Plan Review Details - Project Z16010025
Plan Review Stops For Project Z16010025
Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 02-10-2016 Cont ID  
Sent By rbrown Date 02-10-2016 Time 12:16 Rev Time 0.00
Received By rbrown Date 02-10-2016 Time 12:16 Sent To  
Notes
2016-02-10 12:21:33DEVELOPMENT SERVICES DEPARTMENT, BUILDING DIVISION,
 COMMENTS:
  
 1. PLANS/ELEVATIONS SHOWING THE SQUARE FOOTAGE OF
 OPENINGS ON THE WEST ELEVATION OF THE PHASE I BUILDING
 WHERE IT IS CLOSEST TO THE PHASE II BUILDING, AND THE
 SQUARE FOOT AREA OF OPENINGS ON THE EAST ELEVATION OF
 PHASE II BUILDING WHERE IT IS CLOSEST TO THE PHASE I
 BUILDING, ARE REQUIRED IN ORDER TO VERIFY COMPLIANCE
 WITH ALL BUILDING SEPARATION, PERCENTAGE OF OPENINGS
 AND OPENING PROTECTIVE REQUIREMENTS OF CHAPTERS 6 AND 7
 OF THE FLORIDA BUILDING CODE.
  
 ROBERT BROWN
 BUILDING OFFICIAL
 TEL: 561 805 6652
 EMAIL: [email protected]
  

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status P Date 02-04-2016 Cont ID  
Sent By pleduc Date 02-04-2016 Time   Rev Time 0.00
Received By pleduc Date 02-04-2016 Time 17:13 Sent To  
Notes
2016-02-04 17:10:01THE FOLLOWING COMMENTS WERE SUBMITTED BY PETER LEDUC,
 FIRE MARSHAL, BUREAU OF FIRE PREVENTION, WEST PALM
 BEACH FIRE RESCUE.
  
 THIS REVIEW CAN ONLY BE CONSIDERED PRELIMINARY AS THE
 DRAWINGS THAT WERE REVIEWED WERE NOT COMPLETE.
 ADDITIONAL COMMENTS CAN BE EXPECTED WHEN FULL DRAWINGS
 ARE SUBMITTED FOR PERMIT.
  
 1. THE FIRE PREVENTION BUREAU HAS NO OBJECTIONS TO THE
 PROPOSED REPLAT.
  
 2. ENSURE THAT ANY FUTURE PHASE/BUILDING STRUCTURE WORK
 IS SUPPORTED WITH INDEPENDENT LIFE SAFETY SYSTEMS/WATER
 SUPPLY INFASTURCTURE.
  

Review Stop SURVEY SURVEYING
Rev No 1 Status F Date 02-08-2016 Cont ID  
Sent By cranford Date 02-08-2016 Time 15:49 Rev Time 0.00
Received By cranford Date 02-08-2016 Time 15:48 Sent To  
Notes
2016-02-08 15:49:40CITY OF WEST PALM BEACH
 PUBLIC WORKS DEPARTMENT
  
 THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL
 DETAILS, DESIGN CALCULATIONS AND THE POLLUTION
 PREVENTION PLAN WILL BE REVIEWED AS PART OF THE
 ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT
 APPLICATION PROCESSES. THE ENGINEERING DEVELOPMENT
 APPROVAL APPLICATION FORMS CAN BE DOWNLOADED AT
 HTTP://WPB.ORG/ENGINEERING/FORMS-AND-PUBLICATIONS/
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE
 PLAN APPROVAL.
  
 1. PLEASE PROVIDE A NARRATIVE EXPLAINING THE NEED FOR
 THE DECLARATION.
  
 2. DO THE NEW LOT LINES FOR TRACT B REQUIRE A
 MODIFICATION OF THE SITE PLAN?
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO
 ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING
 BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL.
  
 1. A SEPARATE SUBMITTAL WILL BE REQUIRED TO THE
 ENGINEERING DIVISION OF THE PUBLIC WORKS DEPARTMENT FOR
 ENGINEERING DEVELOPMENT APPROVAL. THE ENGINEERING
 DEVELOPMENT APPROVAL APPLICATION FORMS CAN BE
 DOWNLOADED AT
 HTTP://WPB.ORG/ENGINEERING/FORMS-AND-PUBLICATIONS/
  
 2. A SEPARATE SUBMITTAL WILL BE REQUIRED TO THE
 ENGINEERING DIVISION OF THE PUBLIC WORKS DEPARTMENT FOR
 PLAT APPROVAL. PLEASE CONTACT VINCE NOEL AT
 [email protected] TO GET A COPY OF THE PLAT APPLICATION.
 FINAL PLAT APPROVAL WILL BE BASED ON THE APPROVED SITE
 PLAN.
  
  
 KELLY CRANFORD, P.E.
 CAPITAL IMPROVEMENT PLAN MANAGER
 [email protected]
 561-494-1098 (OFFICE)
  
 VINCE NOEL, PSM
 CITY SURVEYOR / REAL ESTATE SUPERVISOR
 [email protected]
 561-494-1096
  
 BRIAN COLLINS, PE
 CITY TRAFFIC ENGINEER
 [email protected]
 561-494-1040
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 561-494-1120
 [email protected]
  
  

Review Stop Z ZONING
Rev No 1 Status F Date 02-10-2016 Cont ID  
Sent By aaponte Date 02-10-2016 Time 13:14 Rev Time 0.00
Received By aaponte Date 02-10-2016 Time 13:14 Sent To  
Notes
2016-02-10 14:02:191. SIDE SETBACK FOR PARKING GARAGE IS SHOWN AS 0'. THE
 CODE ALLOWS 0' WHEN THERE ARE NO OPENINGS ON THE
 FACADE. EXISTING GARAGE HAS OPENINGS THAT WILL BE
 LOCATED ON THE PROPERTY LINE. PLEASE CONSULT WITH
 BUILDING OFFICIAL THE REQUIRED SETBACK FOR THE AMOUNT
 OF EXISTING OPENINGS.
 2. IF THE GARAGE HAS MORE THAN 5 LEVELS, THE REQUIRED
 SIDE SETBACK IS 20' ABOVE TEH 5TH LEVEL.
 3. DAC APPROVAL WILL BE REQUIRED TO AUTHORIZE THE PHASE
 II OFF-SITE PARKING. 99 SPACES ARE NEEDED FOR THE
 PARCEL B. SUCH SPACES WILL BE LOCATED OFF SITE (ON
 PARCEL A OR C) NECESSITATING THE DAC APPROVAL.
 4. IF THE PROJECT IS SUBDIVIDED THE PHASE II WILL NOT
 COMPLY WITH THE PUBLIC OPEN SPACE REQUIREMENT.
 ADDITIONAL PUBLIC SPACE SHALL BE PROVIDED.
 5. PUBLIC OPEN SPACE IN FOR PARCEL A ALONG DIXIE HWAY
 SHALL BE EVALUATED TO DETERMINE COMPLIANCE WITH THE
 REQUIREMENTS FOR PUBLIC OPEN SPACE. AS ONE PORTION OF
 THE SPACE WAS REMOVED, PERCENTAGES OF TREE CANOPY, ,
 VEGETATED AREA AND OVERHEAD COVER MAY NEED TO BE
 ADJUSTED.
 6. PLEASE PROVIDE AN AS BUILT PLAN WITH THE EXACT AREAS
 CALCULATED AS PART OF THE PRIVATE OPEN SPACE IN PHASE
 I. AN ADDITIONAL ROOF TOP TERRACE ABOVE THE GARAGE IS
 INDICATED IN PHASE II TO COMPLY WITH PRIVATE OPEN SPACE
 REQUIREMENTS.
 7. PLEASE CONFIRM THE FAR CURRENTLY PROPOSED FOR PARCEL
 B IS 95,001 SF. PROPOSED FAR ON PARCEL B SHALL NOT
 EXCEED THE MAX FAR ALLOWED IN PARCEL B.
 8. BLANK WALL ARE NOT ALLOWED. THE EAST ELEVATION OF
 THE PARCEL B BUILDING (CLOSER TO THE GARAGE) SHALL
 INCLUDE OPENING TO COMPLY WITH THE BLANK WALL
 REGULATIONS.
 9. A 20' SETBACK WILL BE REQUIRED ABOVE THE 5TH FLOOR
 FOR PARCEL B.