Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status F Date 09-25-2013 Cont ID  
Sent By rbrown Date 09-25-2013 Time 17:55 Rev Time 0.00
Received By rbrown Date 09-25-2013 Time 17:55 Sent To  
Notes
2013-09-25 17:57:32DEVELOPMENT SERVICES DEPARTMENT, BUILDING DIVISION,
 COMMENTS:
  
 COMMENTS FROM PREVIOUS REVIEW HAVE NOT BEEN ADDRESSED
 AT THIS STAGE, BUT MUST ADDRESSED WHEN THE PLANS ARE
 SUBMITTED FOR BUILDING PERMIT. IT IS NOTED THAT THE
 PLANS ARE VERY PRELIMINARY AT THIS STAGE AND ARE NOT
 INTENDED TO SPECIFICALLY ADDRESS BUILDING CODE
 REQUIREMENTS YET. THIS IS NOT A REVIEW FOR FULL
 COMPLIANCE WITH FLORIDA BUILDING CODE.
  
 ROBERT BROWN
 BUILDING OFFICIAL
 TEL: 561 805 6652
 EMAIL: [email protected]

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 09-11-2013 Cont ID  
Sent By pleduc Date 09-06-2013 Time 15:17 Rev Time 0.00
Received By rbrown Date 09-11-2013 Time 09:07 Sent To  
Notes
2013-09-11 09:28:30DEVELOPMENT SERVICES DEPARTMENT, BUILDING DIVISION,
 COMMENTS:
  
 1. IT IS NOTED THAT THE PLANS ARE VERY PRELIMINARY AT
 THIS STAGE AND ARE NOT INTENDED TO SPECIFICALLY ADDRESS
 BUILDING CODE REQUIREMENTS YET. THIS REVIEW IS A
 CURSORY REVIEW AS IT RELATES TO THE SITE. IT IS NOT A
 REVIEW FOR FULL COMPLIANCE WITH FLORIDA BUILDING CODE.
 THE FOLLOWING COMMENTS ARE TO BE ADDRESSED FOR
 PERMITTING.
  
 2. THE PROPOSED BUILDING WILL BE IN A FLOOD ZONE. THE
 LOWEST FLOOR OF THE BUILDINGS AND ALL ASSOCIATED
 MECHANICAL EQUIPMENT (CHILLERS, GENERATORS ETC.) SHALL
 BE EITHER FLOODPROOFED OR ELEVATED TO 6 INCHES
 (FREEBOARD) ABOVE THE BASE FLOOD ELEVATION.
  
 3. WHEN SUBMITTED FOR PERMIT, THE PLANS SHALL SHOW AT
 LEAST ONE ACCESSIBLE ROUTE, COMPLYING WITH SECTIONS
 206.2 AND 402.2 OF FLORIDA ACCESSIBILITY CODE, FROM THE
 PUBLIC RIGHT-OF-WAY TO ALL ACCESSIBLE BUILDING OR
 FACILITY ENTRANCES.
  
 4. WHEN SUBMITTED FOR PERMIT, THE PLANS SHALL SHOW AT
 LEAST ONE ACCESSIBLE ROUTE, COMPLYING WITH SECTIONS
 206.2 AND 402.2 OF FLORIDA ACCESSIBILITY CODE,
 CONNECTING ACCESSIBLE BUILDING OR FACILITY ENTRANCES
 WITH ALL ACCESSIBLE SPACES AND ELEMENTS WITHIN THE
 BUILDING OR FACILITY
  
 5. ANY PART OF AN ACCESSIBLE ROUTE WITH A SLOPE GREATER
 THAN 1:20 SHALL BE CONSIDERED A RAMP AND SHALL COMPLY
 WITH SECTION 405 OF FLORIDA ACCESSIBILITY CODE.
  
 6. PER SECTION 208.3 OF FLORIDA ACCESSIBILITY CODE
 ACCESSIBLE PARKING SPACES ARE TO BE LOCATED ON THE
 SHORTEST POSSIBLE ROUTE OF TRAVEL FROM ADJACENT PARKING
 TO AN ACCESSIBLE ENTRANCE FOR EACH BUILDING. THE DESIGN
 OF ACCESSIBLE PARKING SPACES SHALL COMPLY WITH SECTION
 502 OF FLORIDA ACCESSIBILITY CODE
  
 7. PER SECTION 208.2.4 OF FLORIDA ACCESSIBILITY CODE,
 ONE IN EVERY SIX ACCESSIBLE SPACES (AT LEAST ONE) IN A
 PARKING STRUCTURE, SHALL BE ?VAN ACCESSIBLE? AND
 DESIGNED IN ACCORDANCE WITH SECTION OF 502 OF FLORIDA
 ACCESSIBILITY CODE (VERTICAL CLEARANCE NOT LESS THAN 98
 INCHES AT SPACE AND VEHICLE ACCESS ROUTE)
  
 8. THE TYPE OF CONSTRUCTION FOR THE BUILDINGS SHALL BE
 IN ACCORDANCE WITH THE HEIGHT, AREA AND OCCUPANCY
 LIMITATIONS IN CHAPTER 5 OF THE FLORIDA BUILDING CODE
  
 9. COMPLIANCE WITH ALL BUILDING SEPARATION, PERCENTAGE
 OF OPENINGS AND OPENING PROTECTIVE REQUIREMENTS OF
 CHAPTERS 6 AND 7 OF THE FLORIDA BUILDING CODE SHALL BE
 VERIFIED.
  
 10. ENCLOSED PARKING GARAGES MUST HAVE EXHAUST SYSTEMS
 DESIGNED TO MINIMIZE NOISE LEVELS USING INLINE FAN
 SILENCERS OR OTHER APPROVED METHODS.
  
 11. ALL APPLICABLE PERMITS MUST BE OBTAINED BEFORE
 COMMENCING THE WORK.
  
 12. FOR STREET ADDRESSING CONTACT JOSH MILLS, GIS
 SUPPORT SPECIALIST ON 561 494 1084
  
 ROBERT BROWN
 BUILDING OFFICIAL
 TEL: 561 805 6652
 EMAIL: [email protected]
  

Review Stop ENG - PPRC ENGINEERING - PPRC
Rev No 1 Status F Date 09-10-2013 Cont ID  
Sent By mgonzale Date 09-10-2013 Time   Rev Time 8.00
Received By mgonzale Date 09-10-2013 Time   Sent To  
Notes
2013-09-11 12:24:39CASE 1445X (Z13080022), 1445Y (Z13080023) AND
 1445Z (Z13080024) RYBOVICH COMMERCIAL MARINE
  
 WATER
 EXISTING WATER UTILITIES ARE ALREADY LOCATED ADJACENT
 TO THE PROPERTY AND TWO (2) TAPS (16 X 12) AND (8 X 12)
 ARE INDICATED.
  
 THE PROPOSED 16 X 12 TAP IS SHOWN ON THE 16? DI
 SUBAQUEOUS LINE THAT CROSSES THE INTER COASTAL WATERWAY
 (ICW) AND SERVES THE NORTHERN PORTION OF THE TOWN OF
 PALM BEACH (TPB). A 12" TAP ON THIS LINE MAY CREATE
 PRESSURE ISSUES FOR THE TPB.
  
 ALSO, THE PROPOSED 8 X 12 TAP MAY NOT PROVIDE ENOUGH
 FLOW/PRESSURE THROUGH THE EXISTING 8" WATER MAIN TO
 PROVIDE SUFFICIENT DOMESTIC/FIRE LINE WATER FLOW TO
 SERVE THE FIVE (5) MULTI STORY CONDOS.
  
 ADDITIONAL FLOW WOULD BE AVAILABLE FROM THE EXISTING
 20" WATER MAIN THAT RUNS NORTH/SOUTH ON BROADWAY/US 1.
 THIS LINE MAY BE TAPPED VIA 38TH STREET WITH A SHORT
 DIRECTIONAL UNDER THE EXISTING PARKING LOT AT THE
 ELEMENTARY SCHOOL ACROSS THE STREET FROM THE EXISTING
 RYBOVICH MARINE LOCATION.
  
  
  
 SANITARY SEWER
 THE PROPOSED TIE-INS TO THE CITY'S SANITARY COLLECTION
 SYSTEM APPEAR UNDERSIZED BOTH FOR THE PROPOSED AND
 EXISTING FLOW DYNAMICS.
  
 THE EXISTING SANITARY SEWER LINE COLLECTS GRAVITY AND
 CASCADING FORCE MAIN (FM) FLOWS FROM THE ENTIRE NORTH
 END OF THE CITY EAST OF FLORIDA GULF COAST RAILROAD
 (FGC) AND ALSO ST. MARY?S HOSPITAL. THIS 24" LINE
 EXPANDS TO 36" (AND TO 42") BEFORE A 36" LINE ENTERS
 LIFT STATION 23 (LS 23) AT CURRY PARK WHICH PUMPS TO
 THE CITY'S 14" FORCE MAIN THAT IS DIRECTLY CONNECTED TO
 THE REGIONAL WASTE WATER PLANT (ECR).
  
 THE PROPOSED TOWERS 3 AND 4 SHOW DOGHOUSE MANHOLE
 CONNECTIONS TO THE 24" GRAVITY MAIN AND THIS WOULD NOT
 BE PREFERRED. THESE FLOWS SHOULD BE COLLECTED BY THE
 EXISTING PRIVATE MASTER LIFT STATION CURRENTLY ON THE
 RYBOVICH SITE.
  
 THE PROPOSED 4" FM TIE-IN TO THE EXISTING 12" FM IS NOT
 PREFERRED BECAUSE THIS LINE IS A CASCADING FLOW TO THE
 DOWNSTREAM MANHOLE. ADDITIONAL FLOW IN THIS LINE MAY
 CAUSE ADDITIONAL HEAD PRESSURE TO THE DISCHARGE OF THE
 UPSTREAM LIFT STATION 26 (LS26).
  
 THE NEED FOR SANITARY SEWER SYSTEM IMPROVEMENTS FOR
 THIS SITE MAY BE A SUBSTANTIAL CHALLENGE FOR THE CITY
 AND THE DEVELOPER.
  
  
  
 STORM WATER
 THE PROPOSED DESIGN ROUTES ALL COLLECTED STORM FLOWS TO
 THE ICW WITH NO DIRECT IMPACT THE CITY?S STORM WATER
 SYSTEM.
  
  
  

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status F Date 09-06-2013 Cont ID  
Sent By   Date 09-06-2013 Time   Rev Time 0.00
Received By pleduc Date 09-06-2013 Time 14:49 Sent To  
Notes
2013-09-06 15:16:56ALL ACCESS ROADS APPEAR TO BE DEAD ENDS WITH NO
 EMERGENCY VEHICLE ACCESS TURN AROUND POINTS. ACCESS TO
 THE DOCKS AND INTERIOR PROPERTY POINTS IS CRITICAL FOR
 FIRE AND RESCUE OPERATIONAL TACTICS AND STRATEGIES.
  
 BUILDINGS AND DOCKAGE FIRE HYDRANT AND FDC LOCATION AND
 IDENTIFICATION WILL BE NECESSARY.
  
 WATER SUPPLY CAPABILITIES MUST BE EVALUATED IN SUPPORT
 OF FIRE GROUND OPERATIONS AND THAT MEET MINIMUM
 REQUIREMENTS.
  
 ALL PROPOSED PROJECT EXITING CAPABILITES, CAPACITIES,
 PROTECTED EXIT WAYS, PROTECTED CORRIDORS, SAFE PUBLIC
 WAYS, ETC, REQUIRE CLEAR DISTINCTION AND EVALUATION.
  
  
  
 ALL CONSTRUCTION SHALL MEET THE LIFE AND FIRE SAFETY
 REQUIREMENTS OF THE CURRENT EDITION OF FLORIDA FIRE
 PREVENTION CODE.
  
  

Review Stop L LANDSCAPING
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop PARK PARKING
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop POLICE POLICE
Rev No 1 Status F Date 09-10-2013 Cont ID  
Sent By   Date 09-10-2013 Time   Rev Time 0.00
Received By ktucker Date 09-10-2013 Time 13:17 Sent To  
Notes
2013-09-10 13:21:37NOT ENOUGH INFORMATION AT THIS TIME FOR A CRIME
 PREVENTION REVIEW: WILL COMMENT WHEN THE APPLICANT
 SUBMITS THE FORMAIL SITE PLAN APPLICATION
  
  
  
 CONDITIONS FOR APPROVAL
 PRIOR TO ISSUANCE OF THE FIRST BUILDING PERMIT, THE
 APPLICANT SHALL PREPARE A CONSTRUCTION SITE SECURITY
 AND MANAGEMENT PLAN FOR APPROVAL BY THE CITY OF WEST
 PALM BEACH POLICE DEPARTMENT CPTED OFFICIAL.
 A. AFTER SITE CLEARING AND PLACEMENT OF CONSTRUCTION
 TRAILERS, THE DEVELOPER/PROJECT MANAGER SHALL INSTITUTE
 SECURITY MEASURES TO REDUCE OR ELIMINATE OPPORTUNITIES
 FOR THEFT. THE MANAGEMENT PLAN SHALL INCLUDE, BUT NOT
 BE LIMITED TO, TEMPORARY LIGHTING, SECURITY PERSONNEL,
 VEHICLE BARRIERS, CONSTRUCTION/VISITOR PASS,
 REDUCE/MINIMIZE ENTRY/EXIT POINTS, ENCOURAGE
 SUBCONTRACTORS TO SECURE MACHINERY, TOOLS AT END OF
 WORK DAY, FENCING WITH SCREENING AND OR ANY OTHER
 MEASURE DEEMED APPROPRIATE TO PROVIDE A SAFE AND SECURE
 WORKING ENVIRONMENT.
 B. THE SECURITY MANAGEMENT PLAN SHALL BE MAINTAINED
 THROUGHOUT THE CONSTRUCTION PHASE OF THE PROJECT.
 NON-COMPLIANCE WITH THE APPROVED PLAN SHALL RESULT IN A
 STOP-WORK ORDER FOR THE ENTIRE PLANNED UNIT
 DEVELOPMENT.
 C. PROPERTY SHALL BE POST ?NO TRESPASSING? SIGNS EVERY
 500 FEET AROUND THE PERIMETER OF THE SITE.
  

Review Stop PW PUBLIC WORKS
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop STORM STORMWATER
Rev No 2 Status P Date 10-01-2013 Cont ID  
Sent By tward Date 10-01-2013 Time 01:20 Rev Time 0.00
Received By tward Date   Time   Sent To  
Notes
2013-10-01 01:34:041. STORM DRAINAGE CONNECTIONS NEED TO BE CLARIFIED FOR
 THE FIRST PROPOSED ONSITE MANHOLE FOR THE CITY'S
 DRAINAGE SYSTEM THROUGH THE SITE (THE MANHOLE EAST OF
 THE DRIVEWAY LANDSCAPE ISLAND. IT APPEARS THERE IS A
 PIPE COMING DUE SOUTH OUT OF THE MANHOLE AND CONNECTING
 TO AN INLET ALONG THE WEST PROPERTY LINE. FROM THIS
 INLET, THERE IS A PIPE TO THE SOUTHEAST THAT CONNECTS
 TO A PROPOSED STORM MANHOLE. THE STORM MANHOLE HAS
 PROPOSED EXFILTRATION TRENCH SOUTH OF THE MANHOLE. THE
 DRAINAGE SYSTEM THEN TURNS TO THE EAST AND CONNECTS TO
 AN EXISTING OUTFALL JUST TO THE EAST-SOUTHEAST OF TOWER
 3. THUS IT APPEARS FROM THE INITIAL MANHOLE IN THE
 DRIVEWAY, WATER CAN FLOW SOUTH THEN EAST TO THE OUTFALL
 SOUTH OF TOWER 3 OR CONTINUE EAST OUT OF THE MANHOLE TO
 THE EXISTING 66" OUTFALL NORTHEAST OF THE EXISTING
 RESTAURANT. THE SOUTH CONVEYANCE WILL BYPASS THE
 PROPOSED POLLUTANT RETARDANT BASIN ON THE 66" OUTFALL
 PIPE.
 2. PERMITS FROM SFWMD AND/OR FDEP WILL BE NEEDED FOR
 THE SITE DRAINAGE SYSTEM AND THE CHANGES TO THE OUTFALL
 PIPE SIZES.
 3. PREVIOUS COMMENTS TO BE ADDRESSED IN LATER
 DEVELOPMENT PROCESS SUBMITTALS TO THE CITY.
  
 TRACY L. WARD, P.E.
 SENIOR STORMWATER ENGINEER
 ENGINEERING AND PUBLIC WORKS DEPARTMENT
 561-494-1120
  

Review Stop STORM STORMWATER
Rev No 1 Status F Date 09-11-2013 Cont ID  
Sent By tward Date 09-11-2013 Time 06:37 Rev Time  
Received By tward Date 09-11-2013 Time   Sent To  
Notes
2013-09-11 06:48:101. INDICATE IF PROPOSED PROJECT COMPLIES WITH
 SUPPLEMENTAL DISTRICT REGULATIONS 94-307:
 "ALL DEVELOPMENT SHALL PROVIDE FOR ADEQUATE DRAINAGE
 AND STORMWATER MANAGEMENT. COMPLIANCE WITH THE
 STORMWATER MANAGEMENT REQUIREMENTS OF SOUTH FLORIDA
 WATER MANAGEMENT DISTRICT F.A.C. 40E-4, SHALL
 CONSTITUTE COMPLIANCE WITH THIS PROVISION AND WITH THE
 PROVISIONS OF THE CITY'S COMPREHENSIVE PLAN WHICH
 RELATE TO THE AQUIFER RECHARGE AREAS. PROVIDED,
 HOWEVER, THAT THERE SHALL BE NO NEW DRAINAGE OUTFALLS
 INTO LAKE WORTH."
 2. IT APPEARS ONSITE DRAINAGE SYSTEM SOUTH OF 40TH
 STREET IS CONNECTED TO BOTH THE DRAINAGE SYSTEM FROM
 FLAGLER DRIVE AND TO ANOTHER OUTFALL INTO LAKE WORTH.
 THIS WILL ALLOW BYPASS OF THE STORM CEPTOR STRUCTURE.
 3. DRAINAGE EASEMENT FOR THE DRAINAGE SYSTEM FROM
 FLAGLER DRIVE TO THE OUTFALL WILL BE NEEDED. EASEMENT
 WIDTH AND RELATIVE LOCATION TO STORM PIPES TO BE
 DETERMINED.
 4. PLUG EXISTING 66" OUTFALL AT THE SEAWALL AFTER THE
 FLAGLER DRIVE DRAINAGE SYSTEM IS DIVERTED.
 5. ORIENT PLAN SHEETS TO HAVE NORTH ARROW POINTING IN
 SAME DIRECTION ON THE SHEETS.
 6. SFWMD ERP OR ERP MODIFICATION WILL NEED TO BE
 SUBMITTED TO CWPB ENGINEERING SERVICES BEFORE START OF
 CONSTRUCTION.
 7. SWPPP WILL NEED TO BE SUBMITTED WITH THE ENGINEERING
 PERMIT APPLICATION.
 8. FDEP NPDES CONSTRUCTION PERMIT WILL NEED TO BE
 SUBMITTED TO ENGINEERING SERVICES BEFORE START OF
 CONSTRUCTION.
  
 TRACY L. WARD, P.E.
 SENIOR STORMWATER ENGINEER
 ENGINEERING AND PUBLIC WORKS DEPARTMENT
 561-494-1120

Review Stop SURVEY SURVEYING
Rev No 2 Status P Date 09-26-2013 Cont ID  
Sent By vnoel Date 09-26-2013 Time 08:46 Rev Time 0.00
Received By vnoel Date   Time   Sent To  
Notes
2013-09-26 08:46:14PASSED BUT CONDITIONAL UPON REPLAT AND SITE/CIVIL
 SUBMITTAL TO ENGINEERING SERVICES.

Review Stop SURVEY SURVEYING
Rev No 1 Status F Date 09-09-2013 Cont ID  
Sent By vnoel Date 09-09-2013 Time 08:04 Rev Time  
Received By vnoel Date 09-09-2013 Time   Sent To  
Notes
2013-09-09 08:04:291. BOTH PROPERTIES WILL NEED TO BE REPLATTED.
 2. SEPARATE APPLICATION WILL BE NEEDED FOR SITE/CIVIL
 REVIEW AND FOR PLATS.
 3. EXISTING DEVELOPER'S AGREEMENT WITH RYBOVICH
 CONCERNING FLAGLER DRIVE WILL NEED REVIEW.
 4. THE INTERIM MARINA PLAN AND EXISTING CONDITIONS PLAN
 APPEAR TO BE THE SAME.
 5. THE SMALL FDOT TRIANGULAR PARCEL ALONG FLAGLER MAY
 NEED TO BE ACQUIRED.

Review Stop TRAFFIC TRAFFIC ENGINEERING
Rev No 2 Status P Date 11-22-2013 Cont ID  
Sent By jroach Date 11-22-2013 Time 15:08 Rev Time 0.00
Received By jroach Date 11-22-2013 Time 15:08 Sent To  
Notes
2013-11-22 15:09:28PURSUANT TO EMAIL FROM BRIAN COLLINS, CITY TRAFFIC
 ENGINEER, DATED 11/22/2013 (SEE ATTACHED)...
  
 I HAVE REVIEWED THE LATEST TRAFFIC STUDY, DATED
 NOVEMBER 2013, FOR THE PROPOSED TRG NORTH FLAGLER
 DEVELOPMENT. THIS STUDY ADDRESSES THE COMMENTS AND
 ISSUES PREVIOUSLY RAISED. IF APPROVED, I RECOMMEND THE
 FOLLOWING CONDITIONS:
  
 CHANGE TRAFFIC FLOW ON 40TH STREET BETWEEN FLAGLER
 DRIVE TO SPRUCE AVENUE FROM ONE-WAY TO TWO WAY.
 APPLICANT TO IMPLEMENT SIGNAL MODIFICATIONS AND CHANGES
 TO SIGNAGE AND STRIPING. PLANS WILL BE SUBMITTED TO,
 AND APPROVED BY, THE CITY OF WEST PALM BEACH
 ENGINEERING AND PUBLIC WORKS DEPARTMENT SIGNAL
 MODIFICATIONS TO BE COORDINATED WITH, AND APPROVED BY
 PALM BEACH COUNTY TRAFFIC DIVISION.
 APPLICANT TO CONSTRUCT NORTHBOUND LEFT TURN LANE ON
 FLAGLER DRIVE AT 45TH STREET. DESIGN TO BE APPROVED BY
 THE CITY OF WEST PALM BEACH ENGINEERING AND PUBLIC
 WORKS DEPARTMENT.
 APPLICANT WILL WORK WITH STAFF TO DETERMINE SCHEDULING
 OF THE ABOVE IMPROVEMENTS.
 APPLICANT TO BOND AND CONSTRUCT, WHEN WARRANTED, A
 TRAFFIC SIGNAL AT THE INTERSECTION OF FLAGLER DRIVE AND
 45TH STREET. APPLICANT WILL PREPARE TRAFFIC SIGNAL
 WARRANT STUDIES ANNUALLY STARTING AFTER THE FIRST
 OCCUPANCY PERMIT IS ISSUED.
  
 WITH THESE CHANGES, FLAGLER DRIVE AND ALL STUDY AREA
 INTERSECTIONS ARE PROJECTED TO OPERATE AT AN ACCEPTABLE
 LEVEL OF SERVICE AT FULL PROJECT BUILD-OUT.
  
  
 BRIAN A. COLLINS, P.E.
 CITY TRAFFIC ENGINEER
 TRANSPORTATION DIVISION
 ENGINEERING AND PUBLIC WORKS DEPARTMENT
 CITY OF WEST PALM BEACH
  
 TEL:(561) 494 - 1040
 FAX:(561) 494 - 1069

Review Stop TRAFFIC TRAFFIC ENGINEERING
Rev No 1 Status F Date 09-10-2013 Cont ID  
Sent By   Date 09-10-2013 Time   Rev Time 0.00
Received By bcollins Date 09-10-2013 Time 09:31 Sent To  
Notes
2013-09-10 09:37:23APPLICANT IS PREPARING A TRAFFIC IMPACT STUDY. WILL
 MAKE COMMENTS BASED ON REVIEW OF THAT STUDY AND THE
 TRAFFIC IMPACTS IN THE VICINITY OF THE PROJECT, THE
 ORIGINAL CONDITIONS ON THE RYBOVICH APPROVAL RELATING
 TO OFF-SITE IMPROVEMENTS, AND THE MULTIPLE ACCESS
 POINTS ALONG FLAGLER DRIVE.

Review Stop Z ZONING
Rev No 2 Status F Date 09-18-2013 Cont ID  
Sent By jroach Date 09-18-2013 Time 15:04 Rev Time 0.00
Received By jroach Date 09-18-2013 Time 15:04 Sent To  
Notes
2013-09-18 15:04:55THE FOLLOWING COMMENTS WERE PROVIDED BY ALEX HANSEN,
 SENIOR TRANSPORTATION PLANNER, REGARDING THE FUTURE
 LAND USE AMENDMENT TRAFFIC ANALYSIS...
  
 I HAVE THE FOLLOWING COMMENTS ON THE COMPREHENSIVE PLAN
 AMENDMENT TRAFFIC ANALYSIS FOR TRG NORTH FLAGLER
 PREPARED BY KIMLEY-HORN AND DATED AUGUST 2013:
  
 - WHILE FOR THE MOST PART THE ANALYSIS FOLLOWS THE
 GUIDELINES OF PALM BEACH COUNTY FLU ELEMENT POLICY
 3.5-D, WHICH IS WHAT WE ADVISE APPLICANTS TO FOLLOW,
 THERE ARE TWO COMPONENTS WHERE THE STUDY DOES NOT MEET
 THE GUIDELINES OF 3.5-D:
  
 1) THE YEAR 2035 MODEL VOLUMES INCLUDED IN THE STUDY
 WERE OBTAINED FROM THE 2035 GREATER TREASURE COAST
 REGIONAL PLANNING COUNCIL. POLICY 3.5-D CALLS FOR THE
 USE OF THE MPO'S LATEST ADOPTED LONG RANGE
 TRANSPORTATION PLAN (LRTP) AS AMENDED. AS A RESULT, THE
 STUDY SHOULD BE REVISED TO USE THE PROJECTED MPO LRTP
 VOLUMES.
  
 2) POLICY 3.5-D ALSO REQUIRES THE TRAFFIC STUDY TO
 REFLECT THE TRIPS FROM THE LATEST AVAILABLE FUTURE LAND
 USE AMENDMENTS THAT BECAME EFFECTIVE SUBSEQUENT TO THE
 ADOPTION OF THE LRTP, WHICH I BELIEVE HAPPENED AROUND
 2010.

Review Stop Z ZONING
Rev No 1 Status F Date 09-11-2013 Cont ID  
Sent By jroach Date 09-11-2013 Time 09:59 Rev Time 0.00
Received By jroach Date 09-11-2013 Time 09:59 Sent To  
Notes
2013-09-11 10:00:16ZONING PLANS AND PLATS REVIEW COMMITTEE (PPRC) REVIEW
 ___________________________________________
  
 DATE OF REVIEW: 09.11.2013
 PROJECT NO.: Z13080022, Z13080023 AND Z13080024
 CASE NO.: PB 1445X, Y AND Z
 ADDRESS: 4200 NORTH FLAGLER DRIVE
 APPLICANT/CONTACT: LYNDA HARRIS AND JOSEPH VERDONE
 TELEPHONE NO.: 561.659.7070
 ___________________________________________
  
 PLEASE PROVIDE A WRITTEN RESPONSE TO THE FOLLOWING
 REVIEW COMMENTS:
  
 1. THERE ARE SIGNIFICANT CONCERNS WITH THE PROPOSED
 UTILIZATION OF THE PERMISSIBLE BUILDING AREAS (PBAS)
 AND DESIGN GUIDELINES GIVEN THE AMOUNT OF INFORMATION
 THAT HAS BEEN PROVIDED. THE REQUIREMENTS SPELLED OUT ON
 THE MASTER PLAN AND THE DESIGN GUIDELINES LEAVE A LOT
 OF UNKNOWN ABOUT WHAT COULD POTENTIALLY BE BUILT WITHIN
 SUCH PARAMETERS. IN ORDER TO HAVE A COMFORT LEVEL WITH
 PBAS, THERE NEEDS TO BE SIGNIFICANT DETAIL IN THE
 DESIGN GUIDELINES SO THAT EVERYONE KNOWS ULTIMATELY
 WHAT THE DEVELOPMENT COULD AND WILL LOOK LIKE. SOME
 EXAMPLES INCLUDE, BUT ARE NOT LIMITED TO:
  
 A. NO MAXIMUM HEIGHT IS SPECIFIED, WITH THE EXCEPTION
 OF THE NUMBER OF STORIES. THEREFORE, A BUILDING COULD
 VARY IN HEIGHT SIGNIFICANTLY AND THE ONLY REQUIREMENT
 IS THAT IT BE 50-55 FEET FROM THE PROPERTY LINE.
  
 B. IF THE PRESCRIBED SIZE OF THE BUILDING FOOTPRINT IS
 UTILIZED, WHAT DOES THIS TRANSLATE TO IN THE FINAL
 PRODUCT? HAVE 3-D MODELS BEEN PREPARED TO SHOW WHAT THE
 MAXIMUM BUILD-OUT COULD BE UNDER THE GUIDELINES
 PROPOSED?
  
 C. HOW ARE THE FACADES OF THE GARAGES ADDRESSED? THERE
 IS SIGNIFICANT CONCERN THAT NEARLY ALL OF THE BUILDINGS
 ARE SHOWN AS UN-LINED GARAGES OPEN TO NORTH FLAGLER
 DRIVE, AS WELL AS TO THE NORTH AND SOUTH. IN
 COMBINATION WITH COMMENT D. BELOW, THIS DOES NOT
 POSITIVELY ADDRESS THE STREET AND ALLOW THE PROJECT TO
 INTERACT WITH THE SURROUNDING COMMUNITY.
  
 D. CROSS SECTIONS HAVE ONLY BEEN PROVIDED FOR A PORTION
 OF THE NORTH FLAGLER DRIVE BUFFER. WHAT DOES THE
 REMAINDER LOOK LIKE? ADDITIONALLY, ELEVATING THE
 SIDEWALK, BUILDING A BERM, ETC. ?WALLS-OFF? THE PROJECT
 FROM THE RIGHT-OF-WAY; AND IN CONNECTION WITH EXPOSED
 PARKING GARAGES, DOES NOT POSITIVELY ADDRESS THE STREET
 AND SURROUNDING AREA.
  
 E. THE DESIGN GUIDELINES INDICATE THAT 30% OF THE
 DENSITY/INTENSITY CAN BE TRANSFERRED BETWEEN PBAS; DOES
 THIS MEAN THAT MASSING, ETC. CAN BE TRANSFERRED AS WELL
 (I.E. SIZE OF BUILDING FOOTPRINT)? THIS LEAVE A
 SIGNIFICANT AMOUNT OF FLEXIBILITY THAT MAKES IT HARD TO
 DETERMINE THE MAXIMUM BUILD-OUT POTENTIAL.
  
 F. BUILDINGS CAN BE PLACED ANYWHERE WITHIN THE PBA.
  
 STAFF WOULD REQUEST THAT A FOLLOW-UP MEETING BE HELD TO
 DISCUSS THESE ISSUES IN FURTHER DETAIL AND DETERMINE
 THE BEST SOLUTION. AS PROPOSED, THE REQUIREMENTS ARE
 TOO VAGUE AND THE IMPACT OF THE POTENTIAL BUILD-OUT
 CANNOT BE DETERMINED. AT THIS MEETING, MORE SPECIFIC
 COMMENTS CAN BE PROVIDED REGARDING THE CONTENTS OF THE
 DESIGN GUIDELINES.
  
 2. A NEW TRAFFIC CONCURRENCY APPROVAL SHALL BE PROVIDED
 FROM PALM BEACH COUNTY.
  
 3. PROJECT FACT SHEET SHALL BE COMPLETED AND PROVIDED.
  
 4. JUSTIFICATION STATEMENT
  
 A. ON PAGE 2 IT INDICATES THAT RYBOVICH HAD PREVIOUSLY
 PROPOSED 488 UNITS?ONLY 448 UNITS WERE APPROVED.
  
 B. ON PAGE 4, UNDER THE ?FLU AMENDMENT? SECTION, IT
 INDICATES THAT THE TRG PROPERTY IS BEING CHANGED FROM
 MULTIFAMILY TO COMMERCIAL. OTHER DOCUMENTATION
 INDICATES THAT IT IS BEING CHANGED TO COMMERCIAL EAST
 (CE). PLEASE CLARIFY AND ENSURE ALL DOCUMENTATION,
 STUDIES, PLANS, ETC. ARE CONSISTENT.
  
 C. ON PAGE 4, IT INDICATES THAT NO OTHER COMMERCIAL
 USES ARE PROPOSED ON THE TRG PROPERTY. THE PROPOSED
 MASTER PLAN INDICATES THE BEACH CLUB IS PROPOSED.
 PLEASE CLARIFY AND ENSURE THAT ALL DOCUMENTATION AND
 PLANS ARE CONSISTENT. PLEASE PROVIDED ADDITIONAL DETAIL
 REGARDING THE BEACH CLUB?IS THIS OPEN TO THE PUBLIC? IS
 IT RESTRICTED TO JUST RESIDENTS WITHIN THE DEVELOPMENT?
 WHAT DOES THE BEACH CLUB CONSIST OF?SPA?
  
 D. ON PAGE 8, NO RESPONSE WAS PROVIDED TO STANDARD #8
 OF THE REZONING REQUEST.
  
 E. ON PAGE 9, IT INDICATES THAT THE EXISTING LAND USE
 IS MULTIFAMILY 32?IT SHOULD ONLY READ MULTIFAMILY (MF).
  
 F. ON PAGE 9, IT INDICATES THAT THE PROPOSED LAND USE
 AS COMMERCIAL. OTHER DOCUMENTATION INDICATES THAT
 COMMERCIAL EAST IS PROPOSED. PLEASE CLARIFY AND ENSURE
 ALL DOCUMENTATION, STUDIES, AND PLANS ARE CONSISTENT.
  
 G. ON PAGE 9, IT INDICATES THAT A MAXIMUM BUILDING
 HEIGHT OF 405 FEET IS PROPOSED. THIS IS NOT OUTLINED
 ANYWHERE ON THE MASTER PLAN OR WITHIN THE DESIGN
 GUIDELINES.
  
 H. ON PAGE 12, IT INDICATES THAT THE MINIMUM REQUIRED
 LANDSCAPE BUFFER IS PROPOSED TO BE 21 FEET; HOWEVER,
 THE DESIGN GUIDELINES ONLY INDICATE 15 FEET ALONG THE
 NORTH AND SOUTH PROPERTY LINES. ADDITIONALLY, THE
 JUSTIFICATION STATES THAT A 25 FOOT LANDSCAPE BUFFER
 WILL BE PROVIDED ALONG NORTH FLAGLER; THE DESIGN
 GUIDELINES INDICATES ONLY 15 FEET IS REQUIRED. PLEASE
 ENSURE THAT ALL PLANS AND DOCUMENTATION IS CONSISTENT.
  
 I. PLEASE EXPLAIN THE PARKING WAIVER THAT IS DISCUSSED
 ON PAGES 13-14. WHAT WAIVER IS BEING REQUESTED?
  
 J. THE SECTION PERTAINING TO DOCKS ON PAGE 14 IS
 MISLEADING. THE JUSTIFICATION STATEMENT SHOULD DESCRIBE
 (IN ALL PART OF THE STATEMENT), WHAT IS ULTIMATELY
 PROPOSED TO BE BUILT ON THE SITE. EXPLAINING WHAT
 EXISTS AND WHAT WILL BE ADDED CAN BE ADDITIONAL
 INFORMATION.
 K. ON PAGE 14 IT INDICATES THAT THE TRAFFIC IMPACT
 STUDY INDICATES THAT THE PROJECT MEETS OR EXCEEDS THE
 CITY?S STANDARDS?THIS STUDY HAS NOT BEEN PROVIDED.
  
 L. NO DESCRIPTION REGARDING THE NEED FOR A DENSITY
 WAIVER? PLEASE ENSURE THAT ALL WAIVERS ARE DESCRIBED
 AND JUSTIFIED. I WOULD RECOMMEND THAT A TABLE BE
 GENERATED INDICATING ALL REQUESTED WAIVERS.
  
 M. ON PAGE 17, IT INDICATES THAT ALL RESIDENTIAL
 BUILDINGS WILL BE SET BACK 90 FEET FROM NORTH FLAGLER
 DRIVE (WITH THE EXCEPTION OF PBA #3). THIS IS NOT
 OUTLINED ANYWHERE IN THE DESIGN GUIDELINES.
  
 5. AFFIDAVIT FROM PAGE 19 OF THE DEVELOPMENT
 APPLICATION SHALL BE PROVIDED.
  
 6. UTILITY LETTER SHALL BE PROVIDED FROM THE CITY?S
 ENGINEERING SERVICES DEPARTMENT.
  
 7. APPROVED SCHOOL CONCURRENCY APPLICATION SHALL BE
 PROVIDED.
  
 8. FOR THE FUTURE LAND USE MAP AMENDMENT, A LEVEL OF
 SERVICE ANALYSIS SHALL BE PROVIDED FOR ALL SERVICES,
 NOT JUST TRAFFIC. THE LEVEL OF SERVICE ANALYSIS SHALL
 COMPARE THE ?WORST-CASE? SCENARIO UNDER THE EXISTING
 FLU AND COMPARE IT TO THE ?WORST-CASE? SCENARIO UNDER
 THE PROPOSED FLU. THE ANALYSIS SHALL LOOK AT THE
 FOLLOWING:
  
 A. DRAINAGE
 B. POTABLE WATER
 C. WASTE WATER (SEWER)
 D. SOLID WASTE
 E. SCHOOLS
 F. PARKS
 G. TRAFFIC
  
 9. THE PROPOSED DEVELOPMENT UTILIZED FOR THE TRAFFIC
 EQUIVALENCY STATEMENT PREPARED BY KIMBLEY-HORN (DATED
 AUGUST 21, 2013) IS INCORRECT. THE LETTER INDICATES
 THAT ONLY 660 RESIDENTIAL UNITS ARE PROPOSED. FOR THE
 PURPOSES OF TRAFFIC EQUIVALENCY, I BELIEVE YOU NEED TO
 COMPARE THE APPROVALS OF TRG AND RYBOVICH
 (COLLECTIVELY) VS. THE PROPOSED OVERALL DEVELOPMENT
 (I.E. 1059 DWELLING UNITS, ETC.)
  
 10. PLEASE CLARIFY THE PROPOSED 40 FOOT MINIMUM SETBACK
 FROM FLAGLER DRIVE. IS THIS THE SETBACK REQUIRED PER
 SECTION 94-305(D), AS MEASURED FROM THE CENTERLINE OF
 THE ROAD?
  
 11. MORE DETAIL NEEDS TO BE ADDED INTO THE MASTER PLAN:
  
 A. MAXIMUM # OF SLIPS THAT WILL BE PERMITTED INTO THE
 CMPD.
  
 B. MASTER PLAN SHOULD SHOW THE ENTIRE IN-WATER MARINA
 LAYOUT, SHOWING LOCATIONS OF DOCK, NUMBER OF SLIPS,
 ETC., AS DONE IN THE RYBOVICH MASTER PLAN, OR AT LEAST
 SHOW THE ENTIRE EXTENT OF THE MARINA BOUNDARIES.
  
 C. WHAT IS THE YELLOW LINE ALONG THE SOUTH PROPERTY
 LINE?
  
 D. PLEASE TRY TO SIMPLIFY THE MASTER PLAN BY MAKING IT
 JUST A LINE DRAWING?REMOVING THE LANDSCAPING, ETC.
 ALSO, IT IS UNCLEAR AS TO WHERE THE FRONTAGE ROAD IS
 PROPOSED. IT LOOKS LIKE WHAT IS SHOWN ON THE MASTER
 PLAN DOES NOT MATCH WHAT HAS BEEN CONCEPTUALLY SHOWN ON
 THE PAVING, GRADING, AND DRAINAGE PLAN.
  
 E. DOES THE BUILDING FOOTPRINT SIZE INCLUDE THE PARKING
 GARAGES?
  
 12. CROSS SECTIONS SHOW THAT 20 FEET WORTH OF
 IMPROVEMENTS ARE SHOWN OUTSIDE OF THE RIGHT-OF-WAY?AND
 THEN A 50 FOOT SETBACK FROM THE PROPERTY LINE. IS THERE
 SPACE FOR ALL OF THIS? HOW TO ALL OF THE CROSS SECTIONS
 RELATE TO THE MASTER PLAN? CROSS SECTIONS ARE NOT
 PROVIDED FOR ALL AREAS OF THE DEVELOPMENT. ARE THE
 CROSS SECTIONS TO BE INCLUDED IN THE REGULATIONS?
  
 13. CORRECTIONS NEED TO BE MADE TO THE MASTER PLAN
  
 A. EXISTING ZONING SHOULD BE LABELED AS RPD AND CMPD.
  
 B. PROPOSED ZONING SHOULD ONLY BE CMPD?NO MF32 WILL
 EXIST.
  
 C. EXISTING LAND USE (FUTURE LAND USE) SHOULD BE MF AND
 C.
  
 D. PROPOSED LAND USE (FUTURE LAND USE) SHOULD BE C AND
 CE.
  
 E. IN THE LOWER LEFT-HAND TABLE, IT INDICATES THAT OPEN
 SPACE IS A (BUILDING FOOTPRINT) +B (ON-GRADE PERVIOUS);
 OPEN SPACE SHOULD BE ANYTHING THAT IS NOT BUILDING.
  
 14. PBA #4 IS SHOWN ON LAND THAT IS CURRENTLY
 SUBMERGED?IS THIS PROPOSED TO BE FILLED IN? IS LAND ON
 WHAT IS NOW TRG PROPOSED TO BE FILLED?
  
 15. TRAFFIC STUDY SHALL BE PROVIDED SHOWING THE IMPACT
 OF THE PROPOSED DEVELOPMENT (AT FULL BUILD-OUT) ON THE
 SURROUNDING ROAD NETWORK. STUDY SHALL INCLUDE EXISTING
 TRAFFIC CONDITIONS, APPROVED AND UN-BUILT FUTURE
 DEVELOPMENTS, AS WELL AS BUILD-OUT OF OTHER PROPERTIES
 IN THE CORRIDOR.
  
 16. ALEX HANSEN, SENIOR TRANSPORTATION PLANNER, IS
 FURTHER REVIEWING THE TRAFFIC IMPACT ANALYSIS FOR THE
 FLU AMENDMENT. SOME INITIAL CONCERNS WERE:
  
 A. USE OF THE GREATER TREASURE COAST REGIONAL PLANNING
 MODEL. THE PALM BEACH COUNTY COMPREHENSIVE PLAN
 CURRENTLY SPECIFIES USE OF THE METROPOLITAN PLANNING
 ORGANIZATION (MPO) MODEL. MR. HANSEN IS AWAITING
 RESPONSES FROM PALM BEACH COUNTY TO FURTHER ADDRESS
 THIS COMMENT.
  
 B. THE LONG RANGE CUMULATIVE IMPACT DID NOT APPEAR TO
 ACCOUNT FOR ADOPTED FLU AMENDMENTS THAT HAVE BEEN
 APPROVED SINCE THE ESTABLISHMENT OF THE PLANNING MODEL.
 PER PALM BEACH COUNTY?S COMPREHENSIVE PLAN, THE
 CUMULATIVE IMPACT SHOULD ACCOUNT FOR AMENDMENTS THAT
 HAVE OCCURRED SINCE THE MODEL WAS ESTABLISHED. AGAIN,
 MR. HANSEN IS AWAITING INFORMATION FROM PALM BEACH
 COUNTY TO FURTHER ADDRESS THIS COMMENT.
  
 17. THE FLU TRAFFIC ANALYSIS INDICATES THAT THE TRG
 PROPERTY IS 5.11 ACRES, WHILE THE MASTER PLAN INDICATES
 THAT IT IS 5.09 ACRES. ALL DOCUMENTATION, ETC. NEEDS TO
 BE ACCURATE AND CONSISTENT.
  
 18. ELECTRONIC COPIES OF ALL PLANS, DESIGN GUIDELINES,
 ETC. SHALL BE PROVIDED.
 ___________________________________________
  
 PLEASE NOTE THE FOLLOWING WHEN RESUBMITTING:
  
 A) WRITTEN RESPONSES TO COMMENTS MADE BY ALL
 DEPARTMENTS SHALL BE PROVIDED UPON RESUBMISSION.
  
 B) 15 SETS OF REVISED PLANS AND/OR DOCUMENTS SHALL BE
 PROVIDED, ALONG WITH ONE (1) REDUCED COPY (11IN X
 17IN), AND AN ELECTRONIC COPY OF ALL PLANS.
  
 C) PLEASE NOTE THAT RE-SUBMITTALS MAY BE SUBJECT TO
 ADDITIONAL COMMENTS.
  
 D) IF NO RESPONSE IS RECEIVED WITHIN 60 DAYS OF THE
 ISSUANCE OF THESE COMMENTS, THE APPLICATION WILL BE
 CONSIDERED WITHDRAWN AND ANY FURTHER ACTION WILL
 REQUIRE SUBMISSION OF A NEW DEVELOPMENT APPLICATION.
  
 E) PLEASE NOTE THAT YOU WILL BE PERMITTED ONE (1)
 RESUBMITTAL AT NO ADDITIONAL COST. IF PREVIOUSLY-ISSUED
 COMMENTS CONTINUE TO NOT BE SUFFICIENTLY ADDRESSED, THE
 APPLICANT WILL BE ACCESSED A RESUBMITTAL FEE. SUCH FEE
 WILL BE 20% OF THE ORIGINAL APPLICATION FEE.
  
 F) IN ORDER TO BE CONSIDERED FOR THE NEXT PLANNING
 BOARD AGENDA, ALL COMMENTS AND CONCERNS SHALL BE
 SATISFACTORILY ADDRESSED. PLEASE SUBMIT ALL REVISED
 DOCUMENTS/PLANS NO LATER THAN FRIDAY, SEPTEMBER 20,
 2013, TO BE CONSIDERED FOR THE OCTOBER 16, 2013,
 PLANNING BOARD HEARING.
  
 G) TO BE PLACED ON THE OCTOBER 16, 2013, PLANNING BOARD
 AGENDA, SIGNS SHALL BE POSTED ON THE PROPERTY NO LATER
 THAN OCTOBER 1, 2013. SIGNAGE SHALL CONFORM AND BE
 INSTALLED WITH THE REQUIREMENTS OF THE CITY?S ZONING
 AND LAND DEVELOPMENT REGULATIONS, AS ALSO PROVIDED IN
 THE DEVELOPMENT APPLICATION. A SIGNED AND NOTARIZED
 AFFIDAVIT SHALL BE PROVIDED BY THE DEADLINE REFERENCED
 ABOVE.
 ___________________________________________
  
 QUESTIONS/COMMENTS, PLEASE CONTACT THE FOLLOWING:
  
 JOHN ROACH, PRINCIPAL PLANNER
 CITY OF WEST PALM BEACH
 DEVELOPMENT SERVICES DEPARTMENT ? PLANNING DIVISION
 401 CLEMATIS STREET - P.O. BOX 3147
 WEST PALM BEACH, FLORIDA 33402
  
 PHONE: 561.822.1448
 FAX: 561.822.1460
  
 EMAIL: [email protected]
  
 WWW.WPB.ORG
  

  Print


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved