Plan Review Details - Project Z19120009
Plan Review Stops For Project Z19120009
Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 01-07-2020 Cont ID  
Sent By rbrown Date 01-07-2020 Time 19:06 Rev Time 0.00
Received By rbrown Date 01-07-2020 Time 19:06 Sent To  
Notes
2020-01-07 19:08:59DEVELOPMENT SERVICES DEPARTMENT, BUILDING DIVISION,
 COMMENTS:
  
 1. THIS REVIEW IS A CURSORY REVIEW AS IT RELATES TO THE
 SITE. IT IS NOT A REVIEW FOR FULL COMPLIANCE WITH
 FLORIDA BUILDING CODE. THE FOLLOWING COMMENTS ARE TO BE
 ADDRESSED FOR THE BUILDING PERMIT APPLICATION.
  
 2. BUILDING SIZE. WHEN SUBMITTED FOR BUILDING PERMIT,
 THE PLANS SHALL SHOW THAT THE TYPE OF CONSTRUCTION FOR
 THE BUILDINGS WILL BE IN ACCORDANCE WITH THE HEIGHT,
 AREA AND OCCUPANCY LIMITATIONS IN CHAPTER 5 OF THE
 FLORIDA BUILDING CODE.
  
 3. ENCLOSED PARKING GARAGES. IF THE PARKING GARAGE DOES
 NOT HAVE WALL OPENINGS, OR SUFFICIENT WALL OPENINGS TO
 MEET THE DEFINITION OF AN OPEN PARKING GARAGE, IT WILL
 BE CONSIDERED AN ENCLOSED PARKING GARAGE AND MUST HAVE
 EXHAUST SYSTEMS. THE EXHAUST SYSTEMS SHALL BE DESIGNED
 TO MINIMIZE NOISE LEVELS USING INLINE FAN SILENCERS OR
 OTHER APPROVED METHODS.
  
 4. SEPARATE PERMITS REQUIRED. ALL APPLICABLE PERMITS
 AND SUB-PERMITS MUST BE OBTAINED BEFORE COMMENCING THE
 WORK. SEPARATE PERMITS, PLANS AND FEES, ARE REQUIRED
 FOR SIGNS, SWIMMING POOLS AND SPAS, GAS SYSTEMS,
 GENERATORS, FIRE ALARM SYSTEMS, FIRE SPRINKLER AND
 OTHER FIRE SUPPRESSION SYSTEMS, GREASE INTERCEPTORS,
 SITE LIGHTING, SITE LANDSCAPE, SITE IRRIGATION, ETC.
  
 5. CONTRACTOR VEHICLE PARKING. PROPERTY OWNER AND
 CONTRACTOR SHALL MAKE ARRANGEMENTS FOR PARKING OF
 CONTRACTOR VEHICLES TO MINIMIZE THE IMPACT ON ALL
 NEIGHBORING PROPERTIES.
  
 6. PROTECTION OF NEIGHBORING PROPERTY. PROPERTY OWNER
 AND CONTRACTOR SHALL PROTECT ALL NEIGHBORING PROPERTY,
 INCLUDING VEHICLES, FROM DAMAGE OR DIRT CAUSED BY THE
 CONSTRUCTION, AND SHALL NOTIFY THE OCCUPANTS OF
 NEIGHBORING PROPERTIES ABOUT ALL STAGES OF CONSTRUCTION
 THAT MAY AFFECT THE USE OF THEIR PROPERTY.
  
 7. ART IN PUBLIC PLACES. THIS PROJECT WILL BE SUBJECT
 TO ART IN PUBLIC PLACES (AIPP) ASSESSMENT. FOR ADVICE
 ON THE PROVISION OF PUBLIC ARTWORK IN LIEU OF THE AIPP
 ASSESSMENT, CONTACT SYBILLE WELTER, ART IN PUBLIC
 PLACES COORDINATOR, AT (561) 822-1521, OR BY EMAIL:
 [email protected]
  
 ROBERT BROWN
 BUILDING OFFICIAL
 TEL: 561 805 6652
 EMAIL: [email protected]
  

Review Stop ENG - PPRC ENGINEERING - PPRC
Rev No 3 Status P Date 07-13-2020 Cont ID  
Sent By rrossano Date 07-13-2020 Time   Rev Time 0.00
Received By rrossano Date 07-13-2020 Time   Sent To  
Notes
2020-07-13 10:58:40PASSED WITH PROVISOS FOR ENGINEERING SUBMITTAL::
  
 REMOVE OBSOLETE STANDARD DETAILS WS-2 AND WS-4.
  
 SHOW VERTICAL CLEARANCE BETWEEN PROPOSED WATER &
 EXISTING SANITARY PIPE.
  
 LABEL POINT OF SERVICE FOR DOMESTIC WATER.
  
 IF PROPOSED WATER SOURCE FOR IRRIGATION IS WELL WARE,
 DETAIL MUST BE PROVIDED INCLUDING PROPOSED LOCATION,
 SCREENING FOR PUMP, ETC. WHICH WOULD NEED ZONING
 APPROVAL.
  
  
  
  
  

Review Stop ENG - PPRC ENGINEERING - PPRC
Rev No 2 Status F Date 04-24-2020 Cont ID  
Sent By rrossano Date 04-24-2020 Time   Rev Time 0.00
Received By rrossano Date 04-24-2020 Time   Sent To  
Notes
2020-04-25 09:36:36PLEASE UPDATE STANDARD DETAILS TO MOST CURRENT
 VERSIONS.
  
 PLEASE PROVIDE ENLARGED DETAIL OF PROPOSED WATER
 METER/BACKFLOW AREA.
  
 PLEASE PROVIDE CLEARANCES AT PROPOSED UTILITY
 CROSSINGS.
  
  
 COMMENTS FROM MARK HURLEY, CUSTOMER SERVICE SUPERVISOR,
 PUBLIC UTILITIES, [email protected] 561-822-2262
  
 -SEWER DEMAND WAS REFERRED TO IN COMMENT RESPONSE BUT
 NOT LISTED ON THE PLAN C-2. PLEASE ADD.
  
 -WILL THERE BE ANY IRRIGATION? IF SO AND RUNS OFF CITY
 WATER, ADD TO DEMAND CALCULATION.
  
 -RELOCATE 6? GATE VALVE NEAREST DCDA A BIT DOWNSTREAM
 SO THAT IT SHUTS OFF ONLY THE FIRELINE AND LABEL AS
 POINT OF SERVICE FOR FIRELINE.
  
 -CANNOT SEE UTILITY EASEMENT BOUNDARIES NEAR THE WATER
 METERS. PLEASE MAKE CLEARER. FIRE AND DOMESTIC BACKFLOW
 ASSEMBLIES CANNOT BE IN UTILITY EASEMENTS.
  
 -WATER SERVICE PIPE MATERIAL NOT LABELED.
  
 -EACH 2? METER SHOULD HAVE IT?S OWN TAP AND SERVICE
 LINE FROM THE 6? PIPE.
  
 -NEED UTILITY EASEMENT FOR CITY FIRE HYDRANT LOCATED
 NEAR SW CORNER OF PROPERTY.
  
 FEEL FREE TO CONTACT US IF YOU HAVE ANY QUESTIONS OR
 CONCERNS, THANKS.
 RICK ROSSANO, PROJECT COORDINATOR, ENGINEERING SERVICES
 DEPARTMENT
 DIRECT: (561) 494-1098 [email protected]
  

Review Stop ENG - PPRC ENGINEERING - PPRC
Rev No 1 Status F Date 01-07-2020 Cont ID  
Sent By rrossano Date 01-07-2020 Time   Rev Time  
Received By rrossano Date 01-07-2020 Time   Sent To  
Notes
2020-01-07 07:29:10SHOW ADDRESS ON PLANS
 PROVIDE WATER AND SEWER DEMANDS ON PLANS. WILL EXISTING
 METERS BE SUFFICIENT? WILL SANITARY NEED TO BE UPSIZED
 DOWNSTREAM?
 PROVIDE CCTV OF SEWER AND STORM ALONG PROJECT FRONTAGE
 CONFIRM/VERIFY SANITARY FLOW DIRECTION
 SHOW MATERIALS, PIPE SIZES ETC.
 SHOW CONFLICTS AND PROFILES AT PROPOSED UTILITY
 CROSSINGS.
 SHOW FM IN RAILROAD ROW
 FOR ENGINEERING SUBMITTAL, SHOW ENLARGED DETAIL OF
 PROPOSED METER LOCATION WITH EASEMENT FOR METER
 PLACEMENT.
  
 FOLLOWING COMMENTS FROM MARK HURLEY, PUBLIC UTILITIES
 CUSTOMER SERVICE SUPERVISOR, [email protected],
 561-822-2262:
 -THE PLAN LOOKS TO BE TAKING INTO ACCOUNT THE
 FORTHCOMING BANYAN STREETSCAPE PROJECT, BUT NEEDS TO BE
 PREPARED IF CHANGES OCCUR. FOR INSTANCE, THE EXISTING
 WATER SERVICES AND METER BOXES ON BANYAN MAY POSSIBLY
 BE ELIMINATED (BOTH OF THEM). IF THE ONE TO THE
 SOUTHWEST IS NOT ELIMINATED AND GOING TO USE 2 IN.
 METER, WOULD LIKE IT BROUGHT OUT OF SIDEWALK AND INTO
 SMALL GRASS U.E. NOT SURE IF PLAN ACCOUNTED FOR
 EXISTING SERVICE TO FAR SOUTHEAST.
 -THERE MAY BE A FORTHCOMING TAMARIND UTILITY PROJECT
 THAT HAS BEEN IN PLANNING FOR LONG TIME. PLAN MAY NEED
 ADJUSTMENT IF THAT TAKES PLACE BEFOREHAND.
 -DOMESTIC METER SIZE NEEDS TO BE DETERMINED AS METERS
 ABOVE 2 IN. REQUIRE MUCH MORE SPACE AND NEED TO BE
 ABOVE-GROUND AND OUT OF TRAFFIC.
 -WATER MAIN MATERIAL NOT SHOWN ON LABEL. SERVICE SIZE
 AND METER SIZE ALSO NOT SHOWN AND LABELED.
 -DOMESTIC BACKFLOW ASSEMBLY NOT SHOWN. RECOMMEND
 PARALLEL DOMESTIC BACKFLOW ASSEMBLIES SO CUSTOMER IS
 NOT WITHOUT WATER DURING MAINTENANCE. THEY CANNOT BE
 LOCATED INSIDE BUILDING, IN SIDEWALK, OR IN ROW.
 -ADD WS SD # TO LABEL IF CONSTRUCTING SOMETHING THAT
 WOULD REFERENCE IT SUCH AS A FIRELINE BACKFLOW
 ASSEMBLY. PUT COPY OF THAT WATER SERVICE STANDARD
 DETAIL IN PLAN.
 -NEED LABEL CONFLICT CROSSING OF FIRELINE WITH FM & S.
 PREFER WATER LINES ABOVE SEWER LINES WHEN POSSIBLE.
 -SIZE OF WET TAP NOT LABELED ALONG WITH SIZE OF
 FIRELINE AND SIZE OF DCDA. TYPE OF MATERIAL IS ALSO NOT
 ON LABEL. NEED POINT OF SERVICE VALVE AT PROPERTY LINE
 ? LIKE IT TO BE OUT OF HEAVY TRAFFIC WHEN POSSIBLE.
 -20 IN. WATER MAIN MATERIAL NOT LABELED.
 -THE WESTERN DRIVEWAY IS BEING BUILT OVER LARGE SEWER
 PIPES (FM & S) WHICH COULD BE PROBLEMATIC IF
 MAINTENANCE WERE NEEDED WHERE DRIVEWAY HAD TO BE SHUT
 DOWN AND DRIVEWAY EXCAVATED. CAN GARAGE PARKING STILL
 BE FUNCTIONALLY USED IN THAT EVENT?
 FEEL FREE TO CONTACT US IF YOU HAVE ANY QUESTIONS OR
 CONCERNS, THANKS.
 RICK ROSSANO, PROJECT COORDINATOR, ENGINEERING SERVICES
 DEPARTMENT
 401 CLEMATIS STREET, 4TH FLOOR WPB, FL 33401 (MAILING
 ADDRESS: P.O. BOX 3366, ZIP 33402)
 MAIN PHONE: (561) 822-1200 DIRECT: (561) 494-1098
 FAX: (561) 494-1116 MOBILE: (561) 246-9525
 EMAIL: [email protected] WWW.WPB.ORG/ENGINEERING
  

Review Stop FIRE FIRE DEPARTMENT
Rev No 3 Status P Date 06-15-2020 Cont ID  
Sent By pleduc Date 06-15-2020 Time   Rev Time 0.00
Received By pleduc Date 06-15-2020 Time 14:45 Sent To  
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 2 Status P Date 06-10-2020 Cont ID  
Sent By pleduc Date 06-10-2020 Time   Rev Time 0.00
Received By pleduc Date 06-10-2020 Time 12:29 Sent To  
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status P Date 01-03-2020 Cont ID  
Sent By pleduc Date 01-03-2020 Time   Rev Time 0.00
Received By pleduc Date 01-03-2020 Time 14:52 Sent To  
Notes
2020-01-03 15:24:58THE FOLLOWING COMMENTS WERE SUBMITTED BY PETER LEDUC,
 FIRE MARSHAL, BUREAU OF FIRE PREVENTION, WEST PALM
 BEACH FIRE RESCUE.
  
 THIS REVIEW CAN ONLY BE CONSIDERED PRELIMINARY AS THE
 DRAWINGS THAT WERE REVIEWED WERE NOT COMPLETE.
 ADDITIONAL COMMENTS CAN BE EXPECTED WHEN FULL DRAWINGS
 ARE SUBMITTED FOR PERMIT.
  
 THE FIRE PREVENTION BUREAU HAS NO OBJECTIONS TO THE
 PROPOSED PROJECT.
  
 1. CONSTRUCTION, DEMOLITION, AND RENOVATION TO COMPLY
 WITH NFPA 241. EXTRA ATTENTION SHALL BE GIVEN TO THE
 PERMITTING AND LOCATION OF CONSTRUCTION TRAILERS. A
 PERMIT IS REQUIRED FOR ANY CONSTRUCTION TRAILER RELATED
 TO THIS PROJECT. SEPARATION DISTANCES FROM MAIN
 STRUCTURES AS WELL AS OTHER TRAILERS SHALL BE CLOSELY
 MONITORED FOR THE REQUIREMENTS OF FIRE SPRINKLER
 PROTECTION.
  
 2. SITE ACCESS AND EXIT POINTS ARE TO BE CLEARLY
 IDENTIFIED AND MAINTAINED FOR EMERGENCY VEHICLES DURING
 ALL CONSTRUCTION ACTIVITIES.
  
 3. THE BUILDING ADDRESS SHALL BE CLEARLY VISIBLE FROM
 ALL ACCESS ROADWAYS, INCLUDING DURING CONSTRUCTION.
 ADDRESS NUMBERS SHALL CONTRAST WITH THEIR BACKGROUND
 AND SHALL NOT BE LESS THAN SIX (6) INCHES IN HEIGHT
 WITH A ONE (1) INCH STROKE FOR ALL BUILDINGS.
  
 4. DURING CONSTRUCTION, TRASH AND DEBRIS IS TO BE
 REMOVED FROM THE SITE DAILY OR MORE OFTEN TO REDUCE THE
 ACCUMULATION OF POTENTIAL LIFE AND FIRE SAFETY HAZARDS.
  
 5. THE CONSTRUCTION OF THE BUILDING SHALL COMPLY WITH
 THE 6TH EDITION OF THE FLORIDA FIRE PREVENTION CODE,
 INCLUDING NFPA 1 & 101, AND ALL ASSOCIATED FIRE CODES.
  
 6. ALL PARKING STRUCTURES SHALL COMPLY WITH NFPA 88A,
 PARKING STRUCTURES AND NFPA 101, THE LIFE SAFETY CODE,
 INCLUDING MORE SPECIFICALLY, CHAPTER 42 STORAGE
 OCCUPANCIES (PARKING STRUCTURES)
  
 7. A NFPA 13 COMPLAINT FIRE SPRINKLER SYSTEM AND NFPA
 14 COMPLIANT WET STANDPIPE SYSTEM ARE REQUIRED FOR THIS
 STRUCTURE. TEMPORARY STANDPIPES ARE REQUIRED WHEN THE
 BUILDING REACHES THREE LEVELS OR THIRTY FEET WHILE
 BEING CONSTRUCTED.
  
 SEPARATE SHOP DRAWINGS, ARE REQUIRED TO BE SUBMITTED,
 REVIEWED AND APPROVED BY THE FIRE PREVENTION BUREAU
 PRIOR TO ANY INSTALLATION.
  
 IT IS RECOMMENDED FOR APARTMENT BUILDINGS OF THIS SIZE
 THAT TWO SEPARATE FDC BE LOCATED REMOTELY FROM EACH
 OTHER. ONE IS INDCATED ON THE SOUTHWEST CORNER, THE
 OTHER IS RECOMMENDED TO BE LOCATED AND THE SOUTHEAST
 CORNER.
  
 7A. PER NFPA 14, 6.4.5.4* FIRE DEPARTMENT CONNECTIONS
 SHALL BE LOCATED NOT MORE THAN 100 FT (30.5 M) FROM THE
 NEAREST FIRE HYDRANT CONNECTED TO AN APPROVED WATER
 SUPPLY.
  
 7B. PLEASE REVIEW THE DISTANCE SEPARATION OF THE
 STAIRWELLS AS THE SEPARATION DISTANCE IS NOT INDICATED.
  
 7.3.2.2* WHERE THE MOST REMOTE PORTION OF A
 NON-SPRINKLERED FLOOR OR STORY IS LOCATED IN EXCESS OF
 150 FT (45.7 M) OF TRAVEL DISTANCE FROM A HOSE
 CONNECTION IN OR ADJACENT TO A REQUIRED EXIT OR THE
 MOST REMOTE PORTION OF A SPRINKLERED FLOOR OR STORY
 IS LOCATED IN EXCESS OF 200 FT (61 M) OF TRAVEL
 DISTANCE FROM A HOSE CONNECTION IN OR ADJACENT TO A
 REQUIRED EXIT, ADDITIONAL HOSE CONNECTIONS SHALL BE
 PROVIDED, IN APPROVED LOCATIONS, WHERE REQUIRED BY THE
 LOCAL FIRE DEPARTMENT OR THE AHJ.
  
 7C. PER NFPA 1
  
 18.3 WATER SUPPLIES.
  
 18.3.1* AN APPROVED WATER SUPPLY CAPABLE OF SUPPLYING
 THE REQUIRED FIRE FLOW FOR FIRE PROTECTION SHALL BE
 PROVIDED TO ALL PREMISES UPON WHICH FACILITIES,
 BUILDINGS, OR PORTIONS OF BUILDINGS ARE HEREAFTER
 CONSTRUCTED OR MOVED INTO THE JURISDICTION. THE
 APPROVED WATER SUPPLY SHALL BE IN ACCORDANCE WITH
 SECTION 18.4.
  
 PER FLORIDA ADMINISTRATIVE CODE SECTION 61G15-32.004,
 FIRE PROTECTION ENGINEERING DOCUMENTS SHALL INCLUDE THE
 POINT OF SERVICE FOR THE WATER SUPPLY, A LIST OF
 APPLICABLE NFPA STANDARDS APPLICABLE TO THE PROJECT,
 CLASSIFICATION OF HAZARD OCCUPANCY FOR EACH ROOM OR
 AREA, SUPPRESSION SYSTEM TYPE, DESIGN DENSITIES, WATER
 SUPPLY DATA (FIRE PUMP DATA, HYDRANT FLOW TEST DATA)
 AND ANY PERFORMANCE BASED INFORMATION SUCH AS
 PRE-ENGINEERED SYSTEMS.
  
 FOR THE PROPOSED FIRE PUMP(S) , WHAT IS(ARE) THE
 PRIMARY AND SECONDARY POWER SOURCES?
  
 7D. THE LOCATION OF THE DDCC FIRE LINE LOCATION SHALL
 MEET THE REQUIREMENTS OF NFPA 24 AND SHALL BE
 COORDINATED WITH THE OFFICE OF FIRE MARSHAL, THE CITY'S
 ENGINEERS OFFICE, THE LANDSCAPE PLANNER, AND THE CITY'S
 PLANNING AND ZONING OFFICE.
  
 8. A CLASS ?A? NFPA 72 COMPLIANT MONITORED FIRE ALARM
 SYSTEM IS REQUIRED FOR THIS STRUCTURE. SEPARATE SHOP
 DRAWINGS, ARE REQUIRED TO BE SUBMITTED, REVIEWED AND
 APPROVED BY THE FIRE PREVENTION BUREAU PRIOR TO ANY
 INSTALLATION.
  
 9. ALL ELEVATORS SHALL BE EQUIPPED WITH A REGION 7
 KEYWAY SYSTEM.
  
 ALL NEW ELEVATORS SHALL CONFORM TO THE FIRE FIGHTER?S
 EMERGENCY OPERATIONS REQUIREMENTS OF ASME A17.1/CSA
 B44, SAFETY CODE FOR ELEVATORS.
  
 ANY BUILDING THAT IS MORE THAN THREE STORIES HIGH OR IN
 WHICH THE VERTICAL DISTANCE BETWEEN THE BOTTOM TERMINAL
 LANDING AND THE TOP TERMINAL LANDING EXCEEDS 25 FEET
 MUST BE CONSTRUCTED TO CONTAIN AT LEAST ONE PASSENGER
 ELEVATOR THAT IS OPERATIONAL AND WILL ACCOMMODATE AN
 AMBULANCE STRETCHER 76 INCHES LONG AND 24 INCHES WIDE
 IN THE HORIZONTAL POSITION.
  
 10. COMPLETE LIFE SAFETY PLANS FOR EACH OCCUPANCY SHALL
 BE PROVIDED THAT ILLUSTRATE OCCUPANT LOADS, TRAVEL
 DISTANCES, COMMON PATHS OF TRAVEL, DEAD-END CORRIDORS,
 EXIT SIGNS, EMERGENCY LIGHTING, EXITS LEADING TO A
 PUBLIC WAY, FIRE EXTINGUISHER LOCATIONS, AND ALL FIRE
 SAFETY FEATURES AND EQUIPMENT.
  
 10A. FOR PLAN REVIEW PURPOSES, PLEASE REVIEW THE POOL
 DECK OCCUPANCY LOAD CALCULATIONS TO ENSURE REQUIRED
 NUMBER OF EXITS. TWO ARE SHOWN, THREE MAY BE REQUIRED.
  
 10B. FOR PLAN REVIEW PURPOSES, PLEASE REVIEW THE DOOR
 SWING OF THE POOL DECK EXIT DOOR FROM THE INTERIOR
 CORRIDOR. THIS DOOR IS REQUIRED TO SWING IN THE
 DIRECTION OF EGRESS FROM THE POOL DECK (ASSEMBLY).
  
 11. ALL EXISTING AND NEW FIRE HYDRANTS PLANNED FOR THIS
 DEVELOPMENT SHALL BE CLEARLY INDICATED AND IDENTIFIED
 ON THE PLAN AND CLOSELY COORDINATED WITH THE BUREAU OF
 FIRE PREVENTION.
  
 ALL NEW FIRE HYDRANTS AND FDC?S PLANNED FOR THIS
 DEVELOPMENT SHALL BE CLOSELY COORDINATED WITH THE
 BUREAU OF FIRE PREVENTION. PROPOSED FIRE HYDRANTS AND
 FDC?S SHOULD BE LOCATED ON THE SAME SIDE OF THE STREET
 OR ACCESS ROADWAY TO ALLOW FREE ACCESS FOR OTHER
 ARRIVING EMERGENCY VEHICLES.
  
 12. RADIO
  
 NFPA 1, CHAPTER 11, BUILDING SERVICES; 11.10 TWO-WAY
 RADIO ENHANCEMENT SERVICES.
  
 11.10.1 IN ALL NEW AND EXISTING BUILDINGS, MINIMUM
 RADIO SIGNAL STRENGTH FOR FIRE DEPARTMENT
 COMMUNICATIONS SHALL BE MAINTAINED AT A LEVEL
 DETERMINED BY THE AHJ.
  
 NFPA 72, 24.5.2* TWO-WAY RADIO COMMUNICATIONS
 ENHANCEMENT SYSTEMS.
 24.5.2.2 RADIO COVERAGE. RADIO COVERAGE SHALL BE
 PROVIDED THROUGHOUT THE BUILDING AS A PERCENTAGE OF
 FLOOR AREA AS SPECIFIED IN 24.5.2.2.1 THROUGH
 24.5.2.2.3.
 24.5.2.2.1 CRITICAL AREAS. CRITICAL AREAS, SUCH AS THE
 EMERGENCY COMMAND CENTER(S), THE FIRE PUMP ROOM(S),
 EXIT STAIRS, EXIT PASSAGEWAYS, ELEVATOR LOBBIES,
 STANDPIPE CABINETS, SPRINKLER SECTIONAL VALVE
 LOCATIONS, AND OTHER AREAS DEEMED CRITICAL BY THE
 AUTHORITY HAVING JURISDICTION, SHALL BE PROVIDED WITH
 99 PERCENT FLOOR AREA RADIO COVERAGE.
 24.5.2.2.2 GENERAL BUILDING AREAS. GENERAL BUILDING
 AREAS SHALL BE PROVIDED WITH 90 PERCENT FLOOR AREA
 RADIO COVERAGE.
 24.5.2.3 SIGNAL STRENGTH.
 24.5.2.3.1 INBOUND. A MINIMUM INBOUND SIGNAL STRENGTH
 OF -95 DBM, OR OTHER SIGNAL STRENGTH AS REQUIRED BY THE
 AUTHORITY HAVING JURISDICTION, SHALL BE PROVIDED
 THROUGHOUT THE COVERAGE AREA.
 24.5.2.3.2 OUTBOUND. A MINIMUM OUTBOUND SIGNAL STRENGTH
 OF -95 DBM AT THE DONOR SITE, OR OTHER SIGNAL STRENGTH
 AS REQUIRED BY THE AUTHORITY HAVING JURISDICTION, SHALL
 BE PROVIDED FROM THE COVERAGE AREA.
  
 THE SYSTEM SHALL MAINTAIN A MINIMUM RADIO SIGNAL
 STRENGTH OF -95 DBM FOR THE RADIO SYSTEM USED BY WEST
 PALM BEACH FIRE RESCUE. TESTING SHALL BE BY AN
 ACCEPTABLE NATIONAL STANDARD DOCUMENTING PERCENTAGES
 NOTED ABOVE AND BY ACTUAL RADIO TESTING BY FIRE
 PERSONNEL. IF THE MINIMUM CANNOT BE MAINTAINED, A
 BI-DIRECTIONAL AMPLIFIED SYSTEM SHALL BE INSTALLED WITH
 A MINIMUM 2-HOUR RUN TIME BATTERY BACK-UP.
  
 13. KNOX-BOX KEY SYSTEM SHALL BE REQUIRED FOR THIS
 BUILDING. THE KNOX BOX LOCATION(S) SHALL BE DETERMINED
 THROUGH REVIEW WITH THE FIRE MARSHALS OFFICE FOR
 EFFECTIVE AND EFFICIENT FIREGROUND OPERATIONAL
 PURPOSES.
  
 ANY GATE(S) SHALL BE PROVIDED WITH KNOX KEY ACCESS
 LOCKS, PADLOCKS AND/OR SWITCHES FOR 24 HOUR EMERGENCY
 ACCESS.
  
 14. ANY SMOKE CONTROL SYSTEM SHALL COMPLY WITH NFPA
 101, CHAPTER 9, BUILDING SERVICE AND FIRE PROTECTION
 EQUIPMENT, INCLUDING:
 THE SMOKE CONTROL SYSTEMS SHALL BE INSTALLED,
 INSPECTED, TESTED, AND MAINTAINED IN ACCORDANCE WITH
 NFPA 92, STANDARD FOR SMOKE CONTROL SYSTEMS; NFPA 204,
 STANDARD FOR SMOKE AND HEAT VENTING; OR NATIONALLY
 RECOGNIZED STANDARDS, ENGINEERING GUIDES, OR
 RECOMMENDED PRACTICES, AS APPROVED BY THE AUTHORITY
 HAVING JURISDICTION.
  
 THE ENGINEER OF RECORD SHALL CLEARLY IDENTIFY THE
 INTENT OF THE SYSTEM, THE DESIGN METHOD USED, THE
 APPROPRIATENESS OF THE METHOD USED, AND THE REQUIRED
 MEANS OF INSPECTING, TESTING, AND MAINTAINING THE
 SYSTEM.
  
 ACCEPTANCE TESTING SHALL BE PERFORMED BY A SPECIAL
 INSPECTOR IN ACCORDANCE WITH SECTION 9.9.
  
 15. THE BUREAU'S APPROVAL OF THIS SUBMITTED PROJECT
 DOES NOT CONSTITUTE IT'S FINAL REVIEW OR APPROVAL.
  
 16. THE BUREAU SHALL REVIEW ALL SUBMITTED BUILDING
 PLANS AT THE APPROPRIATE TIME AND IN ACCORDANCE WITH
 THE REQUIREMENTS OF ALL APPLICABLE CODES AND STANDARDS.
  
 PETER LEDUC
 FIRE MARSHAL
 561-804-4709
 [email protected]
  

Review Stop L LANDSCAPING
Rev No 3 Status P Date 06-16-2020 Cont ID  
Sent By rcaranci Date 06-16-2020 Time 14:13 Rev Time 0.00
Received By rcaranci Date 06-16-2020 Time 14:13 Sent To  
Notes
2020-06-16 14:13:46FROM: RAY CARANCI, LANDSCAPE PLANNER 561-822-1462
 PROJECT: 301 BANYAN Z19120009
 JUNE 16, 2020
 I HAVE REVIEWED THE ABOVE REFERENCED PETITION, AND
 PROVIDE THE FOLLOWING COMMENTS:
  
 1. MAKE THE FOLLOWING CORRECTIONS TO THE TREE
 DISPOSITION PLAN:
 ? SATISFIED. TREES AND PALMS CANOPY SQUARE FOOTAGE TO
 BE MITIGATED BASED ON CATEGORY. MANGO AND SEA GRAPE ARE
 CATEGORY 1.
 CANOPY DIAMETER MAY CHANGE SOME SQUARE FOOTAGE.
 ? SATISFIED. ANY TREES 20 FEET OR MORE CANOPY DIAMETER
 TO BE MITIGATED BY ACTUAL SQUARE FOOTAGE. CANOPY
 DIAMETER MUST BE PROVIDED FOR EACH TREE AND
 CALCULATIONS ARE ROUNDED UP TO THE NEXT FULL SQUARE
 FOOT.
 PROVIDE CANOPY DIAMETER FOR EACH TREE. CHANGE THE
 CANOPY (SQ-FT) COLUMN TO CANOPY DIAMETER. THIS NEEDS TO
 BE SHOWN TO DETERMINE CALCULATION OF MITIGATION SQUARE
 FOOTAGE BY CATEGORY OR ACTUAL SQUARE FOOTAGE. PALMS DO
 NOT NEED CANOPY DIAMETER, ONLY CATEGORY.
 ? SATISFIED. PROVIDE THE TOTAL SQUARE FOOTAGE OF
 MITIGATION FOR ALL TREES AND PALMS PROPOSED TO BE
 REMOVED.
 ADJUST ALL MITIGATION FOR THE ABOVE COMMENTS AND
 PROVIDE NEW TOTAL.
 ? SATISFIED. PROVIDE THE MITIGATION VALUES BY CATEGORY
 FOR THE PROPOSED TREES AND PALMS BASED ON CATEGORY AND
 PROVIDE THE TOTAL MITIGATION SQUARE FOOTAGE. THEN
 PROVIDE ANY OVERAGE OR DEFICIENCY SQUARE FOOTAGE.
 AFTER MITIGATION SQUARE FOOTAGE DUE IS RECALCULATED,
 UPDATE AND PROVIDE ONE TOTAL FOR DEFICIENCY, THEN
 CALCULATE PAYMENT IN LIEU.
 2. SATISFIED. STAFF REQUESTS THAT A NARRATIVE BE ADDED
 THAT EXPLAINS THE REASON THE EXISTING BLACK OLIVE TREES
 IN THE RIGHT OF WAY CANNOT BE RETAINED. THERE IS A
 ZONING REVIEW COMMENT REGARDING THE SETBACK OF THE
 BUILDING THAT MAY POSITIVELY AFFECT THE TREES. ALSO
 EXPLAIN THE PROGRESSION OF THE BANYAN STREETSCAPE
 PROJECT DESIGN THAT WAS INTENDED TO PRESERVE THE
 EXISTING CANOPY TREES, AND WHAT THE REPLACEMENT TREE
 CANOPY WILL BE.
 BLACK OLIVE TREES WERE ORIGINALLY TO REMAIN IN PLACE
 FOR THE BANYAN STREETSCAPE PROJECT. DEVELOPMENT OF THE
 SITE AT THE CURRENT BUILDING SETBACK IS THE CAUSE TO
 REMOVE THE TREES AND REDESIGN THE BANYAN STREETSCAPE
 PROJECT TO ADJUST FOR THE BUILDING DEVELOPMENT. THE
 BUILDING SETBACK IS CURRENTLY BEING DISCUSSED AS PART
 OF THE ZONING REVIEW AND MAY CHANGE. PLEASE PROVIDE THE
 CORRECT NARRATIVE.
  
 3. SATISFIED. SHOW STREETSCAPE REQUIRED FOR TAMARIND
 AVE. ADJACENT TO THE PROPERTY. PER SECTION 94-113.
  
 4. SATISFIED. QBD-3 ZONING WITH LOT SIZE LESS THAN
 50,000 SQ FT REQUIRES 25% PRIVATE OPEN SPACE. SURVEY
 INDICATES 33279.7 SQ FT, 25% EQUALS 8319.925 SQ FT.
 ROUND TO 8320 SQ FT REQUIRED.
 PRIVATE OPEN SPACE AREAS SHOWN ON SHEET A-1.07 MUST BE
 BROKEN DOWN TO SHOW THE REQUIRED VEGETATED AREA AND ANY
 TREE CANOPY REQUIREMENT FOR EACH AREA AS THE ALLOWED
 OPEN SPACE TYPE PER TABLE IV-6, AND DEFINITIONS FOUND
 IN 94-109. TERRACE REQUIRES 20% MINIMUM VEGETATED AREA.
 ROOFTOP GARDEN REQUIRES 30% VEGETATED AREA AND 20% TREE
 CANOPY. TREE CANOPY VALUES CAN BE FOUND IN SECTION
 94-109 TABLE IV-8. THIS INFORMATION MUST BE REFLECTED
 ON THE LANDSCAPE PLAN.
 SHEET LP-1.02 NEEDS TO SHOW THE OPEN SPACE AREA
 MATCHING SHEET A-1.07 AND BE LABELED AS ROOFTOP GARDEN
 TO MATCH THE LANDSCAPE REQUIREMENTS CHART IF THE
 CALCULATIONS ARE CORRECT. TERRACE IS A SEPARATE PRIVATE
 OPEN SPACE TYPE THAT MAY BE USED, BUT THE PLAN AND THE
 CHART MUST BE CONSISTENT.
  
 5. SATISFIED. SHOW LOCATIONS OF UTILITY LINES ON
 LANDSCAPE PLAN, ALSO LOCATIONS OF VALVES AND BACKFLOW
 PREVENTERS AND FPL TRANSFORMERS.
  
 6. SATISFIED. SHOW LOCATIONS OF ANY ROOT BARRIERS
 REQUIRED TO PROTECT UTILITY LINES.
  
 7. SATISFIED. SHOW COMPLIANCE WITH SECTION 94-445 L.
 PLANT SPECIES. A MINIMUM OF 60 PERCENT OF PLANT
 MATERIAL ADDED SHALL BE FLORIDA NATIVE OR DROUGHT
 TOLERANT SPECIES SELECTED FROM THE CITY LIST OR THE
 LIST OF SPECIES IN THE MOST RECENT EDITION OF SOUTH
 FLORIDA WATER MANAGEMENT DISTRICT WATERWISE SOUTH
 FLORIDA LANDSCAPES.
  
 PROVIDE THE ACTUAL PERCENTAGE CALCULATED FROM THE PLANT
 LIST FOR THE PROJECT. SEPARATE THE OFFSITE PARCEL.
  
 ADDITIONAL COMMENTS 4/22/20:
  
 8. SATISFIED. PROVIDE SEPARATE COLUMNS ON THE PLANT
 LIST FOR NATIVE AND DROUGHT TOLERANT CLASSIFICATIONS.
  
 9. SATISFIED. PROJECTS MUST BE SEPARATED FOR ALL
 LANDSCAPE REQUIREMENTS AND CALCULATIONS. THIS WOULD
 MEAN ALL FLORIDA FRIENDLY POINTS, ETC. MUST BE ON A
 SEPARATE SHEET FOR THE LANDSCAPING THAT IS FOR THE
 SEPARATE NORTH PARCEL.
  
 10. SATISFIED. EAST BUFFER HAS WIDE GAPS IN THE
 LANDSCAPING, A CONTINUOUS HEDGE NEEDS TO BE PROVIDED.
  
  
 CONDITIONS OF APPROVAL
 1. PRIOR TO THE REMOVAL OR RELOCATION OF ANY TREES ON
 THE PROPERTY, A TREE ALTERATION PERMIT SHALL BE
 SUBMITTED, REVIEWED AND APPROVED BY THE DEVELOPMENT
 SERVICES DEPARTMENT, PLANNING DIVISION.
 2. THE APPLICANT, SUCCESSORS AND ASSIGNS SHALL BE
 RESPONSIBLE FOR THE PERMITTING AND INSTALLATION OF THE
 STREET TREES AND RIGHT OF WAY LANDSCAPING AND
 IRRIGATION APPROVED WITH THIS PETITION.
 3. THE APPLICANT, SUCCESSORS AND ASSIGNS SHALL BE
 RESPONSIBLE FOR THE MAINTENANCE OF THE ROAD RIGHT OF
 WAY LANDSCAPING AND IRRIGATION. THIS WILL BE THROUGH A
 SEPARATE MAINTENANCE AGREEMENT WITH THE CITY.
  
  

Review Stop L LANDSCAPING
Rev No 2 Status F Date 04-23-2020 Cont ID  
Sent By rcaranci Date 04-23-2020 Time 15:53 Rev Time 0.00
Received By rcaranci Date 04-23-2020 Time 15:53 Sent To  
Notes
2020-04-23 15:53:35FROM: RAY CARANCI, LANDSCAPE PLANNER 561-822-1462
 PROJECT: 301 BANYAN Z19120009
 APRIL 22, 2020
 I HAVE REVIEWED THE ABOVE REFERENCED PETITION, AND
 PROVIDE THE FOLLOWING COMMENTS:
  
 1. MAKE THE FOLLOWING CORRECTIONS TO THE TREE
 DISPOSITION PLAN:
 ? PARTIALLY SATISFIED. TREES AND PALMS CANOPY SQUARE
 FOOTAGE TO BE MITIGATED BASED ON CATEGORY. MANGO AND
 SEA GRAPE ARE CATEGORY 1.
 CANOPY DIAMETER MAY CHANGE SOME SQUARE FOOTAGE.
 ? PARTIALLY SATISFIED. ANY TREES 20 FEET OR MORE CANOPY
 DIAMETER TO BE MITIGATED BY ACTUAL SQUARE FOOTAGE.
 CANOPY DIAMETER MUST BE PROVIDED FOR EACH TREE AND
 CALCULATIONS ARE ROUNDED UP TO THE NEXT FULL SQUARE
 FOOT.
 PROVIDE CANOPY DIAMETER FOR EACH TREE. CHANGE THE
 CANOPY (SQ-FT) COLUMN TO CANOPY DIAMETER. THIS NEEDS TO
 BE SHOWN TO DETERMINE CALCULATION OF MITIGATION SQUARE
 FOOTAGE BY CATEGORY OR ACTUAL SQUARE FOOTAGE. PALMS DO
 NOT NEED CANOPY DIAMETER, ONLY CATEGORY.
 ? PARTIALLY SATISFIED. PROVIDE THE TOTAL SQUARE FOOTAGE
 OF MITIGATION FOR ALL TREES AND PALMS PROPOSED TO BE
 REMOVED.
 ADJUST ALL MITIGATION FOR THE ABOVE COMMENTS AND
 PROVIDE NEW TOTAL.
 ? PARTIALLY SATISFIED. PROVIDE THE MITIGATION VALUES BY
 CATEGORY FOR THE PROPOSED TREES AND PALMS BASED ON
 CATEGORY AND PROVIDE THE TOTAL MITIGATION SQUARE
 FOOTAGE. THEN PROVIDE ANY OVERAGE OR DEFICIENCY SQUARE
 FOOTAGE.
 AFTER MITIGATION SQUARE FOOTAGE DUE IS RECALCULATED,
 UPDATE AND PROVIDE ONE TOTAL FOR DEFICIENCY, THEN
 CALCULATE PAYMENT IN LIEU.
 2. NOT SATISFIED. STAFF REQUESTS THAT A NARRATIVE BE
 ADDED THAT EXPLAINS THE REASON THE EXISTING BLACK OLIVE
 TREES IN THE RIGHT OF WAY CANNOT BE RETAINED. THERE IS
 A ZONING REVIEW COMMENT REGARDING THE SETBACK OF THE
 BUILDING THAT MAY POSITIVELY AFFECT THE TREES. ALSO
 EXPLAIN THE PROGRESSION OF THE BANYAN STREETSCAPE
 PROJECT DESIGN THAT WAS INTENDED TO PRESERVE THE
 EXISTING CANOPY TREES, AND WHAT THE REPLACEMENT TREE
 CANOPY WILL BE.
 BLACK OLIVE TREES WERE ORIGINALLY TO REMAIN IN PLACE
 FOR THE BANYAN STREETSCAPE PROJECT. DEVELOPMENT OF THE
 SITE AT THE CURRENT BUILDING SETBACK IS THE CAUSE TO
 REMOVE THE TREES AND REDESIGN THE BANYAN STREETSCAPE
 PROJECT TO ADJUST FOR THE BUILDING DEVELOPMENT. THE
 BUILDING SETBACK IS CURRENTLY BEING DISCUSSED AS PART
 OF THE ZONING REVIEW AND MAY CHANGE. PLEASE PROVIDE THE
 CORRECT NARRATIVE.
  
 3. SATISFIED. SHOW STREETSCAPE REQUIRED FOR TAMARIND
 AVE. ADJACENT TO THE PROPERTY. PER SECTION 94-113.
  
 4. PARTIALLY SATISFIED. QBD-3 ZONING WITH LOT SIZE LESS
 THAN 50,000 SQ FT REQUIRES 25% PRIVATE OPEN SPACE.
 SURVEY INDICATES 33279.7 SQ FT, 25% EQUALS 8319.925 SQ
 FT. ROUND TO 8320 SQ FT REQUIRED.
 PRIVATE OPEN SPACE AREAS SHOWN ON SHEET A-1.07 MUST BE
 BROKEN DOWN TO SHOW THE REQUIRED VEGETATED AREA AND ANY
 TREE CANOPY REQUIREMENT FOR EACH AREA AS THE ALLOWED
 OPEN SPACE TYPE PER TABLE IV-6, AND DEFINITIONS FOUND
 IN 94-109. TERRACE REQUIRES 20% MINIMUM VEGETATED AREA.
 ROOFTOP GARDEN REQUIRES 30% VEGETATED AREA AND 20% TREE
 CANOPY. TREE CANOPY VALUES CAN BE FOUND IN SECTION
 94-109 TABLE IV-8. THIS INFORMATION MUST BE REFLECTED
 ON THE LANDSCAPE PLAN.
 SHEET LP-1.02 NEEDS TO SHOW THE OPEN SPACE AREA
 MATCHING SHEET A-1.07 AND BE LABELED AS ROOFTOP GARDEN
 TO MATCH THE LANDSCAPE REQUIREMENTS CHART IF THE
 CALCULATIONS ARE CORRECT. TERRACE IS A SEPARATE PRIVATE
 OPEN SPACE TYPE THAT MAY BE USED, BUT THE PLAN AND THE
 CHART MUST BE CONSISTENT.
  
 5. SATISFIED. SHOW LOCATIONS OF UTILITY LINES ON
 LANDSCAPE PLAN, ALSO LOCATIONS OF VALVES AND BACKFLOW
 PREVENTERS AND FPL TRANSFORMERS.
  
 6. SATISFIED. SHOW LOCATIONS OF ANY ROOT BARRIERS
 REQUIRED TO PROTECT UTILITY LINES.
  
 7. PARTIALLY SATISFIED. SHOW COMPLIANCE WITH SECTION
 94-445 L. PLANT SPECIES. A MINIMUM OF 60 PERCENT OF
 PLANT MATERIAL ADDED SHALL BE FLORIDA NATIVE OR DROUGHT
 TOLERANT SPECIES SELECTED FROM THE CITY LIST OR THE
 LIST OF SPECIES IN THE MOST RECENT EDITION OF SOUTH
 FLORIDA WATER MANAGEMENT DISTRICT WATERWISE SOUTH
 FLORIDA LANDSCAPES.
  
 PROVIDE THE ACTUAL PERCENTAGE CALCULATED FROM THE PLANT
 LIST FOR THE PROJECT. SEPARATE THE OFFSITE PARCEL.
  
 ADDITIONAL COMMENTS 4/22/20:
  
 8. PROVIDE SEPARATE COLUMNS ON THE PLANT LIST FOR
 NATIVE AND DROUGHT TOLERANT CLASSIFICATIONS.
  
 9. PROJECTS MUST BE SEPARATED FOR ALL LANDSCAPE
 REQUIREMENTS AND CALCULATIONS. THIS WOULD MEAN ALL
 FLORIDA FRIENDLY POINTS, ETC. MUST BE ON A SEPARATE
 SHEET FOR THE LANDSCAPING THAT IS FOR THE SEPARATE
 NORTH PARCEL.
  
 10. EAST BUFFER HAS WIDE GAPS IN THE LANDSCAPING, A
 CONTINUOUS HEDGE NEEDS TO BE PROVIDED.
  
  
 CONDITIONS OF APPROVAL
 1. PRIOR TO THE REMOVAL OR RELOCATION OF ANY TREES ON
 THE PROPERTY, A TREE ALTERATION PERMIT SHALL BE
 SUBMITTED, REVIEWED AND APPROVED BY THE DEVELOPMENT
 SERVICES DEPARTMENT, PLANNING DIVISION.
 2. THE APPLICANT, SUCCESSORS AND ASSIGNS SHALL BE
 RESPONSIBLE FOR THE PERMITTING AND INSTALLATION OF THE
 STREET TREES AND RIGHT OF WAY LANDSCAPING AND
 IRRIGATION APPROVED WITH THIS PETITION.
 3. THE APPLICANT, SUCCESSORS AND ASSIGNS SHALL BE
 RESPONSIBLE FOR THE MAINTENANCE OF THE ROAD RIGHT OF
 WAY LANDSCAPING AND IRRIGATION. THIS WILL BE THROUGH A
 SEPARATE MAINTENANCE AGREEMENT WITH THE CITY.
  

Review Stop L LANDSCAPING
Rev No 1 Status F Date 01-06-2020 Cont ID  
Sent By rcaranci Date 01-06-2020 Time 15:07 Rev Time 0.00
Received By rcaranci Date 01-06-2020 Time 15:07 Sent To  
Notes
2020-01-06 15:07:41FROM: RAY CARANCI, LANDSCAPE PLANNER 561-822-1462
 PROJECT: 301 BANYAN Z19120009
 JANUARY 6, 2020
 I HAVE REVIEWED THE ABOVE REFERENCED PETITION, AND
 PROVIDE THE FOLLOWING COMMENTS:
  
 1. MAKE THE FOLLOWING CORRECTIONS TO THE TREE
 DISPOSITION PLAN:
 ? TREES AND PALMS CANOPY SQUARE FOOTAGE TO BE MITIGATED
 BASED ON CATEGORY. MANGO AND SEA GRAPE ARE CATEGORY 1.
 ? ANY TREES 20 FEET OR MORE CANOPY DIAMETER TO BE
 MITIGATED BY ACTUAL SQUARE FOOTAGE. CANOPY DIAMETER
 MUST BE PROVIDED FOR EACH TREE AND CALCULATIONS ARE
 ROUNDED UP TO THE NEXT FULL SQUARE FOOT.
 ? PROVIDE THE TOTAL SQUARE FOOTAGE OF MITIGATION FOR
 ALL TREES AND PALMS PROPOSED TO BE REMOVED.
 ? PROVIDE THE MITIGATION VALUES BY CATEGORY FOR THE
 PROPOSED TREES AND PALMS BASED ON CATEGORY AND PROVIDE
 THE TOTAL MITIGATION SQUARE FOOTAGE. THEN PROVIDE ANY
 OVERAGE OR DEFICIENCY SQUARE FOOTAGE.
  
 2. STAFF REQUESTS THAT A NARRATIVE BE ADDED THAT
 EXPLAINS THE REASON THE EXISTING BLACK OLIVE TREES IN
 THE RIGHT OF WAY CANNOT BE RETAINED. THERE IS A ZONING
 REVIEW COMMENT REGARDING THE SETBACK OF THE BUILDING
 THAT MAY POSITIVELY AFFECT THE TREES. ALSO EXPLAIN THE
 PROGRESSION OF THE BANYAN STREETSCAPE PROJECT DESIGN
 THAT WAS INTENDED TO PRESERVE THE EXISTING CANOPY
 TREES, AND WHAT THE REPLACEMENT TREE CANOPY WILL BE.
  
 3. SHOW STREETSCAPE REQUIRED FOR TAMARIND AVE. ADJACENT
 TO THE PROPERTY. PER SECTION 94-113.
  
 4. QBD-3 ZONING WITH LOT SIZE LESS THAN 50,000 SQ FT
 REQUIRES 25% PRIVATE OPEN SPACE. SURVEY INDICATES
 33279.7 SQ FT, 25% EQUALS 8319.925 SQ FT. ROUND TO 8320
 SQ FT REQUIRED.
 PRIVATE OPEN SPACE AREAS SHOWN ON SHEET A-1.07 MUST BE
 BROKEN DOWN TO SHOW THE REQUIRED VEGETATED AREA AND ANY
 TREE CANOPY REQUIREMENT FOR EACH AREA AS THE ALLOWED
 OPEN SPACE TYPE PER TABLE IV-6, AND DEFINITIONS FOUND
 IN 94-109. TERRACE REQUIRES 20% MINIMUM VEGETATED AREA.
 ROOFTOP GARDEN REQUIRES 30% VEGETATED AREA AND 20% TREE
 CANOPY. TREE CANOPY VALUES CAN BE FOUND IN SECTION
 94-109 TABLE IV-8. THIS INFORMATION MUST BE REFLECTED
 ON THE LANDSCAPE PLAN.
  
 5. SHOW LOCATIONS OF UTILITY LINES ON LANDSCAPE PLAN,
 ALSO LOCATIONS OF VALVES AND BACKFLOW PREVENTERS AND
 FPL TRANSFORMERS.
  
 6. SHOW LOCATIONS OF ANY ROOT BARRIERS REQUIRED TO
 PROTECT UTILITY LINES.
  
 7. SHOW COMPLIANCE WITH SECTION 94-445 L. PLANT
 SPECIES. A MINIMUM OF 60 PERCENT OF PLANT MATERIAL
 ADDED SHALL BE FLORIDA NATIVE OR DROUGHT TOLERANT
 SPECIES SELECTED FROM THE CITY LIST OR THE LIST OF
 SPECIES IN THE MOST RECENT EDITION OF SOUTH FLORIDA
 WATER MANAGEMENT DISTRICT WATERWISE SOUTH FLORIDA
 LANDSCAPES.
  
  
 CONDITIONS OF APPROVAL
 1. PRIOR TO THE REMOVAL OR RELOCATION OF ANY TREES ON
 THE PROPERTY, A TREE ALTERATION PERMIT SHALL BE
 SUBMITTED, REVIEWED AND APPROVED BY THE DEVELOPMENT
 SERVICES DEPARTMENT, PLANNING DIVISION.
 2. THE APPLICANT, SUCCESSORS AND ASSIGNS SHALL BE
 RESPONSIBLE FOR THE PERMITTING AND INSTALLATION OF THE
 STREET TREES AND RIGHT OF WAY LANDSCAPING AND
 IRRIGATION APPROVED WITH THIS PETITION.
 3. THE APPLICANT, SUCCESSORS AND ASSIGNS SHALL BE
 RESPONSIBLE FOR THE MAINTENANCE OF THE ROAD RIGHT OF
 WAY LANDSCAPING AND IRRIGATION. THIS WILL BE THROUGH A
 SEPARATE MAINTENANCE AGREEMENT WITH THE CITY.
  

Review Stop PARK PARKING
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop POLICE POLICE
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop PW PUBLIC WORKS
Rev No 3 Status P Date 06-16-2020 Cont ID  
Sent By   Date 06-16-2020 Time   Rev Time 0.00
Received By   Date 06-16-2020 Time   Sent To  
Notes
2020-06-16 16:31:54NO FURTHER COMMENTS FROM PUBLIC WORKS.
  
 MATT HEJAZI
 DEPT. OF PUBLIC WORKS
 [email protected]

Review Stop PW PUBLIC WORKS
Rev No 2 Status F Date 05-11-2020 Cont ID  
Sent By   Date 05-11-2020 Time   Rev Time 0.00
Received By   Date 05-11-2020 Time   Sent To  
Notes
2020-05-11 14:20:18PLEASE PROVIDE THE FOLLOWINGS:
  
 1- LEVEL OF SERVICE (LOS) ANALYSIS FOR SOLID WASTE
 GENERATION
 2- TRASH ROOM SPECIFICATIONS (I.E. DOOR HEIGHT, WIDTH,
 FLOOR, ETC.)
 3- COMPACTOR TYPE, SIZE
  
 MATT HEJAZI
 DEPT. OF PUBLIC WORKS
 [email protected]
 561-822-2045

Review Stop PW PUBLIC WORKS
Rev No 1 Status F Date 01-03-2021 Cont ID  
Sent By   Date 01-03-2020 Time   Rev Time  
Received By   Date 01-03-2021 Time   Sent To  
Notes
2020-01-03 15:38:43PLEASE PROVIDE THE FOLLOWINGS:
 1- LOS (LEVEL OF SERVICE ANALYSIS) TO REFLECT THE SOLID
 WASTE VOLUME PRODUCED ALONG WITH THE SIZE AND TYPE OF
 THE CONTAINER (I.E. DUMPSTER/COMPACTOR) THAT WILL BE
 UTILIZED THAT WILL BE UTILIZED FOR THE SANITATION
 SERVICE.
 2- TRASH ROOM SPECIFICATIONS (I.E. DIMENSIONS, OPENING
 CLEARANCE, FLOOR MATERIAL ETC.)
 3- AUTO TURN FOR THE SANITATION SERVICE, FRONT LOADER
 TRUCK
 - TRUCK LENGTH: 35 FT
 - TRUCK WIDTH: 11 FT
 - TURNING RADIUS:
 - SAE TURNING RADIUS: 32.5 FT
 - CURB-TO-CURB DIAMETER: 74 FT
 - WALL-TO-WALL DIAMETER: 86.3 FT
  
  
 MATT HEJAZI
 DEPT. OF PUBLIC WORKS
 [email protected]
 561-822-2045
  

Review Stop STORM STORMWATER
Rev No 3 Status P Date 06-23-2020 Cont ID  
Sent By tward Date 06-23-2020 Time 15:18 Rev Time 0.00
Received By tward Date 06-23-2020 Time 15:39 Sent To  
Notes
2020-06-23 15:39:11THE FOLLOWING COMMENTS ARE FROM THE REVIEW OF THE
 6/19/2020 CIVIL PLANS AND CAN BE ADDRESSED DURING
 ENGINEERING PERMIT SUBMITTAL.
  
 1. VERIFY THERE WILL BE SUFFICIENT VERTICAL CLEARANCE
 BETWEEN THE BOTTOM OF THE TOP SLAB OF THE CONTROL
 STRUCTURE MANHOLES AND THE TOP OF THE WEIRS. MANHOLES
 SHOULD BE FLUSH WITH THE SURROUNDING AREA.
  
 2. ALL OF THE DRAINAGE STRUCTURES ON THE NORTH SIDE OF
 BANYAN BLVD. SHOULD BE LABELED "... TO BE INSTALLED IN
 WPB PROJECT ...".
  
 3. LABEL THE PIPE SIZES, MATERIAL AND INVERTS OF THE
 STORM PIPES BETWEEN THE CONTROL STRUCTURES AND DRAINAGE
 STRUCTURES ON BANYAN BLVD. MINIMUM 15" RCP.
  
 4. PROVIDE THE DESIGN INFORMATION FOR THE STRUCTURES ON
 BANYAN BLVD. PROVIDE A REFERENCE TO WHERE THE
 INFORMATION CAME FROM.
  
 5. ON THE CROSS SECTIONS, SHOW THE LANDSCAPE AREAS WITH
 SWALE (DEPRESSION) SECTION. THE ONSITE AREAS SHOULD NOT
 DRAIN DIRECTLY TO ADJACENT PROPERTIES.
  
 6. THE PIPE FOR THE WEST EXFILTRATION TRENCH DOES NOT
 APPEAR TO BE CENTERED IN THE TRENCH. THE EXFILTRATION
 TRENCH IS TO BE COMPLETELY LOCATED WITHIN THE PROPERTY.
  
 7. PROVIDE DETAILS FOR EXFILTRATION TRENCH, PRB,
 CONTROL STRUCTURES, ETC.
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 [email protected]
 561-494-1120 (O)
 561-351-0510 (M)

Review Stop STORM STORMWATER
Rev No 2 Status F Date 04-15-2020 Cont ID  
Sent By tward Date 04-15-2020 Time 11:41 Rev Time 0.00
Received By tward Date 04-15-2020 Time 15:54 Sent To  
Notes
2020-04-15 15:54:28THE FOLLOWING COMMENTS ARE FROM THE REVIEW OF THE
 4/10/2020 SUBMITTAL PACKAGE.
  
 1. THIS REVIEW DOES NOT INCLUDE THE PROPOSED
 IMPROVEMENTS ON THE CRA PROPERTY. PROVIDE A SEPARATE
 SET OF PLANS.
  
 2. PROVDE A MAP LABELING THE PIPES AND STRUCTURE
 NUMBERS USED IN THE CCTV VIDEOS/REPORTS.
  
 3. THE DRAINAGE SYSTEM ON THE EAST SIDE OF THE PROPERTY
 IS PROPOSING TO CONNECT TO AN INLET THAT IS BEING
 INSTALLED AS PART OF THE BANYAN BLVD IMPROVEMENT
 PROJECT. IF THIS PROJECT DOES NOT PROCEED, YOU WILL
 NEED TO REVISE WHERE THE DRAINAGE SYSTEM WILL CONNECT
 TO THE MS4, WHICH MAY REQUIRE INSTALLING A MANHOLE
 DIRECTLY SOUTH ON THE STORM MAIN. CHANGE THE MANHOLE IN
 THE RIGHT OF WAY WITHIN THE BIKE LANE ON THE SOUTHEAST
 SIDE OF THE BUILDING TO A CATCH BASIN INLET TO BE
 LOCATED COMPLETELY OUTSIDE THE BIKE LAKE. ANY REASON
 WHY THIS CATCH BASIN INLET CANNOT CONNECT TO THE ONSITE
 MANHOLE INSTEAD OF THE ONSITE CATCH BASIN?
  
 4R. PROVIDE CROSS SECTIONS FOR ALL FOR SIDES OF THE
 BUILDING EXTENDING FROM THE FACE OF THE BUILDING TO
 ROADWAY CENTERLINES AND PROPERTY LINES. THERE SHOULD
 NOT BE FLOW ONTO ADJACENT PROPERTIES.
  
 5. ON THE SITE PLAN, SHEET SP-1, PROPERLY SHOW THE
 ALLEY AND 20 FT ROW NORTH OF THE SITE AS PRIVATE
 PARCELS.
  
 6. MOVE THE FH IN THE SOUTHWEST CORNER OF THE SITE INTO
 THE RIGHT-OF-WAY.
  
 TRACY WARD, P.E.
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 [email protected]
 561-494-1120

Review Stop STORM STORMWATER
Rev No 1 Status F Date 01-08-2020 Cont ID  
Sent By tward Date 01-08-2020 Time 11:29 Rev Time 0.00
Received By tward Date 01-08-2020 Time 11:30 Sent To  
Notes
2020-01-08 11:30:51THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL
 DETAILS, DESIGN CALCULATIONS AND THE POLLUTION
 PREVENTION PLAN WILL BE REVIEWED AS PART OF THE
 ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT
 APPLICATION PROCESSES. THE ENGINEERING DEVELOPMENT
 APPROVAL APPLICATION FORMS CAN BE DOWNLOADED AT
 HTTPS://WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FO
 RMS,-PERMITS-APPLICATIONS
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE
 PLAN APPROVAL:
  
 1. ALL PLANS AND SURVEYS SHOULD USE THE SAME VERTICAL
 DATUM. THE CITY'S VERTICAL DATUM IS NGVD 1929. THE CITY
 HAS ALLOWED THE USE OF NAVD1988 AS LONG AS THE
 CONVERSION EQUATION TO NGVD1929 IS PROVIDED. THE
 VERTICAL DATUM AND CONVERSION EQUATION TO NGVD1929
 SHOULD BE LISTED ON EVERY PLAN SHEET WITH ELEVATION
 INFORMATION.
  
 2. ROOF DRAINAGE NEEDS TO BE CONNECTED TO THE ONSITE
 STORMWATER MANAGEMENT SYSTEM.
  
 3. CONSIDER OTHER LOW IMPACT DEVELOPMENT (LID) BEST
 MANAGEMENT PRACTICES BESIDES EXFILTRATION TRENCHES FOR
 STORMWATER TREATMENT.
 4. STORMWATER MANAGEMENT SYSTEM TO BE DESIGNED TO MEET
 SFWMD CRITERIA FOR WATER QUALITY TREATMENT AND PEAK
 FLOW ATTENUATION.
  
 5. SITE DATA ON SHEET C-1 DOES NOT MATCH WHAT IS LISTED
 ON SHEET SP-1.
  
 6. ON SHEET C-1 IDENTIFY THROUGH HATCHING OR SHADING
 WHERE THE 29,318 S.F. OF PERVIOUS SPACE IS LOCATED ON
 THE 33,280 S.F PARCEL.
  
 7. IT APPEARS THE DRIVEWAY ON BANYAN STREET MAY AFFECT
 A LIGHT POLE.
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO
 ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING
 BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL.
  
 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION MAY
 BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT.
 THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS
 CAN BE DOWNLOADED AT: HTTP://WPB.ORG/DEPARTMENTS/ENGINE
 ERING-PUBLIC-WORKS/FORMS,-PERMITS-APPLICATIONS
  
 2. EROSION CONTROL PLAN AND DETAILS TO BE SUBMITTED
 WITH THE ENGINEERING PERMIT APPLICATION.
  
 3. PROVIDE A COPY OF THE SFWMD ERP PRIOR TO STARTING
 CONSTRUCTION.
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120
 [email protected]
  
  

Review Stop SURVEY SURVEYING
Rev No 2 Status F Date 04-27-2020 Cont ID  
Sent By vnoel Date 04-27-2020 Time 15:30 Rev Time 0.00
Received By vnoel Date   Time   Sent To  
Notes
2020-04-27 15:30:341. APPLICATION FOR MINOR SUBDIVISION (PLAT) WILL NEED
 TO BE SUBMITTED.
 2. PRELIMINARY APPROVAL FOR WATER LINE CONNECTIONS INTO
 THE ALLEY PROPERTY IS GRANTED CONTINGENT ON RECEIPT OF
 PROFILE SHOWING CLEARANCE FROM ALL UTILITIES.
 3. GRAVITY SANITARY SEWER LINE WILL, AT THE LEAST, NEED
 TO BE LINED. SANITARY O & M IS REVIEWING.
 4. IMPROVEMENTS FOR THE LINEAR PARK SHOULD BE A
 SEPARATE PROJECT. THE PROPOSED DRAINAGE, IF ANY, WILL
 BE REVIEWED BASED ON PROPOSED IMPROVEMENTS AND CRA
 APPROVAL.

Review Stop SURVEY SURVEYING
Rev No 1 Status F Date 01-06-2020 Cont ID  
Sent By vnoel Date 01-06-2020 Time 11:02 Rev Time  
Received By vnoel Date   Time   Sent To  
Notes
2020-01-06 11:02:441. REPLAT WILL BE REQUIRED.
 2. VERTICAL DATUM ON SURVEY IS NGVD-29, ENG. PLAN CALLS
 OUT AS NAVD 88.
 3. SITE PLAN SHOWS A POSSIBLE DRAINAGE LINE INSIDE
 NORTH PROPERTY LINE. IS THIS PROPOSED OR EXISTING?
 4. IF APPROVED, HORIZONTAL PROJECTION ARCHITECTURAL
 FEATURE WILL REQUIRE AN AERIAL ENCROACHMENT EASEMENT.

Review Stop TRAFFIC TRAFFIC ENGINEERING
Rev No 4 Status P Date 07-13-2020 Cont ID  
Sent By   Date 07-13-2020 Time   Rev Time 0.00
Received By   Date 06-30-2020 Time   Sent To  
Notes
2020-07-13 17:10:52PASSED WITH THE FOLLOWING CONDITIONS.
  
 PROVIDE PROPER AUTOTURN ANALYSIS, SPECIFICALLY:
  
 1) GROUND FLOOR SERVICE TRUCK:
 A. COLORED PATH FOR VEHICLE DYNAMIC ENVELOPE AND WHEELS
 PATHS
 B. SEPARATE DRAWINGS FOR VEHICLE ENTERING AND DOCKING,
 AND VEHICLE MOVING OUT OF THE DOCK AND EXITING
  
 2) 2ND FLOOR PARKING: SHOWCASE A VEHICLE REACHING THE
 DEAD-END AND MANEUVER OUT OF IT
  
  
 VALERIO ORICCHIO
 CITY TRANSPORTATION ENGINEER, PE, PTOE
 561-494-1092
 [email protected]

Review Stop TRAFFIC TRAFFIC ENGINEERING
Rev No 3 Status F Date 06-19-2020 Cont ID  
Sent By   Date   Time   Rev Time 0.00
Received By   Date 06-03-2020 Time   Sent To  
Notes
2020-06-19 17:58:40UPDATED ON 6/22/2020
  
 TRAFFIC STUDY COMMENTS:
 1. THE HCS ANALYSES SHOWCASE LEVEL OF SERVICE ?F? FOR
 THE BANYAN/TAMARIND INTERSECTION AND SIGNIFICANT QUEUE
 LENGTHS IN THE EB AND WB, FOR THE AM AND PM PERIOD,
 RESPECTIVELY. DUE TO SUCH CONDITIONS AT BUILDOUT YEAR,
 SIGNIFICANT MITIGATION MEASURES ARE REQUIRED.
 2. PROVIDE THE FOLLOWING TRANSPORTATION DEMAND
 MANAGEMENT (TDM) MEASURES, INCLUSIVE OF DETAILED
 IMPLEMENTATION PLANS, AND PROVIDE YEARLY STATISTICS OF
 TDM UTILIZATION SUMMARY TO THE CITY TO ENCOURAGE
 MULTI-MODAL TRANSPORTATION, SPECIFICALLY:
 A. REDUCE THE PROPOSED NUMBER OF PARKING SPACES ?
 LATEST RESUBMITTAL ONLY SHOWS A REDUCTION OF 2 PARKING
 SPACES (FROM 81 TO 79). FURTHER REDUCTION IS REQUIRED
 OR JUSTIFICATION FOR THE PROPOSED HIGH NUMBER OF EXTRA
 SPACES
 B. PROPOSE AND PROVIDE TRANSIT SUBSIDIES TO RESIDENTS -
 PLEASE PROVIDE A STATEMENT OR ACKNOWLEDGMENT
  
 SITE PLAN COMMENTS:
 3. PER THE TRAFFIC STUDY, THE TRAFFIC CONDITIONS NEAR
 THE SITE ARE EXPECTED TO SIGNIFICANTLY IMPACT VEHICULAR
 ACCESS. THE WESTBOUND QUEUE AT BANYAN/TAMARIND IS
 EXPECTED TO BE OVER 2,000 FEET DURING WEEKDAY PM PEAK
 HOUR. INBOUND AND OUTBOUND LEFT-TURNING VEHICLES COULD
 RESULT IN POTENTIAL SAFETY CONCERN TO ROAD USERS. A
 MEDIAN ISLAND IS BEING CONSIDERED AS PART OF THE BANYAN
 BOULEVARD IMPROVEMENT.
 A. PLEASE COORDINATE WITH THE WGI TEAM WORKING ON
 BANYAN BLVD IMPROVEMENTS AND INCORPORATE THEIR MEDIAN
 ISLAND DESIGN IN THE SITE PLAN
 4. THE DEVELOPMENT IS PROPOSING 79 PARKING SPACES,
 WHICH IS 37 SPACES OVER THE MINIMUM REQUIREMENT OF 42.
 PROVIDING EXCESS PARKING SPACES IS LIKELY TO INDUCE
 EXTRA VEHICULAR TRIPS. IT IS RECOMMENDED THAT A
 FLEXIBLE PARKING ARRANGEMENT BE MADE, SPECIFICALLY: THE
 2ND FLOOR COULD BE CONVERTED TO ANOTHER USE IN THE
 FUTURE, WHILE IN THE MEANTIME THE 1ST FLOOR COULD BE
 LEASED OUT AS PUBLIC PARKING FOR TRI-RAIL PASSENGERS,
 WITH REVENUE SHARING WITH THE CITY TO SUPPORT THE
 CITY?S TRANSIT OPERATION FUND. MOREOVER, AS THIS IS A
 TAX CREDIT AFFORDABLE HOUSING AND ALSO A MICRO UNIT
 PROJECT, THE AMOUNT OF VEHICLE USE WILL BE MUCH LOWER
 THAN A TYPICAL RESIDENTIAL PROJECT. PLEASE PROVIDE
 DETAILED JUSTIFICATION TO THE EXCESSIVE NUMBER OF
 PARKING SPACES.
 5. PROVIDE PATHS FOR TRUCKS EXITING THE LOADING ZONE
 ONTO BANYAN BOULEVARD ? TRUCK AUTOTURN ANALYSIS FOR THE
 LOADING ZONE IN THE ARCHITECTURAL PLANS SHOWCASES
 VEHICLE EXITING INTO BANYAN BLVD IN A BACKWARD FASHION.
 PLEASE CLARIFY AND/OR REVISE.
 6. PROVIDE SIDEWALK EASEMENT FOR THE PORTION OF
 PUBLICLY ACCESSIBLE SIDEWALK AND PATHWAYS WITHIN THE
 PROPERTY RIGHT-OF-WAY.
 7. PROVIDE AUTOTURN ANALYSIS FOR THE TANDEM PARKING
 SPACES ON THE 2ND FLOOR NEARBY THE RAMP
  
  
 VALERIO ORICCHIO
 CITY TRANSPORTATION ENGINEER, PE, PTOE
 561-494-1092
 [email protected]

Review Stop TRAFFIC TRAFFIC ENGINEERING
Rev No 2 Status F Date   Cont ID  
Sent By   Date 04-28-2020 Time   Rev Time 0.00
Received By   Date   Time   Sent To  
Notes
2020-04-28 09:12:09TRAFFIC STUDY COMMENTS:
 1. PROVIDE QUEUEING ANALYSIS FOR THE GATED ENTRY.
 2. THE HCS ANALYSES SHOWCASE LEVEL OF SERVICE "F" FOR
 THE BANYAN/TAMARIND INTERSECTION AND SIGNIFICANT QUEUE
 LENGTHS IN THE EB AND WB, FOR THE AM AND PM PERIOD,
 RESPECTIVELY. DUE TO SUCH CONDITIONS AT BUILDOUT YEAR,
 SIGNIFICANT MITIGATION MEASURES ARE REQUIRED.
 3. PROVIDE THE FOLLOWING TRANSPORTATION DEMAND
 MANAGEMENT (TDM) MEASURES, INCLUSIVE OF DETAILED
 IMPLEMENTATION PLANS, AND PROVIDE YEARLY STATISTICS OF
 TDM UTILIZATION SUMMARY TO THE CITY TO ENCOURAGE
 MULTI-MODAL TRANSPORTATION, SPECIFICALLY:
 A. UNBUNDLE PARKING SPACES FROM THE RESIDENTIAL LEASE
 B. REDUCE THE PROPOSED NUMBER OF PARKING SPACES
 C. PROPOSE AND PROVIDE TRANSIT SUBSIDIES TO RESIDENTS
 D. PROVIDE MICROMOBILITY STATION ACCESSIBLE BY THE
 PUBLIC
 E. CONTRIBUTE FUNDING TOWARDS THE CITY'S TRANSIT
 OPERATIONS FUND
  
  
 SITE PLAN COMMENTS:
 4. PER THE TRAFFIC STUDY, THE TRAFFIC CONDITIONS NEAR
 THE SITE ARE EXPECTED TO SIGNIFICANTLY IMPACT VEHICULAR
 ACCESS. THE WESTBOUND QUEUE AT BANYAN/TAMARIND IS
 EXPECTED TO BE OVER 2,000 FEET DURING WEEKDAY PM PEAK
 HOUR. INBOUND AND OUTBOUND LEFT-TURNING VEHICLES COULD
 RESULT IN POTENTIAL SAFETY CONCERN TO ROAD USERS. A
 MEDIAN ISLAND IS BEING CONSIDERED AS PART OF THE BANYAN
 BOULEVARD IMPROVEMENT.
 5. PROVIDE ADDITIONAL BIKE RACKS NEAR THE CORNER OF
 TAMARIND/BANYAN.
 6. A TURNAROUND SPACE AND BACK UP AREA AT THE DEAD-END
 AISLE IS REQUIRED ON THE FIRST AND SECOND FLOOR PARKING
 GARAGE. PER CITY CODE, A MINIMUM THREE-FOOT BACK UP
 AREA SHALL BE PROVIDED AT THE TERMINUS OF ANY DEAD-END
 DRIVE AISLE TO ALLOW FOR VEHICLES TO SAFELY PULL OUT OF
 THE END PARKING SPACES. IN ADDITION, THE EQUIVALENT OF
 ONE PARKING SPACE AT THE TERMINUS OF A DEAD-END AISLE
 SHALL BE STRIPED AS A DEDICATED PULL-IN AREA FOR
 TURNING AROUND.
 7. PROVIDE AUTOTURN FOR THE DEAD-END TURNAROUND AREA
 AND THE SET OF TANDEM SPACES ON THE SECOND FLOOR OF THE
 GARAGE WITHIN THE RAMP LOOP.
 8. THE DEVELOPMENT IS PROPOSING 81 PARKING SPACES,
 WHICH IS 43 SPACES OVER THE MINIMUM REQUIREMENT OF 38.
 THAT IS A 113% SURPLUS. PROVIDING EXCESS PARKING SPACES
 IS LIKELY TO INDUCE EXTRA VEHICULAR TRIPS. IT IS
 RECOMMENDED THAT A FLEXIBLE PARKING ARRANGEMENT BE
 MADE, SPECIFICALLY: THE 2ND FLOOR COULD BE CONVERTED TO
 ANOTHER USE IN THE FUTURE, WHILE IN THE MEANTIME THE
 1ST FLOOR COULD BE LEASED OUT AS PUBLIC PARKING FOR
 TRI-RAIL PASSENGERS, WITH REVENUE SHARING WITH THE CITY
 TO SUPPORT THE CITY'S TRANSIT OPERATION FUND. MOREOVER,
 AS THIS IS A TAX CREDIT AFFORDABLE HOUSING AND ALSO A
 MICRO UNIT PROJECT, THE AMOUNT OF VEHICLE USE WILL BE
 MUCH LOWER THAN A TYPICAL RESIDENTIAL PROJECT. PLEASE
 PROVIDE DETAILED JUSTIFICATION TO THE EXCESSIVE NUMBER
 OF PARKING SPACES.
 9. PROVIDE PATHS FOR TRUCKS EXITING THE LOADING ZONE
 ONTO BANYAN BOULEVARD.
 10. PROVIDE SIDEWALK EASEMENT FOR THE PORTION OF
 PUBLICLY ACCESSIBLE SIDEWALK AND PATHWAYS WITHIN THE
 PROPERTY RIGHT-OF-WAY.
 11. PROVIDE PHOTOMETRIC ANALYSIS.
 12. CLARIFY GARBAGE PICK-UP OPERATIONS.
 13. PROVIDE LOCATION OF THE EXISTING PALM TRAN SHELTER
 ON THE SITE PLAN
  
 SHING TSOI
 CITY IN-HOUSE TRAFFIC CONSULTANT
 561-494-1141
 [email protected]
 TUESDAYS TO THURSDAYS)

Review Stop TRAFFIC TRAFFIC ENGINEERING
Rev No 1 Status F Date   Cont ID  
Sent By   Date 01-08-2020 Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
2020-01-08 16:32:03TRAFFIC STATEMENT COMMENTS:
 1. PROVIDE THE COUNTY TPS LETTER.
 2. PLEASE INCLUDE THE RETAIL IN THE TRIP GENERATION
 ESTIMATES.
 3. PROVIDE INTERSECTION ANALYSIST AT TAMARIND/BANYAN.
 SITE PLAN COMMENTS:
 4. THE DEVELOPMENT IS OVER PARKED BY 52 PARKING SPACES
 OVER THE 38 REQUIRED PARKING SPACES. PROVIDING EXCESS
 PARKING SPACES IS LIKELY TO INDUCE EXTRA VEHICULAR
 TRIPS. IT IS RECOMMENDED THAT THE FLEXIBLE PARKING
 ARRANGEMENT BE MADE. THE 2ND FLOOR COULD BE CONVERTED
 TO ANOTHER USE IN THE FUTURE, WHILE IN THE MEANTIME THE
 1ST FLOOR COULD BE LEASED OUT AS PUBLIC PARKING FOR
 TRI-RAIL PASSENGERS, WITH REVENUE SHARING WITH THE CITY
 TO SUPPORT THE CITY'S TRANSIT OPERATION FUND.
 5. PLEASE CLARIFY THE OPERATION OF THE LOADING AREA.
 THE CITY CODE PROHIBIT BACKING IN AND OUT OF CITY
 STREETS.
 6. THE ACCESS FOR LOADING ON BANYAN BOULEVARD SHOULD BE
 REMOVED, AND A SECONDARY ACCESS SHOULD BE PROVIDED ON A
 VEHICULAR CONNECTION ALONG THE EASTERN FRONTAGE, WHICH
 COULD ALSO BE USED FOR LOADING ACCESS.
 7. PLEASE CONSTRUCT THE TRAIL ALONG THE NORTHERN
 PROPERTY FRONTAGE AS PART OF CITY'S RAIL TO TRAIL
 PROJECT IN THE CITY'S MOBILITY PLAN TO SUPPORT
 MULTIMODAL TRANSPORTATION.
 8. WIDEN THE SIDEWALK ON TAMARIND AVENUE AND SIDEWALK
 SHOULD MAINTAIN THE SAME LEVEL ACROSS THE DRIVEWAYS.
 9. TANDEM PARKING SPACES ARE PROPOSED. WOULD THERE BE
 ASSIGNED PARKING?
 10. A TURNAROUND SPACE AT THE DEAD-END AISLE IS
 REQUIRED ON THE SECOND FLOOR PARKING GARAGE.
 11. PROPOSED TDM MEASURES TO ENCOURAGE MULTI-MODAL
 TRANSPORTATION.
  
 SHING TSOI
 CITY IN-HOUSE TRAFFIC CONSULTANT
 561-494-1141
 [email protected]
 (IN-HOUSE ON TUESDAYS AND WEDNESDAYS)
  

Review Stop Z ZONING
Rev No 3 Status P Date 06-16-2020 Cont ID  
Sent By elevesqu Date 06-16-2020 Time 16:34 Rev Time 0.00
Received By elevesqu Date 06-16-2020 Time 16:33 Sent To  
Notes
2020-06-16 16:34:12CONDITIONS OF APPROVAL:
  
 1. A RESTRICTIVE COVENANT AND DEVELOPMENT AGREEMENT
 SHALL BE PROCESSED BY THE CITY AND SIGNED BY THE CITY
 AND DEVELOPER FOR THE UTILIZATION OF CITY OWNED TDRS
 FOR THE AFFORDABLE HOUSING
 2. PLEASE ENSURE THAT THE LATEST BANYAN BOULEVARD
 STREETSCAPE DESIGN IS INCORPORATED INTO THE SITE PLAN
 AS THE REVIEW PROGRESSES.
 3. ANY MODIFICATIONS TO THE INTERNAL LAYOUT OF THE
 FLOOR PLAN MAY REQUIRE UPDATED GBA AND FAR DIAGRAMS
 WITH BUILDING PERMITS TO ENSURE REQUIREMENTS ARE NOT
 EXCEEDED.
 4. A RESTRICTIVE COVENANT SHALL BE RECORDED ON CITY
 APPROVED FORMS, AND RECORDED IN THE PUBLIC RECORDS FOR
 THE UTILIZATION OF TANDEM PARKING SPACES INDICATING
 THAT THEY ARE RESERVED FOR THE SAME UNIT.
 5. NEAR TIME OF CO, STAFF CAN DETERMINE THE APPROPRIATE
 AMOUNT OF PARKING SPACES TO BE DEDICATED FOR CAR
 SHARING SPACES BASED ON CURRENT MARKET AND NEED. FIVE
 SPACES ARE SHOWN FOR NOW AND SHALL REMAIN THROUGHOUT
 PERMIT PROCESS.
 6. THE MOST APPROPRIATE LOCATION FOR PUBLIC BIKE RACKS
 TO BE DETERMINED THROUGH SITE PLAN APPROVAL OR BUILDING
 PERMIT.
 7. EXACT PLACEMENT OF INTERIOR BICYCLE RACKS TO BE
 DETERMINED THROUGH BUILDING PERMIT PROCESS, MUST MAKE
 SURE THEY FIT. CORRECT NUMBER OF RACKS SHALL BE
 INCLUDED AND INSPECTED PRIOR TO CO.
 8. ALL ABOVE GROUND UTILITIES SHALL BE UNDERGROUNDED.
 THE LINE AND POLES THAT ARE IN CLOSE PROXIMITY TO THE
 NORTH PROPERTY LINE SHALL BE REMOVED IF POSSIBLE.
 9. ALL ROOF MOUNTED MECHANICAL EQUIPMENT SHALL BE
 SCREENED TO THE HEIGHT OF THE EQUIPMENT. ALL WALL
 MOUNTED MECHANICAL EQUIPMENT SHALL BE PAINTED TO MATCH
 COLOR OF ADJACENT BUILDING FA?ADE.
 10. ALL FDC SHALL BE WALL MOUNTED SUBJECT FIRE
 DEPARTMENT APPROVAL. IF GROUND MOUNTED, SHALL BE
 PAINTED TO MATCH SURROUNDING LANDSCAPING IF POSSIBLE.
 ALL GROUND MOUNTED EQUIPMENT SHALL BE PAINTED TO MATCH
 SURROUNDING LANDSCAPE IF POSSIBLE AND SHALL BE SCREENED
 BY LANDSCAPING.
 11. FINAL LOCATION OF BACKFLOW PREVENTER AND WATER
 METER SUBJECT TO CITY ENGINEERING REVIEW AND APPROVAL,
 WITH ZONING REVIEW AS WELL. ALL GROUND MOUNTED
 UTILITIES SHALL BE SCREENED BY LANDSCAPING TO THE
 FULLEST EXTENT POSSIBLE.
 12. PHOTOMETRIC PLANS AND LOCATION OF PROPOSED LIGHT
 POLES ON THE ROW TO BE REVIEWED THROUGH SEPARATE
 ELECTRICAL PERMIT.
 13. A MAINTENANCE AGREEMENT BETWEEN THE DEVELOPER AND
 CITY SHALL BE REQUIRED FOR THE PROJECT PER SECTION
 94-113(7) WITHIN 30 DAYS OF CO.
 14. IF THE BANYAN BOULEVARD STREETSCAPE DOES NOT MOVE
 FORWARD, THE DEVELOPER SHALL BE RESPONSIBLE FOR
 INSTALLATION OF IMPROVEMENTS ALONG BANYAN BOULEVARD
 15. THE SIDEWALK AND BICYCLE LANE SHALL BE KEPT LEVEL
 AT THE DRIVEWAY ENTRANCE TO THE PROJECT.
 16. THE PEDESTRIAN PASSAGEWAY DESIGN SHALL INCORPORATE
 A HIGHER VARIETY OF NATIVE LANDSCAPE, AND THE
 INCORPORATION OF HARDSCAPE VARIETY SHALL BE REVIEWED.
 SEATING SHALL BE PROVIDED WHERE POSSIBLE. THE LANDSCAPE
 SHALL BE DESIGNED ON BOTH SIDES OF THE PASSAGEWAY IN AN
 EFFORT TO SCREEN BOTH THE ADJACENT FEDERAL PARKING LOT
 AND CHAIN LINK FENCE, AND SCREEN THE PROJECT?S PARKING
 GARAGE AND RAMP. THE EXFILTRATION TRENCH SHALL BE
 COORDINATED TO ALLOW FOR LANDSCAPE.
 17. THE PEDESTRIAN PASSAGEWAY SHALL REQUIRE A PERPETUAL
 PEDESTRIAN ACCESS AGREEMENT AND MAINTENANCE OF THE
 PRIVATE EXFILTRATION TRENCH AND PASSAGEWAY SHALL BE THE
 RESPONSIBILITY OF THE DEVELOPER
 18. THE AMOUNT OF OPENINGS ALONG THE NORTH FA?ADE SHALL
 BE COORDINATED AT TIME OF BUILDING PERMIT WITH THE
 BUILDING DIVISION.
 19. THE EXACT LOCATION OF THE UPGRADED AND ENHANCED BUS
 SHELTER SHALL BE DETERMINED PRIOR TO CO. THE BUS
 SHELTER CANNOT BE IN CENTER OF SIDEWALK AS PROPOSED IN
 BANYAN BOULEVARD STREETSCAPE REDESIGN. THE APPLICANT
 SHALL WORK WITH CITY STAFF (VLAD) TO FIND APPROPRIATE
 LOCATION TO FIT A SHELTER. AN ADDITIONAL BICYCLE RACK
 WILL BE REQUIRED ADJACENT TO BUS SHELTER.
 20. PUBLIC ACCESS SHALL BE MAINTAINED TO THE RETAIL
 PARKING SPACES
 21. THE MICROMOBILITY STATION SHALL BE RELOCATED TO
 WITHIN THE PUBLIC ROW ALONG TAMARIND AVENUE. NEEDS TO
 BE ON PAVER OR CONCRETE AREA THAT IS NO MORE THAN 2%
 SLOPE (NOT LANDSCAPED AREA).
 22. SUGGESTED THAT APPLICANT WORK WITH THE FEDERAL
 GOVERNMENT TO REMOVE OR REPLACE THE CHAIN LINK FENCE ON
 THE FEDERAL PROPERTY, AS THE EXISTING WILL DETRACT FROM
 THE PEDESTRIAN PASSAGEWAY.
 23. PRIOR TO ISSUANCE OF BUILDING PERMIT, A LEGAL
 DOCUMENT MUST BE IN PLACE TO RESTRICT DEVELOPMENT ON
 THE ADJACENT 34 FOOT LAND (LEGAL RESEARCH AND DRAFTING
 OF DOCUMENT CURRENTLY ASSIGNED TO NANCY URCHECK, DEPUTY
 CITY ATTORNEY).
 24. IN THE CASE THAT THE LINEAR PARK IS NOT
 CONSTRUCTED, THE APPLICANT SHALL INSTALL A FIVE FOOT
 LANDSCAPE BUFFER ALONG THE NORTH FA?ADE. A PORTION OF
 THIS LANDSCAPE WOULD BE ON THE CRA/CITY PROPERTY, FOR
 WHICH A MAINTENANCE AGREEMENT WOULD BE RECORDED FOR
 AGREEMENT OF MAINTENANCE.
 25. THE DRIVEWAY SHALL BE RESTRICTED TO RIGHT IN/RIGHT
 OUT TURNING MOVEMENTS ONLY.
 26. THE APPLICANT SHALL PROVIDE A STAGING AREA AT THE
 CURB SIDE OF BANYAN BOULEVARD FOR DUMPSTER AND
 RECYCLING BINS. A DROP CURB MAY BE REQUIRED SUBJECT TO
 FURTHER REVIEW BY CITY STAFF.
 27. THE APPLICANT SHALL INCORPORATE A WARNING SIGNAL
 FOR PEDESTRIANS AND BICYCLISTS WHEN A VEHICLE IS
 EXITING THE DRIVEWAY TO REDUCE POTENTIAL IMPACTS
 BETWEEN VEHICLES AND PEDESTRIANS/BICYCLISTS.
 28. THE APPLICANT SHALL WORK WITH STAFF TO ANALYZE
 OPTIONS FOR ARCHITECTURALLY APPROPRIATE RAILING DESIGN;
 CONSIDERATION FOR STUCCO RAIL WALLS AND/OR RAILING AND
 WALL COMBINATION AROUND THE POOL DECK; OPTIONS FOR
 PARAPET ARTICULATION AND DESIGN; AND COLOR OPTIONS FOR
 THE STUCCO. THE ARTIFICIAL GREEN WALL SHALL BE REMOVED.
 29. THE LINEAR PARK PROJECT SHALL REQUIRE A SEPARATE
 PPRC REVIEW AND IS NOT APPROVED AS PART OF THIS SITE
 PLAN REVIEW.
 30. A MINOR AMENDMENT SHALL BE SUBMITTED AFTER FINAL CO
 WITH THE AS-BUILT PLANS FOR ZONING RECORDS.
 31. NOTE - PROJECT NOT SUBJECT TO AIPP REQUIREMENT DUE
 TO AFFORDABLE HOUSING PROVISION.
  
 LIZ LEVESQUE, URBAN DESIGN PLANNER
 [email protected]
 561 822 1426
  

Review Stop Z ZONING
Rev No 2 Status F Date 04-24-2020 Cont ID  
Sent By elevesqu Date 04-24-2020 Time 15:50 Rev Time 0.00
Received By elevesqu Date 04-24-2020 Time 15:50 Sent To  
Notes
2020-04-24 15:52:00NEW COMMENTS LISTED UNDER APRIL 24, 2020
 OLD COMMENTS MARKED AS ONGOING, NOT SATISFIED,
 PARTIALLY SATISFIED, OR SATISFIED.
 IF NOT SATISFIED, WILL HAVE NEW TEXT UNDER ORIGINAL
 COMMENT WITH EXPLANATION OF STATUS
  
 JANUARY 2, 2020:
  
 1. ONGOING. AREA ALL OF THE UNITS AFFORDABLE OR ARE
 SOME MARKET RATE? IF SOME ARE MARKET RATE, THE TOTAL
 INCENTIVE PERMITTED FOR AFFORDABLE HOUSING AND MARKET
 RATE IS CALCULATED USING THE CITY?S MOST RECENT VERSION
 OF THE PURCHASE AFFORDABILITY TABLE AS ADMINISTERED BY
 THE HOUSING AND COMMUNITY DEVELOPMENT DEPARTMENT PER
 SECTION 94-134.
 CONTINUED CONVERSATION SHALL BE HAD WITH CITY STAFF
 FROM ZONING AND HOUSING AND COMMUNITY DEVELOPMENT TO
 ENSURE AFFORDABLE UNITS FOR INCENTIVE.
 2. ONGOING. THE PROPOSED PROJECT DOES NOT UTILIZE THE
 CRA PROPERTY, BUT IS DIRECTLY ADJACENT TO THE LAND THAT
 CONNECTS TO THE NORTHWEST NEIGHBORHOOD. THE CRA IS
 WILLING TO INCENTIVIZE THIS PROJECT AS IT IS AN
 IMPORTANT PROPERTY FOR ENTERING INTO THE NORTHWEST
 NEIGHBORHOOD. STAFF WOULD LIKE TO CONTINUE CONVERSATION
 WITH THE CRA AND THE DEVELOPER TO APPROPRIATELY CONNECT
 THIS PROPERTY TO THE NEIGHBORHOOD.
 PLEASE CLEARLY DELINEATE BETWEEN DEVELOPMENT PROPERTY
 AND CRA PROPERTY. PLEASE PROVIDE SEPARATE SITE PLAN
 THAT DOES NOT INCLUDE CRA PROPERTY FOR DAC SUBMITTAL
 (AS MAIN SITE PLAN) AND INCLUDE SEPARATE PLAN THAT
 INCLUDES CRA PROPERTY (AND RENAME). PLEASE DO THE SAME
 FOR LANDSCAPE PLANS, CIVIL PLANS, ETC.
 3. NOT SATISFIED. PLEASE EXPLAIN WHY THE EXISTING BLACK
 OLIVE TREES CANNOT BE PRESERVED. THE PRESERVATION OF
 THESE TREES WAS INTENDED THROUGH THE BANYAN BOULEVARD
 STREETSCAPE IMPROVEMENTS.
 NO EXPLANATION PROVIDED- NEED NARRATIVE. SEE LANDSCAPE
 PLANNER COMMENTS. THIS SHALL BE PROVIDED PRIOR TO DAC.
 4. ONGOING. ZONING ATLAS IV ILLUSTRATES AN EXTENSION OF
 DOUGLAS AVENUE TO BE A ?NEW SECONDARY ROAD?. THIS IS
 FURTHER REFERENCED:
 A. SECTION 94-119 (A): ADDITIONALLY, THIS DISTRICT
 SHALL CREATE A STRONG CONNECTION WITH THE NORTHWEST
 NEIGHBORHOOD BY EXTENDING THE STREET GRID FROM BANYAN
 BOULEVARD TO 2 ND STREET.?
 B. SECTION 94-119(E): PROPOSED DEVELOPMENTS UTILIZING
 ANY INCENTIVE PROGRAM SHALL ACCOMMODATE THE EXTENSION
 OF DIVISION AND DOUGLAS AVENUES NORTH OF BANYAN
 BOULEVARD PURSUANT TO SECTION 94-133 TO ENHANCE
 CONNECTIVITY TO THE NORTHWEST NEIGHBORHOOD.
 THIS REQUIREMENT WILL NEED TO BE FURTHER ANALYZED AS
 THE PROPOSED DESIGN OF THE PEDESTRIAN CONNECTIVITY DOES
 NOT SATISFY THE INTENT OF THIS SECTION.
 THE PROPOSED PEDESTRIAN CONNECTIVITY STILL REQUIRES
 SOME ADDITIONAL IMPROVEMENT. THE LANDSCAPE PROVIDED IS
 NOT SUFFICIENT OR CONTINUOUS. THE BLANK FA?ADE AND
 PROPOSED GARAGE SCREENING DOES NOT CREATE AN ENHANCED
 PEDESTRIAN AREA. NO SEATING IS PROVIDED. THE
 ENHANCEMENT OF THIS AREA NEEDS TO BE DESIGNED TO
 ENHANCE CONNECTIVITY TO THE NORTHWEST NEIGHBORHOOD.
 OPTIONS SHALL NEED TO BE EXPLORED AND A FINAL SUBMITTED
 PRIOR TO DAC MEETING.
 5. ONGOING. THE PROPOSED PEDESTRIAN CONNECTION DOES NOT
 PROVIDE SATISFACTORY CONNECTIVITY TO THE NEIGHBORHOOD.
 HOW WILL THIS AREA BE IMPROVED? THIS AREA IS ADJACENT
 TO BLANK WALL AND MECHANICAL ROOM AND DOES NOT PROVIDE
 ANY PUBLIC BENEFIT FOR ITS USERS. TREE GRATES DOES NOT
 EFFECTIVELY ENHANCE THE AREA.
 SEE RESPONSE TO NUMBER 4 ABOVE.
 6. PARTIALLY SATISFIED. ACTIVE USES ARE REQUIRED ALONG
 THE SIDE INTERIOR LOT LINE (30%), AS ZONING ATLAS IV
 ILLUSTRATES A ?NEW SECONDARY ROAD? EXTENSION OF
 DOUGLASS AVENUE.
 BICYCLE STORAGE IS NOT AN ACTIVE USE. THE STORAGE NEEDS
 TO BE RELOCATED AND THIS AREA SHALL BE RESERVED FOR
 COMMERCIAL, RESIDENTIAL OR OTHER ACTIVE USE PER THE
 DEFINITION OF ACTIVE USE. THIS SHALL BE ADDRESSED PRIOR
 TO DAC.
 7. SATISFIED
 8. PARTIALLY SATISFIED. THERE ARE ACTIVE USE
 REQUIREMENTS FOR GROUND FLOOR AND ACTIVE USE LINER
 REQUIREMENTS FOR THE SECOND FLOOR. TAMARIND AVENUE IS A
 PRIMARY PEDESTRIAN STREET AND REQUIRES 65% ACTIVE USE
 ALONG THE GROUND FLOOR AND 60% ACTIVE USE LINER FOR
 FLOOR 2 (ALONG PARKING GARAGE USE). SEE DEFINITIONS OF
 ACTIVE USE AND ACTIVE USE LINER IN SECTION 94-109.
 THE RESIDENT STORAGE AREA ON THE 2ND FLOOR ALONG
 TAMARIND AVENUE IS NOT ACTIVE USE. THIS AREA NEEDS TO
 BE RESERVED FOR ANOTHER USE MEETING THE DEFINITION OF
 ACTIVE USE (TO A MIN. DEPTH OF 15 FEET FOR RESIDENTIAL
 USE OR 20 FEET FOR COMMERCIAL USE). THIS SHALL BE
 ADDRESSED PRIOR TO DAC SUBMITTAL.
  
 THE ACTIVE USE REQUIREMENT IS SEPARATE FOR THE GROUND
 FLOOR (60%) AND SEPARATE FOR FLOORS 2-5 (60%). THE
 TOTAL ACTIVE USE PERCENTAGE IS NOT COMBINED. PLEASE
 AMEND THE ACTIVE USE DATA AND SEPARATE GROUND FLOOR
 PERCENTAGE TOTAL AND 2-5 FLOOR LINER PERCENTAGES.
  
 9. THE REQUIRED ACTIVE USE LINER DEPTH FOR RESIDENTIAL
 USE IS 15? FOR FLOOR 2. PLEASE COMPLY WITH ACTIVE USE
 LINER REQUIREMENT AND UPDATE REQUIREMENTS IN SITE DATA
 TABLE ON SHEET A-1.03 TO REFLECT CORRECT REQUIREMENT.
 THIS INCLUDES BANYAN BOULEVARD, TAMARIND AVENUE AND THE
 SIDE INTERIOR LOT LINE (NEW SECONDARY STREET).
  
 THE ACTIVE USE LINER REQUIREMENT OF 15? IS NOT MET.
 PLEASE INDICATE REQUEST FOR VARIANCE THROUGH VARIANCE
 TABLE. PLEASE RESPOND TO VARIANCE CRITERIA FOR EACH
 VARIANCE REQUESTED WITH DAC SUBMITTAL.
  
 THE ACTIVE USE REQUIREMENT IS SEPARATE FOR THE GROUND
 FLOOR (60%) AND SEPARATE FOR FLOORS 2-5 (60%). THE
 TOTAL ACTIVE USE PERCENTAGE IS NOT COMBINED. PLEASE
 AMEND THE ACTIVE USE DATA AND SEPARATE GROUND FLOOR
 PERCENTAGE TOTAL AND 2-5 FLOOR LINER PERCENTAGES.
  
 PLEASE INCLUDE DATA IN THE DATA TABLE FOR THE ACTIVE
 USE ALONG THE SIDE INTERIOR LOT LINE (SECONDARY
 STREET).
  
 10. ONGOING. PLEASE ENSURE THAT THE LATEST BANYAN
 BOULEVARD STREETSCAPE DESIGN IS INCORPORATED INTO THE
 SITE PLAN AS THE REVIEW PROGRESSES.
 CONTINUE TO UPDATE AS NECESSARY AS DESIGN PROGRESSES.
 11. SATISFIED.
 12. NOT SATISFIED. ALL SETBACKS SHALL BE MEASURED FROM
 THE EXISTING CURB LINE. PLEASE INDICATE EXISTING CURB
 LINE AND PROPOSED CURB LINE CLEARLY ON ALL PLANS. THE
 BUILDING APPEARS TO EXCEED THE MAXIMUM SETBACK OF 30?
 ALONG TAMARIND AVENUE ON THE GROUND FLOOR AND THE
 TOWER.
  
 PLEASE INCLUDE MAXIMUM SETBACKS IN THE SITE DATA TABLE.
  
 THE MINIMUM SETBACK ALONG BANYAN BOULEVARD SHALL BE
 MEASURED FROM THE EXISTING CURB LINE. THIS SHALL BE
 ADJUSTED TO MEET THE REQUIRED SETBACK. IF VARIANCE IS
 REQUESTED FOR REAR SETBACK, PLEASE INCLUDE IN VARIANCE
 TABLE AND ADDRESS VARIANCE CRITERIA FOR THE VARIANCE IN
 THE DAC APPLICATION.
  
 THE STRUCTURE EXCEEDS THE MAXIMUM SETBACK OF 30 FEET
 FROM TAMARIND AT THE GROUND FLOOR AND UPPER LEVELS. THE
 SETBACK IS MEASURED FROM THE BACK OF CURB. PLEASE
 INCLUDE THE PROPOSED SETBACK LINE PARALLEL TO THE CURB
 ALONG THE ENTIRE BUILDING FRONTAGE ON THIS FACADE.
 PLEASE INCLUDE THE MAXIMUM PROVIDED SETBACK FROM
 TAMARIND AVENUE IN THE SITE DATA TABLE. IF REQUESTING
 VARIANCE FROM MAXIMUM SETBACK, PLEASE INCLUDE IN
 VARIANCE TABLE ON SITE PLAN AND RESPOND TO VARIANCE
 CRITERIA IN DAC APPLICATION.
  
 13. PARTIALLY SATISFIED. PLEASE INCLUDE THE SETBACK
 DIMENSION TO THE UPPER FLOORS ON THE SITE PLAN SHEET
 SP-1.
 PLEASE INCLUDE ON SITE PLAN SHEET SP-1.
 14. SATISFIED.
 15. NOT SATIFISED. PLEASE INCLUDE A PROPOSED HARDSCAPE
 PLAN.
 DIDN?T RECEIVE WITH RESUBMITTAL.
 16. SATISFIED
 17. PARTIALLY SATISFIED. CONSIDER THE ROLLING OF
 DUMPSTERS TO THE BANYAN BOULEVARD CURB THROUGH THE
 IMPROVED PEDESTRIAN WALKWAY AREA, WITH A DUMPSTER
 HOLDING AREA ALONG THE FRONTAGE OF BANYAN BOULEVARD.
 NEED TO INCLUDE PUBLIC WORKS DEPARTMENT IN DISCUSSION.
 THIS WILL ELIMINATE NEED FOR LARGE ROLLING DOOR WHICH
 NEGATIVELY IMPACTS THE BUILDING FA?ADE ALONG BANYAN
 BLVD.
 PLEASE CONTINUE TO COORDINATE. HOW WILL DUMPSTERS BE
 ROLLED OUT. A RESERVED HOLDING AREA WILL BE REQUIRED.
 PLEASE DISCUSS WITH PUBLIC WORKS REGARDING NEED FOR
 DROP CURB. NEEDS TO BE RESOLVED PRIOR TO SITE PLAN
 APPROVAL.
 18. PARTIALY SATISFIED. THE ARCHITECTURE DOES NOT MEET
 THE INTENT OR REQUIREMENTS WITHIN THE DOWNTOWN MASTER
 PLAN ZONING OR THE INTENT OF THE COMPREHENSIVE PLAN FOR
 ARCHITECTURAL COMPATIBILITY AND DESIGN. ON FACADES
 ENCLOSING ACTIVE USES (SEE SEC. 94-109 FOR DEFINITION
 OF ACTIVE USE), FENESTRATION SHALL COVER A MINIMUM OF
 15% OF THE FA?ADE AREA ? THIS DOES NOT INCLUDE PAINTED
 OR FAUX FENESTRATION. ON FACADES ENCLOSING NON-ACTIVE
 USES, ARCHITECTURAL TREATMENT SHALL BE PROVIDED (SEE
 SECTION 94-109 FOR DEFINITION OF ARCH. TREATMENT). SEE
 TABLE IV-4: FA?ADE ARTICULATION REQUIREMENTS AT THE END
 OF SECTION 94-109 FOR MORE DETAIL.
 THANK YOU FOR THE UPDATED DESIGN WHICH STAFF FEELS IS
 COMPATIBLE WITH THE SURROUNDING AREA AND FOR THE
 INCLUSION OF MORE ARCHITECTURAL TREATMENT. SEE NEW
 COMMENTS 60-70
 19. PARTIALY SATISFIED. THE PROPOSED ARCHITECTURE IS
 NOT COMPATIBLE OR APPROPRIATE FOR THIS LOCATION, WHICH
 SERVES AS AN IMPORTANT ENTRANCE INTO THE CITY FROM
 AUSTRALIAN AVENUE, AS WELL AS A KEY ENTRANCE INTO THE
 HISTORIC NORTHWEST NEIGHBORHOOD. PLEASE EVALUATE THE
 SURROUNDING AREAS AND ARCHITECTURE FOR AN ARCHITECTURAL
 DESIGN THAT IS APPROPRIATE FOR THIS AREA.
 SEE NEW COMMENTS 60-70
  
 20. PARTIALLY SATISFIED. PER SECTION 94-119(E), MAIN
 BUILDING ENTRANCES TO LOBBIES AND COMMON AREAS SHALL
 HAVE A HIGH QUALITY DESIGN ENTRANCE CANOPY
 SEE NEW COMMENT 70
 21. SATISFIED.
 22. PARTIALLY SATSFIED. PLEASE ILLUSTRATE COMPLIANCE
 WITH THE REQUIRED BUILDING FOOTPRINT FOR LEVELS 2-8,
 WHICH CANNOT EXCEED 90% PER FLOOR. PLEASE SEE
 DEFINITION OF FOOTPRINT IN SECTION 94-109 WHICH
 EXCLUDES SOME AREAS INCLUDING ROOFTOP DECKS, AND POOLS,
 ETC.
 PLEASE INCLUDE PERCENTAGES PER FLOOR IN DATA. REQUIRED
 PRIOR TO SITE PLAN APPROVAL.
  
 23. PARTIALLY SATISFIED. THE FAR IS CALCULATED BASED ON
 GROSS BUILDING AREA AND DOES NOT INCLUDE MECHANICAL
 ROOMS, TRASH ROOMS, ETC. PER DEFINITION OF GROSS
 BUILDING AREA IN SECTION 94-109. PLEASE REVISE SHEET
 A-1.01 AND SITE PLAN DATA TO REFLECT.
 PLEASE UPDATE AS NECESSARY AS THINGS ARE ADJUSTED.
 NEEDS TO BE ADJUSTED PRIOR TO SITE PLAN APPROVAL
  
 THE BIKE SHARING STATION AREA, WHETHER BICYCLE STORAGE
 OR CHANGED TO A COMMERCIAL/RETAIL USE (TO COUNT AS
 ACTIVE USE), WOULD BE COUNTED AS FAR.
  
 24. PARTIALLY SATISFIED. PLEASE SEPARATE BASE FAR
 PERMITTED AND FAR PERMITTED WITH INCENTIVE. PLEASE
 INDICATE TOTAL SF PERMITTED BY RIGHT AND SEPARATELY,
 THE SF PERMITTED WITH THE INCENTIVE. PLEASE INCLUDE
 TOTAL SF PROPOSED FOR INCENTIVE.
 PLEASE INCLUDE SQUARE FOOTAGE PERMITTED BY RIGHT AND
 PERMITTED WITH INCENTIVE IN DATA TABLE. NEEDS TO BE
 ADJUSTED PRIOR TO SITE PLAN APPROVAL.
  
 25. NOT SATISFIED. THERE IS A DISCREPANCY BETWEEN GROSS
 SF LISTED ON SHEET A-1.01 AND SHEET SP-1. PLEASE
 CLARIFY.
 THERE IS STILL A DISCREPANCY, PLEASE CLARIFY PRIOR TO
 SITE PLAN APPROVAL.
 26. NOT SATIFIED. SHEET A 1.06 LISTS GROSS AREA;
 HOWEVER THE CITY?S DEFINITION OF GROSS AREA EXCLUDES
 MECHANICAL ROOMS, TRASH ROOMS, ETC. PLEASE RELABEL TO
 AVOID CONFUSION WITH SHEET A-1.01.
 PLEASE ADJUST AS REQUESTED PRIOR TO SITE PLAN APPROVAL.
 THIS EXHIBIT DOES NOT MATCH THE DEFINITION FOR GROSS
 BUILDING AREA.
  
 THE BIKE SHARING STATION, AS CURRENTLY PROPOSED, COUNTS
 AS GROSS BUILDING AREA. ANY ACTIVE USE IN THAT LOCATION
 WOULD ALSO COUNT AS GROSS BUILDING AREA.
 27. SATISFIED
 28. PARTIALLY SATISFIED. THE PROPOSED RECESSED
 STAIRWELL ALONG BANYAN BOULEVARD DOES NOT MEET THE
 INTENT OF A PLANAR BREAK PER THE DEFINITION. A PLANAR
 BREAK SHOULD RESULT IN AN OPEN SPACE OR EXTENSION OF
 THE PUBLIC SIDEWALK AT THE GROUND LEVEL.
 PLANAR BREAK REQUIREMENT ALONG GROUND FLOOR (FA?ADE M)
 NOT MET. EXCEEDS MAX. 60% FOR BUILDING FRONTAGE. ADJUST
 PRIOR TO DAC SUBMITTAL.
  
 PLEASE ENSURE THAT ALL PLANAR BREAKS FOR THIS FA?ADE IS
 MINIMUM CUMULATIVE LENGTH OF 20% OF THE ENTIRE FA?ADE.
  
 PLANAR BREAK IS MEASURED IN WIDTH, NOT SQUARE FOOTAGE.
 PLEASE UPDATE DATA.
  
 29. PARTIALLY SATISFIED. FA?ADE H DOES NOT MEET THE
 DEFINITION OF PLANAR BREAK AT THE GROUND LEVEL. PLANAR
 BREAKS ARE REQUIRED AT BOTH GROUND LEVEL AND TOWER
 LEVEL.
 FA?ADE M DOES NOT MEET DEFINITION. MUST NOT EXCEED 60%
 OF BUILDING FA?ADE WITHOUT PLANAR BREAK. PRIOR TO DAC
 SUBMITTAL.
  
 30. PARTIALLY SATISFIED. PARKING SPACES SHALL BE DOUBLE
 STRIPED MEETING REQUIREMENTS OF SECTION 94-485.
 PLEASE ADJUST ON SITE PLAN.
 PLEASE REMOVE HASH STRIPING AND INCLUDE DOUBLE STRIPE
 ON ARCHITECTURAL PLANS TO MATCH SUBMITTED PARKING SPACE
 STRIPING DETAIL.
  BOTH PRIOR TO SITE PLAN APPROVAL.
 31. PARTIALLY SATISFIED. TANDEM PARKING SPACES CAN ONLY
 COUNT AS TWO SPACES IF THE SPACES ARE DEDICATED TO THE
 SAME RESIDENTIAL UNIT, AND A RESTRICTIVE COVENANT SHALL
 BE RECORDED ON CITY APPROVED FORMS, AND RECORDED IN THE
 PUBLIC RECORDS. (SECTION 94-111(E)). THE SITE DATA
 CURRENTLY LISTS THE RESIDENTIAL PARKING AT 1 PER UNIT.
 THE NUMBER OF TANDEM SPACES THAT ARE LABELED AS
 RESERVED FOR 3-UNIT APARTMENTS EXCEEDS THE NUMBER OF
 3-UNIT APARTMENTS. PLEASE ADJUST. TANDEM SPACES CAN BE
 SHARED FOR 2-UNIT APARTMENTS BUT PLEASE ADJUST LABELS
 AS NECESSARY. MATCH WITH THE PARKING DATA TABLE ON SITE
 PLAN SP-1.
  
 THE PROVIDED PARKING NEEDS TO INDICATE THE EXACT NUMBER
 OF PARKING PROPOSED PER EACH TYPE OF UNIT. THERE NEEDS
 TO BE A MINIMUM OF 2 SPACES FOR 15 OF THE 2 OR 3
 BEDROOM UNITS AS THERE ARE 15 SETS OF TANDEM PARKING
 SPACES.
  
 PLEASE INCLUDE MAXIMUM REQUIRED PARKING FOR EACH OF THE
 SEPARATE USES IN ADDITION TO MINIMUM PARKING PER USE.
  
 NEEDS TO BE ADJUSTED PRIOR TO SITE PLAN APPROVAL.
  
 32. SATISFIED
 33. NOT SATISFIED. AN EQUIVALENT OF ONE PARKING SPACE
 SHALL BE PROVIDED AND STRIPED AT THE TERMINUS OF
 DEAD-END DRIVE AISLES FOR A TURN-AROUND SPACE.
 NEED TO INCLUDE TURN AROUND SPACE AT END OF DEAD-END
 DRIVE AISLE ON BOTH FLOORS. EXCEPTION IS IF EACH
 PARKING SPACE WILL BE RESERVED. TO BE MODIFIED PRIOR TO
 SITE PLAN APPROVAL.
 34. PARTIALLY SATISFIED. THE AREA IN FRONT OF THE
 ENTRANCE TO THE TENANT STORAGE AREA IN THE PARKING
 GARAGE SERVES ALSO AS A BACKUP AREA FOR VEHICLES IN THE
 END PARKING SPACE, WHICH IS A DANGEROUS SITUATION.
 PLEASE ADDRESS FOR SAFE ACCESS.
 INCLUDE BOLLARDS AT MINIMUM OF 3 FEET INTO HASH MARKED
 AREA TO PROTECT AREA WHILE STILL PROVIDING REQUIRED 3
 FOOT BACK UP AREA FOR CARS BACKING OUT OF DEAD END
 SPOT.
 35. ONGOING. PLEASE PROVIDE FIVE RESERVED SPACES FOR
 CAR SHARING STATION PARKING. ONCE PROJECT IS FINALIZED,
 STAFF CAN DETERMINE HOW MANY SPACES NEED TO BE OCCUPIED
 BY CAR SHARING AND HOW MANY CAN BE RESERVED FOR FUTURE
 CAR SHARE.
 ONGOING THROUGHOUT BUILDING PERMIT AND PRIOR TO CO
 36. NOT SATISFIED. MICROUNIT PROJECTS ARE REQUIRED TO
 PROVIDE A BIKE SHARING STATION ON SITE. THIS CAN BE
 RESERVED FOR A MICROMOBILITY SHARING STATION AS THE
 CITY IS GOING THROUGH THE PROCESS OF CONTRACTING A
 REPLACEMENT FOR SKYBIKE.
 PLEASE PROVIDE MICROMOBILITY STATION ON SITE. MOST
 LIKELY WITHIN PLAZA AREA ALONG TAMARIND AVENUE. THIS IS
 SEPARATE FROM BICYCLE RACKS. SHALL BE INCLUDED PRIOR TO
 SITE PLAN APPROVAL.
 37. ONGOING. PLEASE NOTE, A PROJECT WITH RESIDENTIAL
 MICRO-UNITS SHALL CONTRIBUTE A TROLLEY FEE PER UNIT PER
 MONTH TO SUPPORT THE OPERATION OF THE CITY?S TROLLEY
 SYSTEM, AS ESTABLISHED BY RESOLUTION.
 38. ONGOING. IN ADDITION TO MICRO-UNIT AND STANDARD
 UNIT BICYCLE RACKS, THE PROJECT IS REQUIRED TO INCLUDE
 BICYCLE RACKS FOR PUBLIC USE AT A RATE OF 1 PER 100
 FEET OF STREET FRONTAGE. THESE PUBLIC BICYCLE RACKS CAN
 BE LOCATED AT THE PROJECT?S ENTRANCE.
 MOST APPROPRIATE LOCATION TO BE DETERMINED THROUGH SITE
 PLAN APPROVAL OR BUILDING PERMIT.
 39. PARTIALLY SATISFIED. THE BICYCLE RACKS FOR MICRO
 AND STANDARD UNITS MUST ALL BE CONTAINED WITHIN THE
 BUILDING, UNDER COVER AND SECURE.
 PROPOSED LOCATION DOES NOT COUNT AS ACTIVE USE. CAN BE
 DISPERSED THROUGH PARKING GARAGE OR BEHIND REQUIRED
 15-20 FOOT ACTIVE USE LINER ON SECOND FLOOR ALONG
 TAMARIND AVENUE.
  
 GENERAL LOCATION SHALL BE REQUIRED PRIOR TO DAC
 SUBMITTAL BUT EXACT DETAILS CAN BE REVIEWED THROUGH
 SITE PLAN APPROVAL OR BUILDING PERMIT.
  
 40. SATISFIED
  
 41. PARTIALLY SATISFIED. ALL ABOVE GROUND UTILITIES
 SHALL BE UNDERGROUNDED.
 THERE IS ONE LINE THAT LOOKS TO BE IN VERY CLOSE
 PROXIMITY TO THE REAR PROPERTY LINE. THIS LINE MAY BE
 TOO CLOSE IN PROXIMITY TO THE BUILDING, ESPECIALLY WITH
 THE ADJUSTED SETBACK. THIS WILL NEED TO BE CHECKED AND
 IF TOO CLOSE IN PROXIMITY, IT WOULD NEED TO RELOCATED,
 UNDERGROUNDED, OR REMOVED IF OBSOLETE (LOOKS TO END
 ABRUPTLY). PLEASE CONFIRM WITH BUILDING DEPARTMENT FOR
 REGULATIONS AND NECESSARY ACTIONS.
  
 42. NOT SATISFIED. PLEASE INDICATE THE PROPOSED
 LOCATION OF THE EXISTING TRAFFIC SIGNAL POLE.
 CANNOT LOCATE ON SITE PLAN ? PLEASE INCLUDE WITH DAC
 SUBMITTAL.
 43. PARTIALLY SATIFSIED. PLEASE NOTE, ANY ROOF MOUNTED
 MECHANICAL EQUIPMENT SHALL BE SCREENED TO THE HEIGHT OF
 THE EQUIPMENT.
 PLEASE INCLUDE HEIGHT OF PARAPET ON BUILDING
 ELEVATIONS. PLEASE INCLUDE PROPOSED HEIGHT OF AC
 UNITS/MECHANICAL EQUIPMENT. PARAPET MAY NEED TO BE
 ADJUSTED IF FURTHER SCREENING NEEDED. CAN BE ADJUSTED
 THROUGH SITE PLAN APPROVAL OR THROUGH BUILDING PERMIT
 REVIEW.
 44. SATISFIED
 45. ONGOING. UNDERSTANDING THE LOCATION MAY CHANGE AS
 THE PROCESS CONTINUES, PLEASE INDICATE PROPOSED
 LOCATION OF BACKFLOW PREVENTER ON PLANS. ALL GROUND
 MOUNTED UTILITIES SHALL BE SCREENED BY LANDSCAPING TO
 THE FULLEST EXTENT POSSIBLE. PLEASE INCLUDE ON
 LANDSCAPE PLANS.
 LOCATION TO BE FINALIZED THROUGHOUT SITE PLAN APPROVAL
 AND ENGINEERING/BUILDING PERMIT REVIEW. ZONING TO BE
 INCLUDED IN LOCATION SELECTION.
 46. ONGOING. PLEASE EVALUATE UTILIZING WALL MOUNTED
 FDC.
 LOCATION TO BE FINALIZED THROUGHOUT SITE PLAN APPROVAL
 AND ENGINEERING/BUILDING PERMIT REVIEW. ZONING TO BE
 INCLUDED IN LOCATION SELECTION.
 47. SATISFIED
 48. SATISFIED
 49. NOT SATISFIED. PLEASE INCLUDE PHOTOMETRIC PLANS AND
 LOCATION OF PROPOSED LIGHT POLES ON THE ROW.
 SHALL BE REQUIRED PRIOR TO SITE PLAN APPROVAL OR
 THROUGH BUILDING PERMIT
 50. SATISFIED
 51. ONGOING. PLEASE NOTE, A MAINTENANCE AGREEMENT SHALL
 BE REQUIRED FOR THE PROJECT PER SECTION 94-113(7).
 TO BE DONE PRIOR TO CO
 52. ONGOING. FOR THE AFFORDABLE HOUSING INCENTIVE
 PROGRAM, PER SECTION 94-134, THE PROPOSED DEVELOPMENT
 SHALL OBTAIN CITY COMMISSION AUTHORIZATION FOR THE
 CONVEYANCE OF CITY-OWNED DEVELOPMENT RIGHTS AS A
 REQUIREMENT OF SITE PLAN APPROVAL. PLEASE NOTE, IF THE
 SITE PLAN APPROVAL EXPIRES PRIOR TO COMMENCEMENT OF
 CONSTRUCTION, THE DEVELOPMENT RIGHTS TRANSFERRED BY THE
 CITY AT NO COST ARE FORFEITED AND REVERT BACK TO THE
 CITY.
 TO BE DONE PRIOR TO CO
 53. ONGOING. PLEASE NOTE, ALL DEVELOPMENTS SEEKING TO
 UTILIZE THE AFFORDABLE HOUSING INCENTIVE SHALL ENTER
 INTO ENTER INTO AN AFFORDABLE HOUSING DEVELOPMENT
 AGREEMENT WITH THE CITY, ON CITY APPROVED FORMS WHICH
 INCLUDE THE CONDITIONS LISTED IN SECTION 94-134(F).
 TO BE DONE PRIOR TO CO
 54. SATISFIED
  
 NEW COMMENTS APRIL 24, 2020
 55. PLEASE NOTE, IF THE BANYAN BOULEVARD STREETSCAPE
 DOES NOT MOVE FORWARD, THE DEVELOPER SHALL BE
 RESPONSIBLE FOR INSTALLATION OF IMPROVEMENTS ALONG
 BANYAN BOULEVARD
 56. PLEASE INCLUDE A VARIANCE TABLE FOR ALL REQUESTED
 VARIANCES WITH CODE SECTION, REQUIRED
 DIMENSION/PERCENTAGE/NUMBER, PROPOSED
 DIMENSION/PERCENTAGE/NUMBER, PERCENTAGE OF VARIANCE
 REQUESTED.
 57. PLEASE SUBMIT A DAC APPLICATION WITH RESPONSES FOR
 SPECIAL REVIEW, AND SEPARATE RESPONSES TO VARIANCE
 CRITERIA FOR EACH REQUESTED VARIANCE. FOR EXAMPLE,
 ACTIVE USE LINER REQUIREMENT ALONG BANYAN BOULEVARD
 (AVENUE DESIGNATION) IS SEPARATE FROM ACTIVE USE LINER
 REQUIREMENT ALONG TAMARIND AVENUE (PRIMARY PEDESTRIAN
 DESIGNATION).
 58. PLEASE CONSIDER MOVING THE GYM TO THE SECOND FLOOR
 AND RESERVING THE SPACE ALONG BANYAN BOULEVARD FOR
 OTHER ACTIVE USES THAT BETTER MEETS THE INTENT OF
 ACTIVE USE.
 59. PLEASE ENSURE THAT THE SIDEWALK AND BICYCLE LANE IS
 KEPT LEVEL AT THE DRIVEWAY ENTRANCE TO THE PROJECT.
 60. PLEASE PROVIDE MATERIAL DETAIL FOR THE
 ARCHITECTURE. PLEASE PROVIDE ILLUSTRATION DETAIL OR
 PICTURE DETAIL FOR VARIOUS MATERIAL.
 61. ARE THE LIGHT POLES SHOWN IN RENDERINGS ALONG
 BANYAN BOULEVARD ACCURATE FOR THE BANYAN STREETSCAPE.
 PLEASE UPDATE IF NECESSARY.
 62. PLEASE EXPLORE REDUCING THE VERTICAL LENGTH OF THE
 ALUMINUM SCREENING PANELS ALONG THE SOUTHERN FA?ADE AND
 INCORPORATING A KNEE WALL SIMILAR TO THAT ON THE EAST
 AND NORTH FA?ADE TO REDUCE THE IMPACT OF PEDESTRIANS
 WALKING BY THE PARKING GARAGE/MECHANICAL ROOMS
 63. PLEASE EXPLORE THE INCORPORATION OF WINDOWS ALONG
 THE EASTERN FA?ADE WHERE THE PARKING GARAGE RAMP IS.
 PARKING RAMPS SHOULD BE SCREENED FROM PUBLIC VIEW TO
 BEST EXTENT POSSIBLE.
 64. WITH REQUIRED MINIMUM SETBACK FROM BANYAN
 BOULEVARD, PLEASE COORDINATE WITH BUILDING DIVISION
 (ROBERT BROWN) AND ZONING FOR REQUIRED PARING GARAGE
 SCREENING AS THE BUILDING WILL BE CLOSER TO THE REAR
 PROPERTY LINE. DISCUSSIONS CAN BE HAD REGARDING THE
 LOCATION OF THE BUILDING PERMITTED TO BE CLOSER TO REAR
 PROPERTY LINE IS THE CRA PROPERTY IS NOT GOING TO BE
 UTILIZED OTHER THAN FOR OPEN SPACE.
 65. THE RENDERING OF THE WEST FA?ADE SHOWS A BUILDING
 ON THE NORTH SIDE OF THE CRA PROPERTY THAT DOESN?T
 MATCH THE EXISTING CONDITION. PLEASE UPDATE
 66. PLEASE UPDATE RENDERINGS PRIOR TO DAC WITH CORRECT
 PROPOSED LANDSCAPE WITHIN PEDESTRIAN CONNECTION ON EAST
 SIDE OF PROPERTY (SEE PRIOR COMMENTS AND COMMENTS FROM
 LANDSCAPE PLANNER R. CARANCI REGARDING CITY
 RECOMMENDATIONS FOR ENHANCING LANDSCAPE WITHIN THIS
 AREA BEFORE UPDATING RENDERINGS- COORDINATE WITH
 LANDSCAPE ARCHITECT).
 67. PLEASE CONSIDER THE INCORPORATION OF BALCONIES ON
 THE TOWER OF THE EAST FA?ADE TO ADD DEPTH TO FA?ADE AND
 TO PROVIDE TENANTS A VIEW OF POOL AMENITY AREA.
 68. PLEASE EXPLORE OPTIONS FOR THE HORIZONTAL ELEMENT
 ON TOP OF THE GROUND FLOOR TO BE VERTICALLY ENLARGED TO
 PROVIDE A STRONGER HORIZONTAL BASE?
 69. THE PROPOSED ALUMINUM PANEL ALONG THE
 ELEVATOR/STAIR ON DOES NOT SEEM NECESSARY COMPATIBLE
 WITH THE CONCRETE COLUMN DETAIL ? PLEASE EXPLORE
 KEEPING THIS AREA SAME AS REST OF FA?ADE OR ANOTHER
 MATERIAL.
 70. PLEASE EXPLORE WAYS OF HIGHLIGHTING CORNER OF
 TAMARIND AND BANYAN (TAMARIND SIDE) AS THIS CORNER IS
 AN IMPORTANT FOCAL POINT BOTH INTO THE NORTHWEST
 NEIGHBORHOOD AND ENTERING THE CITY FROM AUSTRALIAN
 AVENUE.
  
  
  
  
  
  
  
  
  

Review Stop Z ZONING
Rev No 1 Status F Date 01-07-2020 Cont ID  
Sent By elevesqu Date 01-07-2020 Time 16:38 Rev Time 0.00
Received By elevesqu Date 01-07-2020 Time 16:38 Sent To  
Notes
2020-01-07 16:39:061. AREA ALL OF THE UNITS AFFORDABLE OR ARE SOME MARKET
 RATE? IF SOME ARE MARKET RATE, THE TOTAL INCENTIVE
 PERMITTED FOR AFFORDABLE HOUSING AND MARKET RATE IS
 CALCULATED USING THE CITY?S MOST RECENT VERSION OF THE
 PURCHASE AFFORDABILITY TABLE AS ADMINISTERED BY THE
 HOUSING AND COMMUNITY DEVELOPMENT DEPARTMENT PER
 SECTION 94-134.
 2. THE PROPOSED PROJECT DOES NOT UTILIZE THE CRA
 PROPERTY, BUT IS DIRECTLY ADJACENT TO THE LAND THAT
 CONNECTS TO THE NORTHWEST NEIGHBORHOOD. THE CRA IS
 WILLING TO INCENTIVIZE THIS PROJECT AS IT IS AN
 IMPORTANT PROPERTY FOR ENTERING INTO THE NORTHWEST
 NEIGHBORHOOD. STAFF WOULD LIKE TO CONTINUE CONVERSATION
 WITH THE CRA AND THE DEVELOPER TO APPROPRIATELY CONNECT
 THIS PROPERTY TO THE NEIGHBORHOOD.
 3. PLEASE EXPLAIN WHY THE EXISTING BLACK OLIVE TREES
 CANNOT BE PRESERVED. THE PRESERVATION OF THESE TREES
 WAS INTENDED THROUGH THE BANYAN BOULEVARD STREETSCAPE
 IMPROVEMENTS.
 4. ZONING ATLAS IV ILLUSTRATES AN EXTENSION OF DOUGLAS
 AVENUE TO BE A ?NEW SECONDARY ROAD?. THIS IS FURTHER
 REFERENCED:
 A. SECTION 94-119 (A): ADDITIONALLY, THIS DISTRICT
 SHALL CREATE A STRONG CONNECTION WITH THE NORTHWEST
 NEIGHBORHOOD BY EXTENDING THE STREET GRID FROM BANYAN
 BOULEVARD TO 2 ND STREET.?
 B. SECTION 94-119(E): PROPOSED DEVELOPMENTS UTILIZING
 ANY INCENTIVE PROGRAM SHALL ACCOMMODATE THE EXTENSION
 OF DIVISION AND DOUGLAS AVENUES NORTH OF BANYAN
 BOULEVARD PURSUANT TO SECTION 94-133 TO ENHANCE
 CONNECTIVITY TO THE NORTHWEST NEIGHBORHOOD.
 THIS REQUIREMENT WILL NEED TO BE FURTHER ANALYZED AS
 THE PROPOSED DESIGN OF THE PEDESTRIAN CONNECTIVITY DOES
 NOT SATISFY THE INTENT OF THIS SECTION.
 5. THE PROPOSED PEDESTRIAN CONNECTION DOES NOT PROVIDE
 SATISFACTORY CONNECTIVITY TO THE NEIGHBORHOOD. HOW WILL
 THIS AREA BE IMPROVED? THIS AREA IS ADJACENT TO BLANK
 WALL AND MECHANICAL ROOM AND DOES NOT PROVIDE ANY
 PUBLIC BENEFIT FOR ITS USERS. TREE GRATES DOES NOT
 EFFECTIVELY ENHANCE THE AREA.
 6. ACTIVE USES ARE REQUIRED ALONG THE SIDE INTERIOR LOT
 LINE (30%), AS ZONING ATLAS IV ILLUSTRATES A ?NEW
 SECONDARY ROAD? EXTENSION OF DOUGLASS AVENUE.
 7. PLEASE ILLUSTRATE THE USE OF THE HATCHED AREA UNDER
 THE PARKING GARAGE AT THE BUILDING?S NORTHEAST CORNER
 (ADJACENT TO PROPOSED PEDESTRIAN CONNECTION).
 8. THERE ARE ACTIVE USE REQUIREMENTS FOR GROUND FLOOR
 AND ACTIVE USE LINER REQUIREMENTS FOR THE SECOND FLOOR.
 TAMARIND AVENUE IS A PRIMARY PEDESTRIAN STREET AND
 REQUIRES 65% ACTIVE USE ALONG THE GROUND FLOOR AND 60%
 ACTIVE USE LINER FOR FLOOR 2 (ALONG PARKING GARAGE
 USE). SEE DEFINITIONS OF ACTIVE USE AND ACTIVE USE
 LINER IN SECTION 94-109.
 9. THE REQUIRED ACTIVE USE LINER DEPTH FOR RESIDENTIAL
 USE IS 15? FOR FLOOR 2. PLEASE COMPLY WITH ACTIVE USE
 LINER REQUIREMENT AND UPDATE REQUIREMENTS IN SITE DATA
 TABLE ON SHEET A-1.03 TO REFLECT CORRECT REQUIREMENT.
 THIS INCLUDES BANYAN BOULEVARD, TAMARIND AVENUE AND THE
 SIDE INTERIOR LOT LINE (NEW SECONDARY STREET).
 10. PLEASE ENSURE THAT THE LATEST BANYAN BOULEVARD
 STREETSCAPE DESIGN IS INCORPORATED INTO THE SITE PLAN
 AS THE REVIEW PROGRESSES.
 11. PLEASE INCLUDE THE STREET CENTERLINES ON THE SITE
 PLAN.
 12. ALL SETBACKS SHALL BE MEASURED FROM THE EXISTING
 CURB LINE. PLEASE INDICATE EXISTING CURB LINE AND
 PROPOSED CURB LINE CLEARLY ON ALL PLANS. THE BUILDING
 APPEARS TO EXCEED THE MAXIMUM SETBACK OF 30? ALONG
 TAMARIND AVENUE ON THE GROUND FLOOR AND THE TOWER.
 13. PLEASE INCLUDE THE SETBACK DIMENSION TO THE UPPER
 FLOORS ON THE SITE PLAN SHEET SP-1.
 14. PLEASE INCLUDE A MIN. EIGHT FOOT CLEAR SIDEWALK
 ALONG TAMARIND AVENUE. ALL STREETSCAPE REQUIREMENTS OF
 SECTION 94-113 (D) SHALL BE INCORPORATED ALONG TAMARIND
 AVENUE.
 15. PLEASE INCLUDE A PROPOSED HARDSCAPE PLAN.
 16. IN ORDER TO ACCOMMODATE THE BACK OF HOUSE UTILITIES
 AND ROOMS ALONG THE REAR PROPERTY LINE, PLEASE EVALUATE
 OPTIONS TO REORIENT THE PARKING GARAGE. WORKING WITH
 THE CITY?S TRAFFIC ENGINEER, PLEASE EVALUATE LOCATING
 THE ENTRANCE INTO THE PARKING GARAGE FROM BANYAN
 BOULEVARD (AT THE EAST SIDE OF THE PROPERTY) RATHER
 THAN ON TAMARIND AVENUE, AS THE ENTRANCE IS VERY CLOSE
 TO THE INTERSECTION OF BANYAN BOULEVARD AND TAMARIND
 AVENUE. THIS WILL ALSO PERMIT ACTIVE USES OR APPEARANCE
 OF ACTIVE USES ALONG THE BANYAN BOULEVARD FA?ADE RATHER
 THAN A LARGE EXPANSE OF NON-ACTIVE USE WITH LARGE
 ROLLING DOORS.
 17. CONSIDER THE ROLLING OF DUMPSTERS TO THE BANYAN
 BOULEVARD CURB THROUGH THE IMPROVED PEDESTRIAN WALKWAY
 AREA, WITH A DUMPSTER HOLDING AREA ALONG THE FRONTAGE
 OF BANYAN BOULEVARD. NEED TO INCLUDE PUBLIC WORKS
 DEPARTMENT IN DISCUSSION. THIS WILL ELIMINATE NEED FOR
 LARGE ROLLING DOOR WHICH NEGATIVELY IMPACTS THE
 BUILDING FA?ADE ALONG BANYAN BLVD.
 18. THE ARCHITECTURE DOES NOT MEET THE INTENT OR
 REQUIREMENTS WITHIN THE DOWNTOWN MASTER PLAN ZONING OR
 THE INTENT OF THE COMPREHENSIVE PLAN FOR ARCHITECTURAL
 COMPATIBILITY AND DESIGN. ON FACADES ENCLOSING ACTIVE
 USES (SEE SEC. 94-109 FOR DEFINITION OF ACTIVE USE),
 FENESTRATION SHALL COVER A MINIMUM OF 15% OF THE FA?ADE
 AREA ? THIS DOES NOT INCLUDE PAINTED OR FAUX
 FENESTRATION. ON FACADES ENCLOSING NON-ACTIVE USES,
 ARCHITECTURAL TREATMENT SHALL BE PROVIDED (SEE SECTION
 94-109 FOR DEFINITION OF ARCH. TREATMENT). SEE TABLE
 IV-4: FA?ADE ARTICULATION REQUIREMENTS AT THE END OF
 SECTION 94-109 FOR MORE DETAIL.
 19. THE PROPOSED ARCHITECTURE IS NOT COMPATIBLE OR
 APPROPRIATE FOR THIS LOCATION, WHICH SERVES AS AN
 IMPORTANT ENTRANCE INTO THE CITY FROM AUSTRALIAN
 AVENUE, AS WELL AS A KEY ENTRANCE INTO THE HISTORIC
 NORTHWEST NEIGHBORHOOD. PLEASE EVALUATE THE SURROUNDING
 AREAS AND ARCHITECTURE FOR AN ARCHITECTURAL DESIGN THAT
 IS APPROPRIATE FOR THIS AREA.
 20. PER SECTION 94-119(E), MAIN BUILDING ENTRANCES TO
 LOBBIES AND COMMON AREAS SHALL HAVE A HIGH QUALITY
 DESIGN ENTRANCE CANOPY
 21. PLEASE INCLUDE STREET VIEW 3D RENDERINGS.
 22. PLEASE ILLUSTRATE COMPLIANCE WITH THE REQUIRED
 BUILDING FOOTPRINT FOR LEVELS 2-8, WHICH CANNOT EXCEED
 90% PER FLOOR. PLEASE SEE DEFINITION OF FOOTPRINT IN
 SECTION 94-109 WHICH EXCLUDES SOME AREAS INCLUDING
 ROOFTOP DECKS, AND POOLS, ETC.
 23. THE FAR IS CALCULATED BASED ON GROSS BUILDING AREA
 AND DOES NOT INCLUDE MECHANICAL ROOMS, TRASH ROOMS,
 ETC. PER DEFINITION OF GROSS BUILDING AREA IN SECTION
 94-109. PLEASE REVISE SHEET A-1.01 AND SITE PLAN DATA
 TO REFLECT.
 24. PLEASE SEPARATE BASE FAR PERMITTED AND FAR
 PERMITTED WITH INCENTIVE. PLEASE INDICATE TOTAL SF
 PERMITTED BY RIGHT AND SEPARATELY, THE SF PERMITTED
 WITH THE INCENTIVE. PLEASE INCLUDE TOTAL SF PROPOSED
 FOR INCENTIVE.
 25. THERE IS A DISCREPANCY BETWEEN GROSS SF LISTED ON
 SHEET A-1.01 AND SHEET SP-1. PLEASE CLARIFY.
 26. SHEET A 1.06 LISTS GROSS AREA; HOWEVER THE CITY?S
 DEFINITION OF GROSS AREA EXCLUDES MECHANICAL ROOMS,
 TRASH ROOMS, ETC. PLEASE RELABEL TO AVOID CONFUSION
 WITH SHEET A-1.01.
 27. PLEASE INCLUDE PERMITTED HEIGHT BY RIGHT AND
 PERMITTED INCENTIVE HEIGHT IN DATA TABLE.
 28. THE PROPOSED RECESSED STAIRWELL ALONG BANYAN
 BOULEVARD DOES NOT MEET THE INTENT OF A PLANAR BREAK
 PER THE DEFINITION. A PLANAR BREAK SHOULD RESULT IN AN
 OPEN SPACE OR EXTENSION OF THE PUBLIC SIDEWALK AT THE
 GROUND LEVEL.
 29. FA?ADE H DOES NOT MEET THE DEFINITION OF PLANAR
 BREAK AT THE GROUND LEVEL. PLANAR BREAKS ARE REQUIRED
 AT BOTH GROUND LEVEL AND TOWER LEVEL.
 30. PARKING SPACES SHALL BE DOUBLE STRIPED MEETING
 REQUIREMENTS OF SECTION 94-485.
 31. TANDEM PARKING SPACES CAN ONLY COUNT AS TWO SPACES
 IF THE SPACES ARE DEDICATED TO THE SAME RESIDENTIAL
 UNIT, AND A RESTRICTIVE COVENANT SHALL BE RECORDED ON
 CITY APPROVED FORMS, AND RECORDED IN THE PUBLIC
 RECORDS. (SECTION 94-111(E)). THE SITE DATA CURRENTLY
 LISTS THE RESIDENTIAL PARKING AT 1 PER UNIT.
 32. IF THE PARKING SPACES ARE NOT RESERVED, PARKING
 SPACES ADJACENT TO A WALL OR OTHER PHYSICAL BARRIER
 SHALL HAVE AN INCREASED WIDTH OF ONE FOOT. WITH
 OBSTRUCTION ON BOTH SIDES OF THE STALL, THE STALL
 WIDTHS SHALL BE INCREASED BY A MINIMUM OF TWO FEET.
 33. AN EQUIVALENT OF ONE PARKING SPACE SHALL BE
 PROVIDED AND STRIPED AT THE TERMINUS OF DEAD-END DRIVE
 AISLES FOR A TURN-AROUND SPACE.
 34. THE AREA IN FRONT OF THE ENTRANCE TO THE TENANT
 STORAGE AREA IN THE PARKING GARAGE SERVES ALSO AS A
 BACKUP AREA FOR VEHICLES IN THE END PARKING SPACE,
 WHICH IS A DANGEROUS SITUATION. PLEASE ADDRESS FOR SAFE
 ACCESS.
 35. PLEASE PROVIDE FIVE RESERVED SPACES FOR CAR SHARING
 STATION PARKING. ONCE PROJECT IS FINALIZED, STAFF CAN
 DETERMINE HOW MANY SPACES NEED TO BE OCCUPIED BY CAR
 SHARING AND HOW MANY CAN BE RESERVED FOR FUTURE CAR
 SHARE.
 36. MICROUNIT PROJECTS ARE REQUIRED TO PROVIDE A BIKE
 SHARING STATION ON SITE. THIS CAN BE RESERVED FOR A
 MICROMOBILITY SHARING STATION AS THE CITY IS GOING
 THROUGH THE PROCESS OF CONTRACTING A REPLACEMENT FOR
 SKYBIKE.
 37. PLEASE NOTE, A PROJECT WITH RESIDENTIAL MICRO-UNITS
 SHALL CONTRIBUTE A TROLLEY FEE PER UNIT PER MONTH TO
 SUPPORT THE OPERATION OF THE CITY?S TROLLEY SYSTEM, AS
 ESTABLISHED BY RESOLUTION.
 38. IN ADDITION TO MICRO-UNIT AND STANDARD UNIT BICYCLE
 RACKS, THE PROJECT IS REQUIRED TO INCLUDE BICYCLE RACKS
 FOR PUBLIC USE AT A RATE OF 1 PER 100 FEET OF STREET
 FRONTAGE. THESE PUBLIC BICYCLE RACKS CAN BE LOCATED AT
 THE PROJECT?S ENTRANCE.
 39. THE BICYCLE RACKS FOR MICRO AND STANDARD UNITS MUST
 ALL BE CONTAINED WITHIN THE BUILDING, UNDER COVER AND
 SECURE.
 40. HOW WILL THE PARKING GARAGE BE SECURED? HOW WILL
 THE PARKING SPACES FOR THE RETAIL USE BE ACCESSIBLE?
 PLEASE RESERVE THE PARKING SPACES THAT ARE LISTED FOR
 RETAIL USE.
 41. ALL ABOVE GROUND UTILITIES SHALL BE UNDERGROUNDED.
 42. PLEASE INDICATE THE PROPOSED LOCATION OF THE
 EXISTING TRAFFIC SIGNAL POLE.
 43. PLEASE NOTE, ANY ROOF MOUNTED MECHANICAL EQUIPMENT
 SHALL BE SCREENED TO THE HEIGHT OF THE EQUIPMENT.
 44. PLEASE MAKE NOTE ON PLANS THAT ANY WALL MOUNTED
 UTILITIES SHALL BE PAINTED TO MATCH BUILDING FA?ADE
 AND/OR EFFICIENTLY SCREENED FROM THE PUBLIC VIEW.
 45. UNDERSTANDING THE LOCATION MAY CHANGE AS THE
 PROCESS CONTINUES, PLEASE INDICATE PROPOSED LOCATION OF
 BACKFLOW PREVENTER ON PLANS. ALL GROUND MOUNTED
 UTILITIES SHALL BE SCREENED BY LANDSCAPING TO THE
 FULLEST EXTENT POSSIBLE. PLEASE INCLUDE ON LANDSCAPE
 PLANS.
 46. PLEASE EVALUATE UTILIZING WALL MOUNTED FDC.
 47. PLEASE INCLUDE THE FPL TRANSFORMER INSIDE THE
 BUILDING.
 48. PLEASE NOTE, ALL PARKING STRUCTURE ENTRANCES SHALL
 BE REQUIRED TO TREAT THE INTERIOR PORTION OF THE GARAGE
 TO A DEPTH OF AT LEAST 20 FEET, INCLUDING FLOORS WALLS
 AND CEILINGS. ALL MECHANICAL, ELECTRICAL, AND PLUMBING
 SYSTEMS SHALL BE COVERED OR SCREENED. TREATMENT MAY
 INCLUDE, BUT SHALL NOT BE LIMITED TO, STUCCO OR
 PLASTER, FINISHED AND PAINTED COMPARABLE TO A HABITABLE
 SPACE. PLEASE MAKE NOTE ON PLANS TO MEET REQUIREMENT.
 49. PLEASE INCLUDE PHOTOMETRIC PLANS AND LOCATION OF
 PROPOSED LIGHT POLES ON THE ROW.
 50. PLEASE REMOVE REFERENCE TO ANY SIGNAGE OR ADD A
 NOTE ?SIGNAGE TO BE REVIEWED UNDER SEPARATE PERMIT?
 51. PLEASE NOTE, A MAINTENANCE AGREEMENT SHALL BE
 REQUIRED FOR THE PROJECT PER SECTION 94-113(7).
 52. FOR THE AFFORDABLE HOUSING INCENTIVE PROGRAM, PER
 SECTION 94-134, THE PROPOSED DEVELOPMENT SHALL OBTAIN
 CITY COMMISSION AUTHORIZATION FOR THE CONVEYANCE OF
 CITY-OWNED DEVELOPMENT RIGHTS AS A REQUIREMENT OF SITE
 PLAN APPROVAL. PLEASE NOTE, IF THE SITE PLAN APPROVAL
 EXPIRES PRIOR TO COMMENCEMENT OF CONSTRUCTION, THE
 DEVELOPMENT RIGHTS TRANSFERRED BY THE CITY AT NO COST
 ARE FORFEITED AND REVERT BACK TO THE CITY.
 53. PLEASE NOTE, ALL DEVELOPMENTS SEEKING TO UTILIZE
 THE AFFORDABLE HOUSING INCENTIVE SHALL ENTER INTO ENTER
 INTO AN AFFORDABLE HOUSING DEVELOPMENT AGREEMENT WITH
 THE CITY, ON CITY APPROVED FORMS WHICH INCLUDE THE
 CONDITIONS LISTED IN SECTION 94-134(F).
 54. PLEASE INCLUDE CIVIL PLANS FOR ALL SETS WITH
 RESUBMITTALS.
  
 LIZ LEVESQUE, URBAN DESIGN PLANNER