| Plan Review Notes For Permit 99121236 |
| Permit Number |
99121236 |
|
| Review Stop |
M |
| Sequence Number |
1 |
|
| Notes |
| Date |
Text |
| 2001-01-08 00:00:00 | | | | | | | | | | | | | CORRECTED BY REVISIONS3/8/00********* | | | | | | 1) SHT A-31 DETAIL 3 DRYER VENT AND BATH | | | EXHAUST DUCT TO BE ENCLOSED IN SHAFT TO | | | BOTTOM OF ROOF STRUCTURE NOT REQUIRED | | | 2) SHT A-31 DETAIL 2 DRYER VENT TO BE | | | MIN. 4" NOT 3", DRYER VENT TO RUN FULL | | | LENGTH OUT OF BUILDING | | | 3) SHT A-31 DETAIL 4 INDICATE WHICH SIZE | | | CAP TO BE USED- 4" OR 2 1/2" NOTE: FLEX | | | METAL DUCT NOT ALLOWED BY CODE | | | 4) SHT AC-1 AREAS WITH 300CFM OR GREATER | | | REQUIRES RETURN AIR FROM AREA | | | 5) SHT AC-1 PROVIDE MANUFACTURES SPEC'S | | | ON CAPACITY TO PUSH LENGTH OF DUCT USED | | | 6) ANY DUCT PENETRATING RATED CEILING | | | TO HAVE FIRE DAMPERS PER 1997 SMC 610.2 | | | 7) CONDENSING UNIT SERVICE TO BE PER NEC | | | AND 1997 SMC 304.7.2 WHICHEVER IS GREAT- | | | ER. DISCONNECT TO BE WITHIN 6' OF THE | | | SERVICE SIDE OF THE EQUIPMENT AND A 115V | | | GFIC OUTLET REQUIRED. | | | 8) SHT AC 5 OVERFLOW PROTECTION REQUIRED | | | FOR AHU'S PER 1997 SMC 304.8.6 |
|