Plan Review Details - Project Z09090011
Plan Review Stops For Project Z09090011
Review Stop ENG-P ENGINEERING PLANNING REVIEW
Rev No 1 Status N Date 09-29-2009 Cont ID  
Sent By efabian Date 09-29-2009 Time 11:50 Rev Time 0.50
Received By efabian Date 10-09-2009 Time 14:26 Sent To  
Notes
2009-10-14 14:26:44A REQUEST FROM ERIC SCHNEIDER FOR ENGINEERING
 DEPARTMENT'S APPROVAL ON WHEEL-STOPS 6 INCHES FROM THE
 EDGE OF PARKING SPACES PAVEMENT WAS RESOLVED BY A
 MODIFIED VERSION OF OUR STANDARD DETAIL GC-3 BY EMAIL
 YESTERDAY (10-13-09), WHICH WAS LATER FURTHER RESOLVED
 AT TODAY'S PPRC MEETING. THE PROJECT MANAGER, RYAN
 JOHNSTON PROPOSED TO LENGTHEN EACH PARKING SPACE TO
 OBTAIN THE FULL 2 FEET OVERHANG NEEDED BEYOND EACH
 WHEEL STOP NULLIFYING ANY FURTHER CONSIDERATION.
  
 THE ONLY OTHER QUESTION SITE DEVELOPMENT RELATED TO ES
 PRELIMINARY REVIEW AT THIS POINT WAS THE DUMPSTER
 ENCLOSURE DIMENSIONS. IT APPEARS THE CORRECT DIMENSIONS
 (12'-6") SHOWN HAD JUST SHIFTED SLIGHTLY ON THE PLANS
 SET, OFF-SETTING THE LINES IN RELATIONSHIP TO THE
 DETAIL.
  
 NO OTHER CONCERNS/COMMENTS.

Review Stop FIRE FIRE DEPARTMENT
Rev No 2 Status F Date 11-18-2009 Cont ID  
Sent By mcarsill Date 11-18-2009 Time 13:36 Rev Time 0.00
Received By mcarsill Date 11-18-2009 Time 13:29 Sent To  
Notes
2009-11-18 13:35:28ON NOVEMBER 18, 2009, MET WITH ERIC SCHNEIDER OF THE
 PLANNING DEPARTMENT AND REVIEWED THE REVISED DRAWINGS.
 THE FOLLOWING COMMENTS ARE PROVIDED:
  
 1. WHAT SIZE IS THE LINE THAT THE PROPOSED FIRE HYDRANT
 WILL BE CONNECTED TO.
  
 2. IS THE FIRE HYDRANT LOCATED AT THE OPENING BETWEEN
 THE BUILDINGS NEW OR EXISTING. WHAT SIZE LINE IS THIS
 FIRE HYDRANT CONNECTED OR WILL BE CONNECTED TO.
  
 3. ALL WORK IS SUBJECT TO FIELD INSPECTION AND
 APPROVAL.
  
 4. SEPARATE PLANS AND PERMITS REQUIRED FOR FIRE
 SPRINKLER SYSTEM INSTALLATION.
  
 APPROVED PROVISO
  
 MIKE CARSILLO, BATTALION CHIEF
 BUREAU OF FIRE PREVENTION
 WEST PALM BEACH FIRE RESCUE
 500 NORTH DIXIE HIGHWAY
 WEST PALM BEACH, FLORIDA 33401
 (561) 804-4709 PHONE
 (561) 804-4774 FAX
 [email protected]

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status F Date 09-24-2009 Cont ID  
Sent By mcarsill Date 09-24-2009 Time 09:56 Rev Time 0.00
Received By mcarsill Date 09-24-2009 Time 09:39 Sent To  
Notes
2009-09-24 09:56:46INFORMAL SITE PLAN REVIEW NO. 09-04 (Z09090011)
 10,400 SQUARE FOOT MEDICAL OFFICE BUILDING
  
 1. BUILDING ADDRESS REQUIRED. A MINIMUM OF AT LEAST 6"
 HIGH AND AT LEAST 1" WIDE NUMBERS ARE REQUIRED. THESE
 NUMBERS SHALL CONTRAST TO THE BACKGROUND THEY ARE
 AFFIXED TO. SHOWN ON PAGE A-2 P2.
  
 2. CONSTRUCTION, DEMOLITION, AND RENOVATION TO COMPLY
 WITH NFPA 241.
  
 3. SEPARATE PLANS AND PERMITS REQUIRED FOR THE FIRE
 SPRINKLER SYSTEM INSTALLATION.
  
 4. A FIRE HYDRANT IS REQUIRED TO BE WITHIN 150 FEET OF
 THE FIRE DEPARTMENT CONNECTION.
  
 5. THE FIRE DEPARTMENT CONNECTION IS TO BE EQUIPPED
 WITH KNOX LOCKING CAPS.
  
 6. THE FIRE ALARM AND FIRE SPRINKLER SYSTEM IS TO BE
 SUPERVISED BY A UL LISTED CENTRALS STATION APPROVED FOR
 CENTRAL STATION SERVICE.
  
 7. FIRE HYDRANTS SHALL MEET UTILITY AND FIRE RESCUE
 STANDARDS.
  
 8. A KNOX-BOX IS REQUIRED FOR THE PROPERTY.
  
 9. A SITE PLAN DISPLAYS ONLY ONE FIRE HYDRANT.
 ADDITIONAL FIRE HYDRANTS WILL BE NEEDED TO PROTECT
 20,800 SQUARE FEET.
  
  
 MIKE CARSILLO, BATTALION CHIEF
 WEST PALM BEACH FIRE RESCUE
 BUREAU OF FIRE PREVENTION
 500 NORTH DIXIE HIGHWAY
 WEST PALM BEACH, FLORIDA 33401
 804-4709 PHONE
 804-4774 FAX
 [email protected]

Review Stop L LANDSCAPING
Rev No 2 Status F Date 12-09-2009 Cont ID  
Sent By eschneid Date 11-10-2009 Time 12:53 Rev Time 0.00
Received By eschneid Date 11-10-2009 Time 13:03 Sent To  
Notes
2009-12-09 13:03:20PER ROBERT KUSSNER REVIEW ON 11/10/09.
  
 FAILED
  
 1) MIRROR THE EXISTING OAK TREE ON THE OTHER SIDE OF
 THE INTERIOR ISLAND ON THE OKEECHOBEE FRONTAGE.
  
 2) USE A DIFFERENT TREE SPECIES ALONG THE FRONT
 PROPERTY LINE, SUCH AS THE ORIGINALLY PROPOSED PINK
 TABEBUIA.
  
 3) REVISE THE HEDGE ALONG THE NORTH PROPERTY LINE FOR
 BETTER MAINTENANCE.
  
 4) RECOMMEND THE ENTRY TO HAVE ROYAL PLAMS WITH
 UPLIGHTING.
  
 5) PROVIDE THE HEDGE MATERIAL SPACING AT TIME OF
 INSTALLATION.
  
 6) STAFF RECOMMENDS VERTICAL LANDSCAPE ELEMENTS ALONG
 THE WEST BUILDING FACADES.
  
  

Review Stop L LANDSCAPING
Rev No 1 Status F Date 10-09-2009 Cont ID  
Sent By rkussner Date 10-09-2009 Time 14:26 Rev Time 0.00
Received By rkussner Date 10-09-2009 Time 14:26 Sent To  
Notes
2009-10-09 16:05:01***MID COUNTY MEDICAL CENTER LANDSCAPE REVIEW FAILED***
  
 PLEASE PROVIDE RESPONSES TO REVIEW COMMENTS IN WRITTEN
 FORMAT.
  
 1. PURSUANT TO SECTION 94-443 (C)(3)(A), EACH ROW OF
 PARKING SPACES SHALL BE TERMINATED BY LANDSCAPED
 ISLANDS. THE LANDSCAPED ISLAND SHALL CONTAIN AT LEAST
 ONE SHADE OR FLOWERING TREE. THIS APPLIES TO BOTH
 LANDSCAPE ISLANDS ADJACENT TO THE AMBULANCE PARKING
 SPACE.
  
 2. PROPOSED LANDSCAPING ALONG THE OKEECHOBEE BOULEVARD
 LANDSCAPE BUFFER IS NOT CONSISTENT WITH WHAT THE
 REMAINDER OF THE SHOPPING PLAZA HAS PLANTED ALONG THE
 OKEECHOBEE FRONTAGE. STAFF RECOMMENDS THAT THE ENTIRE
 FRONTAGE BE CONSISTENT. THAT WILL INVOLVE INSTALLING
 PALM GROUPINGS COMPOSED OF THREE SABAL PALMS AND
 ALTERNATING WITH MAHOGANY TREES. THE PALMS SHOULD BE
 UNDERPLANTED WITH FAKAHATCHEE GRASS. THE PROPOSED
 PLANTING LOOKS DISJOINTED AND DOES NOT RELATE TO THE
 BALANCE OF THE SITE.
  
 3, PURSUANT TO SECTION 94-443 (C)(3)(C), WHEN DIVIDER
 MEDIANS ARE USED, SHADE OR FLOWERING TREES WITHIN THE
 DIVIDER MEDIAN SHALL BE PLANTED AT 30-FOOT INTERVALS. A
 MINIMUM OF TWO (2) SHADE OR FLOWERING TREES ARE
 REQUIRED IN THE SQUARE LANDSCAPE AREA IN THE MIDDLE OF
 THE FRONT PARKING LOT.
  
 4. THERE IS A SYMBOL 'AN' ADJACENT TO THE SIGN BUT IT
 IS NOT POINTING TO ANYTHING. PLEASE CLARIFY IF THE
 ANNUALS ARE BEING PROPOSED AROUND THE SIGN..
  
 5. THERE ARE EXISTING SABAL PALM GROUPINGS AT THE FRONT
 CORNERS OF THE EXISTING BUILDING. THERE IS A NOTE ON
 THE PLAN THAT EXISTING PALMS WILL REMAIN, BUT IT
 DOESN'T POINT TO ANYTHING. . PLEASE SHOW ALL TREE AND
 PLANT MATERIAL THAT WILL REMAIN. ALL EXISTING
 VEGETATION SHALL ACCURATELY BE IDENTIFIED.
  
 6. PURSUANT TO SECTION 94-445 (4)(G)(3), AUTOMATIC
 IRRIGATION SYSTEMS SHALL BE USED FOR THE CULTIVATED
 LANDSCAPE AREAS FOR ALL PROPERTIES. THIS INCLUDES THE
 RIGHT-OF-WAY.
  
 7. THE LANDSCAPING ALONG THE WEST PERIMETER OF THE SITE
 WILL BE PLANTED WITHIN AN FPL EASEMENT. WRITTEN
 AUTHORIZATION TO PLANT WITHIN THAT OR ANY OTHER
 EASEMENT WILL BE REQUIRED AT THE TIME OF SITE PLAN
 REVIEW.
  
 8. STAFF RECOMMENDS THAT ADDITIONAL VERTICAL LANDSCAPE
 ELEMENTS AND TIERED PLANTING BE INCORPORATED INTO THE
 FOUNDATION LANDSCAPING TO ACCENTUATE THE ARCHITECTURE,
 ESPECIALLY ON THE NORTH SIDE OF THE PROPOSED BUILDING
 AND ALONG THE SOUTH AND WEST SIDES OF THE EXISTING
 BUILDING. THE SIDEWALK BETWEEN THE BUILDINGS THAT RUNS
 EAST/WEST COULD BE SHIFTED TOWARD THE NORTH TO ALLOW
 FOR PLANTING OF THE VERTICAL ELEMENTS AND GROUND COVER
 ON THE NORTH SIDE OF THE PROPOSED BUILDING.
  
 9. THE LOCATION OF THE SITE LIGHTING SHOWN ON THE
 PHOTOMETRIC PLAN DOES NOT CORRESPOND WITH THE LANDSCAPE
 PLAN. ALL PLANS SHALL BE CONSISTENT. IF THE LIGHT POLES
 ARE INSTALLED AS PER THE PHOTOMETRIC PLAN, THERE WILL
 BE CONFLICTS WITH PROPOSED TREES.
  
 IF YOU HAVE ANY QUESTIONS, PLEASE CONTACT ROBERT
 KUSSNER @ (561) 822-1462.

Review Stop PARK PARKING
Rev No 1 Status P Date 10-02-2009 Cont ID  
Sent By ssamuels Date 10-02-2009 Time 12:18 Rev Time 0.00
Received By ssamuels Date 10-02-2009 Time 12:18 Sent To  
Notes
***NONE***

Review Stop POLICE POLICE
Rev No 2 Status P Date 12-09-2009 Cont ID  
Sent By eschneid Date 11-10-2009 Time 13:24 Rev Time 0.00
Received By eschneid Date 11-10-2009 Time 13:24 Sent To  
Notes
***NONE***

Review Stop POLICE POLICE
Rev No 1 Status F Date 10-14-2009 Cont ID  
Sent By   Date 10-14-2009 Time   Rev Time 0.00
Received By   Date 10-14-2009 Time   Sent To  
Notes
2009-10-07 14:10:51NOT ENOUGH INFORMATION
 NOT SHOWN ON PLAN: IS THERE LIGHTING IN BREEZE WAY,
 EMPLOYEE BREAK AREA, UNDER THE NEW CANOPY. ARE THERE
 WALL PACKS FOR THE EXTERIOR OF THE BUILDING?
 SECURITY ALARM OR CCTV?
 NO INTERIOR PLAN INCLUDED
 SEE THE BELOW CPTED SUGGESTIONS FOR COMMERCIAL
 BUILDINGS
  
 3 COMMERCIAL SECURITY
 3.1 LIGHTING
 A. PARKING LOT AND PEDESTRIAN LIGHTING SHALL BE:
 A) HIGH EFFICACY OF GREATER THAN 70 LUMENS PER WATT
 B) A KELVIN TEMPERATURE OF 3,500 K OR GREATER THAN
 KELVIN TEMPERATURE
 C) COLOR RENDERING INDEX (CRI) OF 70 OR GREATER
 D) LAMP LIFE OF 20 THOUSAND HOURS OR GREATER.
 B. LIGHT POLES 10 ??? 15 FOOT HIGH FOR PEDESTRIAN-SCALE
 LIGHTING SHALL BE USED FOR ALL PEDESTRIAN WALKWAYS.
 C. PARKING LOT LIGHTING SHALL USE 20 -25 FOOT POLES.
 D. LANDSCAPING SHALL NOT OBSTRUCT VIEW OF WINDOWS,
 BUILDING ADDRESS NUMBERS, LIGHTING AND WALKWAYS.
 E. TIMER CLOCK OR PHOTOCELL SENSOR-ENGAGED LIGHTING FOR
 ABOVE OR NEAR ENTRYWAYS TO BUILDINGS FOR DUSK TO DAWN
 OPERATION SHALL BE PROVIDED.
 F. ENTRANCE SIGN LIGHTING SHALL BE PROVIDED. DIRECTORY
 SHOULD BE AT ALL ENTRANCES WITH LIGHTING
 G. BUILDING LIGHTING (NON-GLARE) SHALL BE AROUND
 PERIMETER ON ALL SIDE.
 3.2 NUMERICAL ADDRESS
 A. ILLUMINATION FOR NIGHTTIME VISIBILITY IS REQUIRED.
 ADDRESS SHOULD BE PLACED UNDER A LIGHT FIXTURE OR BE
 BACK LIT.
 B. BI-DIRECTIONAL VISIBILITY FROM THE ROADWAY IS
 REQUIRED.
 C. ADDRESS NUMBERS ON SUITES/OFFICES WITHIN
 MULTI-TENANT BUILDINGS SHALL BE A MINIMUM OF 6 INCHES
 HIGH.
 D. BUILDING NUMBERS SHALL BE A MINIMUM OF 12 INCHES
 HIGH AND PLACED IN A CONSPICUOUS LOCATION AWAY FROM
 LANDSCAPING. MULTIPLE LOCATIONS MAY BE REQUIRED.
 NUMBERS OF CONTRASTING COLORS SHOULD BE USED.
 3.3 DOORS
 A. EXTERIOR DOORS SHALL ALL BE EQUIPPED WITH SECURITY
 HINGES AND SHALL BE REINFORCED WITH CASE HARDENED
 STRIKE PLATES. CASE HARDENED DEADBOLT LOCKS SHALL BE
 PROVIDED ON ALL EXTERIOR DOORS WITH A MINIMUM (1) INCH
 THROW OR MECHANICAL INTERLOCK.
 B. GLASS PERIMETER DOORS SHALL BE EQUIPPED WITH CASE
 HARDENED GUARD RINGS TO PROTECT THE MORTISE LOCK
 CYLINDER.
 C. REAR DOORS SHALL BE EQUIPPED WITH 180-DEGREE
 PEEPHOLE/ SECURITY VIEWER.
 3.4 MAILBOXES
 A. MAILBOX LOCATIONS SHALL BE IN A WELL LIT, HIGH
 TRAFFIC LOCATION.
 3.5 DESIGN
 A. BUILDING ARCHITECTURE SHALL ALLOW FOR ENHANCED
 NATURAL SURVEILLANCE OF ALL PARKING LOTS AND PROVIDE A
 SENSE OF SECURITY TO PATRONS AND VISITORS.
 B. DRIVE-THRU LANES SHALL HAVE ONE WAY SIGNAGE STATING
 SAME.
 C. LANDSCAPING SHALL NOT OBSTRUCT VIEW FROM WINDOWS OR
 WALKWAYS.
 D. CROSSWALKS SHALL BE RAISED AND DELINEATED BY USING
 CONTRASTING PAVER BLOCKS AS OPPOSED TO SURFACE
 STRIPING.
 E. ALL BUILDINGS SHALL BE PRE-WIRED FOR CLOSED-CIRCUIT
 TELEVISION (CCTV) AND ALARM SYSTEMS.
 F. DUMPSTERS SHALL NOT ALLOW FOR EASY CONCEALMENT,
 CREATE BLIND SPOTS OR HIDING AREAS AND SHOULD BE ABLE
 TO BE LOCKED.
 G. SIGNS SHALL CLEARLY IDENTIFY PUBLIC ENTRANCES.
 H. LANDSCAPING SHALL BE MAINTAINED AT 3 FEET OR LESS.
 TREES SHALL BE INSTALLED SO AS NOT TO CONFLICT WITH THE
 LIGHTING SYSTEM. LOWER CANOPY LIMBS ON TREES SHALL BE
 MAINTAINED AT 8 FEET OR HIGHER.
 I. CONVEX MIRRORS SHALL BE INSTALLED IN STAIRWELL
 ENABLING VIEWS OF UPPER AND LOWER STAIRWAYS.
 J. GRILLS SHALL BE PLACED ON ALL DUCTS, VENTS AND
 OPENINGS GREATER THAN 12 INCHES.
 K. BIKE RACKS SHOULD BE AT THE FRONT OF THE BUILDING OR
 COMPLEX, NOT IN THE PARKING LOT FOR EASY SURVEILLANCE
 AND SAFETY.
  

Review Stop STORM STORMWATER
Rev No 1 Status   Date   Cont ID  
Sent By   Date 09-24-2009 Time   Rev Time 0.00
Received By jrenault Date 09-24-2009 Time 12:22 Sent To  
Notes
2009-09-24 12:46:29PRIOR TO RECEIVING A BUILDING PERMIT , PROVIDE THE
 FOLLOWING :
 1)CONSTRUCTION PLANS FOR THE PROPOSED STORMWATER
 IMPROVEMENTS , SIGNED & SEALED
 2) PROVIDE CALCULATIONS , SIGNED & SEALED , INCLUDING
 WATER QUALITY , IN ACCORDANCE WITH SFWMD VOLUME IV
 3) TOPO SURVEY TO SHOW WHETHER OR NOT OFF SITE FLOWS
 CONTRIBUTE TO THE SYSTEM
 4) PROVIDE COPY OF LWDD APPROVAL*-

Review Stop SURVEY SURVEYING
Rev No 2 Status P Date 12-09-2009 Cont ID  
Sent By eschneid Date 11-10-2009 Time 13:23 Rev Time 0.00
Received By eschneid Date 11-10-2009 Time 13:23 Sent To  
Notes
***NONE***

Review Stop SURVEY SURVEYING
Rev No 1 Status F Date 09-30-2009 Cont ID  
Sent By vnoel Date 09-30-2009 Time 09:37 Rev Time 0.00
Received By vnoel Date 09-30-2009 Time 09:37 Sent To  
Notes
2009-09-30 09:36:241. MAY NEED TO CHECK WITH FPL FOR PROPOSED DUMPSTER IN
 THEIR EASEMENT.
 2. EXISTING DRAINAGE SHOWN ON CONCEPTUAL ENGINEERING
 PLANS IS ONLY PROPOSED PER SURVEY AND SITE VISIT.
 3. UNITY OF TITLE WILL BE REQUIRED. APPLICATION CAN BE
 MADE THROUGH ENGINEERING SERVICES.

Review Stop TRAFFIC TRAFFIC ENGINEERING
Rev No 2 Status P Date 12-09-2009 Cont ID  
Sent By eschneid Date 11-10-2009 Time 13:22 Rev Time 0.00
Received By eschneid Date 11-10-2009 Time 13:22 Sent To  
Notes
***NONE***

Review Stop TRAFFIC TRAFFIC ENGINEERING
Rev No 1 Status F Date 10-01-2009 Cont ID  
Sent By   Date 10-01-2009 Time   Rev Time 0.00
Received By bcollins Date 10-01-2009 Time 08:05 Sent To  
Notes
2009-10-01 07:59:28CONCURRENCY LETTER FROM COUNTY? NO OTHER COMMENTS.

Review Stop Z ZONING
Rev No 2 Status F Date 12-09-2009 Cont ID  
Sent By eschneid Date 11-10-2009 Time 13:04 Rev Time 0.00
Received By eschneid Date 11-10-2009 Time 13:21 Sent To  
Notes
2009-12-09 13:21:25INFORMAL SITE PLAN REVIEW CASE NO. 09-04
 BENOIST PLAZA - ADDITIONAL MEDICAL OFFICE BUILDING
 RESUBMITTAL 11/10/09
  
 - PLEASE PROVIDE RESPONSES TO REVIEW COMMENTS IN
 WRITTEN FORMAT.
  
 - WHEN RESUBMITTING, PLEASE PROVIDE A MINIMUM OF SIX
 (6) COPIES, ONE (1) REDUCED COPY (11" X 17"), AND AN
 ELECTRONIC COPY IN .PNG FORMAT OF ALL PLANS. PLEASE
 NOTE THAT RE-SUBMITTALS MAY BE SUBJECT TO ADDITIONAL
 COMMENTS.
  
 - PLEASE NOTE THAT IF THE PLANNING AND ZONING
 DEPARTMENT HAS NOT RECEIVED A RESPONSE TO THESE
 COMMENTS WITHIN 60 DAYS THE CASE SHALL BE CONSIDERED
 WITHDRAWN. ANY FURTHER ACTION SHALL REQUIRE RESUBMITTAL
 OF A NEW DEVELOPMENT APPLICATION.
  
 - PLEASE NOTE THAT PREVIOUSLY-ISSUED COMMENTS WERE NOT
 BE SUFFICIENTLY ADDRESSED, THEREFORE YOU ARE BEING
 ACCESSED A RESUBMITTAL FEE OF $200 (20% OF THE ORIGINAL
 APPLICATION FEE).
  
 1) REPEAT COMMENT: PROVIDE VERIFICATION FROM PALM BEACH
 COUNTY WATER UTILITIES THAT THE TREES AND DUMPSTER
 ENCLOSURE MAY BE LOCATED AS SHOWN IN THE EASEMENT ON
 THE SOUTH SIDE OF THE BUILDING.
  
