Plan Review Details - Project E22100035
Plan Review Stops For Project E22100035
Review Stop ENG-A ENGINEERING FORMAL REVIEW
Rev No 3 Status P Date 04-07-2023 Cont ID  
Sent By lquinone Date 04-07-2023 Time 15:11 Rev Time 0.00
Received By lquinone Date 04-07-2023 Time 15:11 Sent To  
Notes
***NONE***

Review Stop ENG-A ENGINEERING FORMAL REVIEW
Rev No 2 Status F Date 12-09-2022 Cont ID  
Sent By rrossano Date 12-09-2022 Time   Rev Time 0.00
Received By rrossano Date 12-09-2022 Time   Sent To  
Notes
2022-12-09 14:21:00E22090007 - MINT ECO 10.25.22 RESUB REVIEW
  
 COMMENTS FROM RICK ROSSANO, PROJECT COORDINATOR,
 ENGINEERING SERVICES DEPT., 561-494-1098
 [email protected] :
  
 SPECIFY PIPE SIZE AND MATERIAL OF WATER LINE BEING
 TAPPED AT CONNECTION AND ADD TO PLAN AND BLOW-UP DETAIL
 A.
  
 COMMENTS FROM MARK HURLEY, FIELD CUSTOMER SERVICE
 SUPER., WPB PUBLIC UTILITIES, 561-822-2262 OR
 [email protected]:
  
 -REMINDER TO ADD MEP PLANS IN RESUBMITTAL PACKAGE AS
 REFERRED TO IN RESPONSE LETTER.
  
 -VERIFY THERE WILL BE NO FIRE SPRINKLERS IN BUILDING.
  
 -SEWER CLEANOUT BEHIND DUMPSTER AREA MAY CONFLICT WITH
 PROPOSED PLANTS FROM LANDSCAPING PLAN. CHECK AND
 COORDINATE WITH LANDSCAPING PLAN DESIGNER AS NECESSARY.
  
 -WATER AND SEWER DEMAND CHART HAS REFERENCES TO MANY
 BEDROOMS AND DWELLING UNITS. PLEASE VERIFY AND UPDATE
 THE INFORMATION AS NEEDED.
  
 -IF CAR WASH HAS A DESIGNATED ADDRESS, THEN PLEASE ADD
 TO PLANS.
  
 COMMENTS FROM RICKY ELIZONDO, PUB. UTILITIES PLANS
 EXAMINER, [email protected] , 561-494-1101:
  
 IS A WATER SERVICE LINE BEING REMOVED? IF SO, SHOW ON
 PLANS.
  
 -DENOTE INVERT FOR PROPOSED SEWER LATERAL AS POINT OF
 SERVICE (OR ADD CLEANOUT BEFORE OR JUST WITHIN PROPERTY
 LINE).
  
 -SHOW DIRECTION OF FLOW FOR EXISTING SANITARY LINE.
  
 -PROVIDE A PROFILE FOR SEWER LATERAL TO SHOW SEPARATION
 OF DRY UTILITIES.
  
  
 COMMENTS FROM TRACY WARD, SR. STORMWATER ENG.,
 ENGINEERING SERVICES, [email protected] 561-494-1120:
  
 1. REVISE THE PIPE MATERIAL HDPE TO RCP IN THE
 CONNECTION NOTE TO THE EXISTING CATCH BASIN AT INVERT
 ELEVATION 10.9N.
 2. STRUCTURE A8 ??? INDICATE WHICH INVERT WILL BE
 COVERED BY THE PRB.
 3. STRUCTURE A6 SHOULD HAVE TWO PRBS.
 4. CONTROL STRUCTURE A1 DETAIL:
 A. SECTION VIEW SHOWS FRAME AND GRATE BUT LABEL CALLS
 OUT USF 620- GRATE / NO FRAME (TYPE ???E???)
 B. CONFIRM USF 620 GRATE INSTEAD OF USF 6290, 6300 OR
 6616. (COMMENT ALSO PERTAINS TO THE STANDARD TYPE
 ???C??? & ???E??? INLET DETAIL).
 5. TEXT OVERLAP ON THE CITY DETAIL ST-7.
 6. SHOULDN???T RECLAIM WATER TANKS BE CONNECTED TO THE
 SAND/OIL SEPARATOR? SHOULD DOMESTIC SEWER LINE FLOW
 THROUGH THE SAND/OIL SEPARATOR?
 7. WHAT ARE THE DIMENSIONS OF THE 1500 GALLON RECLAIMED
 WATER TANKS?
 8. PROVIDE SWALES ALONG PROPERTY LINES TO PREVENT
 DIRECT RUNOFF TO ADJACENT PROPERTY OR TO PALM BEACH
 LAKES R/W.
  
  
 FEEL FREE TO CONTACT US IF YOU HAVE ANY QUESTIONS OR
 CONCERNS, THANKS.
 RICK ROSSANO, PROJECT COORDINATOR, ENGINEERING SERVICES
 DEPARTMENT (561) 494-1098 [email protected]
  

Review Stop ENG-A ENGINEERING FORMAL REVIEW
Rev No 1 Status F Date 10-20-2022 Cont ID  
Sent By rrossano Date 10-20-2022 Time   Rev Time  
Received By rrossano Date 10-20-2022 Time   Sent To  
Notes
2022-10-20 12:02:47E22100035 - MINT ECO 9.9.22 SUB REVIEW
  
 COMMENTS FROM RICK ROSSANO, PROJECT COORDINATOR,
 ENGINEERING SERVICES DEPT., 561-494-1098
 [email protected] :
 1. CONFIRM THAT A COMPLETED LOS ANALYSIS SUMMARY TABLE
 HAS BEEN SUBMITTED DIRECTLY TO ENGINEERING (SHEET 33 OF
 CITY OF WPB DEVELOPMENT APPLICATION).
 2. CHECK TO SEE IF FDEP FORMS FOR PROPOSED SANITARY
 SEWER ARE REQUIRED.
 3. PROVIDE CALCULATIONS ON PLANS OF EXISTING AND
 PROPOSED DEMANDS FOR WATER & SEWER (AVERAGE, MAXIMUM
 AND PEAK) AND FIRE FLOW DEMANDS. CALCULATIONS SHALL BE
 PER FAC 64E-8 FOR WATER AND PER FAC 64-E.008 FOR SEWER.
 4. PLEASE PROVIDE CALCULATIONS OF REVISED PERVIOUS AND
 IMPERVIOUS CALCULATIONS FOR THE PROPOSED IMPACTED
 AREAS.
 5. COORDINATE WITH MARK HURLEY, FIELD CUSTOMER SERVICE
 SUPERVISOR WITH CITY OF WPB PUBLIC UTILITIES, REGARDING
 PLACEMENT OF BACKFLOW DEVICES AND WATER METERS. CONTACT
 HIM AT 561-494-2262 OR [email protected]
 6. PLANS SHALL SHOW EXISTING AND PROPOSED LOCATIONS AND
 DIMENSIONS OF ALL WATER, STORMWATER, AND SANITARY AND
 SEWER LINES AND CLEANOUTS, GREASE TRAPS, ETC. INCLUDING
 STUBS TO EACH PROPERTY LINE FOR WATER AND SANITARY
 SEWERS, THE MAKE AND MODEL OF ALL VALVES, POTABLE AND
 IRRIGATION METERS, BACKFLOWS, FIRE HYDRANTS AND FDCS,
 AND OTHER DEVICES TO BE INSTALLED ON THE SYSTEM, CATCH
 BASINS, CULVERTS, DITCHES INCLUDING GRADES, PIPES
 SIZES, MATERIALS, ELEVATIONS, ASSUMPTIONS,
 CALCULATIONS, INVERT ELEVATIONS FOR ALL INLETS AND
 MANHOLES AND PROFILES OF SANITARY SEWER LINES. GATE
 VALVE BOXES SHALL NOT BE INSTALLED IN CURB OR SIDEWALK.
 ALL AVAILABLE ELEVATION SHALL BE SHOWN ON THE PROFILE
 VIEW. DIRECTION OF FLOW SHALL BE SHOWN ON PLAN VIEW ON
 PLAN VIEW FOR ALL SANITARY AND STORM SEWERS. PLEASE
 SHOW SLOPE % ON ALL SANITARY LINES AND CALL OUT
 MATERIAL. ADDITIONALLY, PLAN VIEW SHALL SHOW ALL
 EXISTING AND PROPOSED UNDERGROUND UTILITY LAYOUT,
 INCLUDING FIBER OPTIC, ELECTRIC, GAS, AND CABLEVISION &
 TELECOMMUNICATION FACILITIES INCLUDING PIPES SIZES AND
 MATERIALS, LOCATED ON THE RIGHT-OF-WAY.
 7. PLEASE CUT AND CAP UTILITIES NOT IN USE AND REMOVE
 ANY ABANDONED UTILITY LINES LARGER THAN 2 INCHES FROM
 CITY RIGHT OF WAY.
 8. PLEASE SHOW EXISTING AND PROPOSED UTILITY EASEMENTS,
 INCLUDING THOSE PROPOSED TO ALLOW ACCESS FOR CITY
 PERSONNEL TO PROPOSED UTILITY WATER METERS.
 9. PLEASE PROVIDE ENLARGED VIEW ON PLANS OF PROPOSED
 LOCATION OF WATER METER AND BACKFLOW PREVENTION, AND
 EXISTING METER AND BACKFLOW (TO BE REMOVED?). BACKFLOWS
 SHALL BE INSTALLED ON PRIVATE PROPERTY OUTSIDE OF
 EASEMENTS AND RIGHTS OF WAY. DOMESTIC WATER METERS
 SHALL BE INSTALLED IMMEDIATELY ADJACENT TO PROPERTY
 LINE. 3 INCH AND LARGER WATER METERS SHALL BE INSTALLED
 ABOVE-GROUND ONLY.
 10. PLEASE CALLOUT DOMESTIC BACKFLOW PREVENTER AS RPPA
 AND FIRE BACKFLOW PREVENTER AS DCDA. SPECIFY LEAD FREE
 DESIGN ON ALL BACKFLOWS.
 11. ENGINEERING PLANS SHALL INCLUDE PIGGING, FLUSHING
 AND SAMPLE POINTS ON ANY WATER RUNS 60 FT. IN LENGTH OR
 GREATER.
 12. FOR FORMAL ENGINEERING SUBMITTAL, SFWMD ERP AND
 NPDES NOI REQUIREMENTS WILL BE ENFORCED.
 - AN NOI IS REQUIRED FOR PROJECTS THAT:
 - 1) DISTURB ONE OF MORE ACRES OF LAND OR DISTURB LESS
 THAN ON ACRE OF LAND BUT ARE PART OF A COMMON PLAN OF
 DEVELOPMENT OR SALE;
 - 2) DISCHARGE STORMWATER TO SURFACE WATERS OF THE
 STATE OR TO SURFACE WATERS OF THE STATE THROUGH A
 MUNICIPAL SEPARATE STORM SEWER SYSTEM (MS4).
 - THE SFWMD ERP CAN BE OBTAINED THROUGH A 10-2 SELF
 CERTIFICATION THROUGH FDEP OR AN ERP APPLICATION
 THROUGH SFWMD. EITHER WAY, THE DEVELOPER/ENGINEER SHALL
 SUBMIT A COPY OF THE ERP PERMIT OR FDEP ACKNOWLEDGEMENT
 OF THE 10-2 CERTIFICATION.
 13. PROVIDE PROFILE AND CLEARANCES BETWEEN WATER, SEWER
 AND STORM LINES AT ALL UTILITY CROSSINGS WITHIN ROW PER
 CITY OF WEST PALM BEACH STANDARD DETAIL GN-2 SERIES.
 PLEASE SHOW ALL EXISTING AND PROPOSED UNDERGROUND
 UTILITY LAYOUT, INCLUDING FIBER OPTIC, ELECTRIC, GAS,
 AND CABLEVISION & TELECOMMUNICATION FACILITIES WITH
 PIPE MATERIAL AND SIZE, LOCATED ON THE RIGHT-OF-WAY.
 14. WHEN SUBMITTING APPROVED MATERIALS LIST, PLEASE
 PROVIDE MATERIAL/CUT SHEETS FOR ALL PROPOSED BACKFLOW
 DEVICES SHOWING SPECIFIC MODEL NUMBER AND SPECIFYING
 USC APPROVED LEAD-FREE DESIGN.
 15. PLEASE CLEARLY SHOW ROAD RIGHT OF WAY.
 16. PLEASE PROVIDE SANITARY ELEVATIONS AT MANHOLE
 TIE-IN.
 17. IF SANITARY LINES ARE PROPOSED IN ROW PLEASE SHOW
 ADJACENT SANITARY LATERAL LOCATIONS AND SHOW ADDRESSES
 OF ADJACENT PARCELS.
 18. IF WATER LINES ARE BEING REPLACED IN ROW, SHOW
 ADJACENT PARCEL ADDRESSES.
 19. IF TRENCHING IN IN CITY-MAINTAINED ROADWAY AREAS
 ADD NOTE TO PROVIDE 50 FT. PAVEMENT RESTORATION
 TRANSITION ON EACH SIDE OF PROPOSED TRENCH PER CITY OF
 WPB STANDARD DETAIL GC-4.
 20. PLEASE PROVIDE LEGEND ON ALL PLAN SHEETS TO INCLUDE
 STREETLIGHT, SIGN POSTS, TRANSFORMER BOXES ETC.
 21. PLEASE RESPOND TO ALL COMMENTS IN WRITING AND
 INCLUDE PROJECT NAME, ADDRESS AND PERMIT NUMBER
 (E-XXXXXXXX).
  
 COMMENTS FROM MARK HURLEY, FIELD CUSTOMER SERVICE
 SUPER., WPB PUBLIC UTILITIES, 561-822-2262 OR
 [email protected]:
  
 -WILL ALL THE WATER FROM THE 1500 GALLON RECLAIM WATER
 TANKS GO DIRECTLY TO SANITARY SEWER WITHOUT ANY BEING
 PUMPED ELSEWHERE?
 -ADD RIM ELEVATION TO CLEANOUTS.
 -ADD NOTE IF SANITARY MANHOLE BEING REHABBED.
 -ADD WATER AND SEWER DEMAND CALCULATIONS TO SHEET 7.
 -PROPOSED SEWER LATERAL APPEARS TO BE CONFLICTING WITH
 EXISTING LARGE UTILITY POLE ADJACENT MANHOLE.
 -DOES THE EXISTING SANITARY MANHOLE ALSO HAVE SEWER
 LATERAL CONNECTED FROM 1896 PALM BEACH LAKES?
 -LABEL ADDRESS OF ADJACENT PROPERTIES.
 -SHEET 3 HAS NO INFORMATION ABOUT THE STORM OUTFALL.
 -IF THERE IS AN IRRIGATION SYSTEM, WILL IT RUN OFF OF
 METERED WATER SERVICE?
 -ADD DATUM CONVERSION EQUATION STATEMENT ON SHEETS WITH
 ELEVATIONS.
 -EXISTING WATER SERVICES NOT SHOWN CORRECTLY ON PLANS.
 THERE ARE TWO EXISTING METER BOXES IN THE AREA WITH 17
 INCH BY 30 INCH LIDS. THE EASTERN METER BOX IS A CITY
 WPB PARKS 2??? IRRIGATION METER WITH BACKFLOW ASSEMBLY.
 PROJECT WOULD NEED RECEIVE APPROVAL FROM GREG MIHALKO
 [email protected] OR THEY COULD NOT BE REMOVED. THE
 WESTERN METER BOX IS FOR 1890 PALM BEACH LAKES AND THE
 2??? METER HAS BEEN REMOVED SINCE 2012. BACKFLOW
 ASSEMBLY LOOKS TO HAVE BEEN CUT OUT. BOTH METER BOXES
 SHOULD STILL HAVE THE SERVICE LINES TO THE WATER MAINS
 IN TACT.
 -ADD MARKUP NOTE ON SD WS1 THAT DUAL CHECK VALVE NOT
 USED WHEN A BACKFLOW ASSEMBLY IS BEING INSTALLED.
 -ADD STANDARD DETAIL GS1 TO DETAILS SHEET.
  
 COMMENTS FROM TRACY WARD, SR. STORMWATER ENG.,
 ENGINEERING SERVICES, [email protected] 561-494-1120:
  
 1. PROVIDE THE CONVERSION EQUATION BETWEEN NAVD1988 AND
 NGVD1929 ON EVERY SHEET WITH ELEVATION INFORMATION.
 2. TWO STRUCTURES NUMBERED A2.
 3. LABEL PIPE SIZE AND MATERIAL FOR THE PIPE BETWEEN
 STRUCTURES A2 (SOUTHWEST OF BUILDING) AND A6 (BY
 LOADING ZONE).
 4. CAR WASH EFFLUENT IS NOT ALLOWED TO ENTER THE
 STORMWATER MANAGEMENT SYSTEM. WHAT IS THE PURPOSE OF
 THE TRENCH DRAIN AT THE ENTRANCE OF THE CAR WASH?
 5. CHANGE STORM PIPE WITHIN THE R/W TO RCP. REVISE
 CONTROL STRUCTURE DETAIL.
 6. CALLOUT PRB???S FOR STRUCTURES CONNECTED TO
 EXFILTRATION TRENCH AND FOR CONTROL STRUCTURE A1 (OR
 STRUCTURE A7) TO PREVENT FLOATABLES FROM LEAVING THE
 SITE AND FLOWING INTO THE CANAL.
 7. CONTROL STRUCTURE DETAIL CALLS OUT FRAME AND GRATE
 OR GRATE. IS THE STRUCTURE TO HAVE A MANHOLE RING AND
 COVER? CONSIDER PLACEMENT OF THE TOP SLAB OPENING FOR
 STRUCTURE ACCESS AND MAINTENANCE IF THE WEIR WILL BE
 CONSTRUCTED AS SHOWN ALONG THE STRUCTURE DIAMETER.
 8. BAFFLE ATTACHMENT DETAIL ??? REVISE TO SHOW AS A PRB
 (CLOSED ON TOP AND OPEN ON THE BOTTOM, BOTTOM EDGE
 MINIMUM 6 INCHES BELOW PIPE INVERT TO EXFILTRATION
 TRENCH AND MINIMUM 12 INCHES ABOVE THE STRUCTURE
 BOTTOM).
 9. REVISE TYPICAL PARKING SPACES DETAIL TO MATCH THE
 STALL PAINTING DETAIL IN SECTION 94-485 OF THE CITY???S
 CODE OF ORDINANCES.
 10. SHOW FLOATING TURBIDITY BARRIER AROUND THE OUTFALL
 PIPE IN THE CANAL.
  
 DRAINAGE CALCULATIONS:
 11. EXFILTRATION TRENCH: H2 CANNOT EXTEND PAST THE
 HIGHER OF THE BOTTOM OF THE TRENCH OR THE WET SEASON
 WATER TABLE ELEVATION. H2 = 4.0 FEET.
 12. REQUIRED TRENCH LENGTH = 161 LF. ONLY 158 LF
 PROVIDED.
 13. ICPR CALCULATIONS ??? WEIR LENGTH IS 5 FEET INSTEAD
 OF 4 FEET PER THE CONTROL STRUCTURE DETAIL.
  
  
 COMMENTS FROM MIKE TECHNOW, PUB. UTILITIES ENGINEER,
 [email protected], 561-494-1047:
  
 SHEET 7:
 -ADD NOTE THIS IS WITHIN LS BASIN 73 SERVICE AREA
 -PROVIDE PROFILE OF PROPOSED WM SHOWING VERTICAL
 CLEARANCE/S.
 -ADD NOTE TO REHAB/REPLACE MH (THE ONE TO BE CORED) AS
 REQUIRED.
 -SHOW LOS CALCS AND FIRE FLOW CALCS ON SHEET 7.
 -FIX CALL OUT FOR EXISTING 3??? WATER MAIN ON THE NE
 SIDE OF PROPERTY.
  
  
 FEEL FREE TO CONTACT US IF YOU HAVE ANY QUESTIONS OR
 CONCERNS, THANKS.
 RICK ROSSANO, PROJECT COORDINATOR, ENGINEERING SERVICES
 DEPARTMENT (561) 494-1098 [email protected]
  

Review Stop ENG-D ENGINEERING DEFICIENCY REVIEW
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop ENG-E ENGINEERING ENVR. MIT. REVIEW
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop ENG-F ENGINEERING FINAL DRAWING REV
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop ENG-M ENGINEERING MODIFICATION REV
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop ENG-P ENGINEERING PLANNING REVIEW
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop ENG-T ENGINEERING TRAFFIC STUDY REV
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

  Print


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved