Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 10-07-2014 Cont ID  
Sent By rbrown Date 10-07-2014 Time 18:48 Rev Time 0.00
Received By rbrown Date 10-07-2014 Time 18:48 Sent To  
Notes
2014-10-07 18:50:01DEVELOPMENT SERVICES DEPARTMENT, BUILDING DIVISION,
 COMMENTS:
  
 NO COMMENTS ON THE MAJOR AMENDMENT FOR OUTPARCEL
 SUBDIVISION.

Review Stop ENG - PPRC ENGINEERING - PPRC
Rev No 1 Status P Date 09-30-2014 Cont ID  
Sent By cranford Date 09-30-2014 Time 11:56 Rev Time 0.00
Received By cranford Date 09-30-2014 Time 11:56 Sent To  
Notes
2014-09-30 11:56:39ENGINEERING/PUBLIC WORKS DEPT.
 LAND DEVELOPMENT AND STORMWATER
  
 NO OBJECTIONS TO CREATION OF OUTPARCEL.
  
 KELLY CRANFORD, P.E.
 LAND DEVELOPMENT ENGINEER
 ENGINEERING & PUBLIC WORKS DEPARTMENT
 CITY OF WEST PALM BEACH
 [email protected]
 561-494-1098 (OFFICE)
  

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status P Date 10-06-2014 Cont ID  
Sent By pleduc Date 10-06-2014 Time   Rev Time 0.00
Received By pleduc Date 10-06-2014 Time 14:02 Sent To  
Notes
2014-10-06 14:04:28THE FOLLOWING COMMENTS WERE SUBMITTED BY PETER LEDUC,
 FIRE MARSHAL, BUREAU OF FIRE PREVENTION, WEST PALM
 BEACH FIRE RESCUE.
  
 THIS REVIEW CAN ONLY BE CONSIDERED PRELIMINARY AS THE
 DRAWINGS THAT WERE REVIEWED WERE NOT COMPLETE.
 ADDITIONAL COMMENTS CAN BE EXPECTED WHEN FULL DRAWINGS
 ARE SUBMITTED FOR PERMIT.
  
 THE FIRE PREVENTION BUREAU HAS NO OBJECTIONS TO THE
 PROPOSED PROJECT.
  
 THE BUREAU'S APPROVAL OF THIS SUBMITTED PROJECT DOES
 NOT CONSTITUTE IT'S FINAL REVIEW OR APPROVAL.
  
 THE BUREAU SHALL REVIEW ALL SUBMITTED BUILDING PLANS AT
 THE APPROPRIATE TIME AND IN ACCORDANCE WITH THE
 REQUIREMENTS OF ALL APPLICABLE CODES AND STANDARDS.
  
  

Review Stop SURVEY SURVEYING
Rev No 1 Status P Date 10-02-2014 Cont ID  
Sent By vnoel Date 10-02-2014 Time 13:44 Rev Time  
Received By vnoel Date 10-02-2014 Time   Sent To  
Notes
2014-10-02 13:46:511. REPLAT WILL BE REQUIRED AT TIME OF SUBDIVISION ALONG
 WITH SURVEY SHOWING ALL IMPROVEMENTS.
 2. CROSS ACCESS/PARKING/UTILITY/DRAINAGE AGREEMENT WILL
 BE REQUIRED.

Review Stop TRAFFIC TRAFFIC ENGINEERING
Rev No 1 Status P Date   Cont ID  
Sent By   Date 10-07-2014 Time   Rev Time 0.00
Received By bcollins Date 10-07-2014 Time 08:13 Sent To  
Notes
2014-10-07 08:15:51A TRAFFIC IMPACT STUDY SHALL BE SUBMITTED WITH THE SITE
 PLAN SUBMISSION TO INCLUDE THE INTERSECTIONS OF PALM
 BEACH LAKES BOULEVARD WITH VILLAGE BOULEVARD AND
 ROBBINS DRIVE.

Review Stop Z ZONING
Rev No 1 Status P Date 10-08-2014 Cont ID  
Sent By jroach Date 10-08-2014 Time 15:17 Rev Time 0.00
Received By jroach Date 10-08-2014 Time 15:17 Sent To  
Notes
***NONE***