 2) REPEAT COMMENT: PLEASE PROVIDE THE BELLSOUTH LETTER.
  
 CONTACT ERIC SCHNEIDER @ (561) 822-1446

Review Stop Z ZONING
Rev No 1 Status F Date 10-09-2009 Cont ID  
Sent By eschneid Date 10-09-2009 Time 17:24 Rev Time 3.00
Received By eschneid Date 10-09-2009 Time 17:24 Sent To  
Notes
2009-10-09 18:01:26INFORMAL SITE PLAN REVIEW CASE NO. 09-04
 BENOIST PLAZA - ADDITIONAL MEDICAL OFFICE BUILDING
 PLANS AND PLATS REVIEW COMMITTEE MEETING 10/14/09
  
 - PLEASE PROVIDE RESPONSES TO REVIEW COMMENTS IN
 WRITTEN FORMAT.
  
 - WHEN RESUBMITTING, PLEASE PROVIDE A MINIMUM OF SIX
 (6) COPIES, ONE (1) REDUCED COPY (11??? X 17???), AND
 AN ELECTRONIC COPY IN .PNG FORMAT OF ALL PLANS. PLEASE
 NOTE THAT RE-SUBMITTALS MAY BE SUBJECT TO ADDITIONAL
 COMMENTS.
  
 - PLEASE NOTE THAT IF THE PLANNING AND ZONING
 DEPARTMENT HAS NOT RECEIVED A RESPONSE TO THE PPRC
 COMMENTS WITHIN 60 DAYS FROM THE PPRC MEETING, THE CASE
 SHALL BE CONSIDERED WITHDRAWN. ANY FURTHER ACTION SHALL
 REQUIRE RESUBMITTAL OF A NEW DEVELOPMENT APPLICATION.
  
 - PLEASE NOTE THAT YOU WILL BE PERMITTED ONE (1)
 RESUBMITTAL AT NO ADDITIONAL COST. IF PREVIOUSLY-ISSUED
 COMMENTS CONTINUE TO NOT BE SUFFICIENTLY ADDRESSED, THE
 APPLICANT WILL BE ACCESSED A RESUBMITTAL FEE. SUCH FEE
 WILL BE 20% OF THE ORIGINAL APPLICATION FEE.
  
 1) THE DUMPSTER ENCLOSURES DO NOT CONFORM TO CITY OF
 WEST PALM BEACH MINIMUMS. PLEASE PROVIDE STANDARD
 DETAIL (PROVIDED DETAIL DOES NOT CONFORM TO WPB
 STANDARDS).
  
 2) NEED AN EASEMENT RELEASE FROM FPL TO PUT THE
 DUMPSTER PAD AND ENCLOSURE IN THE FPL EASEMENT.
  
 3) THE ENGINEERING SERVICES DEPARTMENT SHALL APPROVE,
 IN WRITING, THE USE OF WHEEL STOPS 6 INCHES FROM THE
 EDGE OF PAVEMENT WITH THE 1.5 FOOT OVERHANG AS SHOWN.
 THE APPROVAL SHALL INCLUDE THAT THE PROPOSAL WILL
 PROVIDE ADEQUATE STRENGTH TO SECURE THE WHEEL STOPS
 WITHOUT DAMAGE TO THE PAVING. PLEASE NOTE, IF THE
 ENGINEERING SERVICES DEPARTMENT DOES NOT APPROVE THE
 PROPOSAL, THEN A TYPE "D" CURB IS REQUIRED.
  
 4) PROVIDE PARKING DETAILS FOR ALL OF THE PARKING
 CONFIGURATIONS USED ON THE PLAN. THERE ARE NO DETAILS
 PROVIDED FOR THE ANGLED HC SPACES.
  
 5) THE MAXIMUM FOOT CANDLES ALONG THE SOUTH PROPERTY
 LINE IS 0.5.
  
 6) THE BIKE RACK DETAIL DOES NOT CONFORM TO CITY
 STANDARDS - THE WAVE IS NOT ALLOWED. PLEASE CONTACT
 ALEX HANSEN AT (561) 822- 1463 FOR DETAILS. PROVIDE THE
 BIKE PARKING AREA DIMENSIONS ON THE PLAN TO VERIFY THAT
 IT CONTAINS PARKING FOR THE PROPER AMOUNT OF BICYCLES.
 PLEASE NOTE THAT THE BICYCLE PARKING SHALL BE
 DISTRIBUTED FOR BOTH BUILDINGS.
  
 7) PROVIDE A TREE OR GROUPING OF PALMS IN THE LARGE
 ISLAND IN THE NORTHERN PARKING AREA.
  
 8) THE DUMPSTER ENCLOSURE ON THE SOUTH SIDE OF THE
 BUILDING REQUIRES SCREENING ON THE SOUTH SIDE.
  
 9) PLEASE CONSIDER ADDING A RECYCLING CONTAINER
 ENCLOSURE.
  
 10) PROVIDE VERIFICATION FROM PALM BEACH COUNTY WATER
 UTILITIES THAT THE TREES AND DUMPSTER ENCLOSURE MAY BE
 LOCATED AS SHOWN IN THE EASEMENT ON THE SOUTH SIDE OF
 THE BUILDING.
  
 11) THERE APPEARS TO BE A TREE INSTALLED ON THE WATER
 LINE ALONG THE EAST PROPERTY LINE.
  
 12) A TREE IS MISSING FROM THE TERMINAL ISLAND TO THE
 SOUTH OF THE AMBULANCE DROP-OFF.
  
 13) THE LIGHT BY THE PAVER CROSS-WALKS AT THE NORTHEAST
 CORNER OF THE BUILDING APPEARS TO BE IN THE DRIVE
 AISLE.
  
 14) A LIGHT ON THE WEST SIDE OF THE EXISTING BUILDING
 APPEARS TO BE IN THE SIDEWALK.
  
 15) WHERE IS THE AC EQUIPMENT AND THE (FUTURE?)
 GENERATOR LOCATIONS?
  
 16) PLEASE PROVIDE THE BELLSOUTH LETTER.
  
 17) MARK THE NUMBER OF PARKING SPACES WITHIN EACH
 PARKING BAY (DONE IN PHASE I).
  
 18) VERIFY IN WRITING THAT THE FIRE DEPARTMENT DOES NOT
 REQUIRE A 20 FOOT CLEAR ROUTE AROUND THE ENTIRE
 BUILDING.
  
 19) THE USE BREAK DOWN TABLES ON THE SITE AND LANDSCAPE
 PLANS SHALL SEPARATE THE DETENTION AREA FROM THE
 PROVIDED LANDSCAPE CALCULATION. THE CITY DOES NOT COUNT
 DETENTION/RETENTION AREAS TOWARD MEETING THE 15%
 LANDSCAPE REQUIREMENT. IT DOES COUNT TOWARD THE OPEN
 SPACE AND PERVIOUS SURFACE REQUIREMENTS.
  
 20) THE USE BREAK DOWN TABLE STATES THAT THE CANOPIES
 ARE NOT PART OF THE BUILDING COVERAGE. WHERE ARE THEY
 COUNTED?
  
 21) PROVIDE THE BAY AND STALL DEPTHS FOR ALL OF THE
 ANGLED PARKING AREAS - THE HALF BAYS ON THE EAST, SOUTH
 AND WEST SIDES AND THE FULL BAY ON THE WEST SIDE. THE
 AREAS SCALE TOO NARROW.
  
 22) THE 13 FOOT AISLE MEASURE BY THE SOUTHWEST CORNER
 OF THE BUILDING MAY NOT INCLUDE THE CURB.
  
 23) THE ANGLED HC SPACES ON THE EAST SIDE OF THE
 BUILDING INTRUDE INTO THE DRIVE AISLE.
  
 24) THE TERMINAL ISLANDS ON THE EAST SIDE OF THE
 BUILDING AND THE INTERIOR ISLAND ON THE SOUTH SIDE OF
 THE BUILDING SHALL BE ENLARGED TO BE AS DEEP AS THE
 ADJACENT PARKING SPACES.
  
 CONTACT ERIC SCHNEIDER @ (561) 822-1446

  Print


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved