Plan Review Details - Project Z17050039
Plan Review Stops For Project Z17050039
Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time 0.00
Received By tward Date 07-21-2017 Time 09:09 Sent To  
Notes
***NONE***

Review Stop L LANDSCAPING
Rev No 2 Status P Date 07-20-2017 Cont ID  
Sent By rcaranci Date 07-20-2017 Time 16:52 Rev Time 0.00
Received By rcaranci Date 07-20-2017 Time 16:52 Sent To  
Notes
2017-07-20 16:52:50FROM: RAY CARANCI, LANDSCAPE PLANNER
 PROJECT: KEISER U STADIUM Z17050039
 JUNE 20, 2017
 I HAVE REVIEWED THE ABOVE REFERENCED PETITION, AND
 PROVIDE THE FOLLOWING COMMENTS:
  
 1. SATISFIED. PLEASE PROVIDE A TREE DISPOSITION CHART
 AND TREE MITIGATION CHART FOR THE TREES AFFECTED BY THE
 INSTALLATION OF THE PRACTICE FIELD.
  
 2. SATISFIED. PLEASE REVISE THE LANDSCAPE PLAN TO ONLY
 SHOW THE PRACTICE FIELD AND SOUTH BUFFER CHANGES.
  
 CONDITIONS OF APPROVAL
 1. IF DURING CONSTRUCTION IT IS DETERMINED THAT
 EXISTING TREES MAY HAVE TO BE REMOVED, PRIOR TO THE
 REMOVAL OR RELOCATION OF ANY TREES ON THE PROPERTY, A
 TREE ALTERATION PERMIT SHALL BE SUBMITTED, REVIEWED AND
 APPROVED BY THE DEVELOPMENT SERVICES DEPARTMENT,
 PLANNING DIVISION.
  
 2. PRIOR TO SUBMITTAL OF THE LANDSCAPE PERMIT, THE
 FLORIDA FRIENDLY LANDSCAPE CHART SHALL BE UPDATED TO
 SHOW 40 POINTS AS REQUIRED BY LANDSCAPE CODE AS OF
 4/21/17.
  

Review Stop L LANDSCAPING
Rev No 1 Status F Date 06-21-2017 Cont ID  
Sent By rcaranci Date 06-21-2017 Time 09:41 Rev Time 0.00
Received By rcaranci Date 06-21-2017 Time 09:41 Sent To  
Notes
2017-06-21 09:44:01FROM: RAY CARANCI, LANDSCAPE PLANNER
 PROJECT: KEISER U STADIUM Z17050039
 JUNE 20, 2017
 I HAVE REVIEWED THE ABOVE REFERENCED PETITION, AND
 PROVIDE THE FOLLOWING COMMENTS:
  
 1. PLEASE PROVIDE A TREE DISPOSITION CHART AND TREE
 MITIGATION CHART FOR THE TREES AFFECTED BY THE
 INSTALLATION OF THE PRACTICE FIELD.
  
 2. PLEASE REVISE THE LANDSCAPE PLAN TO ONLY SHOW THE
 PRACTICE FIELD AND SOUTH BUFFER CHANGES.
  
 CONDITIONS OF APPROVAL
 1. PRIOR TO THE REMOVAL OR RELOCATION OF ANY TREES ON
 THE PROPERTY, A TREE ALTERATION PERMIT SHALL BE
 SUBMITTED, REVIEWED AND APPROVED BY THE DEVELOPMENT
 SERVICES DEPARTMENT, PLANNING DIVISION.
  
  
  

Review Stop STORM STORMWATER
Rev No 3 Status P Date 08-17-2017 Cont ID  
Sent By tward Date 08-17-2017 Time 10:41 Rev Time 0.00
Received By tward Date 08-17-2017 Time 10:41 Sent To  
Notes
***NONE***

Review Stop STORM STORMWATER
Rev No 2 Status F Date 07-21-2017 Cont ID  
Sent By tward Date 07-21-2017 Time 08:48 Rev Time 0.00
Received By tward Date 07-21-2017 Time 09:09 Sent To  
Notes
2017-07-21 09:08:49THE COMMENTS BELOW ARE BASED UPON THE REVIEW OF THE
 JUNE 28, 2017 SUBMITTAL PACKAGE.
  
 1. THE DRAINAGE CALCULATIONS SHOULD REFERENCE THE SAME
 VERTICAL DATUM AS THE PLANS (NAVD1988).
  
 2. DRAINAGE CALCULATIONS SHOW A 1" RISE IN THE 25-YEAR
 3-DAY PEAK STAGE. DESIGN A PERIMETER BERM TO CONTAIN
 THIS STAGE INCREASE TO THE PROJECT AREA OR PROVIDE
 ADDITIONAL ONSITE STORAGE TO LOWER THE PEAK STAGE TO
 EXISTING CONDITIONS.
  
 3. THE SWALE ON THE LEFT SIDE OF SECTION A-A ON SHEET
 PDD-1 IS SHOWN TO HAVE A SIDE SLOPE OF 20:1 SLOPE
 BETWEEN THE SWALE CENTERLINE AND THE MATCHING SLOPE
 ALONG THE EDGE OF THE SECTION. THE PROPOSED SWALE
 CENTERLINE SPOT GRADES OF 14.9 AND 14.7 APPEAR TO BE
 HIGHER THAN THE EXISTING GRADES TO THE WEST OF THE
 SWALE.
  
 4. THE SPOT GRADES OF 15.4 AND 15.2 FOR THE CENTERLINE
 OF THE EAST SWALE APPEAR TO BE ABOVE THE MATCHING GRADE
 ALONG THE EAST SIDE OF THE SWALE.
  
 TRACY L. WARD, P.E.
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 [email protected]
 561-494-1120

Review Stop STORM STORMWATER
Rev No 1 Status F Date 06-20-2017 Cont ID  
Sent By tward Date 06-20-2017 Time 13:03 Rev Time 0.00
Received By tward Date 06-20-2017 Time 15:19 Sent To  
Notes
2017-06-20 15:18:59THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL
 DETAILS, DESIGN CALCULATIONS AND THE POLLUTION
 PREVENTION PLAN WILL BE REVIEWED AS PART OF THE
 ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT
 APPLICATION PROCESSES. THE ENGINEERING DEVELOPMENT
 APPROVAL APPLICATION FORMS CAN BE DOWNLOADED AT HTTP://
 WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FORMS,-PER
 MITS-APPLICATIONS
  
 THE FOLLOWING COMMENTS WERE GENERATED FROM THE REVIEW
 OF THE PLANS INCLUDED IN THE JUNE 8, 2017 REVIEW
 PACKAGE:
  
 1. LABEL THE VERTICAL DATUM ON THE GRADING AND DRAINAGE
 PLAN SHEET AND SECTIONS SHEET.
  
 2. COVER SHEET OF ENGINEERING PLANS INDICATE THE
 VERTICAL DATUM IS NAVD 1988. THE CITTY'S DATUM IS NGVD
 1929. PROVIDE THE CONVERSION BETWEEN THE TWO VERTICAL
 DATUMS WHEREVER NAVD 1988 IS SHOWN.
  
 3. INDICATE WHAT WILL HAPPEN TO THE TEST WELL.
  
 4. THE LANDSCAPE PLAN SHOWS INLETS AND STORM PIPE FOR
 THE DRY RETENTION AREA. THESE ARE NOT SHOWN ON THE
 ENGINEERING PLANS. THE UTILITIES SHOWN ON THE LANDSCAPE
 PLANS AND ENGINEERING PLANS SHOULD MATCH.
  
 5. INDICATE IF PROJECT AREA IS SUBJECT TO THE C-51
 BASIN RULE FOR FILL WITHIN THE FLOOD PLAIN.
  
 6. PROVIDE DRAINAGE CALCULATIONS SIGNED AND SEALED BY A
 PROFESSIONAL ENGINEERING DEMONSTRATING THE PROJECT
 MEETS SFWMD CRITERIA FOR WATER QUALITY AND WATER
 QUANTITY RUNOFF.
  
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120
 [email protected]
  

Review Stop Z ZONING
Rev No 2 Status P Date 07-20-2017 Cont ID  
Sent By eschneid Date 07-20-2017 Time 17:24 Rev Time 0.00
Received By eschneid Date 07-20-2017 Time 17:24 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status F Date 06-26-2017 Cont ID  
Sent By eschneid Date 06-26-2017 Time 15:53 Rev Time 0.00
Received By eschneid Date 06-26-2017 Time 15:52 Sent To  
Notes
2017-06-26 16:16:15CASE NO. PB1069V
 KEISER UNIVERSITY PRACTICE FIELD
 2600 N. MILITARY TRAIL
  
 - CONTACT ERIC SCHNEIDER @ (561) 822-1446
  
 - PLEASE PROVIDE RESPONSES TO REVIEW COMMENTS IN
 WRITTEN FORMAT.
  
 - WHEN RESUBMITTING, PLEASE PROVIDE A MINIMUM OF FIVE
 (5) PAPER COPIES AND AN ELECTRONIC COPY IN.PDF FORMAT
 OF ALL PLANS. PLEASE NOTE THAT CHANGES ON THE
 RESUBMITTED PLANS OR THE SUBMITTAL OF INFORMATION/PLANS
 TO ADDRESS THE COMMENTS MAY RESULT IN ADDITIONAL
 COMMENTS.
  
 - PLEASE NOTE THAT IF THE PLANNING DIVISION HAS NOT
 RECEIVED A RESPONSE TO THE PPRC COMMENTS WITHIN 60 DAYS
 FROM THE DATE OF THESE COMMENTS (BY AUGUST 26, 2017),
 THE CASE SHALL BE CONSIDERED WITHDRAWN. ANY FURTHER
 ACTION SHALL REQUIRE A NEW DEVELOPMENT APPLICATION.
  
 - PLEASE NOTE THAT YOU WILL BE PERMITTED ONE (1)
 RESUBMITTAL AT NO ADDITIONAL COST. IF PREVIOUSLY-ISSUED
 COMMENTS CONTINUE TO NOT BE SUFFICIENTLY ADDRESSED, THE
 APPLICANT WILL BE ACCESSED A RESUBMITTAL FEE. SUCH FEE
 WILL BE 20% OF THE ORIGINAL APPLICATION FEE ($60).
  
 1) THE LANDSCAPE PLAN SHOWS ITEMS THAT ARE NOT PART OF
 THE APPLICATION FOR THE PRACTICE FIELD ? EX: THE
 PARKING AND IMPROVEMENTS ALONG CECEILE AVENUE WHICH ARE
 BEING REVIEWED AS PART OF THE PENDING MAJOR PD
 AMENDMENT. THE LANDSCAPE PLAN MUST ONLY SHOW CHANGES
 WITHIN THE LIMITS OF WORK FOR THIS APPLICATION. PLEASE
 NOTE THIS IS HOW THE GRADING AND DRAINAGE PLAN HAS BEEN
 PRESENTED. THAT SHOULD BE USED AS THE BASE FOR THE
 LANDSCAPE PLAN AND ANY NEW LANDSCAPE SHOWN ON THE SOUTH
 AND WEST BUFFERS.
  