|
Date |
|
|
|
Cont ID |
|
| Sent By |
|
Date |
|
Time |
|
Rev Time |
|
| Received By |
|
Date |
|
Time |
|
Sent To |
|
|
| Notes |
|
|
| Review Stop |
POLICE |
POLICE |
| Rev No |
1 |
Status |
|
Date |
|
|
|
Cont ID |
|
| Sent By |
|
Date |
|
Time |
|
Rev Time |
|
| Received By |
|
Date |
|
Time |
|
Sent To |
|
|
| Notes |
|
|
| Review Stop |
PW |
PUBLIC WORKS |
| Rev No |
2 |
Status |
P |
Date |
06-08-2021 |
|
|
Cont ID |
|
| Sent By |
|
Date |
06-08-2021 |
Time |
|
Rev Time |
0.00 |
| Received By |
|
Date |
06-08-2021 |
Time |
|
Sent To |
|
|
| Notes |
| 2021-06-08 15:32:13 | CONDITION OF APPROVAL: | | | THE DUMPSTER SHALL BE ON WHEEL AND BE ROLLED OUT ON THE | | | SERVICE DAYS FOR SERVICE ON NORTON AVE. | | | | | | MATT HEJAZI | | | DEPT. OF PUBLIC WORKS | | | [email protected] |
|
|
| Review Stop |
PW |
PUBLIC WORKS |
| Rev No |
1 |
Status |
F |
Date |
02-08-2021 |
|
|
Cont ID |
|
| Sent By |
|
Date |
02-08-2021 |
Time |
|
Rev Time |
|
| Received By |
|
Date |
02-08-2021 |
Time |
|
Sent To |
|
|
| Notes |
| 2021-02-08 12:46:18 | PLEASE PROVIDE THE DUMPSTER ENCLOSURE DETAIL. FOR A | | | FREESTANDING SITE DUMPSTER ENCLOSURE, THE ENCLOSURE | | | SHALL COMPLY WITH THE LATEST REVISION OF CITY OF WEST | | | PALM BEACH GENERAL CONSTRUCTION-GARBAGE ENCLOSURE | | | STANDARD, GC-7. | | | | | | MATT HEJAZI | | | DEPT. OF PUBLIC WORKS | | | [email protected] | | | 561-822-2045 |
|
|
| Review Stop |
STORM |
STORMWATER |
| Rev No |
2 |
Status |
P |
Date |
06-08-2021 |
|
|
Cont ID |
|
| Sent By |
tward |
Date |
06-08-2021 |
Time |
23:13 |
Rev Time |
0.00 |
| Received By |
tward |
Date |
06-08-2021 |
Time |
23:35 |
Sent To |
|
|
| Notes |
| 2021-06-08 23:35:35 | THE FOLLOWING COMMENTS ARE FROM THE REVIEW OF THE APRIL | | | 27, 2021 SUBMITTAL, THEY CAN BE ADDRESSED DURING | | | ENGINEERING PERMIT SUBMITTAL. | | | | | | 1. REVISE EXFILTRATION TRENCH DESIGN AND STORMWATER | | | MANAGEMENT CALCULATIONS TO ACCOUNT FOR THE CHANGE IN | | | THE INLET GRATE ELEVATION TO 14.08 FT NAVD. | | | | | | 2. PROVIDE VERTICAL DATUM REFERENCE IN THE STORMWATER | | | MANAGEMENT CALCULATIONS. | | | | | | 3. PROVIDE ON THE CIVIL ENGINEERING PLANS THE GRATE/RIM | | | AND INVERT ELEVATIONS OF THE EXISTING SANITARY SEWER | | | AND STORMWATER STRUCTURES. | | | | | | 4.PROVIDE SWALES ALONG THE NORTH AND SOUTH PROPERTY | | | LINES THAT DRAIN TOWARD NORTON AVE TO PREVENT RUNOFF | | | FROM FLOWNG ONTO ADJACENT PROPERTIES. | | | | | | 5. CROSS SECTIONS WILL BE NEEDED WITH THE ENGINEERING | | | PERMIT SUBMITTAL THROUGH THE MIDDLE OF THE DRIVEWAY | | | (EAST-WEST) AND THROUGH THE PARKING LOT FROM NORTH PL | | | TO SOUTH PL. | | | | | | TRACY WARD, P.E. | | | SENIOR STORMWATER ENGINEER | | | ENGINEERING SERVICES DEPARTMENT | | | [email protected] | | | 561-494-1120 (O) | | | 561-351-0510 (M) |
|
|
| Review Stop |
STORM |
STORMWATER |
| Rev No |
1 |
Status |
F |
Date |
02-11-2021 |
|
|
Cont ID |
|
| Sent By |
