Plan Review Details - Project Z14090006
Plan Review Stops For Project Z14090006
Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 10-07-2014 Cont ID  
Sent By rbrown Date 10-07-2014 Time 20:02 Rev Time 0.00
Received By rbrown Date 10-07-2014 Time 20:02 Sent To  
Notes
2014-10-07 20:02:47DEVELOPMENT SERVICES DEPARTMENT, BUILDING DIVISION,
 COMMENTS:
  
 NO COMMENTS ON PROPOSED MINOR AMENDMENT.

Review Stop ENG - PPRC ENGINEERING - PPRC
Rev No 1 Status P Date 10-06-2014 Cont ID  
Sent By cranford Date 10-06-2014 Time 12:56 Rev Time 0.00
Received By cranford Date 10-06-2014 Time 12:55 Sent To  
Notes
2014-10-06 12:56:22ENGINEERING/PUBLIC WORKS DEPT.
 LAND DEVELOPMENT AND STORMWATER
  
 NO OBJECTIONS TO THE LOBBY MODIFICATION.
  
 KELLY CRANFORD, P.E.
 LAND DEVELOPMENT ENGINEER
 ENGINEERING & PUBLIC WORKS DEPARTMENT
 CITY OF WEST PALM BEACH
 [email protected]
 561-494-1098 (OFFICE)
  

Review Stop FIRE FIRE DEPARTMENT
Rev No 2 Status P Date 11-10-2014 Cont ID  
Sent By pleduc Date 11-10-2014 Time 14:54 Rev Time 0.00
Received By pleduc Date 11-10-2014 Time 14:54 Sent To  
Notes
2014-11-10 14:55:07THE PREVIOUSLY SUBMITTED FIRE PREVENTION BUREAU
 COMMENTS HAVE BEEN ADDRESSED.
  
 THE BUREAU'S APPROVAL OF THIS SUBMITTED PROJECT DOES
 NOT CONSTITUTE IT'S FINAL REVIEW OR APPROVAL.
  
 THE BUREAU SHALL REVIEW ALL SUBMITTED BUILDING PLANS AT
 THE APPROPRIATE TIME AND IN ACCORDANCE WITH THE
 REQUIREMENTS OF ALL APPLICABLE CODES AND STANDARDS.
  
 PETER LEDUC
 FIRE MARSHAL
 WEST PALM BEACH FIRE RESCUE
  

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status P Date 10-07-2014 Cont ID  
Sent By pleduc Date 10-07-2014 Time   Rev Time 0.00
Received By pleduc Date 10-07-2014 Time 09:22 Sent To  
Notes
2014-10-07 09:26:15THE FOLLOWING COMMENTS WERE SUBMITTED BY PETER LEDUC,
 FIRE MARSHAL, BUREAU OF FIRE PREVENTION, WEST PALM
 BEACH FIRE RESCUE.
  
 THIS REVIEW CAN ONLY BE CONSIDERED PRELIMINARY AS THE
 DRAWINGS THAT WERE REVIEWED WERE NOT COMPLETE.
 ADDITIONAL COMMENTS CAN BE EXPECTED WHEN FULL DRAWINGS
 ARE SUBMITTED FOR PERMIT.
  
 THE FIRE PREVENTION BUREAU HAS NO OBJECTIONS TO THE
 PROPOSED PROJECT.
  
 THE NATURE OF THE REMODEL REQUIRES AN EVALUATION OF THE
 FIRE ALARM AND SPRINKLER SYSTEM FOR CODE COVERAGE AND
 COMPLIANCE.
  
 THE LIFE SAFETY SYSTEMS, FIRE ALARM AND/OR FIRE
 SPRINKLER SHALL REMAIN ACTIVE THROUGHOUT THE
 CONSTRUCTION PERIOD.
  
 ANY AND ALL WORK ON THE FIRE ALARM AND FIRE SPRINKLER
 SYSTEMS SHALL BE DONE UNDER SEPARATE SHOP DRAWINGS AND
 BY CERTIFIED LIFE SAFETY CONTRACTORS.
  
 ANY TIME THAT WORK ON THE LIFE SAFETY SYSTEMS,
 SPRINKLER AND/OR FIRE ALARM, EXCEEDS 4 HOURS, A FIRE
 WATCH SHALL BE IMPLEMENTED AND MAINTAINED UNTIL FULL
 AND COMPLETE PROTECTION IS RETURNED.
  
  

Review Stop L LANDSCAPING
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop PARK PARKING
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop POLICE POLICE
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop PW PUBLIC WORKS
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop STORM STORMWATER
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop SURVEY SURVEYING
Rev No 2 Status P Date 11-07-2014 Cont ID  
Sent By vnoel Date 11-07-2014 Time 10:03 Rev Time 0.00
Received By vnoel Date   Time   Sent To  
Notes
***NONE***

Review Stop SURVEY SURVEYING
Rev No 1 Status F Date 10-06-2014 Cont ID  
Sent By vnoel Date 10-06-2014 Time 09:41 Rev Time  
Received By vnoel Date   Time   Sent To  
Notes
2014-10-06 09:44:371. NO SURVEY PROVIDED.
 2. SEPARATE SUBMITTAL WILL BE REQUIRED FOR SITE/CIVIL
 PLANS.
 3. RIGHT-OF-WAY PERMIT WILL BE REQUIRED FOR CLOSURE.
 4. PLANS DO NOT SHOW REVISED EXIT TO FLAGLER DR./6TH
 STREET.

Review Stop TRAFFIC TRAFFIC ENGINEERING
Rev No 1 Status F Date   Cont ID  
Sent By   Date 10-07-2014 Time   Rev Time 0.00
Received By bcollins Date 10-07-2014 Time 08:19 Sent To  
Notes
2014-10-07 08:20:17SITE PLAN DOES NOT SHOW DRIVEWAY MODIFICATIONS IN
 CONJUNCTION WITH FLAGLER BRIDGE PROJECT.

Review Stop Z ZONING
Rev No 1 Status F Date 10-08-2014 Cont ID  
Sent By aaponte Date 10-08-2014 Time 11:09 Rev Time 0.00
Received By aaponte Date 10-08-2014 Time 11:09 Sent To  
Notes
2014-10-08 11:18:331. FPL IS REQUESTING THE RELOCATION OF SOME EXISTING
 PALMS LOCATED ALONG OLIVE AVENUE DUE TO ITS PROXIMITY
 TO THE POWER LINES. BASED ON CURRENT CONDITIONS, THE
 PALMS CAN BE RELOCATED ADJACENT TO THE BUILDING WALL.
 2. PROPOSED HANDICAP SPACES HAVE THE ACCESSIBLE AISLE
 ON THE DRIVE AISLE. PLEASE STUDY A DIFFERENT OPTION TO
 ENSURE THE SAFETY OF HANDICAP USERS.