Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 03-08-2017 Cont ID  
Sent By rbrown Date 03-08-2017 Time 09:03 Rev Time 0.00
Received By rbrown Date 03-08-2017 Time 09:03 Sent To  
Notes
2017-03-08 09:10:37DEVELOPMENT SERVICES DEPARTMENT, BUILDING DIVISION,
 COMMENTS:
  
 1. THIS REVIEW IS A CURSORY REVIEW AS IT RELATES TO THE
 SITE. IT IS NOT A REVIEW FOR FULL COMPLIANCE WITH
 FLORIDA BUILDING CODE. THE FOLLOWING COMMENTS ARE TO BE
 ADDRESSED FOR PERMITTING.
  
 2. SITE PLAN, SHEET SP-1, DOES NOT SHOW ANY ACCESSIBLE
 ROUTE FROM THE PRESIDETIAL WAY. EMPLOYEES AND VISITORS
 WHO DO NOT ARRIVE BY CAR MUST BE ABLE TO ACCESS THE
 FACILITY. WHEN SUBMITTED FOR PERMIT, THE PLANS SHALL
 SHOW AT LEAST ONE ACCESSIBLE ROUTE, COMPLYING WITH
 SECTIONS 206.2 AND 402.2 OF FLORIDA ACCESSIBILITY CODE,
 FROM THE PUBLIC RIGHT-OF-WAY TO ALL ACCESSIBLE BUILDING
 OR FACILITY ENTRANCES.
  
 3. WHEN SUBMITTED FOR BUILDING PERMIT, THE PLANS SHALL
 SHOW THAT THE TYPE OF CONSTRUCTION FOR THE BUILDINGS
 WILL BE IN ACCORDANCE WITH THE HEIGHT, AREA AND
 OCCUPANCY LIMITATIONS IN CHAPTER 5 OF THE FLORIDA
 BUILDING CODE
  
 4. SEPARATE PERMITS REQUIRED. ALL APPLICABLE PERMITS
 AND SUB-PERMITS MUST BE OBTAINED BEFORE COMMENCING THE
 WORK. SEPARATE PERMITS, PLANS AND FEES, ARE REQUIRED
 FOR SIGNS, GAS SYSTEMS, GENERATORS, FIRE ALARM SYSTEMS,
 FIRE SPRINKLER AND OTHER FIRE SUPPRESSION SYSTEMS,
 GREASE INTERCEPTORS, SITE LIGHTING, SITE LANDSCAPE,
 SITE IRRIGATION, ETC.
  
 5. EACH SEPARATE BUILDING SHALL HAVE A SEPARATE
 ADDRESS. FOR STREET ADDRESSING, CONTACT MICHAEL ORIO,
 GIS SUPPORT SPECIALIST, AT (561) 494 1080, OR BY EMAIL:
 [email protected]
  
 6. IF THE VALUE OF THE ALL OF PROPOSED BUILDINGS AND
 STRUCTURES COMBINED EXCEEDS $750,000, THIS PROJECT WILL
 BE SUBJECT TO ART IN PUBLIC PLACES (AIPP) ASSESSMENT.
 FOR ADVICE ON THE PROVISION OF PUBLIC ARTWORK IN LIEU
 OF THE AIPP ASSESSMENT, CONTACT SYBILLE WELTER, ART IN
 PUBLIC PLACES COORDINATOR, AT (561) 822-1521, OR BY
 EMAIL: [email protected]
  
 ROBERT BROWN
 BUILDING OFFICIAL
 TEL: 561 805 6652
 EMAIL: [email protected]
  

Review Stop ENG - PPRC ENGINEERING - PPRC
Rev No 1 Status F Date 03-07-2017 Cont ID  
Sent By mkhan Date 03-07-2017 Time 16:20 Rev Time 4.00
Received By mkhan Date 03-07-2017 Time 16:20 Sent To  
Notes
2017-03-07 16:23:18CITY OF WEST PALM BEACH
 PUBLIC WORKS DEPARTMENT
 ENGINEERING DIVISION
  
 DATE: 03/07/2017
  
 Z17020023: 2300 PRESIDENTIAL WAY - BANYAN CAY GOLF
 COURSE MAINTENANCE FACILITY AND STORAGE
  
 THIS IS AN INITIAL LEVEL REVIEW. CONSTRUCTION LEVEL
 DETAILS, DESIGN CALCULATIONS, AND THE POLLUTION
 PREVENTION PLAN WILL BE REVIEWED AS PART OF THE
 ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT
 APPLICATION PROCESSES.
  
 THE FOLLOWING GENERAL COMMENTS MUST BE ADDRESSED PRIOR
 TO ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING
 BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL:
  
 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION WILL
 BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT.
 THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS
 CAN BE DOWNLOADED FROM THE FOLLOWING WEBSITE LINK:
  
 HTTP://WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FOR
 MS,-PERMITS-APPLICATIONS
  
 2. PLEASE SUBMIT THE LATEST VERSION OF THE 'AUTO-CALC
 CERTIFIED COST ESTIMATE FORM' FOR SUBMISSION TO CITY OF
 WEST PALM BEACH PUBLIC WORKS DEPARTMENT FOR ADDITIONAL
 WORK PROPOSED. THIS FORM CAN BE DOWNLOADED FROM THE
 FOLLOWING LINK:
  
 HTTP://WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FOR
 MS,-PERMITS-APPLICATIONS
  
 FOLLOWING GENERAL SITE COMMENTS:
  
 3. FOR SANITATION/GARBAGE COLLECTION CONTACT THE CITY'S
 PUBLIC WORKS DEPARTMENT. FINAL APPROVED SITE PLANS NEED
 TO SHOW PROPOSED SANITATION COLLECTION PLANS AND
 DETAILS; AND WILL NEED APPROVAL FROM PETER BIENIEK,
 PUBLIC WORKS DIRECTOR. PLEASE INCLUDE THE CITY OF WEST
 PALM BEACH STANDARD DETAIL FOR THE DUMPSTER ENCLOSURE
 ON THE PLANS. MINIMUM DIMENSIONAL (E.G. THE GATE WIDTH
 MUST BE A MINIMUM OF 12.5 FEET) REQUIREMENTS FOR THE
 ENCLOSURE ARE LISTED IN CODE OF ORDINANCES, SECTION
 94-444(B) OF THE CODE OF ORDINANCES. CITY STANDARD
 DETAIL GC-8 MAY BE DOWNLOADED AT:
  
 HTTP://WPB.ORG/ENGINEERING/ENGINEERING-SERVICES/ENGINEE
 RING-STANDARDS/
  
 4. IN THE FINAL PLANS SHOW ADA ACCESSIBLE RAMPS ON THE
 SIDEWALK AT EACH ENTRANCE AND EXIT /DRIVEWAY APPROACH;
  
 FOLLOWING ARE WATER AND SEWER COMMENTS AND NEED TO BE
 ADDRESSED PRIOR TO ENGINEERING DEPARTMENT APPROVAL:
  
 5. SUBMIT WITH THE ENGINEERING DEVELOPMENT APPROVAL
 APPLICATION SIGNED & SEALED ENGINEER/MEP WATER AND
 SANITARY SEWER CALCULATION (AVERAGE AND PEAK WITH
 PEAKING FACTOR). SUBMIT CALCULATIONS TO VALIDATE METER
 SIZE SELECTION. SHOW THESE CALCULATIONS ON THE UTILITY
 PLAN SHEET AS WELL;
  
 6. SHOW ON THE FINAL PLANS WHERE ARE THE PROPOSED WATER
 AND SANITARY SEWER LINES ARE CONNECTED TO EXISTING
 WATER AND SEWER MAINS ON THE PRESIDENTIAL WAY;
  
 7. THERE IS NO FIRE LINE SHOWN ON THE CONCEPTUAL PLAN;
 EVALUATE FIRE DEMAND FOR THE PROPOSED DEVELOPMENT AND
 PROVIDE CALCULATIONS. ANY PROPOSED FIRE LINE CONNECTION
 WITH APPROPRIATE DETAILS NEED TO BE SHOWN ON THE FINAL
 UTILITY PLANS;
  
 8. SHOW THE NEAREST FIRE HYDRANT TO THIS SITE ON THE
 FINAL UTILITY PLAN. FIRE HYDRANT FLOW TEST DATA FROM
 EXISTING FIRE HYDRANT WILL BE REQUIRED PART OF THE PLAN
 SUBMITTAL;
  
 9. PLEASE INCLUDE THE LATEST VERSION OF THE APPLICABLE
 CITY OF WEST PALM BEACH STANDARD UTILITY DETAILS TO THE
 DETAILS SHEET DURING SUBMISSION OF THE FINAL
 ENGINEERING PLANS. CONTACT THE ENGINEERING SERVICES
 DEPARTMENT FOR THE LATEST REVISED DETAILS IN CAD
 FORMAT. CITY?S STANDARD DETAILS (IN
 PDF FILE FORMAT) CAN BE DOWNLOADED FROM THE FOLLOWING
 SITE:
  
 HTTP://WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FOR
 MS,-PERMITS-APPLICATIONS
  
 10. PLACEMENT OF THE ANY PROPOSED METER, BACKFLOW
 PREVENTER, DCDA ETC. SHALL BE INSTALLED PER THE CITY'S
 STANDARD DETAILS. WATER METER SHOULD BE WITHIN THE
 RIGHT-OF-WAY OR INSIDE AN 'UTILITY EASEMENT' JUST
 INSIDE THE PROPERTY NEAR THE RIGHT-OF-WAY AND
 ACCESSIBLE;
  
 11. IN THE FINAL PLANS, SHOW CONFLICT INFORMATION
 (BOTTOM AND TOP OF CROSSING PIPES) AT THE CONFLICT
 POINTS OF ALL WATER, STORM AND SANITARY SEWER PIPES AS
 WELL AS OTHER FRANCHISE UTILITIES. EXISTING UTILITIES
 WITHIN THE PROPOSED SANITARY SEWER LATERAL ARE TO BE
 VERIFIED VIA SOFTDIGS AND PROVIDE ALL UTILITY CROSSING
 INFORMATION;
  
 12. IN THE FINAL PLANS, SHOW DIRECTION OF FLOW FOR THE
 EXISTING SANITARY SEWER. SHOW INVERT AT CONNECTION
 POINTS AND INCLUDE A PROFILE FOR THE PROPOSED SERVICE
 LATERAL WITH GROUND ELEVATIONS ABOVE THE PIPE;
  
 13. PAVEMENT RESTORATION WILL BE REQUIRED FOR THE
 PROPOSED SANITARY SEWER CONNECTION TO THE EXISTING
 MANHOLE WITHIN THE RIGHT-OF-WAY. REFER TO THE CITY
 STANDARD DETAILS FOR RESTORATION GUIDELINES;
  
 14. SHOW SIZE AND MATERIAL OF ALL EXISTING UTILITIES ON
 PRESIDENTIAL WAY INCLUDING BUT NOT LIMITED TO WATER,
 SEWER, GAS, UNDERGROUND ELECTRIC CONDUITS ETC.;
  
 15. FOR THE FINAL UTILITY PLANS, INCLUDE A NOTE THAT:
 AS OF DECEMBER 20, 2015 THE CITY OF WEST PALM BEACH
 CROSS-CONNECTION CONTROL MANUAL HAS BEEN REVISED,
 MAKING KNOWN THAT "ALL BACKFLOW DEVICES MUST BE LEAD
 FREE." FOR MORE INFORMATION REFER TO THE LINK BELOW:
  
 HTTP://WPB.ORG/DEPARTMENTS/PUBLIC-UTILITIES/FORMS-PUBLI
 CATIONS/BACKFLOW-CROSS-CONNECTION-CONTROL-MANUAL
  
 16. ALL PROPOSED FIRE DEPARTMENT CONNECTIONS SHALL BE
 WITHIN 150 FEET OF A FIRE HYDRANT AND SHALL BE WITHIN
 AN EASEMENT WITHIN THE PROPERTY. LANDSCAPE PLAN SHALL
 SHOW LOCATIONS OF ALL WATER METERS, VALVES, CLEAN-OUTS,
 LIGHT POLES, ETC. ROOT BARRIERS MAY BE REQUIRED WHERE
 PLANTINGS ARE NEAR UNDERGROUND STORMWATER, SANITARY, OR
 POTABLE WATER LINES.
  
 MOSTAQUE KHAN, P.E.
 LAND DEVELOPMENT ENGINEER
 [email protected]
 561-494-1124 (OFFICE)
  

Review Stop FIRE FIRE DEPARTMENT
Rev No 2 Status P Date 04-10-2017 Cont ID  
Sent By pleduc Date 04-10-2017 Time   Rev Time 0.00
Received By pleduc Date 04-10-2017 Time 12:58 Sent To  
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status P Date 03-03-2017 Cont ID  
Sent By pleduc Date 03-03-2017 Time   Rev Time 0.00
Received By pleduc Date 03-03-2017 Time 11:41 Sent To  
Notes
2017-03-03 11:45:09THE FOLLOWING COMMENTS WERE SUBMITTED BY PETER LEDUC,
 FIRE MARSHAL, BUREAU OF FIRE PREVENTION, WEST PALM
 BEACH FIRE RESCUE.
  
 THIS REVIEW CAN ONLY BE CONSIDERED PRELIMINARY AS THE
 DRAWINGS THAT WERE REVIEWED WERE NOT COMPLETE.
 ADDITIONAL COMMENTS CAN BE EXPECTED WHEN FULL DRAWINGS
 ARE SUBMITTED FOR PERMIT.
  
 THE FIRE PREVENTION BUREAU HAS NO OBJECTIONS TO THE
 PROPOSED PROJECT.
  
  
 1. CONSTRUCTION, DEMOLITION, AND RENOVATION TO COMPLY
 WITH NFPA 241. EXTRA ATTENTION SHALL BE GIVEN TO THE
 PERMITTING AND LOCATION OF CONSTRUCTION TRAILERS. A
 PERMIT IS REQUIRED FOR ANY CONSTRUCTION TRAILER RELATED
 TO THIS PROJECT. SEPARATION DISTANCES FROM MAIN
 STRUCTURES AS WELL AS OTHER TRAILERS SHALL BE CLOSELY
 MONITORED FOR THE REQUIREMENTS OF FIRE SPRINKLER
 PROTECTION.
  
  
 2. SITE ACCESS AND EXIT POINTS ARE TO BE CLEARLY
 IDENTIFIED AND MAINTAINED FOR EMERGENCY VEHICLES DURING
 ALL CONSTRUCTION ACTIVITIES.
  
  
 3. THE BUILDING ADDRESS SHALL BE CLEARLY VISIBLE FROM
 ALL ACCESS ROADWAYS, INCLUDING DURING CONSTRUCTION.
 ADDRESS NUMBERS SHALL CONTRAST WITH THEIR BACKGROUND
 AND SHALL NOT BE LESS THAN SIX (6) INCHES IN HEIGHT
 WITH A ONE (1) INCH STROKE FOR ALL BUILDINGS.
  
  
 4. DURING CONSTRUCTION, TRASH AND DEBRIS IS TO BE
 REMOVED FROM THE SITE DAILY OR MORE OFTEN TO REDUCE THE
 ACCUMULATION OF POTENTIAL LIFE AND FIRE SAFETY HAZARDS.
  
  
 5. THE CONSTRUCTION OF THE BUILDING SHALL COMPLY WITH
 THE 5TH EDITION OF THE FLORIDA FIRE PREVENTION CODE,
 INCLUDING NFPA 1 & 101, AND ALL ASSOCIATED FIRE CODES.
  
  
 6. FOR PLAN REVIEW SUBMITTAL, PLEASE INCLUDE THE
 OCCUPANCY TYPE, PER THE FLORIDA FIRE PREVENTION CODE,
 AND WHETHER IT IS MIXED OR SEPARATED OCCUPANCY.
  
  
 7. FOR PLAN REVIEW SUBMITTAL, PLEASE ENSURE THAT A FIRE
 LOAD CALCULATION IS INCLUDED AND THAT ADEQUATE WATER
 SUPPLY IS EXISTING OR WILL BE PROVIDED.
  
  
 8. ALL EXISTING AND NEW FIRE HYDRANTS PLANNED FOR THIS
 DEVELOPMENT SHALL BE CLEARLY INDICATED AND IDENTIFIED
 ON THE PLAN AND CLOSELY COORDINATED WITH THE BUREAU OF
 FIRE PREVENTION.
 ALL NEW FIRE HYDRANTS PLANNED FOR THIS DEVELOPMENT
 SHALL BE CLOSELY COORDINATED WITH THE BUREAU OF FIRE
 PREVENTION. PROPOSED FIRE HYDRANTS SHOULD BE LOCATED TO
 ALLOW FREE ACCESS FOR ARRIVING EMERGENCY VEHICLES.
  
  
 9. COMPLETE LIFE SAFETY PLANS FOR EACH OCCUPANCY SHALL
 BE PROVIDED THAT ILLUSTRATE OCCUPANT LOADS, TRAVEL
 DISTANCES, COMMON PATHS OF TRAVEL, DEAD-END CORRIDORS,
 EXIT SIGNS, EMERGENCY LIGHTING, EXITS LEADING TO A
 PUBLIC WAY, FIRE EXTINGUISHER LOCATIONS, AND ALL FIRE
 SAFETY FEATURES AND EQUIPMENT.
  
  
 11. IT IS HIGHLY RECOMMENDED FOR ANY ACCESS GATES THAT
 THEY BE PROVIDED WITH KNOX KEY ACCESS PADLOCKS AND/OR
 SWITCHES AND BUIDLINGS WITH A KNOX BOX FOR 24 HOUR
 EMERGENCY ACCESS.
  
  
 12. FOR PLAN REVIEW SUBMITTAL, PLEASE ENSURE THAT THE
 MSDS FOR ALL FERTILIZER AND CHEMICALS PROSED FOR
 STORAGE IS PROVIDED. BE SURE TO INCLUDED ALL RACK OR
 SHELVING, SEPARATION DISTANCES, SPILL CONTAINMENT, ETC.
  
  
 13. FOR PLAN REVIEW SUBMITTAL, THE FUELING STATION
 SHALL BE UNDER SEPARATE PERMIT AND COMPLY WITH NFPA 30
 & 30A AND ALL OTHER APPLICABLE LIFE SAFETY CODES AND
 STANDARDS.
  
  
 14. THE BUREAU'S APPROVAL OF THIS SUBMITTED PROJECT
 DOES NOT CONSTITUTE IT'S FINAL REVIEW OR APPROVAL.
  
  
 15. THE BUREAU SHALL REVIEW ALL SUBMITTED BUILDING
 PLANS AT THE APPROPRIATE TIME AND IN ACCORDANCE WITH
 THE REQUIREMENTS OF ALL APPLICABLE CODES AND STANDARDS.
  
  
 PETER LEDUC
 FIRE MARSHAL
 561-804-4709
 [email protected]
  
  
  

Review Stop L LANDSCAPING
Rev No 2 Status F Date 04-24-2017 Cont ID  
Sent By rcaranci Date 04-24-2017 Time 12:47 Rev Time 0.00
Received By rcaranci Date 04-24-2017 Time 12:47 Sent To  
Notes
2017-04-24 12:48:54PROJECT: BANYAN CAY GOLF MAINTENANCE Z17020023
 APRIL 21, 2017
 I HAVE REVIEWED THE ABOVE REFERENCED PETITION, AND
 PROVIDE THE FOLLOWING COMMENTS:
  
 1. NOT SATISFIED. PLEASE PROVIDE A TREE SURVEY AND A
 TREE DISPOSITION CHART FOR THE AREA WITHIN THE PROPERTY
 BOUNDARY. ALSO PROVIDE A TREE MITIGATION CHART
 IDENTIFYING EXISTING TREES ON THE PROPERTY THAT WILL BE
 REMOVED AND MITIGATION PROVIDED PER SECTION 94-448.
  
 PLEASE SHOW THE LOCATIONS OF THE PRESERVED AND
 RELOCATED TREES AND PALMS ON THE LANDSCAPE PLAN.
  
 2. NOT SATISFIED. PLEASE SHOW THE PROPERTY LINE ON THE
 LANDSCAPE PLAN.
  
 PLEASE SHOW PROPERTY LINE ON SHEET L-2 TO MATCH SITE
 PLAN AND SHEET L-1.
  
 3. SATISFIED. PLEASE PROVIDE ADDITIONAL INFORMATION TO
 SUBSTANTIATE THE POINTS CLAIMED FOR DROUGHT TOLERANT
 GRASS SPECIES, EXTRA SHADE TREES IN VEHICULAR USE
 AREAS, AND SOD AREA AS LESS THAN 50% OF LANDSCAPE AREAS
 AS SPECIFIED IN SECTION 94-446(G). PLEASE REVISE AND
 RECALCULATE TO CONFIRM PERCENTAGES FOR POINTS CLAIMED.
  
 4. SATISFIED. PLEASE ADD A COLUMN TO THE PLANT LIST
 IDENTIFYING NATIVE SPECIES.
  
 5. SATISFIED. PLEASE PROVIDE A BUFFER REQUIREMENTS
 CHART LISTING THE REQUIRED BUFFER LENGTH CALCULATIONS
 AND NUMBER OF TREES REQUIRED AND PROVIDED FOR EACH SIDE
 OF THE PROPERTY AND LABEL THE LOCATIONS OF THE 5 FOOT
 REQUIRED BUFFERS PER SECTION 94-442(B).
  
 6. SATISFIED. PLEASE REMOVE THE SITE DESIGN TABULAR
 CHART FROM SHEET L-2.
  
 7. SATISFIED. PLEASE PROVIDE CALCULATIONS TO SHOW THE
 LANDSCAPING MEETS THE 30% REQUIRED AROUND EACH BUILDING
 PER SECTION 94-443(E)(1).
  
 8. NOT SATISFIED. PLEASE PROVIDE CALCULATIONS TO SHOW
 COMPLIANCE WITH SECTION 94-443 (C)(3) AND (4) FOR THE
 LANDSCAPE AREAS REQUIREMENTS WITHIN THE PARKING AND
 PAVED AREAS, INCLUDING REQUIRED NUMBER OF SHADE TREES.
  
 SQUARE FOOTAGE OF REQUIRED AND PROVIDED LANDSCAPING
 WITHIN THE PARKING AREA NEEDS TO BE SHOWN.
  
 9. NOT SATISFIED. PLEASE SHOW ALL UTILITIES INCLUDING
 WATER, SEWER, AND FPL TRANSFORMERS ON THE LANDSCAPE
 PLAN. ADJUST UTILITY LOCATIONS TO AVOID TREES.
  
 PLEASE PROVIDE LOCATIONS OF WATER, SEWER AND FPL LINES
 SERVING THE BUILDING ON THE LANDSCAPE PLAN.
  
 10. NOT SATISFIED. PLEASE SHOW LOCATIONS OF LIGHTING TO
 AVOID CONFLICTS WITH TREES.
  
 AT LEAST 2 LOCATIONS SHOW CONFLICT BETWEEN TREES AND
 LIGHT PLACEMENT. PLEASE REVISE.
  
 11. SATISFIED. PLEASE SHOW CURBS FOR ALL VEHICULAR USE
 AREAS ADJACENT TO LANDSCAPE AREAS.
  
 12. NOT SATISFIED. PLEASE SHOW LOCATIONS OF ROOT
 BARRIERS TO PROTECT INFRASTRUCTURE AND TREES FROM
 CONFLICTS. THIS INCLUDES WATER, SEWER, DRAINAGE,
 SIDEWALKS AND CURBS, AND ANY FIELD STRUCTURES THAT
 COULD BE IMPACTED BY TREE ROOTS.
  
 UTILITIES NEED TO BE SHOWN, ADDITIONAL ROOT BARRIERS
 MAY BE REQUIRED.
  
 13. NOT SATISFIED. PLEASE PROVIDE SCREENING FOR ALL
 GROUND MOUNTED EQUIPMENT AND UTILITIES.
  
 UTILITIES NEED TO BE SHOWN, ADDITIONAL SCREENING MAY BE
 REQUIRED.
  
  
 14. SATISFIED. PLEASE PROVIDE A COMPLETE HEDGE AROUND
 THE THREE NON-ACCESS SIDES OF ALL DUMPSTER OR DEBRIS
 ENCLOSURES AS REQUIRED.
  
 15. SATISFIED. PLEASE INDICATE WHETHER THE CLASS B
 SPECIAL USE WILL ALSO APPLY TO THE PROPOSED REDESIGN OF
 THE LANDSCAPE FOR THE GOLF COURSE.
 ADDITIONAL COMMENTS 4/21/17:
 16. PLEASE ADD THE REQUIRED TREE IN THE TERMINAL
 LANDSCAPE ISLAND BETWEEN THE ROW OF PARKING AND THE
 STORAGE BINS.
  
  
 CONDITIONS OF APPROVAL
 1. PRIOR TO THE REMOVAL OR RELOCATION OF ANY TREES ON
 THE PROPERTY, A TREE ALTERATION PERMIT SHALL BE
 SUBMITTED, REVIEWED AND APPROVED BY THE DEVELOPMENT
 SERVICES DEPARTMENT, PLANNING DIVISION.
  

Review Stop L LANDSCAPING
Rev No 1 Status F Date 03-06-2017 Cont ID  
Sent By rcaranci Date 03-06-2017 Time 12:11 Rev Time 0.00
Received By rcaranci Date 03-06-2017 Time 12:11 Sent To  
Notes
2017-03-06 12:11:35FROM: RAY CARANCI, LANDSCAPE PLANNER 561-822-1462
 PROJECT: BANYAN CAY GOLF MAINTENANCE Z17020023
 MARCH 7, 2017
 I HAVE REVIEWED THE ABOVE REFERENCED PETITION, AND
 PROVIDE THE FOLLOWING COMMENTS:
  
 1. PLEASE PROVIDE A TREE SURVEY AND A TREE DISPOSITION
 CHART FOR THE AREA WITHIN THE PROPERTY BOUNDARY. ALSO
 PROVIDE A TREE MITIGATION CHART IDENTIFYING EXISTING
 TREES ON THE PROPERTY THAT WILL BE REMOVED AND
 MITIGATION PROVIDED PER SECTION 94-448.
  
 2. PLEASE SHOW THE PROPERTY LINE ON THE LANDSCAPE PLAN.
  
 3. PLEASE PROVIDE ADDITIONAL INFORMATION TO
 SUBSTANTIATE THE POINTS CLAIMED FOR DROUGHT TOLERANT
 GRASS SPECIES, EXTRA SHADE TREES IN VEHICULAR USE
 AREAS, AND SOD AREA AS LESS THAN 50% OF LANDSCAPE AREAS
 AS SPECIFIED IN SECTION 94-446(G). PLEASE REVISE AND
 RECALCULATE TO CONFIRM PERCENTAGES FOR POINTS CLAIMED.
  
 4. PLEASE ADD A COLUMN TO THE PLANT LIST IDENTIFYING
 NATIVE SPECIES.
  
 5. PLEASE PROVIDE A BUFFER REQUIREMENTS CHART LISTING
 THE REQUIRED BUFFER LENGTH CALCULATIONS AND NUMBER OF
 TREES REQUIRED AND PROVIDED FOR EACH SIDE OF THE
 PROPERTY AND LABEL THE LOCATIONS OF THE 5 FOOT REQUIRED
 BUFFERS PER SECTION 94-442(B).
  
 6. PLEASE REMOVE THE SITE DESIGN TABULAR CHART FROM
 SHEET L-2.
  
 7. PLEASE PROVIDE CALCULATIONS TO SHOW THE LANDSCAPING
 MEETS THE 30% REQUIRED AROUND EACH BUILDING PER SECTION
 94-443(E)(1).
  
 8. PLEASE PROVIDE CALCULATIONS TO SHOW COMPLIANCE WITH
 SECTION 94-443 (C)(3) AND (4) FOR THE LANDSCAPE AREAS
 REQUIREMENTS WITHIN THE PARKING AND PAVED AREAS,
 INCLUDING REQUIRED NUMBER OF SHADE TREES.
  
 9. PLEASE SHOW ALL UTILITIES INCLUDING WATER, SEWER,
 AND FPL TRANSFORMERS ON THE LANDSCAPE PLAN. ADJUST
 UTILITY LOCATIONS TO AVOID TREES.
  
 10. PLEASE SHOW LOCATIONS OF LIGHTING TO AVOID
 CONFLICTS WITH TREES.
  
 11. PLEASE SHOW CURBS FOR ALL VEHICULAR USE AREAS
 ADJACENT TO LANDSCAPE AREAS.
  
 12. PLEASE SHOW LOCATIONS OF ROOT BARRIERS TO PROTECT
 INFRASTRUCTURE AND TREES FROM CONFLICTS. THIS INCLUDES
 WATER, SEWER, DRAINAGE, SIDEWALKS AND CURBS, AND ANY
 FIELD STRUCTURES THAT COULD BE IMPACTED BY TREE ROOTS.
  
 13. PLEASE PROVIDE SCREENING FOR ALL GROUND MOUNTED
 EQUIPMENT AND UTILITIES.
  
 14. PLEASE PROVIDE A COMPLETE HEDGE AROUND THE THREE
 NON-ACCESS SIDES OF ALL DUMPSTER OR DEBRIS ENCLOSURES
 AS REQUIRED.
  
 15. PLEASE INDICATE WHETHER THE CLASS B SPECIAL USE
 WILL ALSO APPLY TO THE PROPOSED REDESIGN OF THE
 LANDSCAPE FOR THE GOLF COURSE.
  
 CONDITIONS OF APPROVAL
 1. PRIOR TO THE REMOVAL OR RELOCATION OF ANY TREES ON
 THE PROPERTY, A TREE ALTERATION PERMIT SHALL BE
 SUBMITTED, REVIEWED AND APPROVED BY THE DEVELOPMENT
 SERVICES DEPARTMENT, PLANNING DIVISION.
  

Review Stop PARK PARKING
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop POLICE POLICE
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop PW PUBLIC WORKS
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop STORM STORMWATER
Rev No 1 Status F Date 03-08-2017 Cont ID  
Sent By tward Date 03-08-2017 Time 11:39 Rev Time 0.00
Received By tward Date 03-08-2017 Time 11:41 Sent To  
Notes
2017-03-08 11:40:50THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL
 DETAILS, DESIGN CALCULATIONS AND THE POLLUTION
 PREVENTION PLAN WILL BE REVIEWED AS PART OF THE
 ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT
 APPLICATION PROCESSES. THE ENGINEERING DEVELOPMENT
 APPROVAL APPLICATION FORMS CAN BE DOWNLOADED AT HTTP://
 WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FORMS,-PER
 MITS-APPLICATIONS
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE
 PLAN APPROVAL:
  
 1. PRELIMINARY, UPDATED FEMA FLOOD INSURANCE MAPS ARE
 AVAILABLE AT
 HTTP://MAPS.CO.PALM-BEACH.FL.US/GIS/FLOODZONES.ASPX?.
 PLEASE REVIEW THE MAPS AND VERIFY THAT THE NEW MAPS
 WILL NOT IMPACT THE PROPOSED PROJECT.
  
 2. THE FREEBOARD REQUIREMENT FOR STRUCTURES IN A
 SPECIAL FLOOD HAZARD AREA IS ONE FOOT ABOVE BASE FLOOD
 ELEVATION.
  
 3. INDICATE LIMITS OF PRIVATE PORTION OF PRESIDENTIAL
 WAY ON SITE PLAN AND ENGINEERING PLANS.
  
 4. LIST VERTICAL DATUM ON GRADING AND DRAINAGE PLAN. IF
 NAVD 1988 THEN PROVIDE THE RELATIONSHIP BETWEEN NAVD
 1988 DATUM AND NGVD 1929 DATUM AT THIS LOCATION.
  
 5. SHOW EASEMENTS ON GRADING AND DRAINAGE PLAN.
  
 6. SHOW UTILITIES ON THE LANDSCAPE PLANS.
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO
 ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING
 BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL.
  
 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION WILL
 BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT.
 THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS
 CAN BE DOWNLOADED AT: HTTP://WPB.ORG/DEPARTMENTS/ENGINE
 ERING-PUBLIC-WORKS/FORMS,-PERMITS-APPLICATIONS
  
 2. PROVIDE A COPY OF THE SFWMD ERP MODIFICATION FOR
 THIS PROPOSED DEVELOPMENT.
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120
 [email protected]
  

Review Stop SURVEY SURVEYING
Rev No 1 Status F Date 03-03-2017 Cont ID  
Sent By vnoel Date 03-03-2017 Time 09:21 Rev Time  
Received By vnoel Date   Time   Sent To  
Notes
2017-03-03 09:37:431. NEED TO REVISE THE SKETCH AND DESCRIPTIONS OF THE
 FRONT AND BACK NINE TO DESCRIBED THE PARCEL, NOT A
 LESSED OUT DESCRIPTION. SKETCH NEEDS TO BE ANNOTATED
 AND INCLUDE ACREAGE.
 2. ARE THERE ANY UTILITIES IN THE 10' UE THAT CUTS THRU
 THE FACILITY?

Review Stop TRAFFIC TRAFFIC ENGINEERING
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status F Date 03-08-2017 Cont ID  
Sent By jroach Date 03-08-2017 Time 11:54 Rev Time 0.00
Received By jroach Date 03-08-2017 Time 11:54 Sent To  
Notes
2017-03-08 11:54:18PLANS AND PLATS REVIEW COMMITTEE (PPRC) ZONING REVIEW
 ___________________________________________
  
 DATE OF REVIEW: 03.08.2017
 PROJECT NO.: Z17020023
 CASE NO.: ZBA 3351
 ADDRESS: 2300 PRESIDENTIAL WAY
 APPLICANT/CONTACT: JONI BRINKMAN
 TELEPHONE NO.: 561.366.1100
 SCOPE OF REVIEW: GOLF MAINTENANCE FACILITY.
 ___________________________________________
  
 PLEASE PROVIDE A WRITTEN RESPONSE TO THE FOLLOWING
 REVIEW COMMENTS:
  
 1. ALL BUFFERS, SETBACKS, ETC. SHALL BE MEASURED FROM
 THE PROPERTY LINE?NOT THE PLAT LINE.
  
 2. IMPROVEMENTS ARE SHOWN IN EXISTING EASEMENTS.
 EASEMENT CONSENT SHALL BE OBTAINED FROM ALL UTILITY
 COMPANIES.
  
 3. THERE IS CONCERN REGARDING ADDITIONAL TRAFFIC BEING
 ADDED TO AN AREA OF PRESIDENTIAL WAY THAT IS CURRENTLY
 EXPERIENCING CONGESTION ISSUES. HAS ANY DISCUSSION
 OCCURRED WITH THE CITY?S TRAFFIC ENGINEER ON HOW THE
 PROPOSED FACILITY WILL IMPACT TRAFFIC FLOW, CAPACITY
 ETC.?
  
 4. PLEASE EXPLAIN HOW THE GATES WILL BE OPERATED. THERE
 IS INSUFFICIENT STACKING THAT WOULD CAUSE TRAFFIC TO
 BACK UP INTO THE ADJACENT ROADWAY AND BLOCK THE FLOW OF
 TRAFFIC.
  
 5. HAS THERE BEEN ANY COMMUNICATION WITH ADJACENT
 PROPERTY OWNERS/TENANTS? STAFF HAS SIGNIFICANT CONCERNS
 REGARDING THE PLACEMENT OF THE FACILITY AND ITS VARIOUS
 ANCILLARY ACTIVITIES (TRUCK TRAFFIC, VEGETATION DEBRIS
 COLLECTION, MATERIAL STORAGE, EQUIPMENT WASH, ETC.).
 THESE ANCILLARY ACTIVITIES PRESENT CONCERNS WITH REGARD
 TO THEIR INCOMPATIBILITY WITH THE OFFICE AND
 RESIDENTIAL DEVELOPMENTS IMMEDIATE ADJACENT TO THE
 PROPOSED FACILITY. SIGNIFICANT EFFORTS NEED TO BE MADE
 TO ENSURE THAT THE PROPOSED FACILITY DOES NOT
 NEGATIVELY IMPACT SURROUNDING DEVELOPMENT, AND COMPLIES
 WITH ALL OF THE REQUIRED SPECIAL USE STANDARDS REQUIRED
 BY THE CITY?S ZONING AND LAND DEVELOPMENT REGULATIONS.
 CITY STAFF REQUESTS THAT THEY BE NOTIFIED OF THE
 MEETINGS WITH THE RESIDENTS/ASSOCIATIONS AND THAT THEY
 ARE INCLUDED IN SUCH INVITATIONS.
  
 6. PLEASE PROVIDE A CROSS-SECTION, ELEVATION, OR SOME
 FORM OF RENDERING THAT WILL PROVIDE AN ACCURATE
 REPRESENTATION OF THE PROPOSED SCREENING AROUND THE
 FACILITY, SPECIFICALLY ALONG ADJACENT PROPERTIES. IT IS
 STAFF?S POSITION THAT THIS FACILITY SHOULD BE ENTIRELY
 SCREENED FROM VIEW.
 ___________________________________________
  
 PLEASE NOTE THE FOLLOWING WHEN RESUBMITTING:
  
 A) WRITTEN RESPONSES TO COMMENTS MADE BY ALL
 DEPARTMENTS SHALL BE PROVIDED UPON RESUBMISSION.
  
 B) 15 SETS OF REVISED PLANS AND/OR DOCUMENTS SHALL BE
 PROVIDED, ALONG WITH ONE (1) REDUCED COPY (11IN X
 17IN), AND AN ELECTRONIC COPY OF ALL PLANS.
  
 C) PLEASE NOTE THAT RE-SUBMITTALS MAY BE SUBJECT TO
 ADDITIONAL COMMENTS.
  
 D) IF NO RESPONSE IS RECEIVED WITHIN 60 DAYS OF THE
 ISSUANCE OF THESE COMMENTS, THE APPLICATION WILL BE
 CONSIDERED WITHDRAWN AND ANY FURTHER ACTION WILL
 REQUIRE SUBMISSION OF A NEW DEVELOPMENT APPLICATION.
  
 E) PLEASE NOTE THAT YOU WILL BE PERMITTED ONE (1)
 RESUBMITTAL AT NO ADDITIONAL COST. IF PREVIOUSLY-ISSUED
 COMMENTS CONTINUE TO NOT BE SUFFICIENTLY ADDRESSED, THE
 APPLICANT WILL BE ACCESSED A RESUBMITTAL FEE. SUCH FEE
 WILL BE 20% OF THE ORIGINAL APPLICATION FEE.
  
 F) IN ORDER TO BE CONSIDERED FOR THE MAY 4, 2017, ZBA
 AGENDA, ALL COMMENTS SHALL BE SATISFACTORILY ADDRESSED.
 PLEASE SUBMIT ALL REVISED DOCUMENTS/PLANS NO LATER THAN
 FRIDAY, MARCH 31, 2017.
 ___________________________________________
  
 QUESTIONS/COMMENTS, PLEASE CONTACT THE FOLLOWING:
  
 JOHN P. ROACH, AICP, PRINCIPAL PLANNER
 CITY OF WEST PALM BEACH
 DEVELOPMENT SERVICES DEPARTMENT ? PLANNING DIVISION
 401 CLEMATIS STREET - P.O. BOX 3147
 WEST PALM BEACH, FLORIDA 33402
  
 P: 561.822.1448
 F: 561.822.1460
  
 E: [email protected]
  
 W: WPB.ORG
  

  Print


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved