Plan Review Details - Project E22120012
Plan Review Stops For Project E22120012
Review Stop ENG-A ENGINEERING FORMAL REVIEW
Rev No 2 Status F Date 05-01-2023 Cont ID  
Sent By lquinone Date 05-01-2023 Time 13:22 Rev Time 0.00
Received By lquinone Date 05-01-2023 Time 13:21 Sent To  
Notes
2023-05-01 13:22:32E22120012 - ROYAL POINCIANA PLAYHOUSE RESUB 3.28.23
  
 NO COMMENTS FROM LINDA QUI??ONES-CINTRON, PROJECT
 COORDINATOR, ENGINEERING SERVICES DEPARTMENT (561)
 494-1085 [email protected]:
  
  
 COMMENTS FROM MARK HURLEY, FIELD CUSTOMER SERVICE
 SUPER., WPB PUBLIC UTILITIES, 561-822-2262 OR
 [email protected]:
 -PROPOSED WATER DEMAND AVERAGE AND PEAK GPM EXCEED
 THRESHOLDS FOR 1.5 INCH M120 BADGER METER. CANNOT USE
 1.5 INCH DOMESTIC METER. NEED TO RE-EVALUATE WATER
 DEMAND CALCULATIONS OR INCREASE METER SIZE. NEXT METER
 SIZES AND MODELS ARE 2 INCH M170 BADGER METER AND 3
 INCH BADGER COMPOUND METER. PEAK GPM EXCEEDS 2 INCH
 METER AS WELL.
  
 -ADD NOTE ON DEMO PLAN FOR CONTRACTOR TO RETURN REMOVED
 WATER METERS TO CITY WPB. CAN CONTACT [email protected].
  
 -GATE VALVE NEAR TAP FOR 6 INCH FIRELINE IS SHOWING TOO
 CLOSE TO A SIGN. VALVE KEY WILL NOT BE ABLE TO OPERATE
 GATE VALVE.
  
 -REMINDER TO FOLLOWUP ON THE 2 INCH CHILLER LINE ISSUE
 FROM LAST RESPONSE LETTER.
  
 -WATER PLANS DO NOT SHOW THE BE UTILITY AND FPL
 EASEMENTS SHOWN ON SURVEY.
  
 -WATER METER AND BACKFLOW ASSEMBLIES AT NORTH SIDE OF
 150 ROYAL POINCIANA STILL NEED BE RELOCATED
 SIGNIFICANTLY EAST. TO ACCOMPLISH THAT MAY NEED REVISE
 LANDSCAPING PLANS. WOULD NEED UTILITY EASEMENT AROUND
 METER BOX IF ON PRIVATE PROPERTY AND NO UTILITY
 EASEMENT CURRENTLY EXISTS THERE.
  
 -OVERALL LANDSCAPING PLAN SHOWS TWO ADDITIONAL
 TRANSFORMERS NEAR PROPOSED 3 INCH FIRELINE BACKFLOW
 ASSEMBLY AND PIPING. UPDATE ENGINEERING PLANS IF
 TRANSFORMERS ARE SHOWN ACCURATELY ON LANDSCAPING PLAN.
  
 -ADD WATER SERVICE LINE PIPE SIZE AND MATERIAL TYPE
 UPSTREAM OF PROPOSED WATER METER.
  
 -ON LABELS OF PROPOSED BACKFLOW ASSEMBLIES AND WATER
 METERS, ADD REFERENCE TO THE ASSOCIATED WPB WATER
 SERVICE STANDARD DETAIL.
  
 -PLANS NEED BE SIGNED, SEALED, AND DATED.
  
  
 COMMENTS FROM RICKY ELIZONDO, PUB. UTILITIES PLANS
 EXAMINER, [email protected], 561-494-1101:
  
 -COMMENT 2 NOT FULLY ADDRESSED. PLEASE DENOTE THE POINT
 WHERE WPB TAKES OVER MAINTENANCE OF SERVICE. (LINE
 CANNOT BE CONSIDERED ???PRIVATE??? AS DISCUSSED ON
 PHONE CALL)
 -COMMENT 5 NOT FULLY ADDRESSED, PLEASE PROVIDE THE
 PROFILE REGARDLESS OF LENGTH IN ORDER TO DETERMINE LACK
 OF CONFLICTS AND APPROPRIATE CLEARANCE FOR THE PROPOSED
 PIPE.
 -COMMENT 8 NOT FULLY ADDRESSED, PLEASE REVISE.
 (CONFIRMATION GIVEN ON WATER DISTRIBUTION
 DEPARTMENT???S END ON PREFERENCE FOR SEPARATE TAPS)
 -REAPPLY ALL INFO RELATING TO DRY UTILITY LOCATIONS ON
 THE PLAN VIEW
  
 FEEL FREE TO CONTACT US IF YOU HAVE ANY QUESTIONS OR
 CONCERNS, THANKS.
 LINDA QUI??ONES-CINTRON, PROJECT COORDINATOR,
 ENGINEERING SERVICES DEPARTMENT (561) 494-1085
 [email protected]
  
  

Review Stop ENG-A ENGINEERING FORMAL REVIEW
Rev No 1 Status F Date 12-16-2022 Cont ID  
Sent By rrossano Date 12-16-2022 Time   Rev Time  
Received By rrossano Date 12-16-2022 Time   Sent To  
Notes
2022-12-16 09:13:45E21120012 - ROYAL POINCIANA PLAYHOUSE INITIAL REVIEW
 12.15.22
  
 COMMENTS FROM RICK ROSSANO, PROJECT COORDINATOR,
 ENGINEERING SERVICES DEPT., 561-494-1098
 [email protected] :
  
 1. COORDINATE WITH MARK HURLEY, FIELD CUSTOMER SERVICE
 SUPERVISOR WITH CITY OF WPB PUBLIC UTILITIES, REGARDING
 PLACEMENT OF BACKFLOW DEVICES AND WATER METERS. CONTACT
 HIM AT 561-494-2262 OR [email protected]
 2. SHOW EXISTING EASEMENTS FOR EXISTING WM.
 3. LABEL EXISTING SOURCE OF WATER ON ROYAL POINCIANA
 WAY (PIPE SIZE & MATERIAL, METER, ETC.)
 4. SHOW MASTER METER AT ROW (IF EXISTING).
 5. NEED CONFIRMATION FROM CITY OF WPB PUB. UTILITIES
 CUSTOMER SERVICE IF ONSITE LINE IS PUBLIC OR PRIVATE.
 6. PLANS SHALL SHOW EXISTING AND PROPOSED LOCATIONS AND
