| 2001-01-08 00:00:00 | CHECKLIST: |
| | 1-TRUSS DRAWINGS: |
| | -THERE IS ONLY ONE MEAN ROOF HEIGHT FOR |
| | ENTIRE BUILDING. TABLE 1606.2A SBC/97. |
| | -UPDATE ALL GENERAL DETAILS ACCORDING |
| | TO SBC 1997 OR ASCE 7-95. |
| | -CLARIFY WHY THERE ARE SOME DETAILS AND |
| | LETTERS SEALED BY DIFFERENT ENGINEERS. |
| | DATE OF DOCUMENTS TO BE THE DATE WHEN |
| | THEY ARE SEALED. |
| | -WHY IS LETTER FROM SIMPSON STRONG TIE |
| | SEALED BY ANOTHER ENGINEER. |
| | 2-PROVIDE PRODUCT APPROVAL FOR ENTRY |
| | DOORS "INSWING" TYPE AS SHOWN ON |
| | ARCHITECT'S PLANS. |
| | 3-PRODUCT APPROVAL FOR GOLFCART DOOR |
| | DOESN'T MEET THE DESIGN PRESSURES |
| | CALCULATED BY THE ARCHITECT. |
| | 4-ROYAL PALM ALUMINUM LETTER FROM THE |
| | MANAGER OF ENGINEERING TO BE SIGNED, |
| | SEALED AND DATED. |
| | 5-PRODUCT APPROVAL FOR SLIDING GLASS |
| | DOORS WITH TRANSOM ABOVE ASSEMBLY: |
| | -PROVIDE PRODUCT APPROVAL FORM WITH ALL |
| | REQUIRED INFORMATION FROM MANUFACTURER |
| | ENGINEER AND PROFESSIONAL DESIGNER OF |
| | RECORD FOR SITE SPECIFIC INSTALLATION. |
| | |
| | |
| | NOTE: |
| | TO AVOID UNNECESSARY DELAYS, PLEASE TELL |
| | THE ARCHITECT AND ENGINEER TO PROVIDE |
| | ALL THE INFORMATION REQUIRED BY THE |
| | DEPARTMENT OF BUSINESS AND PROFESSIONAL |
| | REGULATION WHEN SUBMITTING DOCUMENTS FOR |
| | PUBLIC RECORDS. |