Plan Review Details - Project E12110001
Plan Review Stops For Project E12110001
Review Stop ENG-A ENGINEERING FORMAL REVIEW
Rev No 1 Status P Date 01-18-2013 Cont ID  
Sent By mgonzale Date 01-18-2013 Time   Rev Time 1.00
Received By mgonzale Date 01-18-2013 Time   Sent To ENG
Notes
2013-01-18 08:51:58APPROVED-AS NOTED WITH THE FOLLOWING PROVISOS:
  
 #1 TAPPING VALVE AND SLEEVE MUST NOT BE STAINLESS
 MATERIAL AS SHOWN ON PLANS.
 #2 CONTRACTOR WILL FIELD VERIFY O.D. (OUTSIDE DIAMETER)
 OF EXISTING 12" WATERMAIN).
 #3 ADDITIONAL 10" RESILIENT WEDGE GATE VALVE
 (RESTRAINED REQUIRED FOR FUTURE PB MALL CONNECTION).
 #4 CONTRACTOR HAS BEEN GIVEN INSTRUCTION TO BACTEE THE
 WATER SERVICE LINE AND WILL CHECK WITH OWNER IF THIS IS
 IN HIS SCOPE OF WORK.
 #5 PROVIDE APPROVED MATERIAL LIST
 #6 VAULT AND LID SHOP DRAWINGS MUST BE SUBMITTED IF
 INSTALLING A 3" METER. (PIPING SERVING 3" METER WILL BE
 4" DIP)
 #7 ROAD RESTORATION PARAMETERS AND COUNTY ROW
 COORDINATION WILL NEED TO BE DONE BETWEEN EOR,
 CONTRACTOR AND PB COUNTY.
 #8 PRIVATE LINE IN PBC ROW MUST MEET VERTICAL
 SEPARATION REQUIREMENTS (WATER LINE WILL CROSS MALL'S
 SANITARY SEWER SERVICE, AN 18" MINIMUM VERTICAL
 SEPARATION IS REQUIRED) 36" COVER MUST BE PROVIDED FOR
 FULL LENGTH OF THE PRIVATE SERVICE. CLEARANCES AND
 DEPTHS MUST BE SHOWN ON AS-BUILTS BY A LICENSED
 SURVEYOR.
 #9 PLAN SHOWS A 12"X10" REDUCER THAT WILL NOT BE
 NEEDED.
 #10 ALL CITY PIPING BEFORE AND UP TO THE METER WILL BE
 DUCTILE IRON PIPE OR COPPER AS PER AML LIST.
 #11 CONSTRUCTION COORDINATION AND ROAD RESTORATION OF
 PALM BEACH LAKES BLVD WILL BE DISCUSSED THRU PALM BEACH
 COUNTY
 #12 PRIVATE LINE WILL REQUIRE TO HAVE A COLOR "BLUE"
 STRIPE OR TAPE AND ALSO A COPPER TRACING WIRE FOR
 PROPERLY LOCATING.
 #13 EOR WILL INSPECT AND CERTIFY WATERMAIN BEYOND CITY
 METER, THIS PORTION IS "PRIVATE".
  
  
  
  
  

Review Stop ENG-D ENGINEERING DEFICIENCY REVIEW
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop ENG-E ENGINEERING ENVR. MIT. REVIEW
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop ENG-F ENGINEERING FINAL DRAWING REV
Rev No 1 Status P Date 11-12-2014 Cont ID  
Sent By Mgonzale Date 11-12-2014 Time   Rev Time 1.00
Received By mgonzale Date 11-12-2014 Time   Sent To I
Notes
2014-11-12 12:35:0311/12/2014
  
 CERTIFICATION LETTER RECEIVED AND AS-BUILTS.
 PERMIT IS CLOSED!
  
 MANUEL JULIAN GONZALEZ
 ENGINEERING PROJECT COORDINATOR
 PUBLIC WORKS DEPARTMENT
 401 CLEMATIS STREET, 4TH FLOOR
 WEST PALM BEACH, FL 33401
 (MAILING ADDRESS: P.O. BOX 3366, ZIP 33402)
 MAIN PHONE: (561) 822-1200
 DIRECT: (561) 494-1085
 FAX: (561) 494-1116
 EMAIL: [email protected]
 WWW.WPB.ORG/ENGINEERING
  

Review Stop ENG-M ENGINEERING MODIFICATION REV
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop ENG-P ENGINEERING PLANNING REVIEW
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop ENG-T ENGINEERING TRAFFIC STUDY REV
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***