 DIMENSIONS OF ALL WATER, STORMWATER, AND SANITARY AND
 SEWER LINES AND CLEANOUTS, GREASE TRAPS, ETC. INCLUDING
 STUBS TO EACH PROPERTY LINE FOR WATER AND SANITARY
 SEWERS, THE MAKE AND MODEL OF ALL VALVES, POTABLE AND
 IRRIGATION METERS, BACKFLOWS, FIRE HYDRANTS AND FDCS,
 AND OTHER DEVICES TO BE INSTALLED ON THE SYSTEM, CATCH
 BASINS, CULVERTS, DITCHES INCLUDING GRADES, PIPES
 SIZES, MATERIALS, ELEVATIONS, ASSUMPTIONS,
 CALCULATIONS, INVERT ELEVATIONS FOR ALL INLETS AND
 MANHOLES AND PROFILES OF SANITARY SEWER LINES.
 7. PLEASE SHOW EXISTING AND PROPOSED UTILITY EASEMENTS,
 INCLUDING THOSE PROPOSED TO ALLOW ACCESS FOR CITY
 PERSONNEL TO PROPOSED UTILITY WATER METERS.
 8. PLEASE PROVIDE ENLARGED VIEW ON PLANS OF PROPOSED
 LOCATION OF WATER METER AND BACKFLOW PREVENTION, AND
 EXISTING METER AND BACKFLOW (TO BE REMOVED?). BACKFLOWS
 SHALL BE INSTALLED ON PRIVATE PROPERTY OUTSIDE OF
 EASEMENTS AND RIGHTS OF WAY. DOMESTIC WATER METERS
 SHALL BE INSTALLED IMMEDIATELY ADJACENT TO PROPERTY
 LINE. 3 INCH AND LARGER WATER METERS SHALL BE INSTALLED
 ABOVE-GROUND ONLY.
 9. ENGINEERING PLANS SHALL INCLUDE PIGGING, FLUSHING
 AND SAMPLE POINTS ON ANY WATER RUNS 60 FT. IN LENGTH OR
 GREATER.
 10. PROVIDE PROFILE AND CLEARANCES BETWEEN WATER, SEWER
 AND STORM LINES AT ALL UTILITY CROSSINGS PER CITY OF
 WEST PALM BEACH STANDARD DETAIL GN-2 SERIES.
 11. WHEN SUBMITTING APPROVED MATERIALS LIST, PLEASE
 PROVIDE MATERIAL/CUT SHEETS FOR ALL PROPOSED BACKFLOW
 DEVICES SHOWING SPECIFIC MODEL NUMBER AND SPECIFYING
 USC APPROVED LEAD-FREE DESIGN.
 12. PLEASE CLEARLY LABEL ROAD RIGHT OF WAY.
 13. PLEASE PROVIDE LEGEND ON ALL PLAN SHEETS TO INCLUDE
 STREETLIGHT, SIGN POSTS, TRANSFORMER BOXES ETC.
 14. PLEASE RESPOND TO ALL COMMENTS IN WRITING AND
 INCLUDE PROJECT NAME, ADDRESS AND PERMIT NUMBER
 (E-XXXXXXXX).
  
 COMMENTS FROM MARK HURLEY, FIELD CUSTOMER SERVICE
 SUPER., WPB PUBLIC UTILITIES, 561-822-2262 OR
 [email protected]:
  
 -CLEARLY SHOW AND LABEL METERED WATER SERVICE FOR 150
 ROYAL POINCIANA PLZ
 -CLEARLY SHOW AND LABEL PROPERTY LINES FOR 150 ROYAL
 POINCIANA PLZ.
 -ADD COPY OF SURVEY TO RESUBMITTAL PACKAGE.
 -ADD COPY OF ANY LANDSCAPING PLAN TO RESUBMITTAL
 PACKAGE, AND ENSURE LANDSCAPING IS DISTANCED FROM WATER
 METERS AND BACKFLOW ASSEMBLIES.
 -DDCV ON SHEET 10 IS EXCESSIVELY FAR FROM WATER MAIN.
 RELOCATE MUCH CLOSER TO WATER MAIN, BUT NOT IN ANY
 UTILITY EASEMENTS.
 -FOR THE FIRELINE ON SHEET 10: WHAT DOES IT SERVICE;
 WHY IS IT ENTERING THE SMALL BUILDING WITH THE CHILLER
 -VERIFY THE PRIVATE FIRE SYSTEMS WILL NOT HAVE ADDED
 CHEMICALS AND WILL NOT BE CONNECTED TO AN AUXILIARY
 WATER SYSTEM SUCH AS A WELL.
 -PROVIDE SIGNED AND SEALED FLOW CALCULATIONS FOR EACH
 FIRELINE AS DIRECTED IN WS5 NOTE 9.
 -LABEL ALL EXISTING WATER MAIN SEGMENTS WITH PIPE SIZE
 AND MATERIAL TYPE.
 -SHOW AND LABEL ALL EXISTING AND PROPOSED UTILITY
 EASEMENTS.
 -PLAN SHOWS WATER METER AND BACKFLOW SLIGHTLY NORTH OF
 PROPOSED 3 INCH FIRELINE ON SHEET 10. CANNOT SEE IT IN
 HISTORIC PICTURES OF AREA. VERIFY IF STILL THERE AND
 LABEL IF PROPOSED.
 -ADD PROPERTY AND BUILDING ADDRESSES.
 -UTILITY BILLING SYSTEM SHOWS EXISTING 6 INCH FIRELINE
 AT 70 ROYAL POINCIANA PLZ. PLEASE SHOW AND LABEL ON
 PLANS.
 -COULD NOT FIND WATER AND SEWER DEMAND CALCULATIONS ON
 WATER PLANS.
 -IS THE 2 INCH CHILLER LINE PROPOSED TO BE FED BY THE
 PROPOSED 1.5 INCH METERED WATER SERVICE? IF SO, VERIFY
 SERVICE LINE AND METER SIZE ARE SUFFICIENT.
 -RELOCATE BACKFLOWS AND WATER METERS SHOWN ON SHEET 11
 MUCH CLOSER TO WATER MAIN. MAKE SURE THEY ARE NOT
 ENCROACHING ON NEIGHBORING PROPERTY AND NOT ON TOP OF
 FPL UTILITY. BACKFLOW ASSEMBLIES SHOULD NOT BE IN ANY
 UTILITY EASEMENTS.
 -IF ANY FDC ARE NEEDED OR REQUIRED, SHOW AND LABEL ON
 PLANS.
 -ENSURE METERS AND BACKFLOWS ARE NOT PROPOSED TOO CLOSE
 TO POLES AND SIGNS.
 -ADD MARKUP NOTE ON WS1 THAT DUAL CHECKS ARE NOT USED
 WHEN BACKFLOW ASSEMBLIES ARE INSTALLED.
 -ADD STANDARD DETAIL WS2 TO SHEET 12.
  
 COMMENTS FROM RICKY ELIZONDO, PUB. UTILITIES PLANS
 EXAMINER, [email protected], 561-494-1101:
  
 -LIST THE SIZE AND MATERIAL OF THE SERVICES BEING
 REMOVED, AS WELL AS THEIR BACKFLOWS AND METERS
 -POINTS OF SERVICE NEED TO BE CALLED OUT
 -PROPOSED 3??? FIRE LINE NEEDS TO HAVE MATERIAL LISTED
 -CROSSING INFO NEEDED BETWEEN 3 INCH FIRE LINE AND
 EXISTING TELEPHONE CONDUIT
 -PROVIDE A PROFILE FOR THE 3 INCH FIRE LINE
 -PROVIDE WATER DEMAND CALCULATIONS FOR EXISTING AND
 PROPOSED CONDITIONS
 -ADD DATUM CONVERSION
 -SEPARATE TAPS REQUIRED FOR FIRE LINE AND POTABLE LINE
 PER DETAILS WS-1 AND WS-4
 -HORIZONTAL SEPARATION BETWEEN PROPOSED WATER LINE AND
 FPL LINE ON SOUTHERN END OF PROJECT IS NOT TO STANDARD
 -WATER MAIN MUST BE DIP PER STANDARDS (NOT PVC)
  
  
 FEEL FREE TO CONTACT US IF YOU HAVE ANY QUESTIONS OR
 CONCERNS, THANKS.
 RICK ROSSANO, PROJECT COORDINATOR, ENGINEERING SERVICES
 DEPARTMENT (561) 494-1098 [email protected]
  
  

Review Stop ENG-D ENGINEERING DEFICIENCY REVIEW
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop ENG-E ENGINEERING ENVR. MIT. REVIEW
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop ENG-F ENGINEERING FINAL DRAWING REV
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop ENG-M ENGINEERING MODIFICATION REV
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop ENG-P ENGINEERING PLANNING REVIEW
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop ENG-T ENGINEERING TRAFFIC STUDY REV
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

  Print


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved