Plan Review Details - Project E17010028
Plan Review Stops For Project E17010028
Review Stop ENG-A ENGINEERING FORMAL REVIEW
Rev No 1 Status F Date 03-14-2017 Cont ID  
Sent By mkhan Date 03-14-2017 Time 15:00 Rev Time 0.00
Received By mkhan Date 01-26-2017 Time 09:32 Sent To  
Notes
***NONE***

Review Stop ENG-D ENGINEERING DEFICIENCY REVIEW
Rev No 1 Status F Date 05-12-2017 Cont ID  
Sent By mkhan Date 05-12-2017 Time 15:14 Rev Time 0.00
Received By mkhan Date 05-02-2017 Time 15:15 Sent To  
Notes
2017-05-12 15:20:45ATTACHED PLEASE FIND THE MARKED UP SHEETS FOR YOUR
 REFERENCE AND IN SUPPORT OF THE COMMENTS THAT I EMAILED
 YOU YESTERDAY:
  
 1. AS YOU WILL SEE ON THE MARK-UP (#1 THROUGH #3) ON
 SHEET 2 OF 7, WE WANTED MORE CLARIFICATION ON THE TYPE
 OF INLET WHICH YOU ARE REFERRING TO HAVE/INSTALLED
 POLLUTION RETARDANT BAFFLES. PLEASE REVISE THE LABEL TO
 CALL OUT THE "TYPE E INLET" ON THE PLAN SHEET AND ADD
 NECESSARY DETAILS.
  
 2. CITY'S PUBLIC UTILITIES DEPARTMENT PREFERS OPEN CUT
 FOR BOTH WATER AND SANITARY SEWER CONNECTIONS. PLEASE
 SUBMIT A LETTER OF DISAPPROVAL OF YOUR APPLICATION FOR
 OPEN CUT ON CONGRESS AVE. FOR WATER CONNECTION.
  
 3. PLEASE NOTE THAT CONSTRUCTION AUTHORIZATION IS
 CONTINGENT UPON SUBMITTAL OF ALL APPROVED PALM BEACH
 COUNTY PERMITS.
  
2017-05-12 15:18:53FOLLOWING ARE OUR COMMENTS MADE FOR THE ABOVE MENTIONED
 PROJECT AFTER AN IN-HOUSE REVIEW OF THE REVISED PLANS
 OF APRIL 24, 2017 AND IN REPLY TO THE RESPONSES (ITEMS
 LISTED CHRONOLOGICALLY) IN THE LETTER DATED, APRIL 23,
 2017:
  
 WATER AND SEWER PLANS (SHEET 2 OF 7):
  
 1) DIRECTIONAL BORING:
  
 A) SIMILAR TO SANITARY SEWER CONNECTION, USE OPEN CUT
 FOR WATER SERVICE CONNECTION INSTEAD OF DIRECTIONAL
 DRILL UNDER CONGRESS AVE.
  
 B) PLEASE CONSIDER USING DIP INSTEAD OF HDPE FOR THE
 PROPOSED 8" WATERLINE FROM CONNECTION POINT TO THE
 WATER METER WHILE CROSSING CONGRESS AVE.
  
 C) LABEL THE LOCATION OF THE WATER METER/S AS 'CITY'S
 POINT OF SERVICE' AND ALSO LABEL THE PUBLIC AND PRIVATE
 PORTION OF THE WATER AND SEWER LINES.
  
 D) ALSO NOTE THAT WATER LINE NEED TO BE AT LEAST 5-FEET
 FROM STORMWATER INLET/BOX STRUCTURE/S. CONSIDER
 RELOCATING THE WATERLINE CONNECTION POINT/TAPPING TO
 THE EXISTING PIPE AWAY FROM THE INLET ON THE SOUTH SIDE
 OF CONGRESS AVE.
  
 3) SEE NOTE ON ITEM NO. 1.
  
 6) A NOTE IS ADDED ON THE PLAN BUT FOR CLARITY LABEL
 THE STRUCTURES DISTINGUISH WHICH STRUCTURES ARE 'E'
 INLETS THOSE HAVE POLLUTION RETARDANT BAFFLES.
  
 8) PALM BEACH COUNTY DRIVEWAYS AND UTILITY PERMITS MUST
 BE SUBMITTED PRIOR TO PRE-CONSTRUCTION MEETING.

Review Stop ENG-E ENGINEERING ENVR. MIT. REVIEW
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop ENG-F ENGINEERING FINAL DRAWING REV
Rev No 1 Status P Date 08-14-2017 Cont ID  
Sent By mgonzale Date 08-14-2017 Time   Rev Time 36.00
Received By mgonzale Date 08-04-2017 Time   Sent To  
Notes
***NONE***

Review Stop ENG-M ENGINEERING MODIFICATION REV
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop ENG-P ENGINEERING PLANNING REVIEW
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop ENG-T ENGINEERING TRAFFIC STUDY REV
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***