Plan Review Details - Project E14120034
Plan Review Stops For Project E14120034
Review Stop ENG-A ENGINEERING FORMAL REVIEW
Rev No 1 Status P Date 02-25-2015 Cont ID  
Sent By Mgonzale Date 02-25-2015 Time   Rev Time 24.00
Received By mgonzale Date 01-26-2015 Time   Sent To  
Notes
2015-02-25 12:14:57PASSED WITH PROVISOS:
  
 FOR FINAL RESTORATION OF THE RIGHT-OF-WAY, EACH LANE
 DISTURBED BY THE TRENCH/CONSTRUCTION SHALL BE MILLED
 AND RESURFACED FOR THE ENTIRE LANE WIDTH FOR DISTAANCE
 OF THE TRENCH LENGTH PLAN 50 FEET IN EITHER DIRECTION
 FROM THE TRENCH. WHERE THERE ARE NO LANE LINES ON A 2
 LANE ROADWAY, THE LANE WIDTH WILL BE CONSIDERED TO BE
 50% OF THE PAVED ROAD AREA.
  
 A RIGHT-OF-WAY PERMIT IS REQUIRED TO CLOSE THE ROAD FOR
 CONSTRUCTION.
  
 MANUEL JULIAN GONZALEZ
 ENGINEERING PROJECT COORDINATOR
 PUBLIC WORKS DEPARTMENT
 401 CLEMATIS STREET, 4TH FLOOR
 WEST PALM BEACH, FL 33401
 (MAILING ADDRESS: P.O. BOX 3366, ZIP 33402)
 MAIN PHONE: (561) 822-1200
 DIRECT: (561) 494-1085
 FAX: (561) 494-1116
 EMAIL: [email protected]
 WWW.WPB.ORG/ENGINEERING

Review Stop ENG-D ENGINEERING DEFICIENCY REVIEW
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop ENG-F ENGINEERING FINAL DRAWING REV
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop ENG-M ENGINEERING MODIFICATION REV
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***