| 2011-06-13 09:47:17 | CASE NO. PB1600C 1ST RESUBMITTAL COMMENTS |
| | PALM BEACH DAY ACADEMY |
| | FORMAL SITE PLAN REVIEW FOR NEW BUILDINGS |
| | 1901 SOUTH FLAGLER DRIVE |
| | JUNE 7, 2011 |
| | |
| | - CONTACT ERIC SCHNEIDER @ (561) 822-1446 |
| | |
| | - PLEASE PROVIDE RESPONSES TO REVIEW COMMENTS IN |
| | WRITTEN FORMAT. |
| | |
| | - WHEN RESUBMITTING, PLEASE PROVIDE A MINIMUM OF SIX |
| | (6) PAPER COPIES AND AN ELECTRONIC COPY IN .PNG FORMAT |
| | OF ALL PLANS. PLEASE NOTE THAT CHANGES ON THE |
| | RESUBMITTED PLANS MAY RESULT IN ADDITIONAL COMMENTS. |
| | |
| | - PLEASE NOTE THAT IF THE PLANNING AND ZONING |
| | DEPARTMENT HAS NOT RECEIVED A RESPONSE TO THE PPRC |
| | COMMENTS WITHIN 60 DAYS FROM THE DATE OF THESE COMMENTS |
| | (AUGUST 7, 2011), THE CASE SHALL BE CONSIDERED |
| | WITHDRAWN. ANY FURTHER ACTION SHALL REQUIRE A NEW |
| | DEVELOPMENT APPLICATION. |
| | |
| | - PLEASE NOTE THAT ADDITIONAL RESUBMITTALS WILL BE |
| | ACCESSED A RESUBMITTAL FEE. SUCH FEE WILL BE 20% OF THE |
| | ORIGINAL APPLICATION FEE ($300). |
| | |
| | 1) REPEAT COMMENT - THE CITY COMMISSION APPROVED |
| | BUILDING HEIGHT IS 36 FEET. THE DATA TABLE LISTS THE |
| | BUILDING HEIGHT FOR THE NEW STRUCTURES AS 42 FEET. |
| | |
| | THE BUILDING HEIGHT IS CORRECTLY STATED ON THE VERSION |
| | OF THE MASTER PLAN THAT WILL BE GOING BEFORE THE CITY |
| | COMMISSION ON JUNE 26. THE CORRECT HEIGHT SHALL BE |
| | STATED ON THE PLANS RESUBMITTED AS PART OF THE FORMAL |
| | SITE PLAN. |
| | |
| | A. REPEAT COMMENT - THE CITY MEASURES THE HEIGHT OF |
| | STRUCTURES FROM THE FINISHED GRADE NOT THE FINISHED |
| | FLOOR. PLEASE PROVIDE THE HEIGHT DIMENSIONS BASED ON |
| | THIS STANDARD. |
| | |
| | THE DIMENSIONS COMPLYING WITH THIS STANDARD WERE NOT |
| | INCLUDED ON THE RESUBMITTED ELEVATIONS. STAFF WILL |
| | REQUIRE THIS DIMENSION AT TIME OF BUILDING PERMIT, SO |
| | IT IS RECOMMENDED THAT THE DIMENSION BE SHOWN WITH THE |
| | RESUBMITTAL. |
| | |
| | B. REPEAT COMMENT - PROVIDE THE HEIGHT DIMENSIONS FOR |
| | ALL ELEMENTS OF THE BUILDINGS (EX. TOPS OF PARAPETS AND |
| | OTHER ARCHITECTURAL ELEMENTS). |
| | |
| | THE DIMENSION TO THE TOP OF THE TOP OF THE TENSILE |
| | FABRIC CANOPY AND ITS SUPPORTS WAS NOT PROVIDED. PLEASE |
| | NOTE THAT THE DIMENSIONS GIVEN FOR THE OTHER ELEMENTS |
| | WERE FROM FINISHED FLOOR NOT FINISHED GRADE. |
| | |
| | C. COMMENT MODIFIED - PLEASE NOTE THAT THE |
| | ARCHITECTURAL ELEMENTS AND MECHANICAL EQUIPMENT MAY NOT |
| | EXCEED 50 FEET. |
| | |
| | THE ARCHITECTURAL ELEMENT HEIGHT IS STATED ON THE |
| | VERSION OF THE MASTER PLAN THAT WILL BE GOING BEFORE |
| | THE CITY COMMISSION ON JUNE 26. THE CORRECT HEIGHT |
| | SHALL BE STATED ON THE PLANS RESUBMITTED AS PART OF THE |
| | FORMAL SITE PLAN. |
| | |
| | 2) REPEAT COMMENT - THE NORTH ELEVATION OF THE |
| | EDUCATION BUILDING SHOWS A STRUCTURAL OVERHANG AT THE |
| | 2ND FLOOR. STRUCTURAL INTRUSIONS MAY PROJECT NO FURTHER |
| | THAN THREE (3) FEET INTO ANY REQUIRED SETBACK. PLEASE |
| | PROVIDE DIMENSIONS FOR THE OVERHANG ON BOTH THE |
| | ELEVATION DRAWINGS AND THE SITE PLAN TO VERIFY THAT THE |
| | OVERHANG IS NO CLOSER THAN 12 FEET FROM THE NORTH |
| | PROPERTY LINE. |
| | |
| | DIMENSIONS NOT INCLUDED. |
| | |
| | 3) REPEAT COMMENT - PROVIDE DETAILS FOR THE PROPOSED |
| | WALL ALONG FLAGLER DRIVE AND SOUTH OLIVE AVENUE, |
| | ESPECIALLY HEIGHT AND MATERIAL. |
| | |
| | THE HEIGHT (4 FEET) AND MATERIAL (CONCRETE) WERE STATED |
| | ON THE PLANS FOR THE FLAGLER DRIVE WALL, BUT NO |
| | ELEVATION DETAIL WAS PROVIDED (AS STATED ON THE PLANS). |
| | A NOTE SHALL BE ADDED FOR THE S. OLIVE WALL STATING, |
| | "WALL SHALL BE CONSTRUCTED IN ACCORDANCE WITH HISTORIC |
| | PRESERVATION DIVISION APPROVED DESIGN". |
| | |
| | 4) REPEAT COMMENT - THE PLANS, ELEVATIONS AND COLOR |
| | RENDERING ALL SHOW SIGNAGE. PROVIDE SIGNAGE DETAILS SO |
| | STAFF MAY REVIEW FOR CODE COMPLIANCE. THIS WILL ENSURE |
| | THAT THE SIGN PERMITTING PROCESS GOES SMOOTHLY. |
| | |
| | NO SIGNAGE DETAILS PROVIDED. |
| | |
| | 5) CLARIFICATION REQUIRED - PROVIDE THE LOCATIONS OF |
| | ALL TRANSFORMERS, GENERATORS, BACKFLOW PREVENTERS, AC |
| | UNITS, AND OTHER MECHANICAL EQUIPMENT AND HOW IT WILL |
| | BE SCREENED BY LANDSCAPE OR ARCHITECTURAL FEATURES. |
| | |
| | THE MASTER PLAN INCLUDES SCREENING FOR TRANSFORMERS. IS |
| | THIS THE METHOD THAT ALL MECHANICAL EQUIPMENT WILL USE |
| | TO SCREEN? NOTE: GENERATORS REQUIRE AN ENCLOSURE AS |
| | WELL AS LANDSCAPE. THE LANDSCAPE PLAN DOES NOT APPEAR |
| | TO HAVE A TRANSFORMER SHOWN, AND THE BACKFLOW PREVENTER |
| | AND ONE OF THE FIRE HYDRANTS ARE LOCATED WITHIN |
| | PLANTING BEDS. THE PLANTING BEDS NEED TO BE ADJUSTED |
| | AND ALL EFFORT SHOULD BE MADE TO DETERMINE THE LOCATION |
| | OF ANY TRANSFORMERS NOW, PRIOR TO THE PLAN BEING |
| | FINALIZED. |
| | |
| | 6) CLARIFICATION REQUIRED - PROVIDE THE LOCATION AND |
| | DETAILS OF ALL LIGHTING ON THE CAMPUS. |
| | |
| | THE SPECIFIC HEIGHT OF THE PEDESTRIAN LIGHTS IS NOT |
| | LISTED, BUT RATHER A RANGE FROM 24 TO 42 INCHES IS |
| | GIVEN. WHICH HEIGHT IS PROPOSED? THE HISTORIC |
| | PRESERVATION DIVISION SHALL APPROVE THE LIGHTS WITHIN |
| | THE MANGO PROMENADE HISTORIC DISTRICT. THE PARKING LOT |
| | LIGHTS WITHIN THE DISTRICT SHALL BE RESIDENTIAL IN |
| | NATURE AND CONFORM TO THE CHARACTER OF THE DISTRICT. |
| | PLEASE CONTACT FRIEDERIKE MITTNER, CITY HISTORIC |
| | PRESERVATION PLANNER. |
| | |
| | 7) CLARIFICATION REQUIRED - A PHOTOMETRIC PLAN IS |
| | REQUIRED. PLEASE NOTE THAT THE PLAN SHALL SHOW THAT |
| | LIGHT LEVELS DO NOT EXCEED 0.5 FOOT CANDLES AT THE |
| | NEIGHBORING RESIDENTIALLY ZONED PROPERTIES [SECTION |
| | 94-310(D)]. |
| | |
| | PLEASE PROVIDE INFORMATION ON THE PROPOSED HOURS OF |
| | OPERATION FOR THE PARKING LOT LIGHTING. PLEASE REMEMBER |
| | THAT THE PARKING LOT IS ADJACENT TO RESIDENTIAL HOMES. |
| | |
| | 8) REPEAT COMMENT - THE SITE AND CIVIL PLANS SHALL |
| | INCLUDE THE DIMENSIONS OF THE BICYCLE RACK (IT DOES NOT |
| | SCALE AS DEEP ENOUGH ON THE CIVIL PLAN). |
| | |
| | THE BICYCLE RACK IS SHOWN AS 14 FEET X 6 FEET ON THE |
| | DETAIL SHEET, YET IT IS SHOWN SMALLER IN BOTH LENGTH |
| | AND WIDTH ON THE SITE, LANDSCAPE AND CIVIL PLANS. THE |
| | BICYCLE RACK SHALL BE SHOWN AT ITS CORRECT SIZE ON THE |
| | PLANS TO PREVENT ANY CONFLICTS. |
| | |
| | 9) REPEAT COMMENT - THE "PROJECT TEAM" TABLES ON ALL |
| | PLANS SHALL BE UPDATED TO REFLECT CORRECT INFORMATION |
| | (UNITY IS NO LONGER THE OWNER). |
| | |
| | LANDSCAPE PLAN NOT UPDATED. |
| | |
| | 10) PARTIAL REPEAT - THE SETBACK PORTION OF THE SITE |
| | DATA TABLE NEEDS TO SEPARATELY STATE THE SETBACKS FOR |
| | THE RELOCATED BUILDING. THIS SHALL INCLUDE THE WAIVERS |
| | APPROVED AS PART OF ORD. NO. 4303-10. |
| | |
| | THE REQUIRED SETBACKS FOR THE RELOCATED BUILDING ARE |
| | NOT CORRECTLY LISTED - GRANTED WAIVERS BY THE |
| | ORDINANCE. |
| | |
| | 11) MODIFIED COMMENT - THE LANDSCAPE DATA SHALL |
| | DIFFERENTIATE BETWEEN THE PHASE I AND PHASE II |
| | LANDSCAPE INSTALLATIONS. PHASE II SHALL ONLY INCLUDE |
| | THE FOUNDATION PLANTING FOR THE ATHLETIC BUILDING. |
| | |
| | THE PHASING SHALL BE REVISED TO INCLUDE THE PARKING LOT |
| | RELOCATION AS PHASE I WITH THE EDUCATION AND ATHLETIC |
| | BUILDINGS AS PHASE II AND PHASE III, RESPECTIVELY. |
| | |
| | 12) REPEAT COMMENT - THE SIZE AND SPECIES OF ALL |
| | EXISTING AND RELOCATED TREES AND SHRUBS SHALL BE |
| | PROVIDED ON THE LANDSCAPE PLAN. THE LANDSCAPE PLAN |
| | APPROVED WITH THIS APPLICATION WILL SERVE AS THE |
| | LANDSCAPE PLAN OF RECORD, SO ALL DETAILS ARE NEEDED. |
| | |
| | THE LANDSCAPE PLANS SHOW A NEW TREE IN THE SOUTHERN ROW |
| | OF EMPLOYEE PARKING. THE WAIVER TO ALLOW UP TO 14 |
| | PARKING SPACES IN A ROW WAS SPECIFICALLY GRANTED TO |
| | PRESERVE THE EXISTING MATURE LIVE OAK TREE. THIS TREE |
| | MAY NOT BE REMOVED. IF IT IS CURRENTLY LOCATED NOT AS |
| | THE ISLAND IS SHOWN, THEN PLEASE DISCUSS WITH STAFF |
| | SOME SOLUTIONS THAT MAY BE APPROPRIATE, SUCH AS A |
| | RECONFIGURATION OF THE LOT TO FLIP THE LOCATION OF THE |
| | DEDICATED TURN AROUND SPACE TO NORTH PARKING ROW. |
| | |
| | 13) REPEAT COMMENT - PROVIDE THE LANDSCAPE BUFFER |
| | DETAILS SHEET WITH THE LANDSCAPE PLAN NOT THE MASTER |
| | PLAN. ADDITIONALLY, THE LANDSCAPE BUFFER DETAIL SHEET |
| | CROSS SECTIONS DO NOT MATCH THE LOCATIONS DESIGNATED ON |
| | THE MASTER PLAN. SOME OF THEM DO NOT REFLECT THE |
| | LANDSCAPE PROPOSED ON THE LANDSCAPE PLAN. |
| | |
| | BUFFER DETAILS NOT CONSISTENT WITH PLAN. |
| | |
| | 14) REPEAT COMMENT - THE 25 FOOT LANDSCAPE AREA ALONG |
| | FLAGLER DRIVE HAS CHANGED FROM THE CONCEPTUAL LANDSCAPE |
| | PLAN APPROVED AS PART OF ORD. NO. 4303-10. THIS AREA IS |
| | TO HAVE UPLAND MEANDERING LANDSCAPE OR BE A BIOSWALE |
| | WITH APPROPRIATE MEANDERING LANDSCAPE. IT IS SHOWN ON |
| | THE SUBMITTED PLANS AS AN OPEN SODDED AREA, WHICH |
| | COMBINED WITH THE CIVIL PLAN'S PROPOSED DRAINAGE |
| | INDICATES THAT IT WILL BE A 25 FOOT WIDE UNLANDSCAPED |
| | SWALE. THIS IS NOT APPROPRIATE FOR A FLAGLER DRIVE |
| | LANDSCAPE BUFFER, NOR DOES IT MEET THE LANDSCAPE CODE |
| | BUFFER REQUIREMENTS. THE FOUNDATION PLANTING FOR THE |
| | ATHLETIC BUILDING MAY NOT DOUBLE AS THE REQUIRED |
| | LANDSCAPE BUFFER. |
| | |
| | RESPONSE PROVIDED WAS "NEED AN ANSWER". STAFF REQUIRES |
| | A BIT MORE NARRATIVE FOR THIS COMMENT TO BE ADDRESSED |
| | OR PREFERABLY, THE PLANS TO BE REVISED. |
| | |
| | 15) REPEAT COMMENT - PER ORD. NO. 4303-10, ALL NEW |
| | TREES SHALL BE A MINIMUM OF 14 FEET IN HEIGHT AT |
| | INSTALLATION. NOT ALL OF THE TREES SPECIFIED ON THE |
| | LANDSCAPE PLAN MEET THIS REQUIREMENT. |
| | |
| | THE 14 FOOT MINIMUM HEIGHT REQUIREMENT FOR ALL NEW |
| | TREES WAS TO OFFSET ALL OF THE REQUESTED LANDSCAPE |
| | WAIVERS, INCLUDING THE LANDSCAPE BUFFER INTERRUPTION |
| | ALONG COCOANUT AND TUXEDO LANES AND THE REDUCED BUFFER |
| | ADJACENT TO THE EMPLOYEE PARKING. |
| | |
| | 16) MODIFIED COMMENT - PER ORD. NO. 4303-10, THE |
| | OVERNIGHT BUS PARKING SPACES SHALL BE SCREENED FROM THE |
| | RESIDENTIAL NEIGHBORHOOD. THE LANDSCAPE MATERIAL |
| | PROPOSED ALONG COCOANUT LANE, WEST OF THE BUS PARKING, |
| | DOES NOT PROVIDE ADEQUATE SCREENING OF THE BUSSES. THE |
| | MATERIAL SHALL BE OF A SUFFICIENT HEIGHT TO SCREEN THE |
| | BUSSES AT INSTALLATION. STAFF RECOMMENDS THE |
| | INSTALLATION OF A SIX (6) FOOT PODOCARPUS HEDGE. THE |
| | HEDGE SHOULD BE LOCATED AS CLOSE TO THE PROPOSED FENCE |
| | AS POSSIBLE. THE TREES SHALL BE LOCATED BETWEEN THE |
| | HEDGE AND THE PEDESTRIAN WALKWAY. |
| | |
| | AT THE MEETING ON JANUARY 26, 2011, THE PBDA AGREED TO |
| | INSTALL A SIX (6) FOOT TALL PODOCARPUS HEDGE ALONG |
| | COCOANUT TO SCREEN THE BUSES IN ORDER TO COMPLY WITH |
| | THE ORDINANCE. |
| | |
| | 17) REPEAT COMMENT - PLEASE REMEMBER THAT PER ORD. NO. |
| | 4303-10, THE FOLLOWING ARE REQUIRED PRIOR TO THE FIRST |
| | BUILDING PERMIT: |
| | |
| | THE FIRST BUILDING PERMITS HAVE BEEN SUBMITTED AND THE |
| | LISTED ITEMS HAVE NOT BEEN PROVIDED. PLEASE NOTE THAT |
| | A., C. AND D. WILL BE REQUIRED FOR THE NEW PHASE II |
| | DEVELOPMENT - CONSTRUCTION OF BUILDINGS AND THE |
| | RELOCATION OF THE ROADWAY. |
| | |
| | A. PROVIDE THE PLANNING AND ZONING DEPARTMENT WITH A |
| | TRAFFIC CONTROL PLAN, APPROVED BY THE CITY'S TRAFFIC |
| | ENGINEER, WHICH INCLUDES THE LOCATIONS OF THE TRAFFIC |
| | DIRECTING PERSONNEL AND A WRITTEN NARRATIVE HOW THE |
| | TRAFFIC CONTROL OPERATIONS WILL FUNCTION FOR THE |
| | PICK-UP AND DROP-OFF TIMES. THE COST TO CONSTRUCT, |
| | INSTALL AND MAINTAIN ANY OFF-SITE SIGNAGE OR TRAFFIC |
| | CONTROL AIDES SHALL BE BORNE BY THE PBDA. |
| | |
| | B. PREPARE A CONSTRUCTION SITE SECURITY AND MANAGEMENT |
| | PLAN FOR APPROVAL BY THE CITY'S POLICE DEPARTMENT CRIME |
| | PREVENTION THROUGH ENVIRONMENTAL DESIGN (CPTED) |
| | OFFICIAL. |
| | |
| | C. RECORD A PLAT FOR THE ENTIRE PBDA CAMPUS. PRIOR TO |
| | RECORDATION, THE PLAT SHALL BE SUBMITTED FOR REVIEW |
| | THROUGH THE MINOR SUBDIVISION PROCESS TO INCLUDE ALL |
| | REQUIRED EASEMENTS. THE RELOCATION AND/OR ABANDONMENT |
| | OF EASEMENTS WILL REQUIRE APPLICATIONS TO BE FILED WITH |
| | THE ENGINEERING SERVICES DEPARTMENT. |
| | |
| | D. SUBMIT COMPREHENSIVE EMERGENCY PLANS TO THE FIRE |
| | DEPARTMENT FOR THEIR APPROVAL. |
| | |
| | 18) NEW COMMENT - PLEASE EXPLAIN THE NEW OUTDOOR STAGE |
| | ON THE SOUTH SIDE OF THE ACADEMICS BUILDING. HOW WILL |
| | IT BE ACCESSED? |
| | |
| | 19) NEW COMMENT - THE REVISED MASTER PLAN SHALL INCLUDE |
| | THE RELOCATED ADA WALKWAY FROM THE EMPLOYEE PARKING LOT |
| | AND THE REVISED PARKING TABLE WHICH CORRECTS THE |
| | PARKING COUNTS AND THE BUS PARKING. |
| | |
| | 20) NEW COMMENT - THE CROSS SECTION PROVIDED WITH THE |
| | SITE WORK PERMIT PAVING AND DRAINAGE PLANS SHOWS THAT |
| | 0.5 FEET OF THE REQUIRED 8.5 FOOT WIDE PARALLEL PARKING |
| | SPACE IS IN THE TUXEDO LANE RIGHT-OF-WAY. THIS NEEDS TO |
| | BE ADDRESSED. A POSSIBILITY IS TO SHIFT THE FEATURES TO |
| | THE SOUTH INTO THE EXCESS 0.7 FEET ADJACENT TO THE |
| | LANDSCAPE BUFFER. PLEASE ENSURE THAT THE EXISTING |
| | ORANGE COURT CIRCLES ARE CORRECTLY REFLECTED AND THAT |
| | LANDSCAPE IS ADJUSTED ACCORDINGLY (THE PLANS APPEAR TO |
| | SHOW HEDGES IN THE 2 FOOT PARKING OVERHANG). |
| | |
| | 21) NEW COMMENT - THE BUS PARKING DETAIL IS IN CORRECT |
| | AS IT SHOWS A HEDGE IN FRONT OF IT, NOT AS SIDEWALK AS |
| | SHOWN ON THE PLANS. THE PARALLEL PARKING SPACE DETAIL |
| | SHOWS THE PARKING SPACE AT 22 FEET LONG. A COMPACT |
| | PARKING SPACE DETAIL IS REQUIRED. |
| | |