Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 09-19-2017 Cont ID  
Sent By rbrown Date 09-19-2017 Time 19:10 Rev Time 0.00
Received By rbrown Date 09-19-2017 Time 19:10 Sent To  
Notes
2017-09-19 19:11:10DEVELOPMENT SERVICES DEPARTMENT, BUILDING DIVISION,
 COMMENTS:
  
 NO COMMENTS ON THE PROPOSED RIGHT-OF-WAY ABANDONMENT.
  

Review Stop ENG - PPRC ENGINEERING - PPRC
Rev No 1 Status F Date 09-14-2017 Cont ID  
Sent By squinone Date 09-14-2017 Time   Rev Time 0.00
Received By squinone Date 09-14-2017 Time   Sent To  
Notes
2017-09-14 13:25:39CITY OF WEST PALM BEACH
 ENGINEERING SERVICES DEPARTMENT
 DATE: 09/20/2017
 PROJECT: CHADBOURNE COURT RIGHT-OF-WAY ABANDONMENT
 STATUS: FAILED
  
 THIS IS AN INITIAL LEVEL REVIEW. CONSTRUCTION LEVEL
 DETAILS, DESIGN CALCULATIONS, AND THE POLLUTION
 PREVENTION PLAN WILL BE REVIEWED AS PART OF THE
 ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT
 APPLICATION PROCESSES.
  
 NO CIVIL ENGINEERING PLANS WERE SUBMITTED IN THE
 INITIAL SITE PLAN PACKAGE INDICATING STORMWATER CONTROL
 AND PLANS FOR WATER AND SEWER SERVICES/CONNECTIONS
 RELOCATION OR EASEMENT. FOLLOWING COMMENTS NEED TO BE
 ADDRESSED PRIOR TO SITE PLAN APPROVAL:
  
 1. SHOW ALL EXISTING UTILITIES WITHIN THE VICINITY OF
 THE PROPOSED SITE AS WELL AS PROPOSED/RELOCATED
 UTILITIES (LABEL SIZE AND MATERIAL OF ALL PIPES AND
 CONDUITS ETC.);
  
 2. WATER MAIN, SEWER, AND STORMWATER FALL WITHIN THE
 PROPOSED PORTION OF CHADBOURNE COURT, WILL REQUIRE
 EASEMENT OVER UTILITIES.
  
 AFTER THE SITE PLAN IS APPROVED, IN THE NEXT PHASE, THE
 FOLLOWING GENERAL COMMENTS MUST BE ADDRESSED PRIOR TO
 ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING
 BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL:
  
 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION WILL
 BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT.
 THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS
 CAN BE DOWNLOADED FROM THE FOLLOWING WEBSITE LINK:
 HTTP://WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FOR
 MS,-PERMITS-APPLICATIONS
  
 2. PLEASE SUBMIT THE LATEST VERSION OF THE 'AUTO-CALC
 CERTIFIED COST ESTIMATE FORM' FOR SUBMISSION TO CITY OF
 WEST PALM BEACH PUBLIC WORKS DEPARTMENT FOR ADDITIONAL
 WORK PROPOSED. THIS FORM CAN BE DOWNLOADED FROM THE
 FOLLOWING LINK:
 HTTP://WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FOR
 MS,-PERMITS-APPLICATIONS
  
 SOFIA QUINONES-BENEJAM, EI
 PROJECT ENGINEER
 CITY OF WEST PALM BEACH
 401 CLEMATIS STREET, 4TH FLOOR
 WEST PALM BEACH, FL 33402
 (MAILING ADDRESS: PO BOX 3366)
 P: 561.494.1108
 C: 561.459.6518
 F: 561.494.1116
 EMAIL: [email protected]

Review Stop STORM STORMWATER
Rev No 1 Status P Date 09-07-2017 Cont ID  
Sent By tward Date 09-07-2017 Time 13:15 Rev Time 0.00
Received By tward Date 09-07-2017 Time 13:16 Sent To  
Notes
2017-09-07 13:16:231. CHADBOURNE COURT TO CONTINUE TO RECEIVE DRAINAGE
 SURFACE RUNOFF FROM S. OLIVE AVENUE OR THE SLOPE OF
 S.OLIVE AVENUE TO BE MODIFIED TO DIRECT THE RUNOFF TO
 THE S. OLIVE AVE DRAINAGE SYSTEM. ?SPREAD? CALCULATIONS
 TO BE PROVIDED FOR THE LATTER OPTION.
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120
 [email protected]
  

Review Stop SURVEY SURVEYING
Rev No 1 Status F Date 09-14-2017 Cont ID  
Sent By vnoel Date 09-14-2017 Time 11:14 Rev Time 0.00
Received By vnoel Date   Time   Sent To  
Notes
2017-09-14 11:45:521. APPRAISAL WILL BE REQUIRED. CITY WILL PROVIDE COST
 ESTIMATE.
 2. NOT ALL UTILITY SIGN-OFFS WERE RECEIVED.
 3. MODIFICATION FO EXISTING WATER SERVICE MAY BE
 REQUIRED.

Review Stop TRAFFIC TRAFFIC ENGINEERING
Rev No 1 Status P Date 09-18-2017 Cont ID  
Sent By   Date   Time   Rev Time 0.00
Received By   Date   Time   Sent To  
Notes
2017-09-18 09:09:26ERIK D. FERGUSON

Review Stop Z ZONING
Rev No 1 Status F Date 09-20-2017 Cont ID  
Sent By jroach Date 09-20-2017 Time 10:03 Rev Time 0.00
Received By jroach Date 09-20-2017 Time 10:03 Sent To  
Notes
2017-09-20 10:12:04ZONING PLANS AND PLATS REVIEW COMMITTEE (PPRC) REVIEW
 ___________________________________________
  
 DATE OF REVIEW: 09.20.2017
 PROJECT NO.: Z17080013
 CASE NO.: PB CASE #1231I
 ___________________________________________
  
 PLEASE PROVIDE A WRITTEN RESPONSE TO THE FOLLOWING
 REVIEW COMMENTS:
  
 1. PLEASE NOTE THAN AN APPRAISAL MAY BE REQUIRED FOR
 THE PROPOSED ABANDONMENT. IT HAS BEEN THE CTIY'S POLICY
 THAT THE ABANDONMENT OF RIGHTS-OF-WAY REQUIRE THAT THE
 APPLICANT PROVIDE COMPENSATION BASED UPON THE APPRAISED
 VALUE OF THE RIGHT-OF-WAY.
  
 2. PLEASE PROVIDE COPIES OF RESPONSES FROM ALL UTILITY
 COMPANIES; NOT ALL RESPONSES WERE PROVIDED.
  
 3. ABANDONMENT OF THE RIGHT-OF-WAY WIL BE SUBJECT TO
 THE SUBMITTAL OF A MAJOR AMENDMENT TO THE FIRST BAPTIST
 CHURCH CSPD TO EXPAND THE BOUNDARIES FO THE DEVELOPMENT
 AND MODIFY THE PARKING LOT ACCORDINGLY. APPROVAL OF
 THIS AMENDMENT WILL BE REQUIRED PRIOR TO EXECUTION OR
 RECORDATION OF ANY DISCLAIMER.
 ___________________________________________
  
 PLEASE NOTE THE FOLLOWING WHEN RESUBMITTING:
  
 A) WRITTEN RESPONSES TO COMMENTS MADE BY ALL
 DEPARTMENTS SHALL BE PROVIDED UPON RESUBMISSION.
  
 B) 15 SETS OF REVISED PLANS AND/OR DOCUMENTS SHALL BE
 PROVIDED, ALONG WITH AN ELECTRONIC COPY OF ALL PLANS.
  
 C) PLEASE NOTE THAT RE-SUBMITTALS MAY BE SUBJECT TO
 ADDITIONAL COMMENTS.
  
 D) IF NO RESPONSE IS RECEIVED WITHIN 60 DAYS OF THE
 ISSUANCE OF THESE COMMENTS, THE APPLICATION WILL BE
 CONSIDERED WITHDRAWN AND ANY FURTHER ACTION WILL
 REQUIRE SUBMISSION OF A NEW DEVELOPMENT APPLICATION.
  
 E) PLEASE NOTE THAT YOU WILL BE PERMITTED ONE (1)
 RESUBMITTAL AT NO ADDITIONAL COST. IF PREVIOUSLY-ISSUED
 COMMENTS CONTINUE TO NOT BE SUFFICIENTLY ADDRESSED, THE
 APPLICANT WILL BE ACCESSED A RESUBMITTAL FEE. SUCH FEE
 WILL BE 20% OF THE ORIGINAL APPLICATION FEE.
  
 F) IN ORDER TO BE CONSIDERED FOR THE NOVEMBER 20, 2017,
 CITY COMMISSION AGENDA, ALL COMMENTS SHALL BE
 SATISFACTORILY ADDRESSED. PLEASE SUBMIT ALL REVISED
 DOCUMENTS/PLANS NO LATER THAN OCTOBER 6, 2017.
  
 G) TO BE PLACED ON THE NOVEMBER 20, 2017, CITY
 COMMISSION AGENDA, SIGNS SHALL BE POSTED ON THE
 PROPERTY NO LATER THAN OCTOBER 21, 2017. SIGNAGE SHALL
 CONFORM AND BE INSTALLED WITH THE REQUIREMENTS OF THE
 CITY'S ZONING AND LAND DEVELOPMENT REGULATIONS, AS ALSO
 PROVIDED IN THE DEVELOPMENT APPLICATION. A SIGNED AND
 NOTARIZED AFFIDAVIT SHALL BE PROVIDED BY THE DEADLINE
 REFERENCED ABOVE.
 ___________________________________________
  
 QUESTIONS/COMMENTS, PLEASE CONTACT THE FOLLOWING:
  
 JOHN ROACH, PRINCIPAL PLANNER
 CITY OF WEST PALM BEACH
 DEVELOPMENT SERVICES DEPARTMENT - PLANNING DIVISION
 401 CLEMATIS STREET - P.O. BOX 3147
 WEST PALM BEACH, FLORIDA 33402
  
 PHONE: 561.822.1448
 FAX: 561.822.1460
  
 EMAIL: [email protected]
  
 WWW.WPB.ORG
  

  Print


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved