Plan Review Details - Project E23020004
Plan Review Stops For Project E23020004
Review Stop ENG-A ENGINEERING FORMAL REVIEW
Rev No 1 Status F Date 02-24-2023 Cont ID  
Sent By rrossano Date 02-24-2023 Time   Rev Time  
Received By rrossano Date 02-24-2023 Time   Sent To  
Notes
2023-02-24 14:11:14COMMENTS FROM RICK ROSSANO, PROJECT COORDINATOR,
 ENGINEERING SERVICES DEPT., 561-494-1098
 [email protected] :
  
 1. CONFIRM THAT A COMPLETED LOS ANALYSIS SUMMARY TABLE
 HAS BEEN SUBMITTED DIRECTLY TO ENGINEERING (SHEET 33 OF
 CITY OF WPB DEVELOPMENT APPLICATION).
 2. CHECK TO SEE IF FDEP FORMS FOR PROPOSED SANITARY
 SEWER ARE REQUIRED.
 3. PROVIDE CALCULATIONS ON PLANS OF EXISTING AND
 PROPOSED DEMANDS FOR WATER & SEWER (AVERAGE, MAXIMUM
 AND PEAK) AND FIRE FLOW DEMANDS. CALCULATIONS SHALL BE
 PER FAC 64E-8 FOR WATER AND PER FAC 64-E.008 FOR SEWER.
 4. COORDINATE WITH MARK HURLEY, FIELD CUSTOMER SERVICE
 SUPERVISOR WITH CITY OF WPB PUBLIC UTILITIES, REGARDING
 PLACEMENT OF BACKFLOW DEVICES AND WATER METERS. CONTACT
 HIM AT 561-494-2262 OR [email protected]
 5. PLANS SHALL SHOW EXISTING AND PROPOSED LOCATIONS AND
 DIMENSIONS OF ALL WATER, STORMWATER, AND SANITARY AND
 SEWER LINES AND CLEANOUTS, GREASE TRAPS, ETC. INCLUDING
 STUBS TO EACH PROPERTY LINE FOR WATER AND SANITARY
 SEWERS, THE MAKE AND MODEL OF ALL VALVES, POTABLE AND
 IRRIGATION METERS, BACKFLOWS, FIRE HYDRANTS AND FDCS,
 AND OTHER DEVICES TO BE INSTALLED ON THE SYSTEM, CATCH
 BASINS, CULVERTS, DITCHES INCLUDING GRADES, PIPES
 SIZES, MATERIALS, ELEVATIONS, ASSUMPTIONS,
 CALCULATIONS, INVERT ELEVATIONS FOR ALL INLETS AND
 MANHOLES AND PROFILES OF SANITARY SEWER LINES. GATE
 VALVE BOXES SHALL NOT BE INSTALLED IN CURB OR SIDEWALK.
 ALL AVAILABLE ELEVATION SHALL BE SHOWN ON THE PROFILE
 VIEW. DIRECTION OF FLOW SHALL BE SHOWN ON PLAN VIEW ON
 PLAN VIEW FOR ALL SANITARY AND STORM SEWERS. PLEASE
 SHOW SLOPE % ON ALL SANITARY LINES AND CALL OUT
 MATERIAL. ADDITIONALLY, PLAN VIEW SHALL SHOW ALL
 EXISTING AND PROPOSED UNDERGROUND UTILITY LAYOUT,
 INCLUDING FIBER OPTIC, ELECTRIC, GAS, AND CABLEVISION &
 TELECOMMUNICATION FACILITIES INCLUDING PIPES SIZES AND
 MATERIALS, LOCATED ON THE RIGHT-OF-WAY.
 6. PLEASE CUT AND CAP UTILITIES NOT IN USE AND REMOVE
 ANY ABANDONED UTILITY LINES LARGER THAN 2 INCHES FROM
 CITY RIGHT OF WAY.
 7. PLEASE SHOW EXISTING AND PROPOSED UTILITY EASEMENTS,
 INCLUDING THOSE PROPOSED TO ALLOW ACCESS FOR CITY
 PERSONNEL TO PROPOSED UTILITY WATER METERS.
 8. PLEASE CALLOUT DOMESTIC BACKFLOW PREVENTER AS RPPA
 AND FIRE BACKFLOW PREVENTER AS DCDA. SPECIFY LEAD FREE
 DESIGN ON ALL BACKFLOWS.
 9. ENGINEERING PLANS SHALL INCLUDE PIGGING, FLUSHING
 AND SAMPLE POINTS ON ANY WATER RUNS 60 FT. IN LENGTH OR
 GREATER.
 10. PROVIDE PROFILE AND CLEARANCES BETWEEN WATER, SEWER
 AND STORM LINES AT ALL UTILITY CROSSINGS WITHIN ROW PER
 CITY OF WEST PALM BEACH STANDARD DETAIL GN-2 SERIES.
 PLEASE SHOW ALL EXISTING AND PROPOSED UNDERGROUND
 UTILITY LAYOUT, INCLUDING FIBER OPTIC, ELECTRIC, GAS,
 AND CABLEVISION & TELECOMMUNICATION FACILITIES WITH
 PIPE MATERIAL AND SIZE, LOCATED ON THE RIGHT-OF-WAY.
 11. WHEN SUBMITTING APPROVED MATERIALS LIST, PLEASE
 PROVIDE MATERIAL/CUT SHEETS FOR ALL PROPOSED BACKFLOW
 DEVICES SHOWING SPECIFIC MODEL NUMBER AND SPECIFYING
 USC APPROVED LEAD-FREE DESIGN.
 12. PLEASE CLEARLY SHOW ROAD RIGHT OF WAY.
 13. ADD PAVEMENT RESTORATION NOTE PER GOVERNING AGENCY
 REQUIREMENTS (FDOT?).
 14. OBTAIN FDOT PERMIT FOR WORK IN STATE ROW.
 15. PLEASE PROVIDE LEGEND ON ALL PLAN SHEETS TO INCLUDE
 STREETLIGHT, SIGN POSTS, TRANSFORMER BOXES ETC.
 16. PLEASE RESPOND TO ALL COMMENTS IN WRITING AND
 INCLUDE PROJECT NAME, ADDRESS AND PERMIT NUMBER
 (E-XXXXXXXX).
  
