| 2014-10-07 16:35:37 | GENERAL COMMENTS: |
| | |
| | 1.) IT SHALL BE UNLAWFUL FOR ANY OWNER, AGENT OR PERSON |
| | HAVING CONTROL OF ANY LAND WITHIN THE CITY TO SUBDIVIDE |
| | OR LAY OUT SUCH LAND INTO MORE THAN FOUR (4) LOTS, |
| | UNLESS BY PLAT, AND DESIGNED IN ACCORDANCE WITH THE |
| | REGULATIONS CONTAINED IN ARTICLE XI OF THE ZONING AND |
| | LAND DEVELOPMENT REGULATIONS [SECTION 94-44(C)]. |
| | SEPARATE SUBMITTAL AND REVIEW PROCESS REQUIRED. PLEASE |
| | CONTACT ENGINEERING SERVICES. |
| | |
| | 2.) 100 PERCENT OF THE GROUND FLOOR BUILDING AREA OF |
| | EACH UNIT SHALL BE CONVEYED TO THE OWNER IN A FEE |
| | SIMPLE TITLE. [SECTION 94-309(G)(3)] |
| | |
| | 3.) A PROPERTY OWNERS ASSOCIATION SHALL BE ESTABLISHED |
| | FOR THE MAINTENANCE OF ALL COMMON AREAS. [SECTION |
| | 94-309(G)(3)] |
| | |
| | 4.) CONCURRENCY LETTERS FROM PALM BEACH COUNTY TRAFFIC |
| | DIVISION AND THE SCHOOL DISTRICT OF PALM BEACH COUNTY |
| | REQUIRED. |
| | |
| | 5.) PROVIDE WRITTEN CONFIRMATION FROM THE PUBLIC |
| | UTILITIES DEPARTMENT INDICATING THAT THERE IS |
| | SUFFICIENT WATER, SEWAGE TREATMENT, STORM DRAINAGE AND |
| | GARBAGE COLLECTION SERVICES TO SERVE THE SITE. |
| | |
| | 6.) PROVIDE LETTERS FROM THE FOLLOWING PUBLIC UTILITIES |
| | CONFIRMING THAT THE PROPOSED PROJECT DOES NOT ENCROACH |
| | INTO THEIR EASEMENTS OR OTHERWISE INTERFERE WITH THE |
| | PROVISIONS OF THEIR SERVICES: AT&T, FLORIDA PUBLIC |
| | UTILITIES (FPU), FLORIDA POWER AND LIGHT (FP&L) AND |
| | COMCAST CABLE COMMUNICATIONS. |
| | |
| | 7.) PRIOR TO THE REMOVAL OF ANY TREES ON THE PROPERTY, |
| | THE APPLICANT SHALL APPLY FOR AND OBTAIN A TREE |
| | ALTERATION PERMIT FROM THE DEVELOPMENT SERVICES |
| | DEPARTMENT - PLANNING DIVISION. |
| | |
| | 8.) THE PARCEL SOUTH OF THE PROJECT (OXBRIDGE ACADEMY) |
| | IS ZONED CS AND NOT RPD. PLEASE CORRECT IN PLANS. |
| | |
| | 9.) PROVIDE A PLAN SHOWING THE LOCATION, HEIGHT AND |
| | INTENSITY OF ALL OUTDOOR ILLUMINATION. |
| | |
| | 10.) PROPOSED 10 FT. UTILITY EASEMENT DOES NOT SEEM |
| | CONNECTED. PLEASE CLARIFY. |
| | |
| | 11.) FDOT APPROVAL REQUIRED FOR CONNECTION ON MILITARY |
| | TRAIL. |
| | |
| | |
| | SITE PLAN: |
| | |
| | 1.) THE SITE PLAN SHALL COMPLY WITH THE GENERAL DESIGN |
| | STANDARDS FOR SUBDIVISION DESIGN PURSUANT TO SECTION |
| | 94-342 OF THE ZONING AND LAND DEVELOPMENT REGULATIONS. |
| | |
| | 2.) MORE INFORMATION IS NEEDED IN THE SITE DATA TABULAR |
| | REGARDING THE PERCENTAGES PROVIDED FOR REQUIRED AND |
| | PROPOSED IMPERVIOUS SPACE, OPEN SPACE, LANDSCAPED SPACE |
| | AND BUILDING COVERAGE AND FAR. THE FIGURES DO NOT ADD |
| | UP. SQUARE FOOTAGE CALCULATIONS AND THE BREAKDOWN OF |
| | OPEN SPACE SHOULD BE INCLUDED IN THE DATA TABULAR. |
| | |
| | 3.) PLEASE MAKE THE FOLLOWING CORRECTIONS IN THE SITE |
| | DATA TABULAR: |
| | A.) 2 PARKING SPACES REQUIRED FOR EACH UNIT (NOT |
| | BEDROOM) |
| | B.) TOTAL PARKING SPACES REQUIRED FOR THE PROJECT IS |
| | 105 (NOT 103) |
| | C.) INCLUDE THE CALCULATIONS FOR GUEST PARKING (1 |
| | PARKING SPACE FOR EVERY 10 UNITS) |
| | |
| | 4.) REVISE NOTE FOR THE PERPETUAL EASEMENT TO INCLUDE |
| | ITS PURPOSE. |
| | |
| | 5.) PROVIDE CLARIFICATION ON THE DRIVEWAY ACCESS TO THE |
| | UNITS. THE CENTER BLOCK CONTAINING BUILDINGS #5, #6, #7 |
| | AND #8 SEEM TO BE CURBED. HOW TO VEHICLES GET ACCESS TO |
| | DRIVEWAYS? |
| | |
| | 6.) WILL THERE BE A GATE AT THE EMERGENCY ACCESS PATH? |
| | IF SO, PLEASE DELINEATE IN THE PLAN. |
| | |
| | 7.) REVISE THE TOWNHOUSE PROPERTY DEVELOPMENT STANDARDS |
| | TO REFLECT A MAXIMUM HEIGHT OF 35 FEET. |
| | |
| | 8.) DELETE THE 6 FT. BY 9 FT. BICYCLE RACK DETAIL IN |
| | SHEET RP.1. THIS RACK WILL NOT BE UTILIZED IN THE |
| | PROJECT. |
| | |
| | 9.) WHAT IS THE HEIGHT OF THE PERIMETER POOL FENCE? THE |
| | HEIGHT OF THE POOL BARRIER MUST COMPLY WITH THE MINIMUM |
| | STANDARDS SET FORTH IN SECTION 94-304(D)(2)(B.) OF THE |
| | ZLDR. |
| | |
| | 10.) A 6 FT. HIGH BLACK CHAIN LINK FENCE IS DEPICTED |
| | WITHIN THE EASTERN PERIMETER BUFFER. PLEASE REVISE |
| | DETAIL E (10' ROW BUFFER WITH 5' U.E. OVERLAP) TO |
| | DELINEATE THE FENCE. THE FENCE, TREES AND SHRUBS CANNOT |
| | BE PLANTED WITHIN THE GENERAL UTILITY EASEMENT. |
| | |
| | 11.) DIRECTIONAL TRAFFIC ARROWS ARE RECOMMENDED AT THE |
| | ENTRANCE GATE. |
| | |
| | 12.) ADDITIONAL PEDESTRIAN FEATURES (I.E. CROSSWALKS |
| | AND SIDEWALKS, ACCESS POINTS IN/OUT OF DEVELOPMENT) ARE |
| | DESIRABLE. |
| | |
| | 13.) WHERE WILL DUMPSTERS BE LOCATED? PUBLIC WORKS |
| | DEPARTMENT TO REVIEW ROADWAY CIRCULATION DESIGN FOR |
| | SERVICE AND VEHICLE ACCESSIBILITY. |
| | |
| | |
| | LANDSCAPE PLAN: |
| | |
| | 1.) LANDSCAPE COMPLIANCE TABULAR REQUIRES CLARIFICATION |
| | IN ORDER TO DETERMINE COMPLIANCE WITH ARTICLE XIV OF |
| | THE ZONING AND LAND DEVELOPMENT REGULATIONS. PLEASE |
| | REVISE CALCULATIONS TO CLEARLY DISPLAY ALL RELEVANT |
| | INFORMATION, INCLUDING, BUT NOT LIMITED TO THE |
| | FOLLOWING: GROSS ACREAGE/SQUARE FOOTAGE, GROSS OPEN |
| | SPACE, SQUARE FOOTAGE OF PAVED LAND AND LANDSCAPED |
| | AREAS, EXISTING AND PROPOSED USE, ZONING DISTRICT, OPEN |
| | SPACE FOR TOWNHOUSE LOTS AND RECREATION AREA. |
| | |
| | 2.) PAVEMENT AND WALKWAYS IS TO COUNT TOWARDS OPEN |
| | SPACE REQUIREMENTS. REVISE DATA TABLES AND ALL |
| | CALCULATIONS. |
| | |
| | 3.) EACH TOWNHOUSE UNIT SHALL COMPLY WITH THE FOLLOWING |
| | LANDSCAPING REQUIREMENTS PER SECTION 94-442(B)(2)(A.) |
| | OF THE ZONING AND LAND DEVELOPMENT REGULATIONS. |
| | A.) ONE (1) SHADE OR FLOWERING TREE REQUIRED PER 1,200 |
| | SQ. FT. OF OPEN SPACE. |
| | B.) ONE (1) SHRUB PER 500 SQ. FT. OF OPEN SPACE. |
| | |
| | 4.) TREES AND SHRUBS CANNOT BE PLANTED WITHIN THE |
| | GENERAL UTILITY EASEMENTS. |
| | |
| | 5.) TREES AND HEDGES CANNOT BE PLANTED OR MAINTAINED |
| | WITHIN 3 FEET OF A FIRE HYDRANT. [ZLDR S.94-302(A)(1)] |
| | |
| | 6.) CONSIDERATION MUST BE GIVEN THE LANDSCAPE PLAN AND |
| | WHETHER OR NOT RESIDENTS WILL HAVE THE ABILITY |
| | CONSTRUCT SCREEN ENCLOSURES, PRIVACY WALLS OR FENCES |
| | ALONG PROPERTY LINES. THIS MAY IMPACT THE DESIGN OF THE |
| | LANDSCAPE PLAN. |
| | |
| | 7.) SUBMIT A PLAN FOR STREET TREES. CONSIDER MOVING |
| | WATER METERS CLOSER TO THE CURB TO ALLOW FOR THE |
| | PLANTING OF STREET TREES. |
| | |
| | 8.) OAK TREES SHALL BE PROVIDED WITH A ROOT BARRIER TO |
| | PREVENT DAMAGE TO BUILDINGS AND PAVEMENT. IT IS |
| | RECOMMENDED THAT THE PROPOSED OAK TREES AT THE REAR |
| | YARDS OF LOTS ARE MOVED FURTHER AWAY FROM THE |
| | STRUCTURE. |
| | |
| | 9.) RECREATION AREA: EACH ROW OF PARKING SPACES SHALL |
| | BE TERMINATED BY LANDSCAPE ISLANDS NOT LESS THAN 5 FEET |
| | IN WIDTH AND NOT LESS THAN THE ADJACENT PARKING STALL. |
| | THE LANDSCAPE ISLAND SHALL HAVE A MINIMUM OF 2 ? FEET |
| | AT ITS END SO AS TO ALLOW FOR CAR MANEUVERING. THE |
| | LANDSCAPE ISLAND SHALL CONTAIN AT LEAST 1 SHADE OR |
| | FLOWERING TREE. [ZLDR S. 94-443(C)(3)(A.)] |
| | |
| | 10.) SEE ADDITIONAL LANDSCAPING REQUIREMENTS FOR |
| | MULTIFAMILY RESIDENTIAL USES [SECTION 94-443(D)]. IT |
| | APPEARS ALL REQUIREMENTS HAVE BEEN MET, BUT PLEASE |
| | INCLUDE THEM IN THE LANDSCAPE CALCULATIONS TABLE. |
| | |
| | 11.) NOTATE THE LOCATION OF UTILITY EASEMENTS AND |
| | BUFFERS IN THE LANDSCAPE PLAN. |
| | |
| | 12.) RECREATION POD LANDSCAPE REQUIREMENTS [SECTION |
| | 94-442(B)(2)(B.)]: ONE (1) SHADE TREE PER 1,600 SQ. FT. |
| | OF OPEN SPACE; ONE (1) FLOWERING TREE PER 6400 SQ. FT. |
| | OF OPEN SPACE; AND ONE (1) SHRUB PER 500 SQ. FT. OF |
| | OPEN SPACE. PLEASE ILLUSTRATE COMPLIANCE. |
| | |
| | |
| | FLOOR PLANS AND ELEVATIONS: |
| | |
| | 1.) UNITS MUST BE A MINIMUM OF 900 SQ. FT. OF NET FLOOR |
| | AREA, EXCLUDING ATTIC, GARAGE AND UTILITY AREAS. IT |
| | APPEARS THAT THIS REQUIREMENT HAS BEEN MET, BUT PLEASE |
| | INCLUDE THE CALCULATIONS. [SECTION 94-309(G)(6)(F.)] |
| | |
| | 2.) FLOOR PLANS AND ELEVATIONS FOR BUILDING TYPE AVANTI |
| | (DL AND DR) DO NOT MATCH. PLEASE ADDRESS. |
| | |
| | 3.) THE SITE PLAN SHOWS ALL UNITS WILL HAVE A PATIO. |
| | PLEASE ADDRESS IN THE ARCHITECTURAL PLANS FOR |
| | CONSISTENCY. |
| | |
| | 4.) IT IS RECOMMENDED THAT THE UNITS FACING THE STREET |
| | WITH A SIDE ENTRANCE ARE IMPROVED WITH ARCHITECTURAL |
| | FEATURES (I.E. SHUTTERS, ORNAMENTS, ETC.) TO PROVIDE |
| | FOR ENHANCED FRONTAGES ALONG STREETS. |
| | |
| | 5.) ADDRESS THE OVERLAPPING TEXT IN THE PLANS. |
| | |
| | |
| | ENTRANCE MONUMENT SIGN: |
| | |
| | 1.) INCLUDE ALL DIMENSIONS IN THE TYPICAL ENTRANCE SIGN |
| | DETAIL. THE FREESTANDING SIGN CANNOT EXCEED 48 SQUARE |
| | FEET. MEASUREMENTS FROM THE SITE PLAN INDICATE THE |
| | MAXIMUM ALLOWABLE SIGN AREA HAS BEEN EXCEEDED. [ZLDR S. |
| | 94-407(2)(B.)(2.)] |
| | |
| | 2.) THE SIGN SHALL BE SETBACK 20 FEET FROM THE PUBLIC |
| | RIGHT-OF-WAY IF NOT PLACED PARALLEL TO THE STREET. |
| | [ZLDR S.94-407(2)(E.)] |
| | |
| | |
| | INSTRUCTIONS FOR RESUBMITTAL: |
| | |
| | * PLEASE PROVIDE RESPONSES TO REVIEW COMMENTS IN |
| | WRITTEN FORMAT. |
| | |
| | * WHEN RESUBMITTING, PLEASE PROVIDE A MINIMUM OF TEN |
| | (10) COPIES, ONE (1) REDUCED COPY (8 ? BY 11), AND AN |
| | ELECTRONIC COPY IN .PNG FORMAT OF ALL PLANS. PLEASE |
| | NOTE THAT RE-SUBMITTALS MAY BE SUBJECT TO ADDITIONAL |
| | COMMENTS. |
| | |
| | * PLEASE NOTE THAT YOU WILL BE PERMITTED ONE (1) |
| | RESUBMITTAL AT NO ADDITIONAL COST. IF PREVIOUSLY-ISSUED |
| | COMMENTS CONTINUE TO NOT BE SUFFICIENTLY ADDRESSED, THE |
| | APPLICANT WILL BE ACCESSED A RESUBMITTAL FEE. SUCH FEE |
| | WILL BE 20% ($200) OF THE ORIGINAL APPLICATION FEE. |
| | |