| 2001-01-08 00:00:00 | REVISION: |
| | ROYAL WALL SYSTEM IN LIEU OF CBS. |
| | |
| | CHECKLIST: |
| | 1-FIRE RATED WALL DOESN'T MEET THE |
| | REQUIREMENTS FOR SECTIONS 709.2.1.4.4 |
| | AND 709.2.1.4.5 SBC 1997. (CALCS ARE |
| | INCORRECT). |
| | 2-WHEN WALL FINISHES ARE ASSUMED TO |
| | CONTRIBUTE TO THE TOTAL FIRE |
| | RESISTANCE OF THE WALL, THEN THEY |
| | SHALL BE INSTALLED AS PER SECTION |
| | 709.3.1.6 SBC 1997. |
| | 3-PROVIDE COMPLETE DETAILS AND SPECS |
| | FOR CONCRETE PANELS WITH ROUND AND |
| | ARCHED OPENINGS. SEC 104.2.2 OF CITY |
| | AMENDMENTS TO SBC 1997. |
| | 4-PROVIDE INFORMATION SHOWING THE R |
| | VALUE (12.9) CALCULATED IN THE ENERGY |
| | CALCULATIONS. SEC 104.2.2 CITY AMENDM. |
| | 5-PROVIDE COPIES OF APPROVED DRAWINGS |
| | REFERENCED ON THE PRODUCT APPROVAL. |
| | 6-PROVIDE COMPLETE DETAILS AND SPECS FOR |
| | COLUMN AT REAR PORCH. |
| | SEC. 104.2.2 CITY AMENDMENTS. |
| | |
| | FROM PREVIOUS PROVISO DATED 10/30/99: |
| | 1-PROVIDE FULL SET OF PRODUCT APPROVALS. |
| | 2-UPDATE ALL ENGINEERED TRUSSES. CUT AND |
| | PASTE IS NOT ACCEPTABLE. |
| | 3-STORM PANELS: |
| | -PROVIDE A COMPLETE INSTALLATION |
| | SCHEDULE AS PER CITY SAMPLE. |
| | -PROVIDE DETAIL FOR INSTALLATION OF |
| | STORM PANELS AT FRONT WINDOWS. SEE |
| | EXTERIOR SILL DETAIL AND INSTALLATION |
| | SCHEDULE. |