Plan Review Details - Project Z20120014
Plan Review Stops For Project Z20120014
Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 12-31-2020 Cont ID  
Sent By rbrown Date 12-21-2020 Time 07:51 Rev Time 0.00
Received By rbrown Date 12-31-2020 Time 19:45 Sent To  
Notes
2020-12-31 19:51:57DEVELOPMENT SERVICES DEPARTMENT, BUILDING DIVISION,
 COMMENTS:
  
 BASED ON A CURSORY REVIEW AS IT RELATES TO THE SITE AND
 NOT A REVIEW FOR FULL COMPLIANCE WITH FLORIDA BUILDING
 CODE WE HAVE NO COMMENTS ON THE MINOR PLANNED
 DEVELOPMENT AMENDMENT TO ADD THE GENERATOR ENCLOSURE,
 ACCESSIBILITY RAMP AND UTILITY BOXES. WHEN DETAILED
 BUILDING PERMIT APPLICATION PLANS ARE SUBMITTED THERE
 MAY BE TYPICAL BUILDING CODE COMPLIANCE COMMENTS..
  

Review Stop ENG - PPRC ENGINEERING - PPRC
Rev No 2 Status P Date 05-07-2021 Cont ID  
Sent By rrossano Date 05-07-2021 Time   Rev Time 0.00
Received By rrossano Date 05-07-2021 Time   Sent To  
Notes
***NONE***

Review Stop ENG - PPRC ENGINEERING - PPRC
Rev No 1 Status F Date 12-17-2020 Cont ID  
Sent By rrossano Date 12-17-2020 Time   Rev Time  
Received By rrossano Date 12-17-2020 Time   Sent To  
Notes
2020-12-17 20:28:10-ELECTRICAL STRUCTURE APPEARS TO HAVE BEEN BUILT OVER
 WATER SERVICE LINE IN UTILITY EASEMENT NEAR THE WATER
 METERS CREATING A MAINTENANCE CONFLICT WHERE PIPING
 COULD NOT BE REPAIRED IN THE EVENT OF A LEAK. CONFLICT
 NEEDS TO BE RESOLVED BEFORE PROJECT APPROVAL, OR REMEDY
 SATISFACTORY TO WPB PUBLIC UTILITIES INCLUDED IN
 PROJECT SCOPE/DESCRIPTION.
  
 -BUSHES APPEAR TO BE VERY CLOSE TO, OR ON TOP OF,
 FIRELINE BACKFLOW ASSEMBLY. PLEASE ENSURE 16IN
 CLEARANCE BETWEEN BACKFLOW ASSEMBLIES AND BUSHES FOR
 MAINTENANCE AND TESTING.
  
 MARK HURLEY
 FIELD CUSTOMER SERVICE SUPERVISOR
 CITY OF WEST PALM BEACH PUBLIC UTILITIES
 561-822-2262
  
 PLEASE PROVIDE VERTICAL DATUM CONVERSION NOTE ON ALL
 RELEVANT CIVIL SHEETS.
 PLEASE PROVIDE SWPPP SHEET WITH BMP DETAILS - DUST
 CONTROL, INLET PROTECTION ETC.
 PLEASE ADD RELEVANT CITY OF WPB STANDARD DETAILS FOR
 PAVING, PAVEMENT MARKING DETAILS ETC.
  
 THANKS,
 RICK ROSSANO, PROJECT COORDINATOR, ENGINEERING SERVICES
 DEPARTMENT
 401 CLEMATIS STREET, 4TH FLOOR, WEST PALM BEACH, FL
 33401
 DIRECT: (561) 494-1098, FAX: (561) 494-1116, MOBILE:
 (561) 246-9525
 EMAIL: [email protected]
 WWW.WPB.ORG/ENGINEERING
  

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop L LANDSCAPING
Rev No 2 Status P Date 05-07-2021 Cont ID  
Sent By rcaranci Date 05-07-2021 Time 13:51 Rev Time 0.00
Received By rcaranci Date 05-07-2021 Time 13:51 Sent To  
Notes
2021-05-07 13:51:54FROM: RAY CARANCI, SENIOR LANDSCAPE PLANNER
 561-822-1462
 PROJECT: MCKEEN TOWERS MINOR PD AMENDMENT Z20120014
 MAY 7, 2021
 I HAVE REVIEWED THE ABOVE REFERENCED PETITION, AND
 PROVIDE THE FOLLOWING COMMENTS:
  
 1. CONDITIONALLY SATISFIED. THERE ARE MISSING TREES AND
 SHRUBS ON THE PROPERTY THAT WERE INSTALLED PER
 PREVIOUSLY APPROVED LANDSCAPE PLANS. ALL MISSING
 MATERIAL MUST BE REPLACED INCLUDING MISSING ROYAL PALMS
 AND TREES ALONG EVERNIA. THIS AMENDMENT ALLOWS THE
 OPPORTUNITY TO MAKE CHANGES TO SPECIES IF NEEDED TO
 ASSURE SUSTAINABILITY OF THE LANDSCAPE. STAFF HAS THE
 LANDSCAPE PLANS AVAILABLE FOR THE APPLICANT TO REVIEW.
 2. SEE ZONING COMMENTS. ADDRESS ALL LANDSCAPE COMMENTS
 IN THE ZONING COMMENTS.
 CONDITION OF APPROVAL:
 1. WITHIN 6 MONTHS OF THE APPROVAL OF THE PLANS WITH
 THIS AMENDMENT, A LANDSCAPE PERMIT SHALL BE SUBMITTED
 AND ISSUED. ALL MISSING LANDSCAPING ON THE ENTIRE SITE
 AND STREETSCAPE SHALL BE REPLACED ACCORDING TO THE
 APPROVED LANDSCAPE PLANS AND SHALL BE INSPECTED AS PART
 OF THE FINAL LANDSCAPE INSPECTION TO CLOSE THE PERMIT.
  

Review Stop L LANDSCAPING
Rev No 1 Status F Date 01-04-2021 Cont ID  
Sent By rcaranci Date 01-04-2021 Time 14:48 Rev Time 0.00
Received By rcaranci Date 01-04-2021 Time 14:48 Sent To  
Notes
2021-01-04 14:48:52FROM: RAY CARANCI, SENIOR LANDSCAPE PLANNER
 561-822-1462
 PROJECT: MCKEEN TOWERS MINOR PD AMENDMENT Z20120014
 JANUARY 4, 2021
 I HAVE REVIEWED THE ABOVE REFERENCED PETITION, AND
 PROVIDE THE FOLLOWING COMMENTS:
  
 1. THERE ARE MISSING TREES AND SHRUBS ON THE PROPERTY
 THAT WERE INSTALLED PER PREVIOUSLY APPROVED LANDSCAPE
 PLANS. ALL MISSING MATERIAL MUST BE REPLACED INCLUDING
 MISSING ROYAL PALMS AND TREES ALONG EVERNIA. THIS
 AMENDMENT ALLOWS THE OPPORTUNITY TO MAKE CHANGES TO
 SPECIES IF NEEDED TO ASSURE SUSTAINABILITY OF THE
 LANDSCAPE. STAFF HAS THE LANDSCAPE PLANS AVAILABLE FOR
 THE APPLICANT TO REVIEW.
 2. ADDRESS ALL LANDSCAPE COMMENTS IN THE ZONING REVIEW.
  

Review Stop PARK PARKING
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop POLICE POLICE
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop PW PUBLIC WORKS
Rev No 2 Status N Date 06-04-2021 Cont ID  
Sent By   Date 06-04-2021 Time   Rev Time 0.00
Received By   Date 06-04-2021 Time   Sent To  
Notes
***NONE***

Review Stop PW PUBLIC WORKS
Rev No 1 Status N Date 01-05-2021 Cont ID  
Sent By elevesqu Date 01-05-2021 Time 12:24 Rev Time  
Received By elevesqu Date   Time   Sent To  
Notes
***NONE***

Review Stop STORM STORMWATER
Rev No 1 Status P Date 01-05-2021 Cont ID  
Sent By tward Date 01-05-2021 Time 14:36 Rev Time 0.00
Received By tward Date 01-05-2021 Time 14:39 Sent To  
Notes
2021-01-05 14:39:00CONVERSION EQUATION BETWEEN NGVD1929 AND NAVD1988
 SHOULD BE LISTED ON THE ENGINEERING PLANS FOR FUTURE
 REFERENCE. THE CONVERSION EQUATION IS SHOWN ON THE
 SURVEY.
  
 TRACY WARD, P.E.
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120 (O)
 561-351-0510 (M)
 [email protected]

Review Stop SURVEY SURVEYING
Rev No 3 Status P Date 05-24-2021 Cont ID  
Sent By vnoel Date 05-24-2021 Time 07:49 Rev Time 0.00
Received By vnoel Date   Time   Sent To  
Notes
2021-05-24 07:51:04PASSED WITH CONDITION OF AGREEMENT PRIOR TO C.O./FINAL
 COMPLETION OF IMPROVEMENTS.

Review Stop SURVEY SURVEYING
Rev No 2 Status F Date 12-29-2020 Cont ID  
Sent By vnoel Date 12-29-2020 Time 08:47 Rev Time 0.00
Received By vnoel Date   Time   Sent To  
Notes
2020-12-29 08:49:211. AN AGREEMENT WILL BE REQUIRED FOR TRANSFORMER PADS
 OVER EXISTING WATER SERVICE. REQUEST WILL BE SUBMITTED
 TO LAW DEPT. FOR PREPARATION.

Review Stop SURVEY SURVEYING
Rev No 1 Status F Date 12-21-2020 Cont ID  
Sent By vnoel Date 12-21-2020 Time 09:16 Rev Time  
Received By vnoel Date   Time   Sent To  
Notes
2020-12-21 09:22:341. THERE ARE EASEMENTS OF RECORD NOT SHOWN ON SURVEY.
 PREVIOUS SURVEY BASED ON A TITLE SEARCH WAS SENT TO
 PLANNER.
 2. IT APPEARS THAT FPL TRANSFORMERS WERE PLACED ON THE
 WATER SERVICE. DEVELOPMENT SERVICES HAS BEEN REQUESTED
 TO PROVIDE ELECTRICAL PERMIT FOR REVIEW.
 3. AN AGREEMENT WILL LIKELY BE REQUIRED FOR OWNER TO
 ASSUME MAINTENANCE RESPONSIBILITY OF WATER SERVICE.

Review Stop TRAFFIC TRAFFIC ENGINEERING
Rev No 4 Status P Date 09-27-2021 Cont ID  
Sent By   Date 09-27-2021 Time   Rev Time 0.00
Received By   Date   Time   Sent To  
Notes
2021-09-27 15:07:58NO FURTHER COMMENTS
  
 SITE PLAN COMMENTS:
 1. SATISFIED. UPDATE PLAN TO PROPERLY DEPICT EXISTING
 CONDITIONS (REMOVE/UPDATE NON EXISTING FEATURES SUCH AS
 THE EXISTING ANTIQUE BUILDING)
 2. SATISFIED. PROVIDE AUTOTURN AND SHOWCASE PATH OF
 GARBAGE COLLECTION/SERVICE VEHICLES. ANALYSIS MUST SHOW
 VEHICLE TURNING IN AND OUT OF THE PROPOSED DEVELOPMENT.
 3. SATISFIED. DEPICT DO-NOT-ENTER SIGN AT THE PHASE 1
 ONE-WAY STOP LOCATION(S)
 4. SATISFIED. PROPERLY DRAW PARKING STALLS NORTH OF THE
 GENERATOR
 5. SATISFIED. UPDATE FACILITY DIMENSIONS (I.E.
 DRIVEWAY, STALLS)
 6. SATISFIED. PROVIDE DETAILS OF THE SIDEWALK ALONG
 OLIVE AVENUE IF IT IS BEING IMPACTED
 7. SATISFIED. UPDATE PARKING TABLE ACCORDINGLY.
 PROPERLY LIST THE TYPE OF PARKING (I.E. HANDICAP VS
 GENERAL) ALSO INCLUDE THE NUMBER OF BICYCLE PARKING
 REQUIRED/PROVIDED. BICYCLE RACKS SHALL BE PLACED NEARBY
 THE ENTRANCE
 8. SATISFIED. PROVIDE MORE DETAILS PERTAINING INTERNAL
 CIRCULATION
 9. SATISFIED. ASSIGN THE NORTH EAST PARKING STALLS TO
 HANDICAP, AS THEY ARE CLOSER TO THE ENTRANCE AND DO NOT
 REQUIRE CROSSING THE AISLE
 10. SATISFIED. REMOVE OR RELOCATE FURTHER EAST THE STOP
 BAR ALONG THE WESTERN ENTRY-DRIVEWAY
 11. SATISFIED. SHOW THE REQUIRED 20 FOOT VISIBILITY
 TRIANGLE ON THE SITE PLAN
  
 VALERIO ORICCHIO
 CITY TRANSPORTATION ENGINEER
 561-494-1092
 [email protected]
  

Review Stop TRAFFIC TRAFFIC ENGINEERING
Rev No 3 Status F Date 06-01-2021 Cont ID  
Sent By   Date 06-01-2021 Time   Rev Time 0.00
Received By   Date   Time   Sent To  
Notes
2021-06-01 18:57:31TRAFFIC COMMENTS:
  
 1. SATISFIED. UPDATE PLAN TO PROPERLY DEPICT EXISTING
 CONDITIONS (REMOVE/UPDATE NON EXISTING FEATURES SUCH AS
 THE EXISTING ANTIQUE BUILDING)
 2. NOT SATISFIED. PROVIDE AUTOTURN AND SHOWCASE PATH OF
 GARBAGE COLLECTION/SERVICE VEHICLES. ANALYSIS MUST SHOW
 VEHICLE TURNING IN AND OUT OF THE PROPOSED DEVELOPMENT.
 3. SATISFIED. DEPICT DO-NOT-ENTER SIGN AT THE PHASE 1
 ONE-WAY STOP LOCATION(S)
 4. SATISFIED. PROPERLY DRAW PARKING STALLS NORTH OF THE
 GENERATOR
 5. UPDATE FACILITY DIMENSIONS (I.E. DRIVEWAY, STALLS)
 6. PROVIDE DETAILS OF THE SIDEWALK ALONG OLIVE AVENUE
 IF IT IS BEING IMPACTED
 7. NOT SATISFIED. UPDATE PARKING TABLE ACCORDINGLY.
 PROPERLY LIST THE TYPE OF PARKING (I.E. HANDICAP VS
 GENERAL) ALSO INCLUDE THE NUMBER OF BICYCLE PARKING
 REQUIRED/PROVIDED. BICYCLE RACKS SHALL BE PLACED NEARBY
 THE ENTRANCE
 8. SATISFIED. PROVIDE MORE DETAILS PERTAINING INTERNAL
 CIRCULATION
 9. ASSIGN THE NORTH EAST PARKING STALLS TO HANDICAP, AS
 THEY ARE CLOSER TO THE ENTRANCE AND DO NOT REQUIRE
 CROSSING THE AISLE
 10. REMOVE OR RELOCATE FURTHER EAST THE STOP BAR ALONG
 THE WESTERN ENTRY-DRIVEWAY
 11. SHOW THE REQUIRED 20 FOOT VISIBILITY TRIANGLE ON
 THE SITE PLAN
  
 VALERIO ORICCHIO
 CITY TRANSPORTATION ENGINEER
 561-494-1092
 [email protected]
  
  
  

Review Stop TRAFFIC TRAFFIC ENGINEERING
Rev No 2 Status F Date 04-29-2021 Cont ID  
Sent By   Date 04-29-2021 Time   Rev Time 0.00
Received By   Date   Time   Sent To  
Notes
2021-04-29 19:52:06SITE PLAN COMMENTS:
 1. SATISFIED. UPDATE PLAN TO PROPERLY DEPICT EXISTING
 CONDITIONS (REMOVE/UPDATE NON EXISTING FEATURES SUCH AS
 THE EXISTING ANTIQUE BUILDING)
 2. NOT SATISFIED. PROVIDE AUTOTURN AND SHOWCASE PATH OF
 GARBAGE COLLECTION/SERVICE VEHICLES. ANALYSIS MUST SHOW
 VEHICLE TURNING IN AND OUT OF THE PROPOSED DEVELOPMENT.
 3. SATISFIED. DEPICT DO-NOT-ENTER SIGN AT THE PHASE 1
 ONE-WAY STOP LOCATION(S)
 4. SATISFIED. PROPERLY DRAW PARKING STALLS NORTH OF THE
 GENERATOR
 5. UPDATE FACILITY DIMENSIONS (I.E. DRIVEWAY, STALLS)
 6. PROVIDE DETAILS OF THE SIDEWALK ALONG OLIVE AVENUE
 IF IT IS BEING IMPACTED
 7. NOT SATISFIED. UPDATE PARKING TABLE ACCORDINGLY.
 PROPERLY LIST THE TYPE OF PARKING (I.E. HANDICAP VS
 GENERAL) ALSO INCLUDE THE NUMBER OF BICYCLE PARKING
 REQUIRED/PROVIDED. BICYCLE RACKS SHALL BE PLACED NEARBY
 THE ENTRANCE
 8. SATISFIED. PROVIDE MORE DETAILS PERTAINING INTERNAL
 CIRCULATION
 9. ASSIGN THE NORTH EAST PARKING STALLS TO HANDICAP, AS
 THEY ARE CLOSER TO THE ENTRANCE AND DO NOT REQUIRE
 CROSSING THE AISLE
 10 REMOVE OR RELOCATE FURTHER EAST THE STOP BAR ALONG
 THE WESTERN ENTRY-DRIVEWAY
 11. SHOW THE REQUIRED 20 FOOT VISIBILITY TRIANGLE ON
 THE SITE PLAN
  
 VALERIO ORICCHIO
 CITY TRANSPORTATION ENGINEER
 561-494-1092
 [email protected]
  

Review Stop TRAFFIC TRAFFIC ENGINEERING
Rev No 1 Status F Date 01-13-2021 Cont ID  
Sent By   Date 01-13-2021 Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
2021-01-13 17:23:03TRAFFIC COMMENTS:
  
 1. UPDATE PLANS TO PROPERLY DEPICT EXISTING CONDITIONS
 (REMOVE/UPDATE NON EXISTING FEATURES SUCH AS THE
 EXISTING ANTIQUE BUILDING)
 2. PROVIDE AUTOTURN SHOWCASING ENTERING/EXITING PATH OF
 GARBAGE COLLECTION/SERVICE VEHICLES
 3. DEPICT DO-NOT-ENTER SIGNS
 4. PROPERLY DRAW PARKING STALLS NORTH OF THE GENERATOR
 5. UPDATE FACILITY DIMENSIONS (I.E. DRIVEWAY, STALLS)
 6. PROVIDE DETAILS OF THE SIDEWALK ALONG OLIVE AVENUE
 IF IT IS BEING IMPACTED
 7. UPDATE PARKING TABLE
 8. PROVIDE MORE DETAILS PERTAINING INTERNAL
 CIRCULATION. POTENTIAL CONFLICTS AT THE INTERNAL
 INTERSECTION SOUTH-EAST OF THE PROPOSED GENERATOR
 LOCATION
  
 VALERIO ORICCHIO
 CITY TRANSPORTATION ENGINEER
 561-494-1092
 [email protected]
  

Review Stop Z ZONING
Rev No 3 Status P Date 09-30-2021 Cont ID  
Sent By   Date 09-30-2021 Time   Rev Time 0.00
Received By   Date 09-30-2021 Time   Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 2 Status F Date 06-03-2021 Cont ID  
Sent By   Date 06-03-2021 Time   Rev Time 0.00
Received By   Date 06-03-2021 Time   Sent To  
Notes
2021-06-03 12:27:14 
  
 1. PLEASE SEE COMMENTS IN ENGINEERING REGARDING WATER
 LINE UNDER UTILITY BOXES ? AGREEMENT SHALL BE REQUIRED
 (ACKNOWLEDGED)
 2. PLEASE UPDATE PARKING NUMBERS TO REFLECT REMOVED
 SPACES. FOUR PARKING SPACES WERE REMOVED AS PART OF
 THIS GENERATOR WORK, NOT THREE (ONE SPACE ADJACENT TO
 BUILDING) (SATISFIED)
 3. PLEASE CLARIFY, WHAT IS THE PURPOSE OF THE PROPOSED
 CURB ALONG THE ROW OF PARKING SPACES DIRECTLY SOUTH OF
 THE PROPOSED RAMP? WILL THIS CAUSE DRAINAGE ISSUES OR
 DIRECT STORMWATER INTO LANDSCAPE? (SATISFIED)
 4. THERE ARE EXISTING BOLLARDS AND EQUIPMENT ALONG THE
 SOUTH SIDE OF THE GENERATOR ENCLOSURE THAT ARE NOT
 INDICATED ON THE LANDSCAPE PLAN. THE PROPOSED LANDSCAPE
 WOULD LIKELY INTERFERE WITH THE EXISTING EQUIPMENT.
 PLEASE CONFIRM (SATISFIED)
 5. PLEASE INCLUDE LANDSCAPE WITHIN THE SOUTH TERMINAL
 ISLAND OF THE ROW OF PARKING SPACES THAT ARE EAST OF
 THE GENERATOR ENCLOSURE (SATISFIED)
 6. APPEARS TO BE SOME CONFLICT BETWEEN PROPOSED
 LANDSCAPE AND EXISTING UTILITIES NORTH OF THE DUMPSTER
 ENCLOSURE (SATISFIED)
 7. PLEASE ADD PROPOSED LANDSCAPE TO A FULL LANDSCAPE
 PLAN THAT INCLUDES ALL PREVIOUS WORK ? PREVIOUS
 LANDSCAPE PLANS CAN BE REQUESTED FROM CITY STAFF.
 (ACKNOWLEDGED)
 8. THE NEW ALIGNMENT OF THE CENTRAL ROW OF PARKING
 SPACES DOES NOT WORK FOR BI-DIRECTIONAL MOVEMENT ALONG
 THE EAST, AS A MINIMUM OF 24 FEET OF DRIVE AISLE IS
 REQUIRED. PLEASE SEE FIGURE XV-2 IN SECTION 94-485. THE
 WIDTH OF THE ONE DIRECTIONAL DRIVE AISLE COULD BE
 REDUCED TO 12? TO ACCOMMODATE THE NEEDED 24? WITHIN THE
 OTHER DRIVE AISLE. PLEASE EXAMINE FOR OTHER
 SOLUTIONS. (SATISFIED)
 9. ARE THE CURB STOPS BEING REPLACE WITHIN PARKING
 SPACES? THEY ARE CURRENTLY STACKED ON THE GREEN AREA.
 PLEASE ADD TO PLAN WHERE NECESSARY.(SATISFIED)
 10. PLEASE INDICATE WHICH PORTIONS OF THE PARKING LOT
 IS BEING RESURFACED. ANY AREAS THAT ARE RESURFACED
 SHALL BE BROUGHT TO CODE STANDARDS IN TERMS OF STRIPING
 (DOUBLE STRIPING REQUIRED) (SATISFIED)
 11. PLEASE UPDATE THE LISTED NUMBER OF PARKING SPACES
 AT SECTION NEAR GENERATOR ENCLOSURE (NO LONGER 30
 SPACES ? 4 WERE REMOVED) (SATISFIED)
 12. UNDERSTANDING THIS IS AN EXISTING CONDITION, CAN
 ANY ADDITIONAL LANDSCAPE SCREENING AND/OR A WRAP BE
 ADDED TO THE ELECTRICAL BOX ALONG THE SIDEWALK ON OLIVE
 AVENUE? THIS COULD BETTER ENHANCE THE STREET FRONTAGE
 ALONG THIS SIDE. (SATISFIED)
 13. PLEASE UPDATE LABELS THAT READ ?RELOCATE AND
 REPLACE EXISTING FIRE HYDRANT WITH NEW? AND OTHERS THAT
 APPLIED TO A PREVIOUS AMENDMENT FOR CLARIFICATION.
 (SATISFIED)
  
 COMMENTS FROM LIZ LEVESQUE, URBAN DESIGN PLANNER
 561 822 1426
 [email protected]
  

Review Stop Z ZONING
Rev No 1 Status F Date 12-30-2020 Cont ID  
Sent By elevesqu Date 12-30-2020 Time 16:23 Rev Time 0.00
Received By elevesqu Date 12-30-2020 Time 16:23 Sent To  
Notes
2020-12-30 16:23:331. PLEASE SEE COMMENTS IN ENGINEERING REGARDING WATER
 LINE UNDER UTILITY BOXES ? AGREEMENT SHALL BE REQUIRED
 2. PLEASE UPDATE PARKING NUMBERS TO REFLECT REMOVED
 SPACES. FOUR PARKING SPACES WERE REMOVED AS PART OF
 THIS GENERATOR WORK, NOT THREE (ONE SPACE ADJACENT TO
 BUILDING)
 3. PLEASE CLARIFY, WHAT IS THE PURPOSE OF THE PROPOSED
 CURB ALONG THE ROW OF PARKING SPACES DIRECTLY SOUTH OF
 THE PROPOSED RAMP? WILL THIS CAUSE DRAINAGE ISSUES OR
 DIRECT STORMWATER INTO LANDSCAPE?
 4. THERE ARE EXISTING BOLLARDS AND EQUIPMENT ALONG THE
 SOUTH SIDE OF THE GENERATOR ENCLOSURE THAT ARE NOT
 INDICATED ON THE LANDSCAPE PLAN. THE PROPOSED LANDSCAPE
 WOULD LIKELY INTERFERE WITH THE EXISTING EQUIPMENT.
 PLEASE CONFIRM
 5. PLEASE INCLUDE LANDSCAPE WITHIN THE SOUTH TERMINAL
 ISLAND OF THE ROW OF PARKING SPACES THAT ARE EAST OF
 THE GENERATOR ENCLOSURE
 6. APPEARS TO BE SOME CONFLICT BETWEEN PROPOSED
 LANDSCAPE AND EXISTING UTILITIES NORTH OF THE DUMPSTER
 ENCLOSURE
 7. PLEASE ADD PROPOSED LANDSCAPE TO A FULL LANDSCAPE
 PLAN THAT INCLUDES ALL PREVIOUS WORK ? PREVIOUS
 LANDSCAPE PLANS CAN BE REQUESTED FROM CITY STAFF
 8. THE NEW ALIGNMENT OF THE CENTRAL ROW OF PARKING
 SPACES DOES NOT WORK FOR BI-DIRECTIONAL MOVEMENT ALONG
 THE EAST, AS A MINIMUM OF 24 FEET OF DRIVE AISLE IS
 REQUIRED. PLEASE SEE FIGURE XV-2 IN SECTION 94-485. THE
 WIDTH OF THE ONE DIRECTIONAL DRIVE AISLE COULD BE
 REDUCED TO 12? TO ACCOMMODATE THE NEEDED 24? WITHIN THE
 OTHER DRIVE AISLE. PLEASE EXAMINE FOR OTHER SOLUTIONS
 9. ARE THE CURB STOPS BEING REPLACE WITHIN PARKING
 SPACES? THEY ARE CURRENTLY STACKED ON THE GREEN AREA.
 PLEASE ADD TO PLAN WHERE NECESSARY.
 10. PLEASE INDICATE WHICH PORTIONS OF THE PARKING LOT
 IS BEING RESURFACED. ANY AREAS THAT ARE RESURFACED
 SHALL BE BROUGHT TO CODE STANDARDS IN TERMS OF STRIPING
 (DOUBLE STRIPING REQUIRED)
 11. PLEASE UPDATE THE LISTED NUMBER OF PARKING SPACES
 AT SECTION NEAR GENERATOR ENCLOSURE (NO LONGER 30
 SPACES ? 4 WERE REMOVED)
 12. UNDERSTANDING THIS IS AN EXISTING CONDITION, CAN
 ANY ADDITIONAL LANDSCAPE SCREENING AND/OR A WRAP BE
 ADDED TO THE ELECTRICAL BOX ALONG THE SIDEWALK ON OLIVE
 AVENUE? THIS COULD BETTER ENHANCE THE STREET FRONTAGE
 ALONG THIS SIDE
 13. PLEASE UPDATE LABELS THAT READ ?RELOCATE AND
 REPLACE EXISTING FIRE HYDRANT WITH NEW? AND OTHERS THAT
 APPLIED TO A PREVIOUS AMENDMENT FOR CLARIFICATION
  
 LIZ LEVESQUE, URBAN DESIGN PLANNER
 561 822 1426
 [email protected]