 COMMENTS FROM MARK HURLEY, FIELD CUSTOMER SERVICE
 SUPER., WPB PUBLIC UTILITIES, 561-822-2262 OR
 [email protected]:
  
 -ON SHEET C300, PLEASE MAKE PIPE MATERIAL TYPE OF 12
 INCH WATER MAIN MORE CLEAR TO READ.
 -FIRELINE MAY NOT BE PVC UPSTREAM OF BACKFLOW ASSEMBLY.
 NEEDS TO BE DIP ALONG WITH BACKFLOW ASSEMBLY UPRIGHTS.
 -ON LABEL OF PROPOSED FIRE HYDRANT, ADD WORDING
 ???(PRIVATE)???
 -ADD GRAPHIC SCALES FOR THE DETAILS ON SHEET C300 IF
 DIFFERENT THAN THE GRAPHIC SCALE AT TOP OF SHEET.
 -SHOW AND LABEL FIRELINE GATE VALVES.
 -ADD FIRE FLOW CALCULATIONS TO UTILITY PLAN AS DIRECTED
 IN NOTE 9 OF STANDARD DETAIL WS5.
 -FIRELINE BACKFLOW ASSEMBLY SHOULD NOT BE IN A UTILITY
 EASEMENT PER NOTE 6 WS5. IF EASEMENT DOES NOT CURRENTLY
 EXIST, MAY REVISE DIMENSION.
 -ON SMALL METERED WATER SERVICES, THE OPERATING VALVE
 IS INSIDE THE METER BOX. THERE IS NOT AN ADDITIONAL
 VALVE OUTSIDE OF BOX OTHER THAN THE CORPSTOP. REFER TO
 STANDARD DETAIL WS1.
 -ADD MARKUP NOTE ON WS1 (SHEET C301) THAT DUAL CHECK
 VALVE IS NOT USED WHEN A BACKFLOW ASSEMBLY IS BEING
 INSTALLED.
 -LABEL EXISTING WATER SERVICES AND FIRE HYDRANT PIPE
 COMING OFF WATER MAINS WITH PIPE SIZE AND MATERIAL
 TYPE.
 -POLY MAY NOT BE USED BETWEEN METER AND BACKFLOW PER
 WS1 NOTE 3. REVISE THAT CALLOUT ON WATER SERVICE
 ENLARGEMENT ??? HYUNDAI.
 -SHOW AND LABEL ALL FRANCHISE UTILITIES NEAR WORK
 AREAS.
 -EXISTING WATER METER AT CONGRESS SIDEWALK IS SHOWN AS
 2 INCH SIZE IN OUR BILLING SYSTEM. WHY PROPOSING TO
 REMOVE IT, PAY ADDITIONAL FEES, AND THEN RUN A NEW 2
 INCH METERED WATER SERVICE PIPE THERE?
 -PER WS1, WATER SERVICE LINES ARE 1 INCH OR 2 INCH
 SIZE. 1 INCH METER WOULD TYPICALLY HAVE 1 INCH SERVICE
 LINE.
 -PVC FIRELINE PIPE BETWEEN BACKFLOW ASSEMBLY AND
 BUILDING IS CONTRADICTING NOTE 22 ON UTILITY PLAN
 SHEET.
 -CANNOT FIND WATER DEMAND CALCULATIONS ON UTILITY PLAN
 SHEET.
 -SHOW AND LABEL SANITARY SEWER INFRASTRUCTURE INCLUDING
 MANHOLES, SEWER LATERALS, AND CLEANOUTS. ALSO SHOW
 EXISTING AND PROPOSED CONNECTION TO CITY SEWER MAIN.
 -ADD STANDARD DETAIL FOR THE PAVEMENT RESTORATION THAT
 WILL BE NEEDED IN FDOT RIGHT OF WAY AS SHOWN ON SHEET
 C200.
  
 COMMENTS FROM TRACY WARD, SR. STORMWATER ENG.,
 ENGINEERING SERVICES, [email protected] 561-494-1120:
  
 DRAINAGE CALCULATIONS:
 1. SITE DISCHARGES TO THE CITY???S WARE CANAL, WHICH IS
 A TRIBUTARY TO SFWMD???S C-51 CANAL THAT RUNS ON THE
 SOUTHSIDE OF SOUTHERN BLVD.
 2. A FACTOR OF SAFETY OF 2 IS TO BE APPLIED TO THE
 EXFILTRATION TRENCH EQUATION. IT IS COMMON PRACTICE TO
 COMBINE THE FACTOR OF SAFETY WITH THE CREDIT ALLOWED
 FOR DRY RETENTION SYSTEMS SO THAT EACH CANCELS THE
 OTHER OUT. THE REQUIRED WATER QUALITY VOLUME IS 0.93
 AC-FT.
 3. APPENDIX A DESCRIBES THE RETENTION AREAS ALONG THE
 NORTH SIDE OF THE SITE AS PONDS (CN = 100) WHEN THEY
 APPEAR TO BE DRY SWALES (BOTTOM ELEVATIONS MORE THAN 2
 FEET ABOVE THE WSWT ELEVATION OF 10.0 FT NAVD.
 4. DIMENSIONS USED FOR THE EXFILTRATION TRENCH
 CALCULATIONS DO NOT MATCH THE EXFILTRATION DETAIL
 PROVIDED ON SHEET C-202 OR THE WEIR ELEVATION PROVIDED
 ON SHEET C-200.
 5. THE EXISTING WEIR ELEVATION IS LISTED AS 13.57 FT
 NAVD. SHEET C-200 LISTS THE WEIR ELEVATION AS 13.71 FT
 NAVD AT STRUCTURE EX-01
 6. TRENCH VOLUME IS 0.0 AC-FT BETWEEN ELEVATIONS 13.75
 FT AND 16.25 FT NAVD IN THE POST DEVELOPMENT STAGE
 STORAGE TABLE.
 7. IN THE ICPR MODEL, THE CANAL WILL LIKELY PEAK CLOSER
 TO THE PEAK OF THE RAINFALL HYETOGRAPH AND REMAIN CLOSE
 TO THAT STAGE UNTIL AFTER THE STORM HAS ENDED. ANY
 CHANGES THOUGH PROBABLY WILL NOT CHANGE THE MODEL
 RESULTS DUE TO THE WEIR ELEVATION BEING HIGHER THAN THE
 PEAK CANAL ELEVATION USED.
 8. REVIEW THE STAGE-STORAGE INFORMATION USED IN THE
 PROPOSED MODEL NODE ONSITE-POND VS. THE STAGE STORAGE
 TABLE IN APPENDIX F.
 9. REVISE THE CALCULATIONS BASED ON THE DESIGN
 INFORMATION ON THE ENGINEERING DRAWINGS.
  
 CIVIL PLANS
 1. THE EXFILTRATION TRENCH BETWEEN DS-01 AND DS-11 IS
 DOWNSTREAM OF THE CONTROL STRUCTURE DS-02. EXPLAIN HOW
 THE EXFILTRATION TRENCH WILL BECOME SURCHARGED.
 2. STRUCTURE DS-17 NOT LISTED IN THE STORM DRAINAGE
 STRUCTURE TABLE ON SHEET C-200.
 3. SUGGEST USING CHANNEL TYPE TRENCH DRAIN INSTEAD OF
 SLOTTED PIPE TRENCH DRAIN AT THE DRIVEWAY TO CONGRESS
 AVE. THE CHANNEL TRENCH DRAIN IS WIDER AND THERE WILL
 BE LESS SPILL OVER COMING FROM THE STEEP DRIVEWAY
 SLOPE.
 4. IT APPEARS ALL OF THE PAVEMENT SOUTH OF THE NORTH
 DRIVEWAY TO CONGRESS AVE WILL DRAIN TO CONGRESS AVE AND
 NOT IN THE DIRECTION OF THE FLOW ARROWS. PROVIDE MORE
 GRADES IN THIS AREA TO INDICATE THE PROPOSED GRADING
 DIRECTION AND/OR CONSIDER INSTALLING A TRENCH DRAIN
 ACROSS THE DRIVEWAY OR ANOTHER INLET IN THE GORE AREA
 OF THE STRIPING TO CAPTURE THE RUNOFF BEFORE IT LEAVES
 THE SITE.
 5. INCLUDE A PRB BAFFLE ON THE WEST PIPE OF STRUCTURE
 DS-08 TO CONTAIN ANY OILS THAT COME FROM THE SERVICE
 BAYS.
 6. LABEL THE STREETS ON THE CROSS SECTIONS PROVIDED ON
 SHEET C-201.
 7. THE SYMBOLS FOR SECTIONS D-D AND E-E APPEAR TO BE
 FACING IN THE WRONG DIRECTION (SHOULD POINT SOUTH
 INSTEAD OF NORTH).
 8. CONFIRM SIDEWALK SLOPE NEXT TO THE PROPERTY LINE IN
 SECTIONS D-D AND E-E.
 9. PROPOSED GRADE ON SECTION E-E IS LOWER THAN EXISTING
 GRADE AT THE PROPERTY LINE.
 10. LEGEND SYMBOLS FOR PROPOSED AND EXISTING ELEVATIONS
 DO NOT MATCH HOW THEY ARE SHOWN ON THE P&G PLAN.
 11. USE THE CITY???S LASTEST STANDARD DETAILS.
  
 COMMENTS FROM RICKY ELIZONDO, PUB. UTILITIES PLANS
 EXAMINER, [email protected] , 561-494-1101:
  
 -2??? CONNECTION OFF OF EXISTING HYDRANT WILL NOT BE
 PERMITTED. PLEASE USER OTHER MEANS OF SOURCING POTABLE
 WATER TO THE BUILDING. (SIDE NOTE, THE CONFIGURATION
 SHOWN HAS THE SERVICE LINE BLEEDING BACK INTO THE ROW.
 PLEASE DO NOT REPEAT THIS IN THE NEXT ITERATION)
 -DOMESTIC WATER CONNECTION FROM EXISTING 1???
 IRRIGATION LINE. ANOTHER METHOD OF POTABLE CONNECTION
 WILL BE REQUIRED
 -PROPERLY SHOW ALL SEWER CONNECTIONS TO EXISTING MAIN,
 AND CALL OUT ALL SEWER FITTINGS AND APPURTENANCES.
 -GATE VALVES WILL BE REQUIRED FOR PROPOSED FIRE LINE
 TAP. ONE AT IMMEDIATELY AFTER THE TAPPING SLEEVE AND
 ANOTHER AT THE R/W TO SERVE AS CITY???S POINT OF
 SERVICE
 -FIRE LINE MAY REQUIRE A PERMIT FROM FDOH. CHECK
 CURRENT STANDARDS TO CONFIRM IF THIS IS THE CASE, OR
 CONTACT JAY HARDMAN FOR FURTHER INFORMATION/GUIDANCE.
 -SAMPLE POINTS FOR FIRE LINE ARE NOT SHOWN
  
 MORE COMMENTS MAY BE IMPENDING BASED ON CHANGES FROM
 THE SECOND SUBMITTAL.
  
  
  

Review Stop ENG-D ENGINEERING DEFICIENCY REVIEW
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop ENG-E ENGINEERING ENVR. MIT. REVIEW
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop ENG-F ENGINEERING FINAL DRAWING REV
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop ENG-M ENGINEERING MODIFICATION REV
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop ENG-P ENGINEERING PLANNING REVIEW
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop ENG-T ENGINEERING TRAFFIC STUDY REV
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***