tward |
Date |
02-11-2021 |
Time |
18:55 |
Rev Time |
0.00 |
| Received By |
tward |
Date |
02-11-2021 |
Time |
18:57 |
Sent To |
|
|
| Notes |
| 2021-02-11 18:57:43 | THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL | | | DETAILS, DESIGN CALCULATIONS AND THE POLLUTION | | | PREVENTION PLAN WILL BE REVIEWED AS PART OF THE | | | ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT | | | APPLICATION PROCESSES. | | | | | | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE | | | PLAN APPROVAL: | | | | | | 1. CONSIDER REDUCING THE DEPTH OF THE PARKING BY 2 FEET | | | AND PROVIDE LANDSCAPE OVERHANG. | | | | | | 2. MOVE S-102 FURTHER FROM THE BACK OF SIDEWALK WITH | | | THE GRATE ELEVATION LOWER THAN THE BACK OF SIDEWALK | | | ELEVATION TO ENSURE THE STORMWATER RUNOFF IS CAPTURED | | | IN THE SYSTEM. | | | | | | 3. DRAINAGE SYSTEM TO BE DESIGNED TO MEET SFWMD ERP | | | CRITERIA. | | | | | | 4. REPLACE SIDEWALK ADJACENT TO THE DRIVEWAY APRON WITH | | | 6? THICK SIDEWALK PER CITY DETAILS. | | | | | | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO | | | ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING | | | BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL. | | | | | | 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION MAY | | | BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT. | | | | | | 2. EROSION CONTROL PLAN AND DETAILS TO BE SUBMITTED | | | WITH THE ENGINEERING PERMIT APPLICATION. | | | | | | 4. DRAINAGE CALCULATIONS WILL BE REVIEWED WITH THE | | | ENGINEERING PERMIT APPLICATION. | | | | | | TRACY WARD, PE | | | SENIOR STORMWATER ENGINEER | | | ENGINEERING SERVICES DEPARTMENT | | | 561-494-1120 (O) | | | 561-351-0510 (M) | | | [email protected] | | | |
|
|
| Review Stop |
SURVEY |
SURVEYING |
| Rev No |
2 |
Status |
P |
Date |
05-06-2021 |
|
|
Cont ID |
|
| Sent By |
vnoel |
Date |
05-06-2021 |
Time |
07:12 |
Rev Time |
0.00 |
| Received By |
vnoel |
Date |
|
Time |
|
Sent To |
|
|
| Notes |
| 2021-05-06 07:13:20 | CONDITION OF APPROVAL: | | | | | | 1. UNITY OF TITLE PRIOR TO BUILDING PERMIT. |
|
|
| Review Stop |
SURVEY |
SURVEYING |
| Rev No |
1 |
Status |
F |
Date |
02-08-2021 |
|
|
Cont ID |
|
| Sent By |
vnoel |
Date |
02-08-2021 |
Time |
09:40 |
Rev Time |
|
| Received By |
vnoel |
Date |
|
Time |
|
Sent To |
|
|
| Notes |
| 2021-02-08 09:52:05 | 1. SHOW CONVERSION TO NGVD. | | | 2. UNITY OF TITLE WILL BE REQUIRED. APPLICATION IS MADE | | | THROUGH ENGINEERING. |
|
|
| Review Stop |
TRAFFIC |
TRAFFIC ENGINEERING |
| Rev No |
3 |
Status |
P |
Date |
06-08-2021 |
|
|
Cont ID |
|
| Sent By |
|
Date |
06-08-2021 |
Time |
|
Rev Time |
0.00 |
| Received By |
|
Date |
|
Time |
|
Sent To |
|
|
| Notes |
| 2021-06-08 15:16:36 | NO FURTHER COMMENTS. | | | | | | VALERIO ORICCHIO | | | CITY TRANSPORTATION ENGINEER | | | 561-494-1092 | | | [email protected] | | | |
|
|
| Review Stop |
TRAFFIC |
TRAFFIC ENGINEERING |
| Rev No |
2 |
Status |
F |
Date |
05-03-2021 |
|
|
Cont ID |
|
| Sent By |
|
Date |
05-03-2021 |
Time |
|
Rev Time |
0.00 |
| Received By |
|
Date |
|
Time |
|
Sent To |
|
|
| Notes |
| 2021-05-03 18:28:04 | TRAFFIC COMMENTS | | | 1) PROVIDE COUNTY TPS LETTER | | | | | | VALERIO ORICCHIO | | | CITY TRANSPORTATION ENGINEER | | | 561-494-1092 | | | [email protected] | | | |
|
|
| Review Stop |
TRAFFIC |
TRAFFIC ENGINEERING |
| Rev No |
1 |
Status |
F |
Date |
02-10-2021 |
|
|
Cont ID |
|
| Sent By |
|
Date |
02-10-2021 |
Time |
|
Rev Time |
|
| Received By |
|
Date |
|
Time |
|
Sent To |
|
|
| Notes |
| 2021-02-10 21:10:21 | TRAFFIC COMMENTS | | | 1) PROVIDE COUNTY TPS LETTER | | | | | | VALERIO ORICCHIO | | | CITY TRANSPORTATION ENGINEER | | | 561-494-1092 | | | [email protected] | | | |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
2 |
Status |
P |
Date |
05-21-2021 |
|
|
Cont ID |
|
| Sent By |
rthermid |
Date |
05-14-2021 |
Time |
|
Rev Time |
0.00 |
| Received By |
rthermid |
Date |
|
Time |
|
Sent To |
|
|
| Notes |
| 2021-05-21 08:26:07 | PLANS AND PLATS REVIEW COMMITTEE (PPRC) ZONING REVIEW | | | ________________________________________ | | | | | | DATE OF REVIEW: 5/14/2021 | | | PROJECT NO.: Z21010025 | | | CASE NO.: ISPR 21-02 | | | ________________________________________ | | | | | | 1. SATISFIED: PURSUANT TO SECTION 94-485 (Q) OF THE | | | CITY'S ZONING AND LAND DEVELOPMENT REGULATIONS (ZLDRS), | | | ONE BICYCLE PARKING SPACE SHALL BE PROVIDED FOR EVERY | | | 20 AUTOMOBILE PARKING SPACES OR FRACTION THEREOF, | | | REQUIRED FOR THE USE. | | | 2. SATISFIED: PURSUANT TO SECTION 94-443 OF THE CITY?S | | | ZONING AND LAND DEVELOPMENT REGULATIONS (ZLDRS), A | | | LANDSCAPE BUFFER OF AT LEAST 5 FEET IN WIDTH SHALL BE | | | PROVIDED WHEN ADJACENT TO NON RESIDENTIAL ZONING | | | DISTRICTS. PLEASE PROVIDE A 5 FOOT SIDE SETBACK ON THE | | | SOUTHERN PORTION OF THE PROPERTY, ADJACENT TO THE | | | PARKING LOT. | | | ________________________________________ | | | | | | QUESTIONS/COMMENTS, PLEASE CONTACT THE FOLLOWING: | | | | | | RAFAELA THERMIDOR, ASSOCIATE PLANNER | | | CITY OF WEST PALM BEACH | | | DEVELOPMENT SERVICES DEPARTMENT ? PLANNING DIVISION | | | 401 CLEMATIS STREET - P.O. BOX 3147 | | | WEST PALM BEACH, FLORIDA 33402 | | | | | | TTY: 800.955.8771 | | | E: [email protected] | | | W: WPB.ORG |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
1 |
Status |
F |
Date |
02-11-2021 |
|
|
Cont ID |
|
| Sent By |
rthermid |
Date |
02-11-2021 |
Time |
|
Rev Time |
|
| Received By |
rthermid |
Date |
02-11-2021 |
Time |
|
Sent To |
|
|
| Notes |
| 2021-02-11 09:55:25 | PLANS AND PLATS REVIEW COMMITTEE (PPRC) ZONING REVIEW | | | ________________________________________ | | | | | | DATE OF REVIEW: 2/11/2021 | | | PROJECT NO.: Z21010025 | | | CASE NO.: ISPR 21-02 | | | ________________________________________ | | | | | | PLEASE PROVIDE A WRITTEN RESPONSE TO THE FOLLOWING | | | REVIEW COMMENTS: | | | | | | 1. PURSUANT TO SECTION 94-485 (Q) OF THE CITY'S ZONING | | | AND LAND DEVELOPMENT REGULATIONS (ZLDRS), ONE BICYCLE | | | PARKING SPACE SHALL BE PROVIDED FOR EVERY 20 AUTOMOBILE | | | PARKING SPACES OR FRACTION THEREOF, REQUIRED FOR THE | | | USE. | | | 2. PURSUANT TO SECTION 94-443 OF THE CITY?S ZONING AND | | | LAND DEVELOPMENT REGULATIONS (ZLDRS), A LANDSCAPE | | | BUFFER OF AT LEAST 5 FEET IN WIDTH SHALL BE PROVIDED | | | WHEN ADJACENT TO NON RESIDENTIAL ZONING DISTRICTS. | | | PLEASE PROVIDE A 5 FOOT SIDE SETBACK ON THE SOUTHERN | | | PORTION OF THE PROPERTY, ADJACENT TO THE PARKING LOT. | | | ________________________________________ | | | | | | PLEASE NOTE THE FOLLOWING WHEN RESUBMITTING: | | | | | | A) WRITTEN RESPONSES TO COMMENTS MADE BY ALL | | | DEPARTMENTS SHALL BE PROVIDED UPON RESUBMISSION. | | | | | | B) 4 SETS OF REVISED PLANS AND/OR DOCUMENTS SHALL BE | | | PROVIDED, ALONG WITH ONE (1) REDUCED COPY (11IN X | | | 17IN), AND AN ELECTRONIC COPY OF ALL PLANS. | | | | | | C) PLEASE NOTE THAT RE-SUBMITTALS MAY BE SUBJECT TO | | | ADDITIONAL COMMENTS. | | | | | | D) IF NO RESPONSE IS RECEIVED WITHIN 60 DAYS OF THE | | | ISSUANCE OF THESE COMMENTS, THE APPLICATION WILL BE | | | CONSIDERED WITHDRAWN AND ANY FURTHER ACTION WILL | | | REQUIRE SUBMISSION OF A NEW DEVELOPMENT APPLICATION. | | | | | | E) PLEASE NOTE THAT YOU WILL BE PERMITTED ONE (1) | | | RESUBMITTAL AT NO ADDITIONAL COST. IF PREVIOUSLY-ISSUED | | | COMMENTS CONTINUE TO NOT BE SUFFICIENTLY ADDRESSED, THE | | | APPLICANT WILL BE ACCESSED A RESUBMITTAL FEE. SUCH FEE | | | WILL BE 20% OF THE ORIGINAL APPLICATION FEE. | | | | | | F) IN ORDER TO BE CONSIDERED FOR THE APRIL 9, 2021, | | | PLANNING BOARD AGENDA, ALL COMMENTS SHALL BE | | | SATISFACTORILY ADDRESSED. PLEASE SUBMIT ALL REVISED | | | DOCUMENTS/PLANS NO LATER THAN TUESDAY, MARCH 9, 2021. | | | | | | G) TO BE PLACED ON THE JUNE 15, 2021, PLANNING BOARD | | | AGENDA, SIGNS SHALL BE POSTED ON THE PROPERTY NO LATER | | | THAN MARCH 9, 2021. SIGNAGE SHALL CONFORM, AND BE | | | INSTALLED ACCORDING TO THE REQUIREMENTS OF THE CITY?S | | | ZONING AND LAND DEVELOPMENT REGULATIONS; SUCH | | | REQUIREMENTS ARE ALSO PROVIDED IN THE DEVELOPMENT | | | APPLICATION. A SIGNED AND NOTARIZED AFFIDAVIT SHALL BE | | | PROVIDED BY THE DEADLINE REFERENCED ABOVE. | | | | | | H) IF AFTER THE CASE HAS BEEN ADVERTISED THE APPLICANT | | | DESIRES TO REQUEST A CONTINUANCE, A FEE OF $50 PLUS THE | | | COST OF ADVERTISING WILL BE CHARGED. | | | ________________________________________ | | | | | | QUESTIONS/COMMENTS, PLEASE CONTACT THE FOLLOWING: | | | | | | RAFAELA THERMIDOR, ASSOCIATE PLANNER | | | CITY OF WEST PALM BEACH | | | DEVELOPMENT SERVICES DEPARTMENT ? PLANNING DIVISION | | | 401 CLEMATIS STREET - P.O. BOX 3147 | | | WEST PALM BEACH, FLORIDA 33402 | | | | | | TTY: 800.955.8771 | | | E: [email protected] | | | W: WPB.ORG |
|
|
| |
Print |
|