Plan Review Details - Project E10030029
Plan Review Stops For Project E10030029
Review Stop ENG-A ENGINEERING FORMAL REVIEW
Rev No 1 Status P Date 04-06-2010 Cont ID  
Sent By dlauderm Date 04-06-2010 Time 08:12 Rev Time 1.00
Received By dlauderm Date 04-06-2010 Time 08:08 Sent To  
Notes
2010-04-06 08:22:00DEAN S. LAUDERMILK, PROJECT COORDINATOR
 DIRECT DIAL: 561-494-1083
 FAX: 561-494-1116
 EMAIL: [email protected]
  
 PASSED WITH PROVIOS:
 1) WE DO NOT HAVE IN OUR APROVED MATERIAL LIST (AML)
 THE BALL CORP REQUIRED. THIS WILL NEED TO BE
 INVESTIGATED.
 2) NORMALLY VALVE FOR FIRE LINES IS AT THE
 RIGHT-OF-WAY/PROPERTY LINE (ROW/PL). WILL NEED TO CHECK
 WITH SUPERVISOR, CURB STOP MAY BE REQUIRED AT (ROW/PL).
 3) IF NOT ALREADY SUBMITTED PLAN WILL NEED TO BE
 SUBMITTED FOR REVIEW THRU CONSTRUCTION SERVICES.
 4) PLANS ARE READY TO BE PICKED UP
  
 NOTES:
 1) PLEASE TURN IN SHOP DRAWINGS/AML AFTER THEY HAVE
 BEEN APPROVED A PREWORK CAN BE SCHEDULED.
 2) ROW PERMIT WILL BE REQUIRED TO CLOSE THE ALLEY. MOT
 WILL BE REQUIRED WITH PERMIT APPLICATION TO CLOSE THE
 ALLEY.
 3) ROW PERMITS CAN BE APPLIED ON LINE OR IN PERSON BY
 THE CONTRACTOR THRU CONSTRUCTION SERVICES AS OF 4/5/10
 4) READ ATTACHED (TO PLANS) DOCUMENT CONCERNING "RECORD
 DRAWINGS"
  
2010-04-06 08:20:50DEAN S. LAUDERMILK, PROJECT COORDINATOR
 DIRECT DIAL: 561-494-1083
 FAX: 561-494-1116
 EMAIL: [email protected]
  
 PASSED WITH PROVIOS:
 1) WE DO NOT HAVE IN OUR APROVED MATERIAL LIST (AML)
 THE BALL CORP REQUIRED. THIS WILL NEED TO BE
 INVESTIGATED.
 2) NORMALLY VALVE FOR FIRE LINES IS AT THE
 RIGHT-OF-WAY/PROPERTY LINE (ROW/PL). WILL NEED TO CHECK
 WITH SUPERVISOR, CURB STOP MAY BE REQUIRED AT (ROW/PL).
 3) IF NOT ALREADY SUBMITTED PLAN WILL NEED TO BE
 SUBMITTED FOR REVIEW THRU CONSTRUCTION SERVICES.
 4) PLANS ARE READY TO BE PICKED UP
  
 NOTES:
 1) PLEASE TURN IN SHOP DRAWINGS/AML AFTER THEY HAVE
 BEEN APPROVED A PREWORK CAN BE SCHEDULED.
 2) ROW PERMIT WILL BE REQUIRED TO CLOSE THE ALLEY. MOT
 WILL BE REQUIRED WITH PERMIT APPLICATION TO CLOSE THE
 ALLEY.
 3) ROW PERMITS CAN BE APPLIED ON LINE OR IN PERSON BY
 THE CONTRACTOR THRU CONSTRUCTION SERVICES AS OF 4/5/10

Review Stop ENG-D ENGINEERING DEFICIENCY REVIEW
Rev No 1 Status F Date 12-13-2011 Cont ID  
Sent By mgonzale Date 12-13-2011 Time   Rev Time 1.00
Received By mgonzale Date 12-13-2011 Time   Sent To  
Notes
2011-12-13 09:27:51PROJECT HAS NOT BEEN PROPERLY CLOSED OUT,
  
 CONTACT:
  
 MANUEL JULIAN GONZALEZ
 ENGINEERING PROJECT COORDINATOR
 ENGINEERING SERVICES DEPARTMENT
 401 CLEMATIS STREET, 4TH FLOOR
 WEST PALM BEACH, FL 33401
 (MAILING ADDRESS: P.O. BOX 3366, ZIP 33402)
 MAIN PHONE: (561) 822-1200
 DIRECT: (561) 494-1085
 FAX: (561) 494-1116
 MOBILE: (561) 644-7301
 EMAIL: [email protected]
 WWW.WPB.ORG/ENGINEERING
  

Review Stop ENG-E ENGINEERING ENVR. MIT. REVIEW
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop ENG-F ENGINEERING FINAL DRAWING REV
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop ENG-M ENGINEERING MODIFICATION REV
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop ENG-P ENGINEERING PLANNING REVIEW
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

Review Stop ENG-T ENGINEERING TRAFFIC STUDY REV
Rev No 1 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time  
Received By   Date   Time   Sent To  
Notes
***NONE***

  Print


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved