| Plan Review Stops For Project Z17080019 |
| Review Stop |
B |
BUILDING (STRUCTURAL) |
| Rev No |
1 |
Status |
P |
Date |
09-19-2017 |
|
|
Cont ID |
|
| Sent By |
rbrown |
Date |
09-19-2017 |
Time |
19:34 |
Rev Time |
0.00 |
| Received By |
rbrown |
Date |
09-19-2017 |
Time |
19:34 |
Sent To |
|
|
| Notes |
| 2017-09-19 19:37:09 | DEVELOPMENT SERVICES DEPARTMENT, BUILDING DIVISION, | | | COMMENTS: | | | | | | 1. THIS REVIEW IS A CURSORY REVIEW AS IT RELATES TO THE | | | SITE. IT IS NOT A REVIEW FOR FULL COMPLIANCE WITH | | | FLORIDA BUILDING CODE. THE FOLLOWING COMMENTS ARE TO BE | | | ADDRESSED FOR PERMITTING. | | | | | | 2. THE DESIGN OF ACCESSIBLE PARKING SPACES SHALL COMPLY | | | WITH SECTION 502 OF FLORIDA ACCESSIBILITY CODE. | | | | | | 3. SEPARATE PERMITS REQUIRED. ALL APPLICABLE PERMITS | | | AND SUB-PERMITS MUST BE OBTAINED BEFORE COMMENCING THE | | | WORK. SEPARATE PERMITS, PLANS AND FEES, ARE REQUIRED | | | FOR SITE LIGHTING, SITE LANDSCAPE, SITE IRRIGATION, | | | ETC. | | | | | | ROBERT BROWN | | | BUILDING OFFICIAL | | | TEL: 561 805 6652 | | | EMAIL: [email protected] | | | |
|
|
| Review Stop |
ENG - PPRC |
ENGINEERING - PPRC |
| Rev No |
1 |
Status |
P |
Date |
09-14-2017 |
|
|
Cont ID |
|
| Sent By |
squinone |
Date |
09-14-2017 |
Time |
|
Rev Time |
0.00 |
| Received By |
squinone |
Date |
09-14-2017 |
Time |
|
Sent To |
|
|
| Notes |
| 2017-09-14 14:58:51 | CITY OF WEST PALM BEACH | | | ENGINEERING SERVICES DEPARTMENT | | | DATE: 09/20/2017 | | | PROJECT: CARDINAL NEWMAN HIGH SCHOOL ? PARKING | | | RECONFIGURATION | | | ADDRESS: 512 SPENCER DRIVE | | | STATUS: PASSED | | | | | | THIS IS AN INITIAL LEVEL REVIEW. CONSTRUCTION LEVEL | | | DETAILS, DESIGN CALCULATIONS, AND THE POLLUTION | | | PREVENTION PLAN WILL BE REVIEWED AS PART OF THE | | | ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT | | | APPLICATION PROCESSES. | | | | | | 1. ROOT BARRIERS MAY BE REQUIRED WHERE PLANTINGS ARE | | | NEAR UNDERGROUND STORMWATER, SANITARY, OR POTABLE WATER | | | LINES; | | | | | | 2. SHOW ON THE SITE PLANS ADA ACCESSIBLE RAMPS ON THE | | | SIDEWALK AT EACH ENTRANCE AND EXIT; | | | | | | AFTER THE SITE PLAN IS APPROVED, IN THE NEXT PHASE, THE | | | FOLLOWING GENERAL COMMENTS MUST BE ADDRESSED PRIOR TO | | | ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING | | | BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL: | | | | | | 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION WILL | | | BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT. | | | THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS | | | CAN BE DOWNLOADED FROM THE FOLLOWING WEBSITE LINK: | | | HTTP://WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FOR | | | MS,-PERMITS-APPLICATIONS | | | | | | 2. PLEASE SUBMIT THE LATEST VERSION OF THE ?AUTO-CALC | | | CERTIFIED COST ESTIMATE FORM? FOR SUBMISSION TO CITY OF | | | WEST PALM BEACH PUBLIC WORKS DEPARTMENT FOR ADDITIONAL | | | WORK PROPOSED. THIS FORM CAN BE DOWNLOADED FROM THE | | | FOLLOWING LINK: | | | HTTP://WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FOR | | | MS,-PERMITS-APPLICATIONS | | | | | | 3. FIRE HYDRANT FLOW TEST DATA FROM EXISTING FIRE | | | HYDRANT WILL BE REQUIRED PART OF THE PLAN SUBMITTAL. | | | SHOW HYDRANT FLOW TEST DATA RESULT ON THE PLANS; | | | | | | 4. PLEASE INCLUDE THE LATEST VERSION OF THE APPLICABLE | | | CITY OF WEST PALM BEACH STANDARD UTILITY DETAILS TO THE | | | DETAIL SHEET/S DURING SUBMISSION OF THE FINAL | | | ENGINEERING PLANS. CONTACT THE ENGINEERING SERVICES | | | DEPARTMENT FOR THE LATEST REVISED DETAILS IN CAD | | | FORMAT. CITY?S STANDARD DETAILS (IN PDF FILE FORMAT) | | | CAN BE DOWNLOADED FROM THE FOLLOWING SITE: | | | HTTP://WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FOR | | | MS,-PERMITS-APPLICATIONS | | | | | | 5. IN THE FINAL PLANS, MUST PROVIDE UTILITY CONFLICT | | | TABLE (BOTTOM AND TOP OF CROSSING PIPES) AT THE | | | CONFLICT POINTS OF ALL WATER, STORM AND SANITARY SEWER | | | PIPES AS WELL AS OTHER FRANCHISE UTILITIES; | | | | | | SOFIA QUINONES-BENEJAM, EI | | | PROJECT ENGINEER | | | CITY OF WEST PALM BEACH | | | 401 CLEMATIS STREET, 4TH FLOOR | | | WEST PALM BEACH, FL 33402 | | | (MAILING ADDRESS: PO BOX 3366) | | | P: 561.494.1108 | | | C: 561.459.6518 | | | F: 561.494.1116 | | | EMAIL: [email protected] | | | |
|
|
| Review Stop |
FIRE |
FIRE DEPARTMENT |
| Rev No |
1 |
Status |
P |
Date |
09-13-2017 |
|
|
Cont ID |
|
| Sent By |
scaldero |
Date |
09-13-2017 |
Time |
14:18 |
Rev Time |
0.00 |
| Received By |
scaldero |
Date |
09-13-2017 |
Time |
14:17 |
Sent To |
|
|
| Notes |
| 2017-09-13 14:18:28 | THE FOLLOWING COMMENTS WERE SUBMITTED BY SUE ELLEN | | | CALDERON, ASST. FIRE MARSHAL, BUREAU OF FIRE | | | PREVENTION, WEST PALM BEACH FIRE RESCUE. | | | | | | THIS REVIEW CAN ONLY BE CONSIDERED PRELIMINARY AS THE | | | DRAWINGS THAT WERE REVIEWED WERE NOT COMPLETE. | | | ADDITIONAL COMMENTS CAN BE EXPECTED WHEN FULL DRAWINGS | | | ARE SUBMITTED FOR PERMIT. | | | | | | THE FIRE PREVENTION BUREAU HAS NO OBJECTIONS TO THE | | | PROPOSED PROJECT. | | | | | | 1. CONSTRUCTION, DEMOLITION, AND RENOVATION TO COMPLY | | | WITH NFPA 241. EXTRA ATTENTION SHALL BE GIVEN TO THE | | | PERMITTING AND LOCATION OF CONSTRUCTION TRAILERS. A | | | PERMIT IS REQUIRED FOR ANY CONSTRUCTION TRAILER RELATED | | | TO THIS PROJECT. SEPARATION DISTANCES FROM MAIN | | | STRUCTURES AS WELL AS OTHER TRAILERS SHALL BE CLOSELY | | | MONITORED FOR THE REQUIREMENTS OF FIRE SPRINKLER | | | PROTECTION. | | | | | | 2. SITE ACCESS AND EXIT POINTS ARE TO BE CLEARLY | | | IDENTIFIED AND MAINTAINED FOR EMERGENCY VEHICLES DURING | | | ALL CONSTRUCTION ACTIVITIES. | | | | | | 3. DURING CONSTRUCTION, TRASH AND DEBRIS IS TO BE | | | REMOVED FROM THE SITE DAILY OR MORE OFTEN TO REDUCE THE | | | ACCUMULATION OF POTENTIAL LIFE AND FIRE SAFETY HAZARDS. | | | | | | 4. ALL EXISTING AND NEW FIRE HYDRANTS PLANNED FOR THIS | | | DEVELOPMENT SHALL BE CLEARLY INDICATED AND IDENTIFIED | | | ON THE PLAN AND CLOSELY COORDINATED WITH THE BUREAU OF | | | FIRE PREVENTION. | | | | | | 5. THE BUREAU'S APPROVAL OF THIS SUBMITTED PROJECT DOES | | | NOT CONSTITUTE IT'S FINAL REVIEW OR APPROVAL. | | | | | | 6. THE BUREAU SHALL REVIEW ALL SUBMITTED BUILDING PLANS | | | AT THE APPROPRIATE TIME AND IN ACCORDANCE WITH THE | | | REQUIREMENTS OF ALL APPLICABLE CODES AND STANDARDS. | | | | | | | | | SUE ELLEN CALDERON | | | ASST. FIRE MARSHAL | | | [email protected] | | | | | | |
|
|
| Review Stop |
L |
LANDSCAPING |
| Rev No |
2 |
Status |
P |
Date |
12-14-2017 |
|
|
Cont ID |
|
| Sent By |
rcaranci |
Date |
12-14-2017 |
Time |
15:51 |
Rev Time |
0.00 |
| Received By |
rcaranci |
Date |
12-14-2017 |
Time |
15:51 |
Sent To |
|
|
| Notes |
| 2017-12-14 15:52:15 | FROM: RAY CARANCI, LANDSCAPE PLANNER 561-822-1462 | | | MEMO TO FILE | | | PROJECT: CARDINAL NEWMAN HS Z17080019 | | | DECEMBER 14, 2017 | | | I HAVE REVIEWED THE ABOVE REFERENCED PETITION, AND | | | PROVIDE THE FOLLOWING COMMENTS: | | | | | | 1. SATISFIED. PARKING LOT LANDSCAPE AREAS MUST MEET THE | | | REQUIREMENTS OF SECTION 94-443(C)(3) AND (4). PLEASE | | | SHOW ALL CALCULATIONS AND PROVIDE A DIAGRAM SHOWING THE | | | AREAS COUNTED TOWARD THIS REQUIREMENT. | | | | | | 2. SATISFIED. PLEASE SHOW LOCATIONS OF ROOT BARRIERS TO | | | PROTECT INFRASTRUCTURE AND TREES FROM CONFLICTS. THIS | | | INCLUDES WATER, SEWER, DRAINAGE, SIDEWALKS AND CURBS, | | | AND ANY FIELD STRUCTURES THAT COULD BE IMPACTED BY TREE | | | ROOTS. | | | | | | 3. SATISFIED. PLEASE ADJUST THE LOCATIONS OF LIGHTING | | | ON THE LANDSCAPE PLAN TO PREVENT CONFLICTS WITH | | | REQUIRED TREES. | | | | | | 4. SATISFIED. PLEASE PROVIDE THE REQUIRED SHADE TREE OR | | | SUBSTITUTION OF PALMS AT 3:1 FOR EACH TERMINAL | | | LANDSCAPE ISLAND. THERE ARE THREE ISLANDS MISSING | | | TREES, AND TEN ISLANDS WITHOUT THE REQUIRED THREE PALM | | | SUBSTITUTION. | | | | | | 5. SATISFIED. THE FUTURE PARKING MUST EITHER BE PART OF | | | THE APPROVAL OR NOT. STAFF SUGGESTS A CONSTRUCTION | | | PHASING LINE IF IT IS TO BE PERMITTED SEPARATELY FOR | | | CONSTRUCTION. | | | | | | 6. SATISFIED. PLEASE INDICATE THE LOCATION OF WHEEL | | | STOPS OR PARKING OVERHANG INTO LANDSCAPE AREAS | | | ACCORDING TO THE LENGTH OF THE PROPOSED PARKING SPACES. | | | | | | 7. SATISFIED. PLEASE PROVIDE AN UPDATED CHART SHOWING | | | COMPLIANCE WITH FLORIDA FRIENDLY LANDSCAPING PER | | | SECTION 94-442 (G). THIS INCLUDES SHOWING DROUGHT | | | TOLERANCE LEVEL AND NATIVE SPECIES ON THE PLANT LIST | | | AND PROVIDING THE REQUIRED 40 POINTS. | | | | | | CONDITIONS OF APPROVAL | | | 1. PRIOR TO THE REMOVAL OR RELOCATION OF ANY TREES ON | | | THE PROPERTY, A TREE ALTERATION PERMIT SHALL BE | | | SUBMITTED, REVIEWED AND APPROVED BY THE DEVELOPMENT | | | SERVICES DEPARTMENT, PLANNING DIVISION. | | | |
|
|
| Review Stop |
L |
LANDSCAPING |
| Rev No |
1 |
Status |
F |
Date |
09-07-2017 |
|
|
Cont ID |
|
| Sent By |
rcaranci |
Date |
09-07-2017 |
Time |
10:27 |
Rev Time |
0.00 |
| Received By |
rcaranci |
Date |
09-07-2017 |
Time |
10:27 |
Sent To |
|
|
| Notes |
| 2017-09-07 10:27:37 | FROM: RAY CARANCI, LANDSCAPE PLANNER 561-822-1462 | | | MEMO TO FILE | | | PROJECT: CARDINAL NEWMAN HS Z17080019 | | | SEPTEMBER 7, 2017 | | | I HAVE REVIEWED THE ABOVE REFERENCED PETITION, AND | | | PROVIDE THE FOLLOWING COMMENTS: | | | | | | 1. PARKING LOT LANDSCAPE AREAS MUST MEET THE | | | REQUIREMENTS OF SECTION 94-443(C)(3) AND (4). PLEASE | | | SHOW ALL CALCULATIONS AND PROVIDE A DIAGRAM SHOWING THE | | | AREAS COUNTED TOWARD THIS REQUIREMENT. | | | | | | 2. PLEASE SHOW LOCATIONS OF ROOT BARRIERS TO PROTECT | | | INFRASTRUCTURE AND TREES FROM CONFLICTS. THIS INCLUDES | | | WATER, SEWER, DRAINAGE, SIDEWALKS AND CURBS, AND ANY | | | FIELD STRUCTURES THAT COULD BE IMPACTED BY TREE ROOTS. | | | | | | 3. PLEASE ADJUST THE LOCATIONS OF LIGHTING ON THE | | | LANDSCAPE PLAN TO PREVENT CONFLICTS WITH REQUIRED | | | TREES. | | | | | | 4. PLEASE PROVIDE THE REQUIRED SHADE TREE OR | | | SUBSTITUTION OF PALMS AT 3:1 FOR EACH TERMINAL | | | LANDSCAPE ISLAND. THERE ARE THREE ISLANDS MISSING | | | TREES, AND TEN ISLANDS WITHOUT THE REQUIRED THREE PALM | | | SUBSTITUTION. | | | | | | 5. THE FUTURE PARKING MUST EITHER BE PART OF THE | | | APPROVAL OR NOT. STAFF SUGGESTS A CONSTRUCTION PHASING | | | LINE IF IT IS TO BE PERMITTED SEPARATELY FOR | | | CONSTRUCTION. | | | | | | 6. PLEASE INDICATE THE LOCATION OF WHEEL STOPS OR | | | PARKING OVERHANG INTO LANDSCAPE AREAS ACCORDING TO THE | | | LENGTH OF THE PROPOSED PARKING SPACES. | | | | | | 7. PLEASE PROVIDE AN UPDATED CHART SHOWING COMPLIANCE | | | WITH FLORIDA FRIENDLY LANDSCAPING PER SECTION 94-442 | | | (G). THIS INCLUDES SHOWING DROUGHT TOLERANCE LEVEL AND | | | NATIVE SPECIES ON THE PLANT LIST AND PROVIDING THE | | | REQUIRED 40 POINTS. | | | | | | CONDITIONS OF APPROVAL | | | 1. PRIOR TO THE REMOVAL OR RELOCATION OF ANY TREES ON | | | THE PROPERTY, A TREE ALTERATION PERMIT SHALL BE | | | SUBMITTED, REVIEWED AND APPROVED BY THE DEVELOPMENT | | | SERVICES DEPARTMENT, PLANNING DIVISION. | | | |
|
|
| Review Stop |
PARK |
PARKING |
| Rev No |
1 |
Status |
|
Date |
|
|
|
Cont ID |
|
| Sent By |
|
Date |
|
Time |
|
Rev Time |
|
| Received By |
|
Date |
|
Time |
|
Sent To |
|
|
| Notes |
|
|
| Review Stop |
POLICE |
POLICE |
| Rev No |
1 |
Status |
|
Date |
|
|
|
Cont ID |
|
| Sent By |
|
Date |
|
Time |
|
Rev Time |
|
| Received By |
|
Date |
|
Time |
|
Sent To |
|
|
| Notes |
|
|
| Review Stop |
PW |
PUBLIC WORKS |
| Rev No |
1 |
Status |
|
Date |
|
|
|
Cont ID |
|
| Sent By |
|
Date |
|
Time |
|
Rev Time |
|
| Received By |
|
Date |
|
Time |
|
Sent To |
|
|
| Notes |
|
|
| Review Stop |
STORM |
STORMWATER |
| Rev No |
2 |
Status |
P |
Date |
12-18-2017 |
|
|
Cont ID |
|
| Sent By |
tward |
Date |
12-18-2017 |
Time |
11:19 |
Rev Time |
0.00 |
| Received By |
tward |
Date |
12-18-2017 |
Time |
11:48 |
Sent To |
|
|
| Notes |
| 2017-12-18 11:46:45 | THE FOLLOWING COMMENTS ARE FROM THE REVIEW OF THE | | | 12/8/2017 REVIEW PACKAGE DISTRIBUTED BY LINDA LOUIE. | | | UNLESS OTHERWISE NOTED, CHANGES TO THE PLANS CAN BE | | | MADE AT TIME OF ENGINEERING PERMIT SUBMIITAL. | | | | | | 1. A COUPLE OF THE CITY'S STANDARD DETAILS (GC-1, GC-5) | | | HAVE LATER REVISION DATES THAN THE ONES IN THE CURRENT | | | PLANS. INCLUDE THE LATEST CITY DETAILS WITH THE PLANS. | | | | | | 2. ARE PRB'S PROPOSED IN THE DRAINAGE STRUCTURES | | | ATTACHED TO EXFILTRATION TRENCHES? IF SO, PROVIDE A | | | DETAIL FOR THE PRB IN THE PLANS AND THE CONSULTANT'S | | | EXFILTRATION TRENCH TYPICAL DETAILS ON SHEET PE-2.2 | | | WILL NEED TO BE REVISED TO SHOW A SUMP DEEPER THAN 12". | | | | | | 3. NOTE CONCRETE STRENGTH FOR MONOLITHIC SIDEWALK | | | (2,500 PSI) IS DIFFERENT THAN SIDEWALK STRENGTH IN | | | DETAIL GC-1 (3,000 PSI). | | | | | | 4. IN THE STORMWATER CALCULATIONS ON SHEET PE-2.2, | | | THERE IS REFERENCE TO "0.06 ACRES OF ADDITIONAL | | | IMPERVIOUS AREA (INCLUDING FUTURE PARKING". IT'S MY | | | UNDERSTANDING THERE IS NO LONGER A FUTURE PARKING LOT. | | | PLEASE REVISE THIS NOTE TO REFLECT THIS. | | | | | | TRACY L. WARD, P.E. | | | SENIOR STORMWATER ENGINEER | | | ENGINEERING SERVICES DEPARTMENT | | | 561-494-1120 | | | [email protected] |
|
|
| Review Stop |
STORM |
STORMWATER |
| Rev No |
1 |
Status |
F |
Date |
09-07-2017 |
|
|
Cont ID |
|
| Sent By |
tward |
Date |
09-07-2017 |
Time |
13:24 |
Rev Time |
0.00 |
| Received By |
tward |
Date |
09-07-2017 |
Time |
13:26 |
Sent To |
|
|
| Notes |
| 2017-09-07 13:26:33 | THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL | | | DETAILS, DESIGN CALCULATIONS AND THE POLLUTION | | | PREVENTION PLAN WILL BE REVIEWED AS PART OF THE | | | ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT | | | APPLICATION PROCESSES. THE ENGINEERING DEVELOPMENT | | | APPROVAL APPLICATION FORMS CAN BE DOWNLOADED AT HTTP:// | | | WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FORMS,-PER | | | MITS-APPLICATIONS | | | | | | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE | | | PLAN APPROVAL: | | | | | | 1. LABEL VERTICAL DATUM ON THE ENGINEERING PLANS AND | | | PROVIDE A CONVERSION EQUATION TO NGVD1929. | | | | | | 2. WILL THE SPEED BUMPS BE REPLACED IN THE NEW PARKING | | | LOT? | | | | | | 3. UPDATE CITY DETAILS. | | | | | | 4. WHAT IS THE SCHEDULE FOR THE FUTURE PARKING LOT? | | | WILL THE PROPOSED TREES ON THE SIDES OF THE CATCH BASIN | | | IN THE PARKING LOT INTERFERE WITH THE DRAINAGE TO THE | | | CATCH BASIN IN THE FUTURE? | | | | | | 5. CHECK THE EXFILTRATION CALCULATIONS ON SHEET PE-2.2. | | | LENGTH OF TRENCH PROVIDED (605 LF) IS LESS THAN THE | | | LENGTH OF TRENCH ALLOWED (REQUIRED?) (752 LF). SHEET | | | PE-1.2 CALLS OUT 752 LF OF EXFILTRATION TRENCH. | | | | | | 6. STOP BAR AND STOP SIGN MAY BE NEEDED AT INTERSECTION | | | OF LONG DRIVE LANE AND CENTER DRIVE AISLE. | | | | | | 7. CROSS WALK IS SHOWN TO HAVE 4? STRIPES INSTEAD OF | | | 12?/24? AS DEPICTED IN FDOT STANDARD INDEX 17346 OR 12" | | | ON PBC?S T-P-13. | | | | | | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO | | | ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING | | | BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL. | | | | | | 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION WILL | | | BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT. | | | THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS | | | CAN BE DOWNLOADED AT: HTTP://WPB.ORG/DEPARTMENTS/ENGINE | | | ERING-PUBLIC-WORKS/FORMS,-PERMITS-APPLICATIONS | | | | | | 2. PROVIDE A COPY OF THE SFWMD ERP FOR THIS PROPOSED | | | DEVELOPMENT. | | | | | | TRACY WARD, PE | | | SENIOR STORMWATER ENGINEER | | | ENGINEERING SERVICES DEPARTMENT | | | 561-494-1120 | | | [email protected] | | | |
|
|
| Review Stop |
SURVEY |
SURVEYING |
| Rev No |
1 |
Status |
P |
Date |
09-15-2017 |
|
|
Cont ID |
|
| Sent By |
vnoel |
Date |
09-15-2017 |
Time |
08:52 |
Rev Time |
|
| Received By |
vnoel |
Date |
|
Time |
|
Sent To |
|
|
| Notes |
| 2017-09-15 08:55:28 | PASSED, BUT AT SOME POINT THIS PROPERTY SHOULD BE | | | REPLATTED. |
|
|
| Review Stop |
TRAFFIC |
TRAFFIC ENGINEERING |
| Rev No |
2 |
Status |
P |
Date |
|
|
|
Cont ID |
|
| Sent By |
|
Date |
|
Time |
|
Rev Time |
0.00 |
| Received By |
|
Date |
|
Time |
|
Sent To |
|
|
| Notes |
| 2017-12-12 14:26:28 | ERIK D. FERGUSON, P.E. | | | CITY TRANSPORTATION ENGINEER |
|
|
| Review Stop |
TRAFFIC |
TRAFFIC ENGINEERING |
| Rev No |
1 |
Status |
F |
Date |
|
|
|
Cont ID |
|
| Sent By |
|
Date |
09-18-2017 |
Time |
|
Rev Time |
|
| Received By |
|
Date |
|
Time |
|
Sent To |
|
|
| Notes |
| 2017-09-18 10:13:11 | BICYCLE PARKING SHALL BE REQIURED PER SECTION 94-485. | | | | | | ERIK D. FERGUSON, P.E. | | | SENIOR PROJECT ENGINEER | | | 561-494-1092 | | | [email protected] |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
2 |
Status |
P |
Date |
12-20-2017 |
|
|
Cont ID |
|
| Sent By |
llouie |
Date |
12-20-2017 |
Time |
|
Rev Time |
0.00 |
| Received By |
llouie |
Date |
12-20-2017 |
Time |
|
Sent To |
|
|
| Notes |
|
|
| Review Stop |
Z |
ZONING |
| Rev No |
1 |
Status |
F |
Date |
09-07-2017 |
|
|
Cont ID |
|
| Sent By |
llouie |
Date |
09-07-2017 |
Time |
|
Rev Time |
|
| Received By |
llouie |
Date |
09-07-2017 |
Time |
|
Sent To |
|
|
| Notes |
| 2017-09-07 16:44:55 | GENERAL COMMENTS: | | | | | | 1.) PROVIDE WRITTEN CONSENT THAT THE PUBLIC UTILITIES | | | DEPARTMENT HAS REVIEWED THE PROPOSAL FOR WATER, SEWAGE | | | TREATMENT, STORM DRAINAGE AND GARBAGE COLLECTION | | | SERVICES. PLEASE CONTACT THE CITY OF WEST PALM BEACH | | | PUBLIC WORKS DEPARTMENT - ENGINEERING SERVICES, AT | | | (561) 494-1040. | | | | | | 2.) PROVIDE LETTERS FROM ALL OF THE FOLLOWING PUBLIC | | | UTILITIES CONFIRMING THAT THE PROPOSED PROJECT DOES NOT | | | ENCROACH INTO THEIR EASEMENTS OR OTHERWISE INTERFERE | | | WITH THE PROVISIONS OF THEIR SERVICES: AT&T, FPL, FPU | | | AND COMCAST. | | | | | | | | | SITE PLAN COMMENTS: | | | | | | 1.) PLEASE MAKE THE FOLLOWING CORRECTIONS IN THE SITE | | | PLAN TABULAR (SHEET SP-1): EXISTING LAND USE AND ZONING | | | IS "COMMUNITY SERVICE (CS)"; PROPOSED LAND USE AND | | | ZONING IS "COMMUNITY SERVICE (CS)"; EXISTING LAND USE | | | IS "SCHOOL"; | | | | | | 2.) PLEASE EXPLAIN HOW THE "REQUIRED" PARKING OF 400 | | | PARKING SPACES WAS TABULATED. | | | | | | 3.) THE SITE PLAN SHOWS TWENTY (20) EXISTING PARALLEL | | | PARKING SPACES ALONG THE SOUTH DRIVEWAY; HOWEVER, THE | | | APPROVED SITE PLAN DOES NOT INDICATE THAT THAT PARALLEL | | | PARKING SPACES HAVE BEEN APPROVED. THESE PARKING SPACES | | | MUST BE REMOVED FROM THE SITE PLAN OR IF THERE IS | | | SUFFICIENT SPACE ALONG THE SOUTH DRIVE, THEN THE SITE | | | PLAN MUST DEMONSTRATE WITH DIMENSIONS, THAT THERE IS | | | ADEQUATE SPACE TO ACCOMMODATE PARALLEL PARKING. THE | | | SCOPE OF THE PROJECT (REVISED JUSTIFICATION STATEMENT) | | | MUST ALSO INCLUDE PARALLEL PARKING, IF THE PARKING | | | ALONG THE SOUTH DRIVE IS TO BE ADDED. | | | | | | 4.) WIDTH OF THE DRIVE AISLES AND NEW CONCRETE | | | SIDEWALKS SHALL BE DIMENSIONED IN THE SITE PLAN. | | | | | | 5.) INCLUDE A PARKING STALL STRIPING DETAIL IN THE SITE | | | PLAN. THE STRIPING DETAIL SHALL BE CONSISTENT WITH THE | | | REQUIREMENTS OF ZLDR S.94-485, STALL PAINTING DETAIL. | | | | | | 6.) BICYCLE PARKING SHALL BE PROVIDED. PURSUANT TO ZLDR | | | S.94-485(Q), ONE (1) BICYCLE PARKING SHALL BE PROVIDED | | | FOR EVERY TWENTY (20) AUTOMOBILE PARKING SPACES. | | | INCLUDE A RACK DETAIL WITH THE PLAN. | | | | | | 7.) THE FUTURE PARKING MUST EITHER BE PART OF THE | | | APPROVAL OR NOT. STAFF SUGGESTS A CONSTRUCTION PHASING | | | LINE IF IT IS TO BE PERMITTED SEPARATELY FOR | | | CONSTRUCTION. | | | | | | | | | LANDSCAPE PLAN COMMENTS: | | | | | | 1.) SHOW DIMENSIONS OF ALL INTERIOR AND TERMINAL | | | ISLANDS IN THE SITE PLAN AND LANDSCAPE PLAN. PURSUANT | | | TO ZLDR S.94-443(C)(3)A. AND B., THE LANDSCAPE ISLANDS | | | SHALL BE A MINIMUM OF 5 FT. WIDE MEASURED INSIDE THE | | | CURB. | | | | | | 2.) A TREE ALTERATION PERMIT IS REQUIRED PRIOR TO THE | | | REMOVAL OF ANY TREES ON THE PROPERTY FOR THE | | | CONSTRUCTION OF THE NEW PARKING LOT. PLEASE CONTACT RAY | | | CARANCI, CITY LANDSCAPE PLANNER, FOR ADDITIONAL | | | INFORMATION. | | | | | | 3.) ADDITIONAL COMMENTS TO BE PROVIDED BY THE CITY'S | | | LANDSCAPE PLANNER, RAY CARANCI @ (561) 822-1462. ALL | | | LANDSCAPE COMMENTS SHALL BE SATISFIED PRIOR TO SITE | | | PLAN APPROVAL. | | | | | | | | | INSTRUCTIONS FOR RESUBMITTAL: | | | | | | * PLEASE PROVIDE RESPONSES TO REVIEW COMMENTS IN | | | WRITTEN FORMAT. | | | | | | * WHEN RESUBMITTING, PLEASE PROVIDE A MINIMUM OF SIX | | | (6) PAPER COPIES, ONE (1) REDUCED COPY IN 8.5 INCHES X | | | 11 INCHES AND ONE (1) SET IN 11 INCHES X 17 INCHES, AND | | | AN ELECTRONIC COPY OF ALL PLANS. PLEASE NOTE THAT | | | CHANGES ON THE RESUBMITTED PLANS MAY RESULT IN | | | ADDITIONAL COMMENTS. | | | | | | * PLEASE NOTE THAT YOU WILL BE PERMITTED ONE (1) | | | RESUBMITTAL AT NO ADDITIONAL COST. IF PREVIOUSLY-ISSUED | | | COMMENTS CONTINUE TO NOT BE SUFFICIENTLY ADDRESSED, THE | | | APPLICANT WILL BE ASSESSED A RESUBMITTAL FEE. SUCH FEE | | | WILL BE 20 PERCENT OF THE ORIGINAL APPLICATION FEE | | | ($60). | | | | | | * CONTACT LINDA LOUIE @ (561) 822-1458 IF THERE ARE | | | QUESTIONS. |
|
|
| |